Sustainable Natural Resources Management and ......The Sustainable Natural Resources Management and...
Transcript of Sustainable Natural Resources Management and ......The Sustainable Natural Resources Management and...
Initial Environmental Examination and Environmental Management Plan
August 2014
Lao PDR: Sustainable Natural Resources
Management and Productivity Enhancement Project
Prepared by the Ministry of Agriculture and Forestry for the Asian Development Bank.
This initial environmental examination and environmental management plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Lao People’s Democratic Republic Peace Independence Democracy Unity Prosperity
Ministry of Agriculture and Forestry Department of Planning and Cooperation
INITIAL ENVIRONMENT EXAMINATION
AND
ENVIRONMENTAL MANAGEMENT PLAN
Lao PDR: Sustainable Natural Resources Management and Productivity Enhancement Project (SNRMPEP)
ADB Grant -0144-LAO(SF)
IFAD Grant 0145-LAO (DSF 8025-LA)
2
ABBREVIATIONS ADB – Asian Development Bank ATT – Attapeu CPA – Champasak COM – Commercialization DAFO – District Agriculture and Forestry Department DoNRE – Department of Natural Resources and Environment DOP – Department of Planning (Ministry of Agriculture and Forestry) DPI – Department of Planning and Investment (provincial) DPWT – Department of Public Work and Transport EIA – Environmental Impact Assessment EMMP – Environment Management and Monitoring Plan EPL – Environment Protection Law IEE – initial environmental examination IFAD – International Fund for Agricultural Development MAF – Ministry of Agriculture and Forestry MONRE – Ministry of Natural Resources and Environment NREO – Natural Resources and Environment Office NTFP – Non-Timber Forest Products PAFES – Provincial Agriculture and Forestry Extension Service PAFO – Provincial Agriculture and Forestry Department PCC – Provincial Coordination Committee PCO – Project Coordination Office PPMS – project Performance Monitoring System PPO – Provincial Project Office PR – Poverty Reduction PSC – Project Steering Committee ROW – Right of Way SAL
SEK SIEE
– – –
Salavanh Sekong Summary Initial Environmental Examination
SVK – Savannakhet SNRMPEP – Sustainable Natural Resources and Productivity Enhancement
Project WUA – Water Use Association
3
Chapter 1: introduction 8
1.1 Overview of the project and environmental safeguard requirements 8
1.2 Objective of the Initial Environmental Examination 8
1.3 Scope of Initial Environmental Examination 8
1.4 Process and Methodologies 10
Chapter 2: Policy, Legal and Administrative Framework ON ENVIRONMEMTAL SAFEGUARDS 11
Chapter 3: describption of the subprojectS 13
3.1 SVK COM 10 Promotion Commercialization ofLivestock in Savanakhet 13
3.2 SVK PR 1Food Security and Poverty Reduction through Livestock in Savannakhet 18
3.4 SAL COM 4: The Integrated Commercial Cultivation of Sweet Potato, Peanut and Banana
Subproject in Lao Ngam district of Salavanh Province 23
3.5 SAL COM1: Irrigation Development in Khong Sedone District of Salavanh 26
3.6 SALPR3:Promotion Commercialization ofLivestock in Salavanh 32
3.7 CPA COM 9: Promotion Commercialization of Small Livestock in Champasak 37
3.8 CPA COM 10: Promotion Commercialization of Pig Farmingin Champasak 41
3.9 SEK COM 4: Promotion Commercialization of Livestock in Sekong 44
3.10 ATT COM 1: Promotion Commercialization of Livestock in Attapeu 48
3.11 ATT COM 2: Integrated Rice-Pulse Based Farming System in Attapeu 56
Chapter 4: describption of environment 60
4.1. SVK COM 10 Promotion Commercialization of Livestock in Savanakhet 60
4.2. SVK PR 1 Food Security and Poverty Reduction through Livestock inSepon District of
Savannakhet 63
4.3. SAL COM 4: Road Rehabilitation in Lao Ngam Distric of Salavanh 66
4.4. SAL COM 1: Irrigation Development in Khong Sedone District of Salavanh 71
4.5. SAL PR3: Promotion Commercialization of Livestock in Salavanh 74
4.6. CPACOM 9: Promotion Commercialization of Small Livestock in Champasak 75
4.7. CPA COM 10: Promotion Commercialization ofPig Farming in Champasak 79
4.8. SEK COM 4: Promotion Commercialization of Livestock in Sekong 79
4.9. ATT COM 1: Promotion Commercialization of Livestock in Attapeu 82
4.10. ATT COM 2: Integrated Rice-Pulse Based Farming System in Attapeu 85
Chapter 5: potential environmental impacts and assessment 87
5.1. Livestock and Small Scale Agriculture Development Subproject Type 87
5.2. Irrigation Development Subproject Type 94
5.3. Road Development Subproject Type 100
Chapter 6: mitigation measures and environment management and monitoring plan 106
6.1. Mitigation Measures and Environmental Management and Monitoring Program 106
6.2. Institutional Arrangement forImplementation of EMMP 106
6.3. Grievance and Redness Mechanism 106
Chapter 7: public consultation and information disclosure 108
Chapter 8: conclusion and recommendation 113
ANNEX 1: ENVIRONMENTAL MANAGEMENT AND MONITORING PLAN of Livestock intervention Subprojects 114
4
ANNEX 2: ENVIRONMENTAL MANAGEMENT PLAN for tHE kongsedone IRRIGATION intervention subproject: SAl/com/01 119
ANNEX 3: ENVIRONMENTAL MANAGEMENT PLAN OF THE LAO NGAM ROAD INTERVENTIONSubproject: SAL/COM/04 122
ANNEX 4: LIST OF KEY PARTICIPANTS OR CONTRIBUTORS IN IEE REPORT DEVELOPMENT 125
5
List of Tables
Table 1: Catergory B suprject which required for IEE and EMMP ....................................... 9
Table 2: List of villages in the SVK Com 10 subprojects ..................................................... 13
Table 3: SVK Com 10 Subproject Implementation Schedule ............................................. 17
Table 4: SVK PR 1 subproject targeted villages ................................................................... 19
Table 5: SVK PR 1 subproject implementation schedule .................................................... 21
Table 6: SAL COM 4 subproject implementation schedule ................................................. 26
Table 7: SAL COM 1 subproject targeted villages ................................................................ 27
Table 8: SAL COM 1 subproject implementation schedule ................................................. 30
Table 9: SAL PR 3 subproject targeted villages .................................................................... 33
Table 10: SAL PR 3 implementation schedule ...................................................................... 36
Table 11: CPA COM 9 subproject targeted villages ............................................................. 38
Table 12: CPA COM 9 subproject implementation schedule .............................................. 41
Table 13: CPA COM 10 subprojecttargeted villages-pig raising ........................................ 42
Table 14: CPA COM 10 implementation schedule ............................................................... 43
Table 15: SEK COM 4 subproject targeted villages ............................................................. 45
Table 16: SEK COM 4 implementation schdule .................................................................... 47
Table 17: ATT COM 1 subproject villages ............................................................................. 49
Table 18: ATT COM 1 implementation schedule .................................................................. 53
Table 19: Name of villages in subproject area ................................................................. 57
Table 20: Implementation schedule ........................................................................................ 59
Table 21: Livestock situration in the subproject area ........................................................... 63
Table 22: Main information of Kumban Phabang .................................................................. 65
Table 23: NBCA in Salavanh .................................................................................................... 67
Table 24:The main information of 5 Kumbans ...................................................................... 70
Table 25: Livestock situation in subproect area .................................................................... 79
Table 26: Existing conditions of three Kumban ..................................................................... 86
Table 27: Potential impact from livestock and small scale griculture subproject type .... 88
Table 28: Impact assessment from livestock and small scale griculture .......................... 90
Table 29: Potential impact from irrigation based subproject type ...................................... 94
Table 30: Impact significance of irrigation development ...................................................... 96
Table 31: Potential impact from road based subproject type ............................................ 101
6
Table 32: Impact significance from road construction ........................................................ 103
Table 33: Site visit to key activities during January, February and March 2013 ............ 108
Table 34: Site visit for validation of impacts and stakeholders consultationJanuary 26-30th, 2014 ................................................................................................................................... 111
7
List of Figures
Figure 1: SVK COM 10 subproject areamap ......................................................................... 15
Figure 2: SVK PR 1 subproject area map .............................................................................. 18
Figure 3:SAL COM 4 subproject area map ............................................................................ 24
Figure 4: Arial map of the proposed road rehabilitation area .............................................. 24
Figure 5: SAL COM 1 subproject area map ........................................................................... 27
Figure 6: SAL PR 3 sub-project area map ......................................................................... 32
Figure 7: CAP COM 9 subproject area map .......................................................................... 37
Figure 8: CAP COM 10 subproject area map-pig raising .................................................... 42
Figure 9: SEK COM 4 subproject area map .......................................................................... 44
Figure 10: ATT COM 1 subproject area map..................................................................... 49
Figure 11: ATT COM 1 subproject area map..................................................................... 57
Figure 12: Temperature in Savannakhet between 1971 to 2009 ....................................... 60
Figure 13: Precipitation in Savannakheet between 1970 to 2010 ...................................... 61
Figure 14: Map of the NBCAs in Savannakhet ...................................................................... 62
Figure 15: Templerature of Salavanh between 1990 and 2009 ......................................... 66
Figure 16: NBCAs in Salavanh ................................................................................................ 68
Figure 17: Overview of road rehabilitation in Teme village, Lao Ngam District ............... 69
Figure 18: Overview forest and land use in the irrigation area in Sedone River .............. 72
Figure 19: Trends of the temperature of Champasak .......................................................... 76
Figure 20: Trends of the precipitation of Champasak .......................................................... 76
Figure 21: NBCA in Champasak .............................................................................................. 77
Figure 22: Temperature in Sekong .......................................................................................... 80
Figure 23: Rainfall in Sekong ................................................................................................... 80
Figure 24: NBCA in Sekong ..................................................................................................... 81
Figure 25: Temperature in Attapeu ......................................................................................... 83
Figure 26: Rainfall in Attapeu ................................................................................................... 83
Figure 27: NBCA in Attapeu ..................................................................................................... 84
Figure 28: Examples of Pig Farming Situation ...................................................................... 93
Figure 29: Irrigation Area Situation .......................................................................................... 99
8
CHAPTER 1: INTRODUCTION
1.1 Overview of the project and environmental safeguard requirements
The Sustainable Natural Resources Management and Productivity Enhancement Project (SNRMPEP) are co-financed by ADB and IFAD with contribution of the Lao Government, approved in 2009 and will be implemented until 2015 with total cost of $36.77 million. Overall, this project aims to achieve sustainable natural resource management and improvedagricultural productivity by implementing threemain componentsof activities namely: (1) capacity building for agriculture and natural sector management; (2): investment in resource management and productivity enhancement (subproject investment); and (3): project management.The project was divided into 70 subprojects which focus on three areas: commercialization of agricultural production, natural resources management and poverty reduction.Of which, the small infrastructure (access road, irrigation, processing facilities) is integrated in all areas.56,000 households in 1,044 villages of five provinces in the south of Laos: Savannakhet, Salavanh, Champasak, Sekong and Attapueparticipatein the project. The Ministry of Agriculture and Forestry (MAF) is the executing agency (EA) and Department of Planning Cooperation (DoPC) represents the MAF for overall overseeing and coordinating implementation of the project. In the local level, Provincial and District Agriculture and Forestry Offices (PAFOs and DAFOs)are the implementing agency.
This project, regarding to environmental safeguards particularly the screening, is classified as
category B project which only Initial Environmental Examination (IEE) isrequired.
This IEE report is prepared to mainly identify key potential impacts on environment and
mitigation measuresor Environmental Management and Monitoring Plan (EMMP)
includinginstitutional arrangement, consultation process and information disclosurefor execution
of the EMMP. It was prepared based on IEE procedures and requirementsdefined in the EIA
Decree No. 112 of Lao PDR and ADB Safeguard Policy 2009 particularly the technical guideline
for impact assessment for Laos, IEE report formats of other projects funded ADB, field visits,
use of affordable and available data and technologies,stakeholders consultation and consensus
with Natural Resources and Environment agencies in each province.
1.2 Objective of the Initial Environmental Examination
Overall the preparation of the IEE is to compliance with Lao PDR and ADB environmental safeguard requirements. Specificallythis report aims to study and analyse the data to estimate the key environmental and social impact including identifying mitigation and prevention measures to address theanticipated impacts.
1.3 Scope of Initial Environmental Examination
The scope of the IEE focuses on 10 Category B subprojects in five provinces mentioned before. Specifically the assessment covered most socioeconomic and environmental aspects in each phrase of project cycle. 10 Category B subprojects and the aspects that this IEE addresses are in the Table 1 and as follows:
9
Table 1: Catergory B suprject which required for IEE and EMMP
Subproject Codes
Name of Subprojects District
1. Attapeu Province: 2
A. Commercialization
ATP/COM/01 Promotion of service providers for the commercial Pig, Poultries, Goat and Fish Raising in Vernkhene and Bat Luang Villages of Samakhixai district, Attapeu province
Samakhixai
ATP/COM/02 Integrated Rice-Pulse based farming system in irrigated areas of Sanamxai, Samakhixai and Saysettha districts
Sanamxai, Samakhixai and
Saysettha
2. Sekong Province:1
A. Commercialization
SEK/COM/04 Promotion of service providers for the commercial Pig, Poultries, Goat and Fish Raising in 4 Kumb Ban of Thateng district of Sekong province
Thateng
3. Salavanh Province:3
A. Commercialization
SAL/COM/01 Integrated Organic Rice Based Farming for the commercialization of organic rice cultivation in Khong Sedone district, Salavanh Province Khong Sedone
SAL/COM/04 Integrated Commercial Cultivation of Sweet Potato, Peanut and Banana in Lao Ngyam district Lao Ngyam
B. Poverty Reduction
SAL/PR/03 Promotion of service providers for the commercial Pig, Poultries and Fish Raising in 6 Kumb Ban of Salavanh district of Salavanh province Salavanh
4. Champasack Province: 2
A. Commercialization
CPA/COM/09 Promotion of service providers for the commercial Poultries, Goat and Fish Raising in Champasak province All
CPA/COM/10 Promotion of service providers for the commercial Pig in Champasak province All
5. Savanakhet Provice: 2
A. Commercialization
SVK/COM/10 Promotion of service providers for the commercial production of Native Chickes, Ducks in Savanakhet province All
B. Poverty Reduction
SVK/PR/01 Food security and poverty reduction through improved agriculture and livestock raising in 9 villages of Sepone districts of Savannakhet Province
Sepone
The socioeconomic and environmental elements that the IEE leveraged in three phases of the projects: pre-construction, during construction and post construction are:
10
Physical Environment: especiallyClimate and ambient air, Geology and Soil, Topography, Water (river and underground) and Hydrologyetc
Biological Environment: Flora (trees, shrubs and herbs) and Fauna (mammals, birds, butterflies, reptiles, amphibians and fishes) Socioeconomic and Cultural Environment: Economic Characteristics, Industrial Development, and Social and Cultural Resources
1.4 Process and Methodologies
As mentioned in the introduction, the IEE preparation followed the IEE procedures particularly 1) review/screening of the subprojects; 2) review environmental safeguard requirements, policies, laws and institutional framework; 3) field visits,data collection and analysis;4) impact identification and assessment; 5) report preparation; 6) consultation with stakeholders and consensus with Natural Resources and Environment agencies in each province.
As for the impact assessment, it was conducted by using impact assessment matrix which considers three dimensions: the type and scale of activities, site circumstance and timeframe to identify and determine degree and aspects of impacts. In addition, impacts were also validated through site visits, consultation/expert judgment and consensus with the stakeholders.
11
CHAPTER 2: POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK ON ENVIRONMEMTAL SAFEGUARDS
Basically the environmental assessment of development or investment projects in Lao PDR is required environmental laws and regulations. In addition, it is required by laws of other sectors and international conventions that Lao PDR ratified depending on the scope and aspects of impacts. Intuitionally, the Natural Resources and Environment (NREA) Authorities is the key body oversees overall environmental assessment including approval and certify the environmental assessment reports with coordination with relevant sectors. The current and specific environmental laws and regulations that regulate the environmental assessment of Laos are the Environmental Protection Law (EPL) 2013, Decree on Environmental Impact Assessment 2010, Decree on the Resettlement and Compensation of Impacted people in the development project 2009, Decree on the Public Involvement 2012 and Natural Resources and Environment Minister’s Agreement on the Environment standard 2009. The EPL 2013 is the updatedand replacement of the first EPL 1999. However, the environment impact assessment is still a core element of the EPL and defined in the article 12 and 13 about Initial Environmental Examination (IEE) and Environmental Impact Assessment (EIA) requirements for investment or development project. In addition, number of articles in the EPL 2013 also calls for other environmental obligations and meeting environmental standards and performance. The recent Decree on Environmental Impact Assessment (ESIA) 2010 (well known as DecreeNo. 112) is the update of the Regulation on Assessment of Environmental Impact 2000. This Decree defines specifically principles, procedures and requirements for Environmental Impact Assessment (EIA) especially screening of the project to determine whether the proposed project is required for IEE (group 1 project) or EIA (group 2 project). Usually Environmental Impact Assessment (EIA) is required for large and complicate project and Initial Environmental Examination (IEE) is required for small scale and impact. In addition, the EIA is encouraged to follow the EIA guideline and good practice; must involve stakeholders and various level consultations, information disclosures and follow the Decree 192 below if there is resettlement and compensation. The Decree on the Resettlement and Compensation 2009(well known as Decree No. 192) provides also principles, procedures, requirements and measures for addressing issues in relation to resettlement and compensation for impacted people in the investment project, when resettlement and compensation is required. Decree on the Public Involvement2012 is a reinforcement policy of the Decree No.112 and 192. It also defines principles, procedures, requirements and mechanisms on public participation. This Decree is implemented in line or along with the Decree on EIA, Resettlement and Compensation mentioned above. The Natural Resources and Environment Minister’s Agreement on the Environment standard defines specific environmental standard and requirements for meeting the standard such quality of drink and use water including waste water discharge, air and emissions standards and so on.
12
The relevant sectoral laws and regulations that is usually applicable and defines environmental management practices or safeguarding requirements in their specific sectors such as law on road, construction, electric, economic zone, forest, wildlife, land, water, competition handling etc depending on the area and aspects of the impacts. In addition, the following are key international conventions that Lao PDR ratified and necessary to take in account when conducting the impact assessment.
1) ASEAN Agreement on the Conservation of Nature and Natural Resources; 2) Convention for the Protection of the World Cultural and Natural Heritage; 3) Agreement on the Cooperation for Sustainable Development of Mekong River Basin; 4) United Nations Convention to Combat Desertification; 5) United Nations Framework Convention for Climate Change; 6) Convention on Biological Diversity; 7) Montreal Protocol on Substances that Deplete the Ozone Layer; 8) Vienna Convention for the protection of theProtocol of the Ozone Layer; 9) Ozone Layer and the Montreal Protocol on Substances that Deplete the Ozone Layer; 10) Millennium Declaration; 11) Convention on International Trade in Endangered Species of Wild Fauna and Flora; 12) Stockholm Convention on Persistent Organic Pollutants; and 13) Wetlands of International Importance Especially as Waterfowl Habitat (Ramsar
Convention).
13
CHAPTER 3: DESCRIBPTION OF THE SUBPROJECTS
3.1 SVK COM 10 Promotion Commercialization ofLivestock in Savanakhet
This subproject is to promote commercialization of pig raising, poultry and fishery through
stainable value chain approach especially by promoting linkage between livestock producer
groups and business operator in Outhoumphonh, Saiphouthong, and Atsaphangthong districts,
Savannakhet province. 3600 households in 70 villages of Outhoumphonh, Saiphouthong and
Atsaphangthong districts will be organized as producer groups and then engaged with 6
operator who can supply inputs (small livestock: pigs, native ducks and chicken; and processed
feed), markets and also meat processing. This subproject was expected to be implemented
between January 2011 and December 2014 by the Division of Livestock and fisheries, PAFO
with total cost of US$ 632,835. Details of the location, activities and implementation schedules
are described below.
3.1.1 Location
The subproject placed at 70 villages in Outhoumphonh, Saiphouthong, and Atsaphangthong
districts of the Savannakhet Province. Those villages are in the Table 2 and a map of location
is shown in the Figure 1 below.
Table 2: List of villages in the SVK Com 10 subprojects
Sub-Sector: Pig raising Total target HH in 3 years: 300
S.N. Village name Kumb Ban District
1 Somphetvilay No 5 Outhoumphonh
2 Nongbouathong
3 Namphou Namphou
Saiphouthong
4 Mouangkhai
5 Thapho Thapho
6 Khanthachanh Khanthachanh
7 Donvay Thamueung
8 Thadane
9 Nala oong Thapho
10 Nakham
Sub-Sector: Duck & Chicken raising Total target HH in 3 years: 3300
S.N. Village name Kumb Ban District
1 Seno
No 1 Outhoumphonh 2 Chanthalangsy
3 Vongsamphanh
4 Saisomboon
14
5 Oudoummyxai
6 Chomphet
7 SAyamongkhoon
No 3
8 Nathad
9 Xai oudom
10 Nondokmai
11 Vathanasomboon
12 Non Ahongnoi
13 Sanamxai
14 Nongkhamhed
No 4
15 Houymao
16 Dongmakngeo
17 Phakkhanga
18 Nonvilay
19 Phonmarnga
20 Loanga
21 Thampha
No 10
22 Nakaso
23 Dongnoi
24 Koudkhee
25 Haokham
26 Khok
No 11
27 Nachanh
28 Nonsavang
29 Phintai
30 Saiyaphet
31 Chaleunsouk
32 Houysangthong
33 Nasenkeo
No 7
Atsaphangthong
34 Dongmakko
35 Phonsikeo
36 Dongnakham
37 Dongkum
No 2
38 Nalaikhok
39 Nalaidong
40 Nongpaksong
41 Tabongphet
42 Donghenh
No 1 43 Dongkilo
44 Sivilay
45 Huameoung No 7
15
46 Dongkhouang
No5
47 Pongdong
48 Nonghoi
49 Nongsai
50 Samakkhysai
51 Palai
52 Phonphang
53 Phonngoi
54 Naphangkhok
55 Pongna
56 Chealamong
No3 57 Phonnokkeane
58 Lieanxai
59 Houy No6
60 Nasavang No
Figure 1: SVK COM 10 subproject areamap
COM 10
COM 10
COM 10
Atsaphangthong
Outhoumphonh
Saiphouthong
16
3.1.2 Activities
There are four components of activities in the subproject. Component 1 is tosupport to business
operator or service providers; Component 2 supportestablishment of revolving funds for the
livestock raising for producer groups; Component 3: formation of producer groups of all 3600
targeted households and Component 4: provision for demonstrations of livestock raising.
The Component 1: Support to Business Support Service Providers (BSSP)is to:
1) Support existing Piglet Production Center for producing at least 2,000 piglets per year to
supply to 300 target beneficiaries and other producers HHs, 10 piglets per household.
2) Support establishing Piglet Production Center for producing at least 40,000 ducklings to
supply to 300 target beneficiaries and other producers HHs,30 ducklings per household.
3) Support establishingChick Production Center for producing at least 40,000 chicks to
supply to 300 target beneficiaries and other producers HHs,30 chicks per household.
4) Support establishingone Meat Processing Centerto process and package pig meat and
poultry
5) Support establishing Feed Processing Factory, minimum one to two tones per day. The
feed processing factory shall have to enter into agreement with maize farmers (whom the
project is supporting)
6) Support production of Maize, applies intercropping with pigeon peain 200 ha to supply as
raw material for animal feed processing center.
Component 2: Provision of revolving fund for livestock raising groups:
1) For purchase of piglets and feedfor 300 households, 30 Groups.
2) For purchase of ducklings and feedfor 1500 households, 150 Groups.
3) Revolving fund for purchase of native chicks and feedfor 1800 households ,180 Groups.
Component 3: Group Formation is to
Supportforming 3 producer groups in each village; Pig, Duck Raising and Chicken Raising
Groups. 30 Pig raising groupsfor 300 households, 150 Duck raising groups for 1500 households
and 180 Chicken raising groups for 1800 households.
Component 4: Demonstration of Livestock Raisinginclude establish:
1) 10 deep litter pig raising system (10 piglets)for 10 project villages
2) 20 Duck raising demonstration (20 ducklings)in each villages.
3) 20 Chicken raising demonstration (20 chicks) in each poorest Kumb Ban
17
3.1.3 Implementation Schedule
The subproject implementation will be started from January 2011 until December 2014by the
Division of Livestock and fisheries ofProvincial Agriculture and Forestry Offices, PAFO.Detail
time schedules of each activity are as in the table below.
Table 3: SVK Com 10 Subproject Implementation Schedule
No. Components 2011 2012 2013 2014
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
1 Support to establish piglet breeding
center
2 Support to establish the duckling
production center
3 Support to establish the Native chick
production center
4 Support to establish the Meat
Processing Center
5 Support to establish the Feed
Processing Factory
6 Support to production of maize with
intercropping with pigeon peas
7 Revolving fund for the purchase of
piglets and feeds
8 Revolving fund for the purchase of
ducklings and Feed
9 Revolving fund for the purchase of
native chicks and feed
10 Formation of Pig Raising Groups
11 Formation of Duck Raising Groups
12 Formation of Chick Raising Groups
13 Demonstration of Pig Raising using the
deep litter system
14 Demonstration of Duck Raising Groups
15 Demonstration of Chicken Raising
Groups
18
3.2 SVK PR 1Food Security and Poverty Reduction through Livestock in Savannakhet
This subproject aims at enhancing food security and poverty reduction through improved
agriculture and livestock raising in 568 households with 3,192 persons in 9 villages Kum Ban
Phabang of Sepone districts of Savannakhet Province. US$519,476 US$ will be invested for
this subproject. Of which US$ 494,976 is under SNRMPEP support and US$ 24,500 contributed
by Farmers.Savannakhet PAFO is the functional Executing agency; the DAFO Sepone and
Governor Office of Sepone district are implementing agencies. Details of the project are
described below.
3.2.1 Location
The subproject will be implemented in 9 villages of Kumb Ban Phabang of Sepone district.
Figure 2 and Table 4 shows the location and villages respectively.
Figure 2: SVK PR 1 subproject area map
PR 1
Sepon
19
Table 4: SVK PR 1 subproject targeted villages
S.No. Village
Code
Village Name Name of Kumban District
1 001 Ban Lousalia Kumban Phabang Sepone
2 002 Ban Tapong
3 004 Ban Sobsalou
4 006 Ban Kok
5 009 Ban Laveun
6 010 Ban Na
7 012 Ban Phabang
8 013 Ban Mai
9 015 Ban Namthone
3.2.2 Activities
There are 6main components in the subproject, the detailed of componentsare as follows:
Component 1: Land Use Planning and Land Allocation
Land use planning in 9 target villages of 1 Kumb Ban, soil analysis, issue of permanent land
certificate for target households, produce land use boundary maps for each target villages
Component 2: Improved Crop Productivity and stabilization of cultivation in upland area
1) Revolving fund for the improved upland Rice-Pigeon pea and other pulse crops based
farming and Zero Tillage Farming System for 450 ha in 9 target villages.50 ha increased
every year.
2) Revolving fund for the other commercial crops/trees cultivationfor 50 ha. 25 ha increased
every year.
3) Revolving fund for the intensive irrigated cultivationfor30 ha area planted under double
cropping system following appropriate crop rotation in Phabang Kumban
4) Establishment of nursery for the production of seedlings of commercial treewith production
capacity of 100,000 commercial tree seedlings under private sector.
Component 3: Livestock development
1) Development of pasture land for the cow and goat raising: 50 ha. Area planted under the
fodder crops like mulato, guinea and Napier grass
2) Revolving fund for the livestock raising: 50 household will raise 3 livestock for each with
improved management practices
3) Male livestock of improvement breed: 18 bulls of Red Sindhi will be provided to the cattle
raising groups, 2 bulls in each village
4) Revolving fund for the Goat raising: 100 families will raise 4 goat for each family with
improved management practices
20
5) Promotion of poultry raising: 100 families start compost making from the organic waste and
animal dung
6) Vaccination Revolving Fund for DAFO: DAFO have one functional vaccination storage and
supply center with refrigerator facilities
7) Cattle shade: Animal cage one for cattle raising group
8) Animal fodder storage: Cattle raising group have storage to give animal dry fodder
9) Bio gas: Cattle raising group have 2 units
Component 4: Construction of Gravity Irrigation Scheme
Survey, design and construct a100 ha Gravity Irrigation Scheme for 40 Householdin Phabang
village.
Component 5: Capacity Building
1) 3 TOTs for the Technical Staff for the upland agriculture and zero tillage farming system.
2) Training for the upland agriculture and zero tillage farming system for 390 farmers (30 from
each village).
3) Training on pasture land development, fodder tree plantation and management for farmers.
4) Training on cattle raising and health management for 50 households each year for 3 years.
5) Training on goat raising and health management for 100 households each year for 3 years.
6) Training onpoultry raising and health management for 100 households each year for 3 years.
7) Training for (2) Village Veterinary Workers on the livestock vaccination and basic training for
the animal disease treatment.
8) 3 trainingson the group fund management for Kumb Ban.
9) 6 trainingsfor WUG in Phabang village on the irrigation system management, water
distribution and judicious use of irrigation water for the crop production.
10) Need based trainings: 10 need based farmers training will be conducted depending upon the
prevailing training need.
Component 6: Farmers Contribution
1) Making 200 poultry cages using local material. Increase 50 households every year.
2) Development and maintenance of 50 ha pasture land.
3) Making 50 cattle shades using local material.
4) Labour for construction of irrigation schemes.
5) Management of 100 ha plantation of Yangbong, banana and black pepper.
3.1 SNK PR 1 Subproject Implementation Schedule
The subproject will start from December 1st, 2011 to December, 2014. Table below is detail
time schedule of each component of activity:
21
Table 5: SVK PR 1 subproject implementation schedule
Activities 2011 2012 2013 2014
Q 1
Q 2
Q 3
Q 4
Q 1
Q 2
Q 3
Q 4
Q 1
Q 2
Q 3
Q 4
Q 1
Q 2
Q 3
Q 4
Land Use Planning and Land Allocation
Land Use Planning in 9 target villages
Natural Resource Conservation Improved Crop Productivity and stabilization of cultivation in upland area Revolving fund for the improved upland Rice-Pigeon pea and other pulse crops based farming system and Zero Tillage Farming System Revolving fund for the other commercial crop/tree cultivation Revolving fund for the intensive irrigated cultivation Establishment of nursery for the production of seedlings of commercial tree
Livestock development Development of pasture land for the cow and goat raising
Revolving fund for the livestock raising
Male livestock of improvement breed
Revolving fund for the Goat raising
Male Goat of improved variety
Promotion of poultry raising
Compost making
Vaccination Revolving Fund for villages
Vaccination Revolving Fund for DAFO
Cattle shade
Animal fodder storage
Bio gas Construction of Gravity Irrigation Scheme Survey and design of Gravity Irrigation Scheme in Thaphing village Construction of Gravity Irrigation Scheme in Thaphing village
Capacity Building TOT for the Technical Staff for the upland agriculture and zero tillage farming system Farmers Training for the upland agriculture and zero tillage farming system Farmers training for the pasture land development and fodder tree plantation and management
22
Activities 2011 2012 2013 2014
Q 1
Q 2
Q 3
Q 4
Q 1
Q 2
Q 3
Q 4
Q 1
Q 2
Q 3
Q 4
Q 1
Q 2
Q 3
Q 4
Farmers training for the cattle raising and cattle health management Farmers training for the Goat raising and Goat health management Farmers training for the Poultry raising and Poultry health management Training of the Village Veterinary Workers for the livestock vaccination and basic training for the animal disease treatment Farmers training for the group fund management Training of WUG for the irrigation system management, water distribution and judicious use of irrigation water for the crop production
Need based trainings
Farmers Contribution Farmers Contribution for poultry raising to make the poultry cages using local material Farmers contribution for the pasture land development Farmers Contribution for Making cattle shade Farmers Contribution for Construction of Irrigation schemes Farmers Contribution for Plantation crop management
23
3.4 SAL COM 4: The Integrated Commercial Cultivation of Sweet Potato, Peanut and Banana Subproject in Lao Ngam district of Salavanh Province
The Integrated Commercial Cultivation of Sweet Potato, Peanut and Banana Subproject in Lao
Ngam district, Salavanh Province aims at development of the new variety crops production,
support the post harvest, processing, road linked with markets and value-adding technology of
sweet potatos, peanuts, bananas for the farmers; leading to improve livelihood and reduce
poverty for 1474 households with 7553 persons in 9 villages in the district. There are 6 main
components of activities defined for the subproject namely Component 1:Establishment of the
production & Processing group; Component 2: Land Use planning & Land Allocation;
Component 3: Establishment of Farm Mechanization Demonstration; Component 4: Revolving
Funds for the planting of the crops; Component 5: Establishment of processing Plant and
Component 6: Rural Access Road to production villages.
The subproject will implement from November 1st, 2011 to November, 2014 with total budget of
US$487,450.7553 persons in the five kumbans are expected to get direct benefits from the
subproject and thousands of people in the neighbor villages can benefit indirectly.Salavanh
PAFO is the functional Executing Agency, the Lao Ngam districts particularly DAFO is the direct
management agency.
This subproject, according to the screening, is classified as category B project and required for
Initial Environmental Examination (IEE) particularly road development. Therefore, following
description was focused on only road construction activity.
3.4.3 Location
As mentioned earlier, the proposed road construction is one of the subproject’s main activities in
Lao Ngam district, Salavanh Province. The proposed roadconnects road No. 20 which link
Pakse and Salavanh at Km 45 or Teme village and passes directly through 9 villages belong 5
Khum Ban. Those villages and Khum Ban are Ban Ngew, Ban Lane, Ban Teme, Ban Donedou,
Ban Nongkae, Ban Dongluang, Ban Dongsuang, Ban Dongban, Ban Vanpeuay. Figure 3 and 4
below shows the location of the subproject and road.
24
Figure 3:SAL COM 4 subproject area map
Figure 4: Arial map of the proposed road rehabilitation area
25
3.4.2 Road Construction
The existing road is 36.30 km long, road surface is 6.00-6.45m wide. There are currently 3 bridges and 25 culverts. In spite of an important alignment of the district, the road was upgraded 4 years ago and now is in poor state. Drainage capacity and road width are not sufficient. In rainy season, traffic is not so convenience, which negatively impacts on domestic and production aspects of local people in the sub-project area and neighboring areas. So Salavanh PAFO, Lao Ngam DAFO, villages and farmers in the villages asked for investment for update 3 km starting point at Teme Village (Km45+00) of the road No. 20 to Ngew Village. The road can assist farmers in subproject area for transportation sweet potato, banana, peanut and other production, agricultural input, especially there are 70 - 92 ha of sweet potato, 25 ha banana, 25 ha peanut nearby of road that will get direct benefit from the road for linked with markets.
Initially the proposed rural access road in the feasibility report was 3 km. Itslocation start from
Teme village at Km 45+00 of Provincial Road No.20 to the connect road to Khongsedone
district (Figure 1). It expected the road to be upgraded to asphalt road grade VI with 7m wide
road-way and 6 wide road surfaces in accordance with the design standard of road Ministry of
Communication and Transportation (MCT) of Lao PDR. The road mainly keeps the existing
alignment. Exceptionally, some sections are locally adjusted. Road-way is designed with
frequency 4% and loading capacity of 11 tons. It follows the elevation of the existing road-way to
minimize backfill volume.Sections Km0+00Km3+00 will constructed with asphalt layer in
accordance with the standard of MCT; 3cm thick. Sub-base is 20 cm thick macadam layer grade
1 above compacted aggregate soil layer K98.Particularly, road surface has never flooded and
will be constructed with asphalt grade 300, 22cm thick ballast 1x2 above aggregate sub-base
with 20cm thick macadam grade. The lower layer is 30cm thick compacted aggregate soil layer
K98.There are totally 25 culverts. Structures are mainly round culverts or concrete slab culverts.
Longitudinal drainage system is triangular earth canal with a dimension of 50x50x100cm. At
some sections with longitudinal slope of ≥ 6%, canal bed will be reinforced with 25 cm thick stone and concrete mortar.System of pickets, signs will be fully equipped to ensure traffic safety
in accordance with road sign regulation. At some backfilled positions with an elevation of ≥ 4m, curves and roads at both ends of bridges, reflective signs will be used. Total cost of road
improvement is US$ 300,000.
However, there were some changes to satisfy local demand and transport necessity, the
proposed road design was changed to 15 km of graveled road with same ROW on the existing
soil packed road. Quarry sites are on the areas along the road. Some sites are under villagers’ ownership but it is voluntarily dedicated to project and/or the quarry sites are converted to fish
pond for the villagers. No camp site and material stock area as the contractor office is in the area
and materials such as soil and gravel are stocked on the road side. Water from nearby river is
used for watering the road.
3.4.3 Implementation schedule
Overall, the subproject will be started from November 1st, 2011 to November, 2014. In which,
the construction of road duration is 24 months and it is estimated that the construction is started
in April 2012 and completed in March, 2014. Below are details about time schedule of each
activity.
26
Table 6: SAL COM 4 subproject implementation schedule
No. Activities 2011 2012 2013 2014
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
1 Establishment of Sweet Potato and
Peanut Production Group
2 Establishment of Peanut Production
Group
3 Establishment of Banana
Production Group
4 Land Use Planning & Land
Allocation
5 Tractor with 90 HP
6 Revolving Fund for the
Management of the Tractor
7 Revolving funds for the planting of
crops
8 Revolving fund for Processing of the
Banana, Peanut and Sweet potato
9 Establishment of Market information
System
10 Survey and design of Road
11 Construction of Road
3.5 SAL COM1: Irrigation Development in Khong Sedone District of Salavanh
The sub-project is to improve the livelihoods for 498 rice producing households in 12 villages of
Khong Sedone district by the adoption of a sustainable irrigation-based organic rice cultivation
farming system particularly through implementation of 5 main components of activities: (1)
Establishment of the Production Groups, (2) Land Use Planning and Land Allocation, (3)
Establishment of the demonstrations and revolving funds for the production, (4) Post Harvest
Processing & Establishment of the Market Information System, (5) Repair of 3 irrigation
schemes.
The subproject will be started from October 1st, 2011 to October, 2014 by PAFO Salavanh
which is the functional Implementation Agency and the Khong Sedone district DAFO which is
the direct management agencies. The toal cost is US$449,649 including training costs.
This subproject, according to the screening, is classified as category B project and required for
Initial Environmental Examination (IEE) particularly development of irrigation schemes.
Therefore, following description was focused on only irrigation schemes.
27
3.5.3 Location
As mentioned, the sub-project’s irrigation schemes located at 12 villages of Khong Sedone district. These villages lie along the Sedone River and National Road No. 13th South. Picture
and table below are the map and list of key villages that the irrigation schemes cover.
Figure 5: SAL COM 1 subproject area map
Table 7: SAL COM 1 subproject targeted villages
No Number and name of Kumb Bans Number and name of villages
Name Number Name
1 Tan Piao 1 Ban Tan Piao
Khamthong 3 1. Khamthong, 2. Donemuang 3. Hin Sieu,
Khong Sedone 4 1.Nahan, 2. Boulapha, 3. None Khor, 4.Bang Kang,
Keng Huat 2 1. Keng Khone, 2. Keng Huat
Tha Luang 2 1. Okart, 2 Nong Khulu
28
3.5.2 Irrigation schemes rehabilitation
The main works for rehabilitation are only repair of pump, the reconstruction of extension concrete canals of about 500 metres or replace earth canals, their associated tertiary canals and control gates. Existing pumps are more than 10 years old and required repair regular or yearly. The existing canals are earth canals which are also more than 10 years, broken and caused water leakage in number of places. Described below are current situation of each irrigation schemes.
1. Tanpiao Irrigation Scheme
This scheme is located in Tanpiao village. Currently 80 ha area is under irrigation by this
scheme. Total 51 households are using this scheme. This scheme is equipped with electric
pump and concrete canal of about 110 meters. Because of not well maintained, there is lot of
leakage of water resulting water logging on head area and shortage of water in tail end. There is
need to repair this scheme and the proposed rehabilitation of this irrigation scheme is to fix the
broken pump, canal and improvement of organization for rehabilitation and water use
mechanism.
2. Khamthong Irrigation Scheme This scheme is located in Khamthong village. Currently 100 ha area is under irrigation by this
scheme. Total 42 households are using this scheme.
This irrigation schemes was developed in 1997 and through improvement in the periods of 1981
to 1985 and 1991-1993. The development and improvement works were under government’s budget. dated This schemes is not well maintained, there is lot of leakage of water resulting
water logging on head area and shortage of water in tail end. There is need to repair this
scheme. The rehabilitation of the irrigation includes the construction of the concrete canal of 410
meters.
3. Beungkang and Khamthong Irrigation Scheme This scheme is located in Beungkang village. Currently 110 ha area is under irrigation by this
scheme. Total 50 households are using this scheme. This schemes is not well maintained,
there is lot of leakage of water resulting water logging on head area and shortage of water in tail
end. There is need to repair this scheme.
4. Kenghuat Irrigation Scheme This scheme is located in Kenghuat village. Currently 85 ha area is under irrigation by this
scheme. Total 50 households are using this scheme. This schemes is not well maintained,
there is lot of leakage of water resulting water logging on head area and shortage of water in tail
end. There is need to repair this scheme.
29
5. Nongkhulu Irrigation Scheme This scheme is located in Nongkhulu village. Currently 100 ha area is under irrigation by this
scheme. Total 26 households are using this scheme. This schemes is not well maintained,
there is lot of leakage of water resulting water logging on head area and shortage of water in tail
end. There is need to repair this scheme.
All irrigated rice production yields 4 t/ha for rice dry season and 3.5 t/ha for rice rainy season.
The total cost for irrigations system development is expected US$ 102,500.
3.5.3 Implementation schedule
Overall, the subproject will be started from October 1st, 2011 to October, 2014. Of which the proposed rehabilitation of irrigation is scheduled in 2012. Table 6 below is the implementation timeframe for each component of activities.
Table 8: SAL COM 1 subproject implementation schedule
June July Aug Sep Oct Nov Dec Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec Jan Feb Mar Apr May
1 Preparation of Sub-project
design & feasibility analysis
2 Form farmer production groups,
organic training, group leader
training
3 Train & mobilize district & Kumban crop extension
specialists
4 Establish Organic production
demonstrations in 6 villages
5 Train revolving fund managers,
disperse funds
6 Survey, design of irrigation canal
extensions
7 Organic rice produced and
certified on trial basis
8 Preparation of bidding plan,
selection of construction
contractors for irrig. Canal
9 Commencement - completion of
irrigation canal construction
10 Source & supply improved seed
variety& bio-fertilizer
11
Preparation of design, bidding
plan, selection of construction
contractors for processing plant
building
2011 2012 2013 2014
31
June July Aug Sep Oct Nov Dec Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec Jan Feb Mar Apr May 12 Identify organic rice market
13
Establish organic rice processing
plant ownership & management
structure
14 Procurement of organic rice
processing equipment
15 Operate organic rice grading & packaging plant
16 Continuing technical support to
organic farmers
17 Organic rice production contracts
to farmers
18 Production of organic rice on
commercial scale
19 Land use planning and title
certificates issued
20 M&E on-going
21 O&M of processing equipment
22 O&M of irrigation infrastructure
2011 2012 2013 2014
32
3.6 SALPR3:Promotion Commercialization ofLivestock in Salavanh
This subproject is to promote commercialization of livestock especially pig, poultry and fishery
with the use of Value Chain Approach which focused on enhancing producer groups and
business service providers in Salavanh, Wapi, Tumlan, Khonsedon districts; Salavanh province.
1950 households in 67 villages in these districts will embrace sustainable value chain; in which
producer groups are established and engaged with 6 business service providers who provide
inputs such as small livestock namely pigs, native ducks and chicken, and fish; processed feed
and buy back the livestock to process meat products for external markets.
Total budget of this subproject is 512,815. Of which is contributed by SNRMPEP 457,815 and
55,000 shared by the private companies. This subproject will be implemented by Division of
Livestock and Fisheries of Salavanh Provincial PAFO.Details of subproject location, activities
and schedule are as follows.
3.6.1 Location
The subproject will be implemented in the Salavanh, Wapi, Tumlan and Khongsedon districts of
the Salavanh province. The Figure 6 show the target villages in the map and numbers of
targeted villagers are was in the Table 8.
Figure 6: SAL PR 3 sub-project area map
33
Table 9: SAL PR 3 subproject targeted villages
No Village name Kumb Ban District
Sub-Sector: Fishery Total target HH in 3 years: 450
1 Nakoisao Nakoisao
Salavanh
2 Nalath
3 Soung Viengkham
4 Phao
5 Thuongnakham Beungkharm
6 Charn Tai
7 Phakpheoset Beungxai
8 Napholeune
9 Nadornkhuang Naphaeng Nhai
10 Naphaeng Nhai
11 Maed Souliya Wapi
12 Muangvernkham Banlaoh
13 Dindark Kalaeng Tumlan
14 Nongkaxorng Khong Nhai Khongsedon
15 Natarnse Kaengkhon
Sub-Sector: Pig Raising Total target HH in 3 years: 300
1 Nakoinsao Nakhoinsao
Salavanh 2 Naxai Noin Naxai Noin
3 Naxai Nhai
4 Beungxai Beungxai
5 Samia Souliya
Wapi 6 Nongphoh
7 Wapi Neua Wapi
8 Hinsew Khamthong
Khongsedon 9 Namouang Nhai Namouang
10 Napong Napong
Sub-Sector: Duck Raising Total target HH in 3 years: 450
1 Koh Viengkham
Salavanh
Kuay
Thuongnakham Beungkharm
Nongmor Beungsay
Beungsay Neua
2 Banlaoh Banlaoh
Wapi
Kangsouthi
Saphah
Bangkhanam Wapi
Huaykhon
3 Hinsew Khamthong Khongsedon
34
No Village name Kumb Ban District
Nonsamlarn
Nongkhuluh
Khok Hinkong Nanuong
Hatdoo Kaenghuat
Sub-Sector: Native Chicken Poultry Total target HH in 3 years: 900
1 Nathoun Nhai Nakhoisao
Salavanh
2 Thathuay
3 DongNong
4 Laengkaoh Naxai Noin
5 Songkalong
6 Kaengkavaoh
7 Thameuangkaoh Naphaeng Nhai
8 Saokadee
9 Khornlath
10 Phon Ngarm Kalaeng
Tumlarn
11 Samakheexay
12 Kaenghang
13 Kokmuang Kokmuang
14 Tabaeng
15 Huaylai Tumlarn
16 Nalacharng
17 Naphontarn Banlaoh
Wapi
18 Nahuahaed
19 Khornsay Khornsay
20 Dornkhaa
21 Khanaoh Naxiat
22 Naxiat
23 Thuongkhian
24 Dinkork Napuong
Khongsedon
25 Koodmyxay
26 Natarndong Namek
27 Namek
28 Nateuay
29 Eleung Namuang
30 Khok Huaxarng
35
3.6.2 Activities
This subproject has four components of activities like the SVK COM4. Component 1 is to
support to business service providers; Component 2 support establishment of revolving funds
for the livestock raising for producer groups; Component 3: formation of producer groups of all
3600 targeted households and Component 4: provision for demonstrations of livestock raising.
Component 1: Support to Business Support Service Providers (BSSP):
1) Establishing the Piglet Production Center can produce and supply at least 2,000 piglets
per year for 300 target beneficiaries (10 piglets per household).
2) 2 functional public and private fish hatcheries which can produce and supply 2 million fish
fingerlings per year for 450 target beneficiaries. One of the fish hatcheries shall be set up
by the Nong Deng Technical Center andthe fish varieties are common carp, cat fish,
tilapia and other varieties of carp.
3) Establishing the Duckling Production Center which can produce and supply at least
40,000 ducklings for450 target beneficiaries (30 ducklings per household).
4) Establishing the Chick Production Center for producing and supplying at least 40,000
chicksfor900 target beneficiaries (30 chicks per household).
5) Establishing one Meat Processing Center to process and package pig meat and poultry.
6) Establishing the Feed Processing Factory, minimum one to two tones per day. (The feed
processing factory shall engage with maize farmers whom the project is supporting).
7) Supporting 60 groups of farmers to produce maize with intercropping with pigeon pea in
100-200 ha to supply as raw material for animal feed processing center.
Component 2: Provision of revolving fund for livestock raising particularly:
1) For the purchase piglets and feed for 300 households organised into 30 Groups.
2) For the purchase ducklings and feed for 450 households organised into 45 Groups.
3) For the purchase fish fingerlings and feedfor 450 households organised into 45 Groups.
4) For purchase native chicks and feed for 900 households organised into 90 Groups.
Component 3: Group Formation
1) 30 Pig raising groups (300 hhs), 45 Fish raising groups (450 hhs), 45Duck raising
groups (450 hhs) and 90 Chicken raising groups (900 hhs) shall be established.
2) 60 farmer groups for maize and pigeon pea integrated cropping for 200 ha/year promoted.
Component 4: Demonstration of Livestock Raising
1) 10 deep litter pig raising system (10 piglets) demonstrated in 10 project villages
2) 23 Fish raising sites (1000 fingerlings of all the 5 native varieties) demonstrated in 23
different villages.
3) 40 Duck raising sites (20 ducklings each) demonstrated in each of the target villages.
36
4) 50 Chicken raising sites (20 chicks each) demonstrated each of the poorest Kumb Ban
3.6.3 Implementation schedule
The Sub-Project will be started from 1st November 2011 to October 2014 in which the time
period to support in establishing service providers is 36 months. Details of activities are as
shown in the table below.
Table 10: SAL PR 3 implementation schedule
No
Components 2011 2012 2013 2014
Q4 Q
1
Q
2
Q
3
Q
4
Q
1
Q
2
Q
3
Q
4
Q
1
Q
2
Q
3
Q
4
1 Support to establish piglet breeding center
2 Support to improve the fish hatchery
3 Support to establish the duckling production center
4 Support to establish the Native chick production center
5 Support to establish the Meat Processing Center
6 Support to establish the Feed Processing Factory
7 Support to production of maize with intercropping with
pigeon peas
8 Revolving fund for the purchase of piglets and feeds
9 Revolving fund for the purchase of Fish fingerlings and feed
10 Revolving fund for the purchase of ducklings and Feed
11 Revolving fund for the purchase of native chicks and feed
12 Formation of Pig Raising Groups
13 Formation of Fish Raising Groups
14 Formation of Duck Raising Groups
15 Formation of Chick Raising Groups
16 Formation of maize and pigeon pea group
17 Demonstration of Pig Raising using the deep litter system
18 Demonstration of Fish Raising Groups
19 Demonstration of Duck Raising Groups
20 Demonstration of Chicken Raising Groups
37
3.7 CPA COM 9: Promotion Commercialization of Small Livestock in Champasak
This subproject promote commercialization of poultry, fishery and frog hatchery with Value
Chain Approach by promoting producer groups and business service providers in 79villages in 9
distircts (Bachieng, Champasak, Khong, Pakse, Phonethong, Sanasomboun, Sukhuma,
Munlapamok and Pathumphone) of Champasak province by:
Creating sustainable value chain for small livestock and meat especially financial,
technological support and market linkage to 3020 households in the 79 villages.
Formation of producer groups healthy livestock rearing and engage with promoted 5
business service providers who can supply small livestock (native ducks, Fishes, Frogs
and chicken); purchase back, processed feed and processed meat products for external
markets.
The Division of Livestock and fisheries is the functional Implementation agency, Champasak
PAFO is the management and O&M agency. The implementation will be started from 1st
January 2012 to December 2014 with total investment of US$ 601,945. Details of subproject
location, activities and implementing schedule are described below.
3.7.1 Location
The subproject will be implemented in the Bachieng, Champasak, Khong, Pakse, Phonethong,
Sanasomboun, Sukhuma, Munlapamok and Pathumphone districts of Champasak province,
Lao PDR. The subproject site and targeted villages are presented in the Figure 8 and Table 9
respectively.
Figure 7: CAP COM 9 subproject area map
38
Table 11: CPA COM 9 subproject targeted villages
No Village name District
Sub-Sector: Fishery
1 1. Lak 20
Pathumphone
2. Lak 25
3. Ban Muang
4. Lak 30
5. Huayphay
6. Nongbuanoi
7. NongbuaNgai
8. Tomotha
9. Pathumphone
2
1. Boungkeo
Sukhuma
2. Kongkian
3. Bark
4. Samkham Thadsampang
5. Nongphanvong
6. Nonghuaban
7. Hae
8. Hauylek
9. Paksang
3
1. Ban Mai
Munlapamok
2. Luangsok
3. Pamok
4. Veunkhaen
5. SaphangNgai
6. HuayNgang
7. Nadi
8. Sanwa
9. Salaosong
10. Veun
4 1. Thahai
Pakse 2. Nonesawang
Sub-Sector: Duck Raising
1 1. Donekhor
Pakse 2. HuayNgangkham
3. Ban Kang
2
1. Nonesawanh
Sanasomboum 2. Boungkha
3. Paksone
3
1. Wathor
Phonethong 2. Thaluang
3. Phonethong
4. Phoxai
4
1. Lak 18
Bachieng 2. Kaengchia
3. Nongkok
5
1. Lak16
Pathumphone 2. Xiengwang
3. Boungkham
39
No Village name District
4. KhoneNoi
6
1. Somhong
Champasak 2. Thatan
3. Nongpham
7
1. Donghuaban
Sukhuma 2. Thaseng
3. Pakuay
4. Boungkeo
8
1. Donepeay
Munlapamok 2. Donenangloi
3. Thahae
9
1. Boung
Khong 2. Hadsaikhoun
3. Kadan
Sub-Sector: Chicken Raising
1 1. Nonesawang
Pakse
2. Xongxe
3. Chadsan
4. Nachieng
5. Dongkalong
6. Phonesikhai
7. Hauylao
8. PhoneGnam
9. Nonedou
10. Hae
2
1. Huayten
Bachieng
2. Pakhuaydeua
3. Nongsai
4. NongbokNgai
5. Lomsaktai
6. Oudomsouk
7. Nonesai
8. Kaeng Ngao
9. Kaengchia
10. Nongkok
3
1. Lak 40
Pathumphone
2. Pathumphone
3. Boungkham
4. Huaymaesang
5. Tomotha
6. Lak 48
7. Paktuay
8. Nongbuanoi
9. Huayphay
10. Muang
40
3.7.2 Activities
This subproject has four components of activities like the SVK COM4 and SAL PR 3.
Component 1 is to support to business service providers; Component 2 support establishment
of revolving funds for the livestock raising for producer groups; Component 3: formation of
producer groups of all 3020 targeted households and Component 4: provision for
demonstrations of livestock raising.
Support to Business Support Service Providers (BSSP) includes:
1) Providing financial support 1 public and 1 private center for purchase of fish seeds, fish
and feed, installation of the sterilization facility which can produce 1 million fish fingerlings
per year for 450 targeted HHs of the subproject.
2) Establishing the ducklings Production Center for producing at least 40,000 ducklings to
supply to 900 target beneficiaries (30 ducklings per household).
3) Establishing the Chick Production Center for producing at least 40,000 chicks to supply to
900 target beneficiaries (30 chicks per household).
4) Establishing3Goat and Sheep production center for producing 2,000 goats and
lambs/kids for 300 target HHs (10 goat or lambs/kids per HH).
Provision of revolving fund for livestock raisingparticularly:
1) For the purchase fish fingerlings and feed for 900 households (90 groups, average 10
members per group) including fund for 60 households (6 groups).
2) For the purchase ducklings and feed for 900 households organised (90groups).
3) For purchase native chicks and feed for 900 households (90groups).
Group Formation includes:
1) 30 goats/sheep raising groups (300 households).
2) 90 fish raising groups for pond fishery and 6 for cage fishing (900 and 60 households
respectively).
3) 90 duck raising groups (900 households).
4) 90 chicken raising groups (900 households).
Demonstration of Livestock Raising includes:
1) 10 goat/sheep demosites (10 kids/lambs) demonstrated in each village.
2) 10 frog raising demo sites in rice fields, 1site for each village.
3) 10 duck raising demo sites (20 ducklings) demonstrated each village.
4) 10 chicken raising sites (20 chicks) demonstrated in each village.
3.1 Implementation schedule
Overall, the implementation will be started from 1st January 2012 to December 2014. In which, each activity will be implemented in different time as show in the table below.
41
Table 12: CPA COM 9 subproject implementation schedule
No. Components 20
11
2012 2013 2014
Q4 Q
1
Q
2
Q
3
Q
4
Q
1
Q
2
Q
3
Q
4
Q
1
Q
2
Q
3
Q
4
1 Support to improve the Government Fish & Frog
Hatchery in government sector
2 Support to improve Fish and Frog Hatchery in the
Private sector
3 Support to establish the duckling production center
4 Support to establish the Native chick production center
5 Support to establish the Goat & Sheep breeding
Center under private sector
6 Revolving fund for the purchase of Fish fingerlings and
feed for Pond Fishery
7 Support for practicing cage fishing
8 Revolving fund for the purchase of ducklings and Feed
9 Revolving fund for the purchase of native chicks and
feed
10 Revolving fund for the purchase of goat
11 Formation of Goat Raising Groups
12 Formation of Fish Raising Groups
13 Formation of Duck Raising Groups
1 Formation of Chick Raising Groups
15 Demonstration of Goat and Sheep raising
16 Demonstration of Frog raising in rice fields
17 Demonstration of Duck Raising Groups
18 Demonstration of Chicken Raising Groups
3.8 CPA COM 10: Promotion Commercialization of Pig Farmingin Champasak
This subproject promotes commercialization of pig raising and feed production with the use of
Value Chain Approach especially enhancing linkage between producers groups of 300
households and 4 business service providers in 11 villages of Bachieng, Champasak, Khong,
Pakse, Sanasomboun, Sukhuma, Munlapamok and Pathumphone districts of Champasak
province. US$ 410,375 will be invested to this subproject which will be commenced on
1stNovember 2011and last until October 2014 by Division of Livestock and fisheries of
Champasak PAFO. Details of project location, activities and implementing schedule are described
below.
42
3.8.1 Location
As mentioned, the subproject will be implemented in 11 villagesof the Bachieng, Champasak,
Khong, Pakse, Sanasomboun, Sukhuma, Munlapamok and Pathumphone districts of
Champasak province. The maps and targeted villages are as in the Figure 9 and Table 11
below.
Figure 8: CAP COM 10 subproject area map-pig raising
Table 13: CPA COM 10 subprojecttargeted villages-pig raising
No Village name District
1 1. BounNgaie Pathumphone
2 1. Sukhuma Sukhuma
3 1. Pamok Munlapamok
4 1. Nahaek Pakse
5 1. Huaxae Bachieng
2. Kaeng Ngao
6 1. Boungkha Sanasomboun
1. Slonoi
7 1. Watsai Champasak
2. Phosai
8 1. Phiangdi Khong
43
3.8.2 Activities
There are four components of activities under this subproject like the CPA COM 9. Component
1 is to support to business service providers; Component 2 support establishment of revolving
funds for the livestock raising for producer groups; Component 3: formation of producer groups
of all 3020 targeted households and Component 4: provision for demonstrations of livestock
raising.
Support to Business Support Service Providers (BSSP):
1) Establishing the Piglet Production Center for producing at least 40,000 piglets to supply to
900 target beneficiaries (30piglets per household).
2) Establishing a feed processing factory to produce pig feed, fish and poultry feed per year
to supply to 3300 HHs.
3) Establishing a meat processing center to process and package pig meat, poultry and fish.
4) Support maize production with intercropping with pigeon pea for 200ha/year.
Provision of revolving fund for livestock raisingparticularlyfor the purchase of piglets and feed for 300 households (30 groups, average 10 members per group).
Group Formation includes:
1) Formation of 30 pig raising groups (300 households).
2) Formation of 60 farmer groups to grow 200 ha/year of maize.
Demonstration of Livestock Raising includes:
1) 18 Pig raising sites using the deep litter system (10 piglets) demonstrated.
2) 10 bio-gas systems for pig farms demonstrated in each village.
3.8.3 Implementation schedule
Overall, the implementation will be will be commenced on 1stNovember 2011and last until October 2014. In which, each activity will be implemented in different time as show in the table below.
Table 14: CPA COM 10 implementation schedule
No Components 2011 2012 2013 2014
Q4 Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
1 Support to establish piglet breeding center
2 Support to establish the feed processing factory
3 Support to establish the meat processing factory
4 Support to Production of Maize with intercropping with pigeon pea
5 Revolving fund for the purchase of piglets and feed
6 Formation of Pig Raising Groups
44
No Components 2011 2012 2013 2014
Q4 Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
7 Formation of maize and pigeon pea group
8 Demonstration of Pigs raising system using the deep litter system
9 Demonstration for Bio gas
3.9 SEK COM 4: Promotion Commercialization of Livestock in Sekong
This subproject promotes commercial pig raising, poultry and fishery with Value Chain Approach
by enhancing linkage between producer group 1950 of households and 6 business service
providers in 50 villages in Thateng and Lamam districts, Sekong province. US$ 551,860 will be
invested for implementation of this Sub-Project for the period 1stNovember 2011 to October
2014. It is managed by the Division of Livestock and fisheries but under Sekong PAFO’s supervision.
3.9.1 Location
As mentioned, the Sub-Project located in two district of Sekong province namely Lamam and
Thateng with targeting producer group comprising of 1950 of households and 6 business
service providers in 50 villages in those districts. Figure 9 and Table 14 below show the details
of location and villages.
Figure 9: SEK COM 4 subproject area map
45
Table 15: SEK COM 4 subproject targeted villages
No Village name Kumb Ban District Fish pond
area (Ha)
Number of HHs Population
Sub-Sector: Fishery Total target HH in 3 years: 450
1 Ban Danh Danh-Dornchan Lamam 0.8 30 170
2 Ban Dornchanh Danh-Dornchan Lamam 0.9 30 175
3 Ban Mo Danh-Dornchan Lamam 1.5 30 182
4 Ban Pholn Ban Pholn Lamam 1.0 30 190
5 Ban Beng Ban Pholn Lamam 1.0 30 170
6 Ban Tiew Ban Pholn Lamam 1.2 30 180
7 Ban Nongbong Ban Pholn Lamam 0.8 30 182
8 Ban Nolnongwah Ban Pholn Lamam 0.7 30 182
9 Ban Huaixye Tadsaban Thateng 0.7 30 170
10 Ban Huaxe Tadsaban Thateng 0.7 30 185
11 Ban Thateng Tai Tadsaban Thateng 1.8 30 200
12 Ban Kapue Ban Kapue Thateng 1.0 30 190
13 Ban Joonla Ban JakamGnai Thateng 1.0 30 180
14 Ban Kandorn Ban JakamGnai Thateng 0.85 30 160
15 Ban Palay Ban JakamGnai Thateng 0.75 30 185
Total 14.70 450 2,701
Sub-Sector: Pig Raising Total target HH in 3 years:300
1 Ban Parktoln Ban Danh-Dornchan Lamam 30 30 180
2 Ban HongLay Ban Pholn Lamam 33 30 170
3 Ban Huaikiew Ban Pholn Lamam 35 30 175
4 Ban PholKham Wadluang Lamam 38 30 185
5 Ban Nolmixay Wadluang Lamam 30 30 155
6 Ban Phiamay Wadluang Lamam 34 30 182
7 Ban ThatengNeua Tadsaban Thateng 32 30 185
8 Ban Kontagnounh Tadsaban Thateng 30 30 180
9 Ban Joonla Ban JakamGnai Thateng 31 30 190
10 Ban Kapue Kapue Thateng 30 30 185
Total 323 300 1,787
Sub-Sector: Duck raising Total target HH in 3 years: 450
1 Ban Mayhuameung Wadluang Lamam 230 30 180
2 Ban Thaluang Wadluang Lamam 220 30 185
3 Ban Xenamnoi Danh-Dornchanh Lamam 250 30 175
4 Ban Lavilamphan Danh-Dornchanh Lamam 180 30 170
46
No Village name Kumb Ban District Fish pond
area (Ha)
Number of HHs Population
Sub-Sector: Fishery Total target HH in 3 years: 450
5 Ban Lavinoi Danh-Dornchanh Lamam 155 30 165
6 Ban songkhone Ban Parkpoon Lamam 150 30 175
7 Ban Kengluang Ban Parkpoon Lamam 160 30 180
8 Yorkthong Ban JakamGnai Thateng 130 30 160
9 Ban Kamkork Ban JakamGnai Thateng 140 30 175
10 Ban Yibmai Ban JakamGnai Thateng 135 30 165
11 Ban Nolsamphan Ban JakamGnai Thateng 143 30 170
12 Ban JakamGnai Ban JakamGnai Thateng 145 30 173
13 Ban Lakaow Tadsaban Thateng 150 30 145
14 Ban Palye Ban Palye Thateng 140 30 160
15 Ban Meuenkang Ban Palye Thateng 135 30 165
Total 2,463 450 2,543
Sub-Sector: Native Chicken Poultry Total target HH in 3 years: 450
1 Ban Lavi Ban Danh-Dornchan Lamam 150 30 170
2 Ban Lavifandeng Ban Danh-Dornchan Lamam 140 30 165
3 Ban Torksaming Ban Pholn Lamam 160 30 175
4 Ban Kengluang Ban Parkpoon Lamam 140 30 160
5 Ban Parkagnong Ban Parkpoon Lamam 152 30 180
6 Ban Parkpoon Ban Parkpoon Lamam 155 30 178
7 Ban Nang Yong Ban Parkpoon Lamam 150 30 168
8 Ban Kasankang Ban Kasankang Lamam 145 30 173
9 Ban Wangsang Ban Kasankang Lamam 137 30 160
10 Ban Kokhai Ban JakamGnai Thateng 160 30 170
11 Ban Kapue Ban Kapue Thateng 164 30 175
12 Ban Nongnok Ban Kapue Thateng 150 30 162
13 Ban Nongbuasai Thedsaban Thateng 160 30 165
14 Ban NongbuaNeu Thedsaban Thateng 150 30 168
15 Ban Nongbua Tai Thedsaban Thateng 163 30 173
Total 2,276 450 2,542
3.9.2 Activities
The Sub-Project implemented will cover 50 villages in Thateng and Lamam districts of Sekong
Province of Laos PDR. There are four components in the Sub-Project which include:
Component 1: Support to 6 business service providers; Component 2: Setting up of revolving
Funds for the livestock raising to producer groups; Component 3: Formation of Producer
47
Groups of all 1950 targeted households and Component 4: Provision for 4 demonstrations of
Livestock Raising in 6 Poorest Kumb Bans.
Support to Business Support Service Providers (BSSP) includes:
1) Support to establish the Piglet Production Center for producing at least 2,000 piglets to
supply to 300 target beneficiaries and other producers HHs,10 piglets per household.
2) 1 public fish hatchery with capacity of producing 2 million fish fingerlings per year to
supply to 450 target beneficiaries and other producers HHs.
3) 1 functional duckling production center with duckling production capacity of 40,000
ducklings benefiting 450 target beneficiaries and other producers HHs.
4) 1 functional Native Chick Production center with production capacity of 40,000 chicks
benefiting 450 target beneficiaries and other producers HHs.
5) 1 functional meat processing center, under private sector to process and package pig
meat, poultry and fish.
6) 1 functional Feed Production Center under private sector to produce pig feed, fish and
poultry feed.
7) Support group of farmers to grow maize with intercropping of pigeon pea in 100 ha to
supply as raw material for animal feed processing.
Provision of revolving fund for livestock raising for 300 households organized into 30 pig raising groups, 450 households organized into 45 duck raiding groups, 450 households organized into 45 fish and 450 households organized into 45 chicken raising groups.
Group Formation includes: 30 Pig raising groups covering 300 households, 45 Fish raising groups covering 450 households, 45 Duck raising groups covering 450 households, 45 Chicken raising covering 450 households and 30 maize grower groups for growing 100 ha/year of maize and other integrated crops. Demonstration of Livestock Raising includes:
1) 6 Pig deep litter raising system (10 piglets) demonstrated in 6 project villages of 6 different
Kumb Bans.
2) 6 Fish raising sites(1000 fingerlings and 5 native varieties) demonstrated in 6 different
villages
3) 6 Duck raising sites (20 ducklings) demonstrated each of the target villages.
4) 6 Chicken raising sites (20 chicks) demonstrated in each of the poorest Kumb Ban
3.9.3 Implementation Schedule
The implementation will be commenced on 1stNovember 2011and last until October 2014. The implementing timing of activities is as follow:
Table 16: SEK COM 4 implementation schdule
48
No Components 2011 2012 2013 2014
Q4 Q
1
Q
2
Q
3
Q
4
Q
1
Q
2
Q
3
Q
4
Q
1
Q
2
Q
3
Q
4
1 Support to establish piglet breeding center
2 Support to improve the fish hatchery
3 Support to establish the duckling production center
4 Support to establish the Native chick production
center
5 Support to establish the Meat Processing Center
6 Support to establish the Feed Processing Factory
7 Support to production of maize with intercropping
with pigeon peas
8 Revolving fund for the purchase of piglets and
feeds
5 Revolving fund for the purchase of Fish fingerlings
and feed
6 Revolving fund for the purchase of ducklings and
Feed
7 Revolving fund for the purchase of native chicks
and feed
8 Formation of Pig Raising Groups
9 Formation of Fish Raising Groups
9 Formation of Duck Raising Groups
10 Formation of Chick Raising Groups
11 Formation of maize and pigeon pea group
10 Demonstration of Pig Raising using the deep litter
system
10 Demonstration of Fish Raising Groups
11 Demonstration of Duck Raising Groups
12 Demonstration of Chicken Raising Groups
3.10 ATT COM 1: Promotion Commercialization of Livestock in Attapeu
This subproject is intended to promote commercial pig raising, poultry and fishery with
application of Value Chain Approach especially enhancing business linkage between producer
groups of 2170 households in 53 villages and business 7 service providers who supply of litters
of small livestock (pigs, native ducks and chicken, goats and fish), processed feed and
processed meat products for external markets in Sanamxai, Samakhixai, Xaysettha, Xanxay
and Phovong districts; Attapeu province.
US$ 784,125 will be invested to complete such activities and from January 2012 to December
2014. The Division of Livestock and fisheries is the functional Implementation agency, Attapeu
PAFO is the management these activities with coordination with PCO and relevant sectors in
the provinces, district and village level. Below are details about location, activities and
implementing timeframe.
49
3.10.1 Location
As stated above, the subproject will be implemented in the Samakhixai, Xaysettha, Sanamxay,
Sanxay and Phouvong districts of Attapeu province. Figure 11 and Table 14 below are details
of map and list of villages under this subproject.
The subproject covers 53 villages in Samakhixai, Xaysettha, Sanamxay, Sanxay and Phouvong
in Attapeu Province of Laos PDR. Currently the village identification has been done for three
years whereas the target households have been identified for 1st year. Other target households
shall be subsequently identified in the second year.
Figure 10: ATT COM 1 subproject area map
Table 17: ATT COM 1 subproject villages
No Village name Kumb Ban District
Fishery Total target HH in 3 years:450
1 Viengxay Namkong Phouvong
2 Kang Vongsamphanh Phouvong
3 Naxueak Khamvongsa Phouvong
4 Somboun NamPa Xanxay
5 Houaysamong Hin Sanamxay
50
No Village name Kumb Ban District
6
Banxay
Vatlouang
Fangdeang
Kaeng Nhai
Phoxay
Phoxay
Phoxay
Phoxay
Saysettha
7
Ban Hom
Vatlouang
Sekamane
Samakkhi
Ban Hom
Thetsaban
Sekamane
Thetsaban
Samakkhixay
Pig Raising Total target HH in 3 years:240
1
Palai
Viengxay
Kang
Naxeuak
Vongsamphanh
Namkong
Vongsamphan
Khamvongsa
Phouvong
2
Donephay
Thahintay
Ban May
Ban Mitsamphanh
BAN Thae
Donesoung
Hinlat
Hinlat
Ban nhay mitsamphan
Ban Thae
Lamam
3
Kaeng nhay
Ban xay
Khanmakong
Ban xaysy
Phoxay Saysettha
4
Sekamane
Sisomphone
Ban Lanhao
Sayphosy
Ban Moun
Dakkiad
Somboun
Phiakeo
Sekamane
Ban Hom
Ban lanhao
Ban xok
Samakkhixay
Duck raising Total target HH in 3 years:600
1 Tamayod
Hinlat
Samong
Pindong
Donephay
Hinlat
Hinlat
Hinlat
Hinlat
Donesoung
Sanamxay
2 Phouxay
Dakhiad
Vangsay
Nampa
Nampa
Nampa
Xanxay
3 Dakyiang Phameuang Saysettha
51
No Village name Kumb Ban District
Daktoud
Vatneua
Vathhat
Vat Louang
Phameuang
Phameuang
Phameuang
Phameuang
4 Sekamane
Lanhao
Sisomphone
Sekamane
Lanhao
Ban Hom
Samakkhixay
5 Ban Viengxay
Ban Phouxay
Ban Kang
Ban Naxeuak
Ban Palai
Namkong
Namkong
Vongsamphanh
Khamvongsa
Vongsamphanh
Phouvong
Chicken Poultry Total target HH in 3 years:900
1
Sekamane
Lanhao
Sisomphone
Saphaothong
Sayphosy
Sekamane
Lanhao
Ban Hom
Thetsaban
Ban xok
Samakkhixay
2
Kaengnhay
Xaysy
Hatsaty
Sakhae
Phoxay
Phoxay
Phonengam
Phonngam
Saysettha
3 Donephay Donesoung Sanamxay
4
Thahintay
Pindong
Thasengchanh
Hinlat
Hinlat
Hinlat
Sanamxay
5
Phiakeo
Somboun
Donekhaen
Hindanh
Vangxay
Phouxay
Nampa
Nampa
Nampa
Nampa
Nampa
Nampa
Xanxay
6
Viengsay
Ban Kang
Naxeuak
Namkong
Vongsamphanh
Khamvongsa
Phouvong
Phouvong
Goat Raising Total target HH in 3 years:100
1 Namxuan
Viengsay
Somboun
Namkong
Phouvong
Phouvong
52
No Village name Kumb Ban District
2
Kanhu
Konghang
Xayphosy
Lanhao
Lanhao
Ban xok
Samakkhixay
3 Ban Chaleunxay Nam su Xanxay
4 Ban Donephay Donesoung Sanamxay
5 Ban daktoud
Ban Nhay Oudom
Phameuang
Ban Nhay Oudom Saysettha
3.10.2 Activities
There are four components of activities in the subproject namely (1) Component 1: Support to
business service providers; (2) Component 2: Setting up of revolving Funds for the livestock
raising to producer groups; (3) Component 3: Formation of Producer Groups of all 2170
targeted households and (4) Component 4: Provision for demonstrations of Livestock Raising.
Support to Business Support Service Providers (BSSP) includes:
1) Support to establish the Piglet Production Center for producing at least 2,000 piglets to
supply to 240 target beneficiaries (10 piglets per household).
2) 1 public fish hatchery with capacity of producing 2 million fish fingerlings per year to
supply to 450 target beneficiaries.
3) 1 functional duckling production center with duckling production capacity of 40,000
ducklings benefiting 600 target beneficiaries.
4) 1 functional Native Chick Production center with production capacity of 40,000 chicks
benefiting 900 target beneficiaries.
5) 1 functional goat breeding center with capacity of 3,000 goat kids per year to supply to
300 target beneficiaries.
6) 1 functional meat processing center, under private sector to process and package pig
meat, poultry and fish.
7) 1 functional Feed Production Center under private sector to produce pig feed, fish and
poultry feed.
8) Support group of farmers to grow maize with intercropping of pigeon pea in 100 ha to
supply as raw material for animal feed processing.
Provision of revolving fund for livestock raising:
- For 300 households (30 pig raising groups), 450 households (45 duck raiding groups), 450 households (45 fish groups) and 450 households (45 chicken raising groups).
Group Formation includes:
- 24 Pig raising groups (240 households), 45 Fish raising groups (450 households), 60
Duck raising groups (600 households), 90 Chicken raising (900 households), 30 goat
53
raising (300 households) and 30 maize grower groups for growing 100 ha/year of maize
and other integrated crops.
Demonstration of Livestock Raising includes:
1) 10 Pig deep litter raising system (10 piglets) demonstrated in each village
2) 10 Fish raising (1000 fingerlings and 5 native varieties) demonstrated in 10 different
villages
3) 10 Duck raising sites (20 ducklings) demonstrated each village.
4) 10 Chicken raising sites (20 chicks) demonstrated in each of the poorest Kumb Ban
5) 10 Goat raising sites (10 goats kids) demonstrated in 10 villages of 10 different Kumb
Bans.
3.10.3 Implementation schedule
Overall, the implementation will be will be commenced on 1stNovember 2011and last until October 2014. In which, each activity will be implemented in different time as show in the table below.
Table 18: ATT COM 1 implementation schedule
No. Activities Indicators Work Partners Time frame
From To
A Support to Establish Service Providers
1
Support to Establish the Piglet Breeding Center
1 functional pig breeding center under private sector with capacity of 2,000 piglets per year to supply to 240 producers HHs.
Private Sector, farmers, Provincial and District Extension Center
Nov-11 Oct-12
2 Support to improve the Fish Hatchery
1 functional fish hatchery under private sector with capacity of producing 2 million fish fingerlings per year to supply to 450 HHs as direct beneficiaries and others as indirect. The breeds to be promoted are local and sterilized (Paa Pak, Pa Nae, Panin, Paduk, Pakin Nya)
Private Sector, farmers, Provincial and District Extension Center
Nov-11 Oct-12
3
Support to establish the duckling production center
1 functional duckling production center under private sector with duckling production capacity of 40,000 ducklings benefiting 600 direct househols and other indirect beneficiaries per year. 50% of the ducklings produced will be meat variety and 50% egg laying variety. Native ducks with good productivity shall be promoted.
Private Sector, farmers, Provincial and District Extension Center
Nov-11 Oct-12
4
Support to establish the Native chick production center
1 functional Native Chick Production center under private sector with production capacity of 40,000 chicks benefiting 900 direct households and other indirect beneficiaries per year. 100% of the chicks produced will be of meat variety. Native chicks with good productivity shall be promoted.
Private Sector, farmers, Provincial and District Extension Center
Nov-11 Oct-12
5
Support to establish the Goat production center
1 functional goat (kid) breeding center under private sector with capacity of 2,000 goat kids per year to supply to 300 producers HHs.
Private Sector, farmers, Provincial and District Extension Center
Nov-11 Oct-12
54
No. Activities Indicators Work Partners Time frame
From To
6
Support to establish the meat processing center
1 functional meat processing center under private sector to process and package pig meat, poultry and fish.
Private Sector, farmers, Provincial and District Extension Center
Nov-12 Oct-13
7
Support to establish the feed processing factory
1 functional Feed Production Center under private sector to produce pig feed, fish and pultry feed.
Private Sector, farmers, Provincial and District Extension Center
Nov-12 Oct-13
8
Support to Production of Maize with intercropping with pigeon pea
Functional groups of farmers to grow maize with intercropping of pigeon pea
Farmers production group for maize
Nov-11 Oct-13
B Revolving Funds for Small Livestock Raising
9
Support for the purchase of piglets and feed
Revolving fund is for 240 households organized into 24 Groups (average10 members/group). Each group will receive funds for 1/3rd of its members and the same money will be revolved to cover all the members in the three years. Per Household the $1000 budget shall be used for purchase of 10 piglets and animal feed. Project will provide vaccination support through other sub-project.
Private Sector, Producer Groups, Provincial and District Extension Center
Nov-11 Oct-14
10
Support for the purchase of Fish fingerlings and feed
Revolving fund is for 450 households organized into 45 Groups (average 10 members/group). Each group will receive funds for 1/3rd of its members and the same money will be revolved to cover all the members within three years. Per Household the $150 budget shall be used for purchase of minimum 2000 fish fingerlings and feed. However, the HHs can decide the variety and numbers to purchase by contributing funds from their own sources.
Private Sector, Producer Groups, Provincial and District Extension Center
Nov-11 Oct-14
11
Support for the purchase of Ducklings and feed
Revolving fund is for 600 households organized into 60 Groups (average 10 members/group). Each group will receive funds for 1/3rd of its members and the same money will be revolved to cover all the members within three years. Per Household the $200 budget shall be used for purchase of minimum 20 ducklings of native variety and feed. However, the HHs can decide the numbers to purchase by contributing funds from their own sources.
Private Sector, Producer Groups, Provincial and District Extension Center
Nov-11 Oct-14
12
Support for the purchase of Native Chicks and feed
Revolving fund is for 900 households organized into 90 Groups (average 10 members/group). Each group will receive funds for 1/3rd of its members and the same money will be revolved to cover all the members within three years. Per Household the $150 budget shall be used for purchase of minimum 20 chicks of native variety and feed. However, the HHs can decide the numbers to
Private Sector, Producer Groups, Provincial and District Extension Center
Nov-11 Oct-14
55
No. Activities Indicators Work Partners Time frame
From To
purchase by contributing funds from their own sources.
13 Support for the purchase of goats
Revolving fund is for 300 households organized into 30 Groups (average 10 members/group). Each group will receive funds for 1/3rd of its members and the same money will be revolved to cover all the members in the three years. Per Household the $800 budget shall be used for purchase of 10 kids and animal feed. Project will provide vaccination support through other sub-project.
Private Sector, Producer Groups, Provincial and District Extension Center
Nov-11 Oct-14
14
Farmers contribution in livestock raising
C Producers Group Formation
15 Formation of Pig Raising Groups
30 Pig raising groups each group comparing of 10 households. Funds will be used for the establishment of group regulation, documentation of the group work, creation of books and stationeries for the groups. No funds will be utilize for the Travel and DSA
Farmer's Production Groups and
Provincial and District Extension
Center
Nov-11 Oct-13
16 Formation of Fish Raising Groups
45 Fish raising groups each group comparing of 450 households. Funds will be used for the establishment of group regulation, documentation of the group work, creation of books and stationeries for the groups. No funds will be utilize for the Travel and DSA
Farmer's Production Groups and
Provincial and District Extension
Center
Nov-11 Oct-13
17 Formation of Duck Raising Groups
60 Duck raising groups each group comparing of 600 households. Funds will be used for the establishment of group regulation, documentation of the group work, creation of books and stationeries for the groups. No funds will be utilize for the Travel and DSA
Farmer's Production Groups and
Provincial and District Extension
Center
Nov-11 Oct-13
18
Formation of Chicken raising Groups
90 Chicken raising groups each group comparing of 10 households with a total of 900 households. Funds will be used for the establishment of group regulation, documentation of the group work, creation of books and stationaries for the groups. No funds will be utilize for the Travel and DSA
Farmer's Production Groups and
Provincial and District Extension
Center
Nov-11 Oct-13
19
Formation of maize and pigeon pean group
100 ha/year area will be planted in potential village. There will be 30 farmer groups promoted under this project and 1/3rd of the group will receive every year.
Farmer's Production Groups and
Provincial and District Extension
Center
Nov-11 Oct-14
20 Formation of Goat raising group
Revolving fund is for 300 households organized into 30 Groups (average 10 members/group). Each group will receive funds for 1/3rd of its members and the same money will be revolved to cover all the members in the three years. Per Household the $1000 budget shall be used for purchase of 10 piglets and animal feed. Project will provide vaccination support through other sub-project.
Farmer's Production Groups and
Provincial and District Extension
Center
Nov-11 Oct-13
56
No. Activities Indicators Work Partners Time frame
From To
D Demonstration of Livestock Raising
21
Demonstration of Pig Raising using the deep litter system
1 Pig raising demonstration with 10 piglets with deep litter system. The demonstration will be done by a farmer to be known as Model Farmer.
Model Family and Provincial and
District Extension Center
Nov-11 Oct-12
22
Demonstration of Fish Raising Groups
10 Fish raising demonstration with 1000 fingerlings of all the 5 native varieties shall be set up. The demonstration shall be region based where all the regions shall be covered. The demonstration will be done by a Model Farmer.
Model Family and Provincial and
District Extension Center
Nov-11 Oct-12
23
Demonstration of Duck Raising Groups
10 duck raising demonstration with 20 native ducklings shall be set up. The demonstration shall be region based where all the regions shall be covered. The demonstration will be done by the Model Farmer.
Model Family and Provincial and
District Extension Center
Nov-11 Oct-12
24
Demonstration of Chicken raising Groups
10 chicken raising demonstration with 20 native chick shall be set up. The demonstration shall be region based where all the regions shall be covered. The demonstration will be done by a farmer to be known as Model Farmer.
Model Family and Provincial and
District Extension Center
Nov-11 Oct-12
25 Demonstration of Goat Raising group
10 Pig raising demonstration with 10 goat kids in 10 project villages of 10 different Kumb Bans. The demonstration shall be region based where all the regions shall be covered. The demonstration will be done by a Model Farmer.
Model Family and Provincial and
District Extension Center
Nov-11 Oct-11
3.11 ATT COM 2: Integrated Rice-Pulse Based Farming System in Attapeu
The subproject aims at improving livelihood and reduces poverty for 5,653 households with 12844 persons in 12 villages of 3 Kumb Bans of three districts (Sanamxai, Samakhixai and Xaysettha) in Attapeu province through rehabilitation of irrigation systems, revolving fund for the agricultural development, farming demonstrations and capacity building for villages and farmers.The subproject will be implemented from October 1st, 2011 to October, 2014 by Attapeu PAFO which is the functional Excuting agency, together with Sanamxai, Samakhixai and Xaysettha districts DAFO and total cost of about 544,095 US$. Details subproject location, activity and implementing schedule are described below.
3.11.1 Location
As mentioned above, the subproject will be implemented in the 12 villages of three Kumb Ban
in three districts, Attapeu province. List of the villages and map are provided below.
57
Table 19: Name of villages in subproject area
No Name of
district
Number and name of Kumb
Bans
Number and name of villages
Number Name Number Name
1 Xaysettha 1 Phameuang 3 Vat Neu, Vat That and Vat Luang
2 Sanamxai 1 Hinlat 3 Tor Mor Yord, Hin Lat, Samong Tay
3 Samakhixai 1 Thetsaban 6 Meuang Mai, Se Nhai, Vat Luang,
Sammakkhi, Sekong, Sivilay
Figure 11: ATT COM 1 subproject area map
3.11.2 Activities
There are four components in the subproject, the detailed of component and sub - components
as follows:
Component 1:Construction three irrigation systems
In Samong, Wat That and Naphok irrigation systems especially construction/rehabilitation of
Samong irrigation system’ concrete second canal with length 1,500 m (rectangle, h = 0.5 m, b =
58
0.55m, t = 10 cm) for increasing 32 ha irrigated in dry season and irrigated additional 16 ha area
in rainy season. Of which:
Construction/rehabilitation of Wat That irrigation system’ concreted second canal with length 824 m (Noong He area: 484 m and Wat Kao area: 340 m) h = 0.5 m, b = 0.55 m for increasing 25 ha. Irrigated area in dry season (22 ha of rice and 3 ha for other crops). Construction/rehabilitation of Naphok irrigation system: Construction/rehabilitation of concrete second canal with length 902 m, h = 0.5 m, b = 0.55 m for increasing 28 ha. irrigated area in dry season. Component 2: Demonstrations
1) 1 ha for SRI Technique of rice plantation crop rotation with legume cropsat each irrigation scheme for 3 schemes.
2) 1 ha of direct seeded (Na Jot) rice plantation crop rotation with legume cropsat each irrigation scheme for 3 schemes.
3) 1 ha for rice planting with improved technology crop rotation with legume cropsat each irrigation scheme for 3 schemes.
4) 1 ha for fodder cultivationat each irrigation scheme for 3 schemes. 5) 1 ha for fish & frog in rice fieldat each irrigation scheme for 3 schemes. 6) A deep litter pig raising for native Pig at each irrigation scheme for 3 schemes. 7) 1 ha of Green Manuringat each irrigation scheme for 3 schemes. 8) 1 ha ofproduction of seed for the green manuring cropat each irrigation scheme for 5
schemes for 3 years. 9) 1 ha for the chilly, tomato etc at each irrigation scheme for 3 schemes. 10) 1 ha for cash crops like peanut, maize intercropping with legume etcat each irrigation
scheme for 3 schemes. 11) 1 ha for increase size of rice fieldat each irrigation scheme for 3 schemes. 12) 1 ha for compost, Dry BE and Wet BE and vermin compostingat each irrigation scheme
for 3 schemes. Component 3: Revolving fund for the agricultural groups
1) Revolving fund for 9 chicken raising groups each group for 30 families each family for 20 chicken
2) Revolving fund for 2,000 fingerling each family for 60 families (20 families at each irrigation scheme).
3) Revolving fund for 9 pig raising group each group for 10 families with 2 piglets per family..
4) Revolving fund for rice plantation and cash crop plantationfor the 160 ha.
3.11.3 Implementation schedule
Overall, the subproject will be implemented from October 1st, 2011 to October, 2014.
Specifically, each activity is expected to implemented as defined in the schedule below.
59
Table 20: Implementation schedule
No Item 2011 2012 2013 2014
Q4 Q
1
Q
2
Q
3
Q
4
Q
1
Q
2
Q
3
Q
4
Q
1
Q
2
Q
3
Q
4
1 Survey and Design for Samong irrigation system
2 Construction of Samong irrigation system
3 Survey and design for the Naphok Irrigation
system
4 Construction of the Naphok Irrigation system
5 Survey and design the Wat That irrigation system
6 Construction of the Wat That irrigation system
7 SRI Technique of rice plantation crop rotation
with legume crops
8 Direct Seeded (Na Jot) Rice plantation crop
rotation with legume crops
9 Rice Planting with improved technology crop
rotation with legume crops
10 Demonstration for Fodder cultivation
11 Demonstration for Fish & Frog in rice field
12 Demonstration for deep litter pig raising for Native
Pig
13 Demonstration for Green Manuring
14 Production of seed for the green manuring crop
15 Demonstration for the Chilly, Tomato etc.
16 Demonstration for Cash crops like peanut, maize
intercropping with legume etc.
17 Demonstration for Increase size of rice field
18 Demonstration for compost, Dry BE and Wet BE
and vermicomposting
19 Farmers Contribution in demonstrations
20 Revolving fund for the Chicken raising groups
21 Revolving fund for Fish raising groups
22 Revolving fund for Pig raising groups
23 Revolving fund for rice plantation and cash crop
plantation
24 Farmers Contribution in the form of Labor for the
cultivation and raising
60
CHAPTER 4: DESCRIBPTION OF ENVIRONMENT
4.1. SVK COM 10 Promotion Commercialization of Livestock in Savanakhet
4.1.1 Physical Environment
Savannakhet Province has a total land area of 21,774 km2. In which, around 90% of the area is
flat land and the rest 10% is mountainous especially northeast part which is linked to Anamite
mountain range.
Soil;Based on the geological survey and finding of dinosaur bones in the province, it was
suggested that soil in this area has been evolved for millions of year. However, as quite large
area of land is or converted from dipterocarp, deciduous forest and flat plain along Mekong
River; soil in or converted from the deciduous and scrub forest region is quite dry and sandy
while it is sandy roam and rather fertile in along Mekong River.
Climate is a tropical wet and dry climate which is generally very warm throughout the year. On
average, temperatureis about 26 C.Of which mean maximum temperature is 31.4 C and mean
minimum is21.2 C. Figure below show the pattern and trend of the temperature in the province.
Figure 12: Temperature in Savannakhet between 1971 to 2009
y = 0.025x + 25.76R² = 0.173
23.00
23.50
24.00
24.50
25.00
25.50
26.00
26.50
27.00
27.50
28.00
28.50
1971
1973
1975
1977
1979
1981
1983
1985
1987
1989
1991
1993
1995
1997
1999
2001
2003
2005
2007
2009
Average Temperature of Savannakhet
61
There are two seasons, wet and dry. The wet season is between April and October and the dry
season is from November to March. The average rainfall is roughly 1500 mm per year. While
the precipitation is significantly different between both season. In the dry season it is so dry and
precipitation is only 25.9 mm per year on average whereas it increases to 220.1 mm/year for
rainy season. The pattern and trend of the precipitation in the province is as in the Figure below.
Figure 13: Precipitation in Savannakheet between 1970 to 2010
Sebanhieng is the main river of the province. Its source is in the northeast bordering with Vietnam. The total length is about 370 km with river basin of 19,223 km2. Its main tributaries are Sepone, Sethamouk and Sechamphone. Mean precipitation in the river basin is about 1,600mmper year and discharge of 538 m3/sec and maximum of 4,097m3/sec on average. However, the annual discharge is remarkably different; 90% of the discharge is in raining season.The dry season discharge is as low as 10%, resulting irrigation is limited for the dry season compare to demand which is about 46m3/sec (WREA, 2008).
4.1.2 Biological Environment
Overall Savannakhet Province is a natural resources rich province especially large flat agricultural land along Mekong River, forest and river network including Mekong tributary. About 1.5 million hectares (ha) or68% of the total provincial land area was classified as agricultural land area. Parts are alluvial soil along the Mekong, however, as mentioned;a large area land is arid and infertile. Forest,particularly NBCA covers quite large proportion of the province. There are four NBCAs lie down within Savannakhet. Phou Xang He to the north, Dong Phou Vieng and part of Xe Xap to the east and part of Xe Bang Nouan to the west. Phou Xang He covers area of 109,900 ha and
y = 3.527x + 1405.R² = 0.028
0.0
500.0
1000.0
1500.0
2000.0
2500.0
1971
1973
1975
1977
1979
1981
1983
1985
1987
1989
1991
1993
1995
1997
1999
2001
2003
2005
2007
2009
Rainfall in Savannakhet
62
it is IUNC’s NBCA category V 1 . Dong Phou Vieng has an area of 220,000ha (IUCN classification is inapplicable). Xe Xap covers 133,550 ha (IUCN classification is inapplicable) and Xe Bang Nouan’s area is 150,000 ha and IUCN’s category IV. However, as the SVK COM 10 subproject’s targeted areas and activities are in Outhoumphonh, Saiphouthong, and Atsaphangthong districts or are not situated and will not cause negative impact to those NBCAs. Below are locations of four NBCAs.
Figure 14: Map of the NBCAs in Savannakhet
As for forest in and around the subproject’s targeted villages especially activity areas; it is, in general, limited. It is also true for wildlife and aquatics which are limited or unlikely to be affected. No endanger species of fauna and flora exists or encountered.Most forest has been converted for resettlement and agricultural land for century. What exists are small village and district forest area, however they are far away from the activity location.Hunting is used to be one of the main activities which now limited because of declining of wildlife population and habitats.
4.1.3 Social Environment
There are about 800 thousand people live in Savannakhet. These populations consist of 12
different ethnic groups, mixed of Lao, Thai, Chinese and Vietnamese communities.
Savannakhet is also a major trading route in the southern part of Laos. Lao, Thai, Chinese and
Vietnamese-made goods pass through this city daily.Agriculture is the main economic sector
sharing 49.04% of the total GDP during 2009-2010. The economics of the province grow rapidly
1http://www.nationalparks-worldwide.info/laos.htm
63
and only 10% of the populations live under poverty line. However, those poor people are high in
eastern part including the subproject’s targeted districts.
As for the subproject, there are70 villages and 3600 households of Outhoumphonh,
Saiphouthong and Atsaphangthong districts involve in.These villages and households main
production and income source are livestock. However, majority livestock keepers are small
scale and embrace traditional livestock keeping approach with some trading or basic breeding,
keeping for self consumption or selling them in the local market only during difficult times. In
addition, there is basic livestock health care and hygiene. Type and population of livestock in
these districts are as in the table below:
Table 21: Livestock situration in the subproject area
No Districts Pigs(heads) Poultry(heads)
1 Outhoumphonh 15,916 212,195
2 Saiphouthong 6,789 127,280
3 Atsaphangthong 11,070 117,194
Total 33,775 456,669
4.2. SVK PR 1 Food Security and Poverty Reduction through Livestock inSepon District of Savannakhet
4.2.1 Physical Environment
Sepon is only one out of 15 districts in Savannakhet province targeted by this subproject. It is
very poor districts situated in the northeast which is rugged terrain of Anamite and share border
with Vietnam, around 70 km from Savanakhet town. It is in between Sepon and Sebanghiang
River; and the altitude, at the Seponriver bank, is about 170 meter2. The Sepon River is the
biggest and important river of Sepon originates from the border between Savannakhet Province
of Laos and Quang Tri province of Vietnam while Sebanghiang is an important tributary of the
Mekong River.
Temperature is quite similar to the average temperature of Savanakhet.Mean temperature is
around 26 C; whereas mean maximum temperature is around 31 C and mean minimum is
around 21C. However, rainfall is slightly higher in Sepon since it is closer and or influenced by
weather from Vietnam Sea3.
The subproject activities are in the northeast of Sepon. They are in low land, community area
and few kilometres to the river(see also Figure 2).
2 http://en.wikipedia.org/wiki/X%C3%A9p%C3%B4n
3 http://en.wikipedia.org/wiki/X%C3%A9p%C3%B4n
64
4.2.2 Biological Environment
Sepon situates about middle of Dong Phou Vieng NBCA (to the south) and Phou Xang He (further northwest). Dong Phou Vieng is one of the most important NBCA with recent area is of about 220,000 ha. Majority of ecological character is the Semi Evergreen and Deciduous Dipterocarp Forest.The key wildlife species are Douc and langur, elephants, cattle, tigers, pangolin, hornbill and vultures.21 villages comprising of around 3,700 people of Sepone lived in or adjacent to the Dong Phou Vieng NBCA during the established year.These villages are Makong, Tri and Phou Thia ethnic4. Phou Xang He has an area is of around 109,000 ha and it is IUCN’s Category V NBCA5. Main forest types are the Mixed Deciduous which covered 44% and the forest is Evergreen 41%. Dominant species are Asian Elephant, Giant Muntjack, Gaur, Banteng, Loris, Douc Langur, Gibbons, Bears, Tiger, Leopard, Civet and wild Dog. In addition, there number of birds species such as Siam Fireback, Wookpecker, Peacock, Partridge, Kingfisher, Hornbill, Barbet, Pitta, Treepie, Tit-babler, Fulvetta ad Mynah. This NBCA covers 4% of Sepone district land area and there were 13 villages under Sepone district settled in and around it6. However, there is limited forest or important ecosystem area in and around the subproject’s activity areas. As mentioned, the activities are mostly in the community area. Although there is river in the area, waste (liquid and solid) is not directly or indirectly discharged to the river (far from the river). It was reported that there is no endanger species of aquatics in the river and fishery is declining since the aquatics are limited.
4.2.3 Social Environment
There are 14 Kumb Ban comprising of 88 villages and 8,325 household in Sepone. Total
population of the districts is 56,523 and women are about half. However, only 9 villages
consisted of 3,192 people (568 households)involved in this subproject. Quite large population is
ethnic minority. Of which, Tri ethnic minority accounted for 90%; Mongkong accounted for 5%
and Lao Theung 5%.
The main income derived from agriculture and livestock. Total cultivationarea is 1,023 ha but
mostly cultivated in wet season and productivity of rice is only 1.5-1.7 tons per hectare.Only
49.3 hectare is irrigated rice field and the rest are other land uses which were showed in the
table below.
4http://www.ecotourismlaos.com/directory/protected_areas/dongphouvieng.htm
5http://www.nationalparks-worldwide.info/laos.htm
6http://www.ecotourismlaos.com/directory/protected_areas/phouxanghe.htm
65
Table 22: Main information of Kumban Phabang
No Item Unit
Kumban Phabang
Total Ban Lousalia
Ban Tapo
ng
Ban Sobsalou
Ban Kok
Ban Laveun
Ban Na
Ban Phabang
Ban Mai
Ban Namthone
1 Total area Ha 54 48 126 65 35 44 145 35 76 628
2 Agricultural land
Ha 42 37 95 58 28.3 55 129 31 63 538.3
3 Total area of rice field
Ha 40 35 71 54 21.3 40 94 25 57 437.3
4 Dry season rice
Ha 5 7 15 2 1.3 5 7 2 5 49.3
5 Upland rice Ha 35 28 56 52 20 35 87 23 52 388
6 Other crops Ha 2 2 24 4 7 15 35 6 6 101
7 Cattle Head
25 30 45 50 42 27 54 24 24 321
8 Buffalo No. 8 13 9 4 3 7 20 5 15 84
9 Pig No. 23 47 35 26 27 34 120 35 35 382
10 Goat No. 42 15 35 24 30 23 53 38 28 288
11 Poultry No. 230 250 80 75 125 230 220 125 86 1421
12 Fish pond No. 12 5 8 6 5 3 12 3 6 60
13 No of population
Persons
125 191 235 528 435
112 420 803 343 3,192
14 No. of household
No. 23 27 67 100 19 111 177 78 73 675
15 No. of population in Agriculture
No. 125 191 235 528 435
112 420 803 343 3,192
16
No. of Women is owner of household
Persons
73 80 141 249 55 242 321 223 219 1,603
Source: Statistics survey by PAFO, June 2011 and Savannakhet PPO survey, June 2011
As limited agriculture land and income opportunity; 448 families learned or produced less than
16 kg of rice per month. In that 24% faced rice shortage for 3 months and 49% experienced 6
months of rice shortage. NTFPs were important sources of food and income for the stress
season. However, NTFPs are declining due to shifting cultivation and land occupying for
intensive private farm; the poor is still vulnerable.
66
4.3. SAL COM 4: Road Rehabilitation in Lao Ngam Distric of Salavanh
4.3.1 Physical Environment
Lao Ngam District situated in the Boloven Plateau and quite large area is flat terrain.Soil is
volcanic evolved and quite fertile. However, it can be dry in surface and easy to generate dust
especially during dry season.
The climate of tropical monsoon, divided into 2 seasons. The dry season is from November to
April meanwhile the rainy season starts from May to October. Temperature is 26.5 0C on
average.Mean maximum of the temperature rose to 31.8 while mean minimum is about ten time
lower or 220C.Figure below show captured the pattern and trend of the temperature of the
province in last 20 years.
Figure 15: Templerature of Salavanh between 1990 and 2009
The annual average precipitation is 2,100 mm. There are about the average relative humidity is 75 %/year.
y = 0.004x + 26.85R² = 0.005
25.00
25.50
26.00
26.50
27.00
27.50
28.00
28.50
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
Average Temperature of Salavanh
67
There is a small river which is about 0.5-1 km away from the road. However, during raining
season, water from this river together with water elsewhere could cause road area inundated.
However, this is only occurred once in 3-4 years. Aquatics and fishery are limited.
Overall, based on observation, air quality is in natural good condition. However, since it is quite
windy in dry season, together with some dry soil, dust can be often observed.
4.3.2 Biological Environment
Overall,there are three main National Biodiversity Conservation Areas (NBCA) in Salavanh; Xebangnouan in the north, Phouxiengthong to the west and along Mekong River and Xe Xap in the east.Xebangnouan, Phouxiengthong and Xe Xap covers an area of about 155,000 ha; 120,000 ha 133,500 ha respectively. Of which, Xebangnouan, Phouxiengthong are classified as Category IV NBCA. Below are some specific characteristics of the NBCAs.
Table 23: NBCA in Salavanh
Name of NBCA Habitat Key wildlife Remark Xebangnouan Eergreen, dry dipterocarp and
mixed deciduous forest with altitudes range from 200-1,000m.
Not available
Phouxiengthong Semi-dry evergreen, dry diptercarp and mixed deciduous with altitude 300-500m and maximum 716m
Peafowl, banteng and leopard
Xe Xap Hill evergreen, semi-evergreen and pine forest with altitudes range from 400-1,400 m
Bear, gaur, dhole, serow, muntjac and tiger
y = 8.302x + 2013.R² = 0.021
0.0
500.0
1000.0
1500.0
2000.0
2500.0
3000.0
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
Rainfall in Salavanh
68
Figure 16: NBCAs in Salavanh
However, the subproject area including road construction in Lao Ngam district is far away from those mentioned NBCA. Environment is different.In general, almost entire area is farm and residential land.Forest is limited in the subproject area.There is only a small area of forest scattering in the area.Of which, there is one water source forest which villagers preserved for protection of the water source is the closest to the village and road (50m). However, it is rather small or less than 3 ha. Natural forest particularly in the road of row is also none. The water source forest of the village is far from road or ROW. Although there are some plantations along the road; it is not in or more than 3 meters from the ROW. Similar to forest; wildlife and aquatics are limited due to lack of forest and river. In addition, no endanger species of fauna and flora encountered in the project area.
69
Figure 17: Overview of road rehabilitation in Teme village, Lao Ngam District
4.3.3 Social Environment
The proposed road initially passes through 9 villages: Ban Ngew, Ban Lane, Ban Teme, Ban
Donedou, Ban Nongkae, Ban Dongluang, Ban Dongsuang, Ban Dongban, Ban Vanpeuay.
There are 1,474 households with 7,553 persons in the area. Of which 43.6% was women and
21.3% is minority group.
A
B
70
Like other villages, agriculture is the important production and economy. Total land of villages is
7,967.6 ha, which includes agricultural land of 2,180.2 ha. In 2010, the farmers grew 342.6 ha of
rice in rainy season and only 42.0 ha of rice in dry season. Subsidiary to rice are peanut and
corn which are a main cash crops and earning. Their areas in 2010 are 206ha and 361 ha
respectively. In addition, villagers also keep livestock. In 2010, there were 688 head of pigs, 998
of cows, 63 of buffalo and more than 13 thousand of poultry (Table 25).
Table 24:The main information of 5 Kumbans
No. Item Ngew/I Dasiar/II Nongkae/VI Nabone/VII Vangpeuay/VIII Total
Total area 1342.7 2902.3 3035.2 443.4 244.1 7967.6
1 Agricultural land 431.8 283.3 902.8 323.3 239.0 2180.2
2 Paddy land 29.5 0.0 313.1 0.0 0.0 342.6
3 Irrigated land 15.0 0.0 0.0 0.0 0.0 15.0
4 Area of rice rainy
season 29.5 0.0 313.1 0.0 0.0 342.6
5 Yield of rice rainy
season 3.0 0.0 3.0 0.0 0.0 3.0
6 Area of rice dry
season 0.0 0.0 42.0 0.0 0.0 42.0
7 Yield of rice dry
season 0.0 0.0 3.0 0.0 0.0 3.0
8 Area of corn 40.0 6.0 143.0 8.0 9.0 206.0
9 Yield of corn 3.7 2.0 4.7 3.0 4.0 3.5
10 Area of ground nut 88.0 12.0 223.0 31.7 7.0 361.7
11 Yield of ground nut 1.5 1.0 1.2 1.5 2.0 1.4
12 Total of pigs 365.0 10.0 115.0 48.0 150.0 688.0
13 Total of Cow 104.0 20.0 835.0 29.0 10.0 998.0
14 Total of Buffalo 15.0 0.0 43.0 4.0 1.0 63.0
15 Total of Poultry 3500.0 2000.0 6130.0 800.0 1000.0 13430.0
16 Total of other
livestock 40.0 0.0 52.0 0.0 0.0 92.0
17 Total of farm
households (FH) 453.0 107.0 654.0 102.0 158.0 1474.0
18 % of poor FH 0.0 0.0 5.9 0.0 0.0 5.9
19 Total of population 2351.0 587.0 3268.0 587.0 760.0 7553.0
20 % women /
population 49.0 26.9 49.5 48.0 44.8 43.6
21 % minority/ total
population 26.7 65.0 9.7 0.0 5.0 21.3
22 % of FH lack of food
for 3 month per year 0.0 0.0 17.4 0.0 0.0 3.5
23 % of FH lack of food
for 6 month per year 0.0 0.0 6.1 20.0 0.0 5.2
71
Numbers of villagers in these villages are under poverty line.3.5% of the population is facing rice
shortage for 3 months per year and 5.2% suffered for 6 months per year. However, because of
there is huge potential of cash crops such as banana, sweet potato, peanut which are grown
along the proposed rehabilitation road; once road access is improved together withmarketing of
agricultural product; it is perceived that local can earns from those cash crops and buy rice
instead of growing rice.
4.4. SAL COM 1: Irrigation Development in Khong Sedone District of Salavanh
4.4.1 Physical Environment
Irrigation area is lowland and along Sedone River and national Road No 13 south . This area is about 300m above see level. The soils are severely lacking in organic matter and most crop nutrients are provided in the form of chemical fertilizers. Farmers not follow the practice of soil fertilility management like crop rotation, use of green manuring, use of compost etc. Dry season rice yields are typically around 4 tonne per ha and wet season yields are around 2.75 tonne per ha. Households with holdings greater than 1 ha and yields of greater than 2.5 tonne per ha have assured food security all year round. Sedone River which originates from northeat of the Bolaven Plateau with total length of 1,574 km is the source of water for irrigation. Its catement area is 7,229 km2 covering Salavanh, Xekong and Champasack province. About 380,000 people live in the catement (2005). Mean annial rain fall is 1,800 mm, mean discharge of 177 m3/s and mean minimum monthly discharge is 5m3/s. However, water discharge is so different from the raining and dry season. About 92 percent of the water dischage found in the raining season and only 8 percent is on the dry season which sometimes causing water shortage in the season. In addition, it is likely that the water would be short if the demand for water use including irrigation continue to increase. The main tributary of Sedone is Seset river which also has its water source from the Bolaven Plateau. Seset 1 and 2 dam were established and are operating in upper part and sometimes results in change in water flow into Sedone river (WREA, 2008).
4.4.2 Biological Environment
In the large view, Kong Sedone is close to Phouxiengthong to the west (Figure above). Phouxiengthong is IUCN’s Category IV NBCA, located along the Mekong River with altitude range from 100 to about 700 m above sea level. The dominant forest is semi-evergreen and dry dipterocarp. About 16 mammals and 188 bird species were recorded in the area. There are about 32 villages comprising of 11,169 people lived in and surrounding areas of the NBCA7. However, the SAL COM 1 subproject area is along Sedone River on the other side which is far or opposite to the NBCA.There some mangrove and scrub forest scattering in the area. However, overall it is limited in the irrigation head pump and canals area. Wildlife is also limited.
7http://www.ecotourismlaos.com/directory/protected_areas/phouxiengthong.htm
72
No endanger species of fauna and flora exists. The majority of the canal is lying along and in the edge of rice paddy, some gardens and far from the community. Fish and aquatics in the Sedone River, based on the interview with Khamthong villagers, are declining and fishery is harder. Majority of fish catched recently are carp and Terapia which released in the river rather than natural fishes.
Figure 18: Overview forest and land use in the irrigation area in Sedone River
A
73
4.4.3 Socioeconomics
Overall, Salavanh occupies a land area of 10,369 km2 and population of 364,405. Around 93%
of the population depend on agriculture and incomes is around 810 US$ per capita per year.
B
C
74
Rice paddy accounts for 64,655 ha and majority of the population lives on the more fertile plain
areas, including Khong Sedone district. There are 10 ethnic minority groups in Salavanh, who
are very poor - the average poverty rate in Salavanhis 10%, but the poverty rate of 3 poor
mountainous districts where ethnic minority people are living is 44%.
As mentioned, there are 12 villages,comprising of households and 10,049 people in the subproject area.Some are ethnic minority people such as Katang and Xouei ethnic groups. 5 percent these households are below poverty line and majority are ethnic people. Rice production is the main activities and source of income. On average, each household own a
land of 1 ha. Rice production is practiced in both rainy and dry season. Productibity was about
2.75 tonne per ha, lower then dry season which rice yields are around 4 tonne per ha.It was
percieved that if household owns a land more than 1 ha and produce more than 2.5 tonne per
ha would be secured from food shortage.
4.5. SAL PR3: Promotion Commercialization of Livestock in Salavanh
4.5.1 Physical Environment
Salavanh’s most area is quiteplain terrainand only northeast part ismountainous and the loop
upstream. The total land area of the province is 10,553 km2. The high mountain area is
covered with quite dense forest while majority of fertile plain is patchwork of rice paddies and
fruits orchard.
The climate is a tropical monsoon which divided into 2 seasons. The dry season is between
November to March and the rainy season is from April to October. The annual average
precipitation is 2500 mm. The average relative humidity of the province is 74%. The annual
average temperature of the province is 25.5 0C with minimum 11 0C while the maximum can go
up to 40 0C.
As mentioned in SAL COM1, the key river for Salavan is Sedone River. In addition, there are
Selamang, Seset and Setapungwhich are also important river for livelihood and hydropower
development. Seset 1 and 2 hydropower dam were already completed in Seset River. Some
micro dams also proposed for Selamang and Setapung
4.5.2 Biological Environment
As show in the Figure 16, there are some NBCAs around the SAL PR 3 subprojects, however, those NBCAs are long distance.In addition, as the livestock keeping is close to villages and homes; the forest in this specific livestock areas is limited and majority are residential and agricultural land especially home gardens and paddy field.
75
Similarly, wildlife and aquatics are also rarely encountered in the livestock raising areas. Although some farmers and producing centres are in Kong Sedone district, they are in long distance to and unlikely to cause impact aquatics in the Sedone River.
4.5.3 Social Environment
In 2010, Salavanh population comprises of 61,211 households and 364,405 people, of which
184,778 people were female. The Lao Loum accounted for 67% and the rest 33% was the
ethnic minority. 10 major ethnic groups are Lao, Katang, Suay, Taoy, Pako, Phuthai, Ngai,
Katou, Ala and Yulaven.
The main economy and occupation is agriculture production. GDP per capita is estimated to be
at $US 710 (the national average at $US 983). However, Salavanh is among the poorest
province in the country, where only its capital town: Salavanh district is not classified as poor
district. In 2010, over 28,790 people or 8.1% of the total population are still living below the
poverty line. The infrastructure especially road is underdeveloped and access to markets and
other services is difficult. Agriculture remains only choice and lack of alternatives for off-season
earnings.
However, in this subproject area, local people have been rearing livestock for century although it
is not yet a farm system for commercialization. So far there are 108,595 heads of pigs and
674,861 heads of poultry Salavanh district; 141,100 heads of pigs and poultry estimates to be
250,000 heads in Wapi district; 123,606 pig heads and 540,260 poultry heads inTumlan district.
4.6. CPACOM 9: Promotion Commercialization of Small Livestock in Champasak
4.6.1 Physical Environment
Champasak province is in the Southern most part of Laos, where Mekong flows through the
middle of land, creating hundreds of islands.Land area is predominant with flat land along
Mekong River, Bolaven plateau and mountainous terrain especially in the northeast part. Total
land area is 15,350 km2;of which, upland area that occupies 26% total area or 74% is low land
area.
Climate, like other province, is tropical monsoon. The average annual temperature is 27°C and
rainfall is 2,300 mm/year. Figures below are trends of the temperature and precipitation in the
province.
76
Figure 19: Trends of the temperature of Champasak
Figure 20: Trends of the precipitation of Champasak
Overall, there are several important rivers flow through Champsak. Among these are Mekong and Sedone. In addition, there are also small important river such as Se Nam Noy, Sekatume and Sekong and Sekaman that also form its way in the province. These rivers are livelihood and economic significance. It is main sources of proteins/fishery, transport, irrigation and agriculture and power development.
y = 0.025x + 26.96R² = 0.440
25
25.5
26
26.5
27
27.5
28
28.5
29
1971
1973
1975
1977
1979
1981
1983
1985
1987
1989
1991
1993
1995
1997
1999
2001
2003
2005
2007
2009
Average Temperature of Champasack
y = 2.939x + 2021.R² = 0.007
0.0
500.0
1000.0
1500.0
2000.0
2500.0
3000.0
3500.0
1970
1972
1974
1976
1978
1980
1982
1984
1986
1988
1990
1992
1994
1996
1998
2000
2002
2004
2006
2008
Rainfall in Champasak
77
4.6.2 Biological Environment
There are two main NBCAs in the province namely Dong Houa Sao and Xepain. Dong Houa Sao has an area of 110,000 ha covering four districts: Champasak, Pathoumphone, Paxong and Bachieng.It is IUCN’s Category III NBCA. The forest is predominant by semi-dry evergreen withelevation of 100-300 m above sea level. However, some areas reached 1000-1,300 m. 62 species mammals, 30 species of bats, 291 species of birds and 41 species of retiles were recorded. Of which key species of wildlife are elephant, tit-babbler and gibbon8. Xepain is in the south of Dong Houa Sao, covers area of 240,000 ha and three districts: Pathoumphone, Khong of Champasak and Sanamxai of Attapeu. The forest is predominant by evergreen, mixed evergreen and deciduous forest with elevation of 150-300 m above sea level. 39 species of mammals, 51 key species of birds, 44 species of reptiles, 21 species of amphibians and 197 species of fish were found in the area. Of which key species of wildlife are tiger, banteng, elephant, guar, bear, pangolin, otter, gibbon, dhole, ibis, crane, white wing-duck, vulture, woolly-necked stork, lesser adjutant, river tern, masked finfoot, peafowl, hornbill, Asiatic giant and soft shell turtle and Irrawaddy dolphin9.
Figure 21: NBCA in Champasak
8http://www.ecotourismlaos.com/donghouasao.htm 9http://www.ecotourismlaos.com/directory/protected_areas/xepian.htm
78
4.6.3 Social Environment
Champasak province is the 2nd largest pollution in Laos, there was 667,305 persons in 2010. It
consists of 10 districts namely: Bachieng chaleunsouk, Champasak, Khong, Muonlapamok,
Pakse, Pakxong, Pathoumphone, Phonethong, Sanasomboun and Sukhuma.Lao Lum is the
majority accounting for 62.1% of the population. Agriculture remains key econmycontributing
49.04% of the total production value of the province.The rest are service and industry sector
which share 26.42% and 24.54% respectively.
There are 9 districts involving the subproject except Pakxong. The area, population and ethnics
are diverse. However, agriculture is till the important sector of the developments.
Bachieng district has total land area is of 78,476 ha. It comprises of 5 communes, 45 villages,
8,175 families and total population of 50,011 people. There are almost 15 ethnic groups and
main tribes are Laolum, Taoy, Phouthasi, Suay, Laven, Alak, Oaung, Talieng, Lavae, Yaheun,
Kachaeng, Gnae, Oy, Katou. 369 out of 8,175 households are recorded as the poor.
Champasak district has total land area of 85,375 ha and consists of 5 communes, 75 villages,
9,988 households. The total population is 61,165 persons of which the main ethnic groups are
Laolum, Phouthai and Phaophakeo and More than 789 families are considered as the poor.
The Khong district occupies 76,291 ha of land area, comprising of 10 communes, 114 villages,
14,769 households. The total population is 85,905 persons and only 2 ethnics groups: Laolum
and Prauo which accounted for 98% and 2% respectively.
Munlapamok district has land area of 237,554 ha and there are 5 communes, 36 villages, 5,588
households with33,799 people. There are also only 2 ethnics groups namely Laolum which
covers 88% of the district and Khmer covering 12% of the population. There are 1,114
households earn a living below the poverty line.
Pakse occupies total land area of 92,039 ha. Its population comprises of 5 communes, 42
villages, 12,998 households and 77,997 people. Women are more than half of the total
population.100% of the population is Laolum and only some households are known as the poor.
Pathumphone covers 287,039 ha and 9 communes, 68 villages, 9,608 households and56,034
people. There are two major ethnic groups namely Laolum figuring in 91.3% and LaoTheung of
8.7%.of which key sub-tribes are Laven, Katang, TaOy, Suay, Lavae, Yaheun, Gnae, Katou,
Oy, Kaseng, Inh, Talieng, Yaeh, Alak and Pakho.Among these 3,666 households are living
under poverty line.
Phonethong district covers 100,855 ha and 5 communes, 71 villages, 16,218 households and
89,769 people. Women are 45,156 persons. Most of the people are Laolum and 1,288 are poor
households.
Sanasomboun district covers 92,039 ha and 5 communes, 73 villages, 11,313 households and
65,037 people.There are 2 ethnics groups namely Laolum which is majority and 3.7% Katang
group.
79
Sukhuma district covers 117,931 ha and 6 communes, 56 villages, 8,630 households and
population 53,212 people. There are 3 ethnics groups: Laolum, Suay and Khmer. 2,957 out of
8,630 are poor households.
As mentioned, the agriculture are important sources of income of the people in the subproject
areas as well as 9 districts. The agriculture covers more than 65% of the economic activity and
present numbers of livestock in the 9 districts are as follows.
Table 25: Livestock situation in subproect area
No Districts Pigs(heads) Fish ponds (in
Ha)
Goats
(heads)
Poultry(heads)
1 Pakse 5,811 49 ha 1,328 46,916
2 Sanasomboun 17,255 206,68 ha 978 111,079
3 Phonethong 12,707 198 ha 640 1,109,789
4 Bachieng 8,574 200 ha 2,904 120,700
5 Pathumphone 20,624 221 ha 694 300,716
6 Champasak 6,640 180.76 ha 0 334,178
7 Sukhuma 10,210 113 ha 230 101,200
8 Munlapamok 7787 96.5 ha 112 349,915
9 Khong 14,522 72 ha 0 486,442
4.7. CPA COM 10: Promotion Commercialization ofPig Farming in Champasak
4.7.1 Physical Environment
This subproject located at the same targeted districts as CPA COM 9; the physical environments of this subproject are referred to what was described in the CPA COM 9 above.
4.7.2 Biological Environment
See the biological environment described in the CPA COM 9.
4.7.3 Social Environment
See the social environment described in the CPA COM 9.
4.8. SEK COM 4: Promotion Commercialization of Livestock in Sekong
4.8.1 Physical Environment
Sekong occupies a total land area of 7,665 km2. It is geographically formed with mountainous and plateau terrain.The high mountain is especially in the northeastern or part of Anamite mountain range. Southwestern connects with Bolavenplateau which is quite flat with volcanic fertile soil. As mentioned, there are two districts, Thaeng and Lamam involved in the subproject.Thateng districtis in the western part of the Bolaven Plateau. Majority of land area is flat with some rolling mountains. Lamam, the capital of Sekong issituated in the middle of the Province and the land
80
area is also in Bolaven which is low land and suitable for agriculture. The altitudes range from 81m to 1269m. The average precipitation is relatively high or up to 3,943.2 mm; resulting height of humidity which accounts for 73%.Temperature is around 27.8 oC while the minimum temperature is 21.4oC and maximum of 32.9 oC.
Figure 22: Temperature in Sekong
Figure 23: Rainfall in Sekong
y = 0.011x + 26.88R² = 0.026
25.8
26
26.2
26.4
26.6
26.8
27
27.2
27.4
27.6
27.8
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
Average Temperature of Sekong
y = -5.207x + 1548.R² = 0.021
0.0
200.0
400.0
600.0
800.0
1000.0
1200.0
1400.0
1600.0
1800.0
2000.0
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
Rainfall in Sekong
81
The main river of the province is Sekong River which flows through most district of the province. Lamam, the capital town of Sekong is situated along Sekong River bank. But Thateng is further away from the river. However, there are some rivers that liedown on Thateng district such as Huay Lamphan Yai and its tributaries.
4.8.2 Biological Environment
In general, Sekong’s territory include part of two NBCAs, Xe Xap to the northeast and Dong Amphan in the southeast. As mentioned above, theXe Xap NBCA isimportant ecosystem and rich in biodiversity. Predominant forest are Hill evergreen, semi-evergreen and pine forest and Key wildlife reported to be found in the area are Bear, gaur, dhole, serow, muntjac and tiger. Dong Amphan NBCA is mainly in Attapeu province, only part of it lies in Sekong in the northeast. Below is the map of Xe Xap while detail of Dong Amphan was described in the NBCAs in Attapeu.
Figure 24: NBCA in Sekong
4.8.3 Social Environment
Sekong is one of the low population and density. Total population, as of 2010, was 101,809
people. 51,737 were female. Ethnic groups are quite dominant and the main groups include
Katang, Tahoy, Pako, Kado and Suay. Majority of these tribes still keep lifestyle as origins.
82
Local economy depends on agriculture and livestock rearing. Based on the estimates, about
71% of Sekong’s households are poor and GDP per capita is estimated to be at $US 426 (the national average at $US 983). Although the agriculture is the main occupation but rice paddy
and other production are limited or small scale;leading province to face food insecurity.
The targeted districts, Lamam and Thateng are provincial capital and new developing district
respectively.
There are 42 villages, 7 Kumb Bans and population of 30,970 people in District. Of whom 15,
835 are females. Majority of the population are ethnic minority groups and only 5% is Laoloum.
Those ethnics are Alak, Ngaeh, Katu, Trieng, Yaehs, Lavy, Laven, Lavae, Souai, Ta Oih,
Katang, Kapork. The main land area is covered by forest which accounted for 136,492 Ha. Only
28,938 Ha is agricultural land and the remaining 13,869 Ha is residential and other land uses.
Small livestock rearing is primary and traditional. At present, there are 4,389 heads of pigs;
1,833 heads goats;27,757 heads of poultry and 80 tons of fish produced in the district.
There are 6 Kumb Ban and 55 villages and total population of 32,176 people in the Thateng
district in 2010. In that 16, 722 were women. Its population consists of the major 8 ethnic
groups namely Katu, Ngaeh, Trieng, Yaehs, Lavy, Laven, Lavae, Katang. Like other ditrict,
livestock is key income earning of Thateng.Based on the estimates made by province, there
are about 5,338 heads of pigs;2,530 heads of goats; 235,263 heads of poultry andalso around
80 tons of fish is being reared.
4.9. ATT COM 1: Promotion Commercialization of Livestock in Attapeu
4.9.1 Physical Environment
Attapeuprovince is located in the most Southeastern of Lao PDR. The capital city, Samakhixai
is built in a large picturesque valley surrounded by mountains and the loop upstream. The total
land area is 10,320 km2. Attapeu is bordered with Sekong in the North, Champasack in the
West, Vietnam in the East and Cambodia in the South. There are 5 districts in the province,
namely: Samakhixai, Xaysettha, Sanamxay, Sanxay and Phouvong.
Attapeu is known for its six rivers: Se Kong, Se Kaman Se Sou, Se Nam Noe, Sepien and Nam
Ngone. People can take a boat along the Se Kong River and then up the Se Pian River to
access Se Pian National Protected area. The remote and little known Nong Fa Lake is the
largest and possibly only crater lake in the country. Overall, the Attapeu river valley is
characterized by a landscape of a fertile plain patterned with a patchwork of rice paddies and
fruits orchard.
The natural protected areas in Attapeu are Se Pian and Dong Ampham National Protected
areas. The Eastern slopes of Bolaven plateau in Attapeu are heavily forested and support
various wildlife species. In Attapeu the main crops are growing, rice, coffee, rubber, vegetables
and fruit tree, and others annual crops.
83
Attapue province has the climate of tropical monsoon with 2 distinguished seasons: the dry
season is from November to March meanwhile the rainy season starts from April to October.
The annual average precipitation is 2,100 mm. There are about the average relative humidity is
74%/year. The annual average temperature is 27.5 0C, minimum 14.2 0C, maximum is 39.8 0C.
Figure 25: Temperature in Attapeu
Figure 26: Rainfall in Attapeu
y = 0.009x + 27.53R² = 0.018
26.00
26.50
27.00
27.50
28.00
28.50
29.00
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
Average Temperature of Attapeu
y = -3.403x + 2334.R² = 0.002
0.0
500.0
1000.0
1500.0
2000.0
2500.0
3000.0
3500.0
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
Rainfall in Attapeu
84
4.9.2 Biological Environment
Dong Amphan NBCAis the key natural resources situated in the east and Annamite mountain range of Attapeu province. It is IUCN’s Category VI NBCAconsisting of 197,500 ha of five districts: Saysetha, Samakhixay, Sanamxay, Xanxay and Phouvong and 188 villages. The forest is predominant by lowland evergreen, semi-evergreen and deciduous and dry dipterocarp forest with wide range of elevation from 120 to 2,000 m above sea level. 80 species of mammals, 280 species of birds and 300-400 species of fish and numerous species of reptileswere documented in the area. The key mammals are Douc Langur, Buff-cheeked Gibbon, Fishing and Asiatic Golden Cat, Clouded Leopard, Tiger, Giant and Trong Song Muntjac and Asian Elephants. Key species of birds are Siamese Fireback , Crested Argus , Masked Finfoot , Lesser Fish Eagles , Red-collared and Pale-headed Woodpeckers, Bar-bellied and Blue-rumped Pittas, Grey-faced Tit Babbler, White-rumpedand Red-headed vulture, and Woolly-necked Stork and Great Hornbills.
Figure 27: NBCA in Attapeu
4.9.3 Social environment
As of 2010, population in the Attapeu province reached a total of 120,886 people, 59,521 of
which were female. Lao Loum group occupy 17% and Ethnic minority groups occupy 83%. The
population density is 11.7 persons/ km2. Attapeu is where one can find many minority peoples,
nine major groups are Alak, Katang, Kaleum, Katou, Suay, Nge, Lave, Tahoy, Nyajeung, these
people live and work follows their unchanging lifestyle for century.
The annual growth rate in Attapeu is 2.7%. The birth rate is 3.7% and the mortality rate is 1.6%.
The average life expectancy is 52 and 55.5 for men and women respectively. 95% of the
population lives in rural areas and the majority of economic revenue comes from the agriculture
sector. (UNDP, 2001)
85
The incidence of poverty is highest in the most remote, mountainous areas of the province.
Sanxay and Phouvong are classified as very poor districts, Sanamxai is classified as a poor
district, and Samakkixay and Xaysettha are not identified as poor (Map14, Poverty in Southern
Lao PDR) (GoL, 2003).
GDP per capita is estimated to be at $US350 (the national average at $US 983), and the main
income of population is agriculture production. The irony is that though agriculture is the main
occupation, the province still lacks in foodgrains, especially rice every year.
Attapeu is ranked as the 7th poorest province in the country with 45.9% of the population falling
under the poverty line (based on Lao Expenditure and Consumption Surveys – LECS).
The impact of poverty is especially severe on women. Work that is traditionally done by women includes clearing fallows for agriculture, rearing livestock, and collecting fire wood. Resource depletion and introduction of new diseases results in a larger labour burden for less overall outputs. Women must also conduct their work while raising young children (SPC, 2001).
4.10. ATT COM 2: Integrated Rice-Pulse Based Farming System in Attapeu
4.10.1 Physical Environment
In general, Attapeu province situated in a large valley, surrounded by mountains and 6 main
rivers: Se Kong, Se Kaman Se Sou, Se Nam Noe, Sepien and nam Ngone. The total land area
is 10,320 km2 and quite large parts of areas are in the Bolaven plateau.
Overall, along the rivers are fertile plainsand now becomes a patchwork of rice paddies and
fruits orchard.
The climate is tropical monsoon 2 distinguished into 2 seasons as other provinces.The dry
season is from November to March meanwhile the rainy season starts from April to October.
The annual rainfall is 2,100 mm on average. Humidity is rather high, indicating 74% on
average. The mean annual temperature is 27.5 0C;with minimum of 14.2 0C and maximum of
39.8 0C.
4.10.2 Biological Environment
As mentioned and shown in the map above, the key forest and habitat of the province is Dong Amphan NBCA. However, the NBCA is in the northeast while subproject area is in the middle and southwest, which further away and unlikely to be impacted by subproject.
4.10.3 Social Environment
There are 5 districts: Samakhixai, Xaysettha, Sanamxay, Sanxay and Phouvong and as of
2010, population in the province was about 120,886 people. 59,521 were female. Lao Loum
group occupy 17% and Ethnic minority groups occupy 83%. The GDP per capita is around US$
614 (while the national average is at US$983).17.8 % of households are under poverty line and
some faced rice shortage for every year.
This subproject covered 3 districts namely: Sanamxai, Samakhixai and Xaysettha. Of which,
there are three clusters of villages (Kumb Bans): Hinlat, Phameuang and Thetsaban;and twelve
villages and around 10% of 3 districts population.Of which, women in the subproject target
86
villages presented 52%. The majority or 90% of population are Lao Loum. The rest 10% are
ethnic minority group which include Ta Lieng, La Vai (Samakkhi village and Thetsabane Kumb
Ban); Su and Ya Heun (Tor Mor Yord, Samong Tay villages and Hinlat Kumb Ban). Almost all
the households depend on agriculture.
Main production and income is agriculture. There are4097 ha of rainy season rice paddy which
its productivity is at 2.5 - 2.9 ton/ha;522 ha of dry season paddy which yield a bit better or 4
ton/ha. However, overall, the cultivation area is relatively small considering the area per
households. In addition, livestock also plays important roles of the local economy. There are
about 5-6 thousand of buffalos and cattle, 3 thousand of pigs, a thousand of goat and 61
thousand of poultries are being raised by farmers in the three districts. Table below shows
basic socioeconomic information of targeted villages.
Table 26: Existing conditions of three Kumban
No Item Unit
Kumb Ban
Total of
three
district
% of 3
Kumb
Bans/
district
Pha
meuang
Thetsa
ban Hinlat Total
Total area Ha 5,671 34,643 209,08 612,22 438,949 0.14
1 Agricultural land Ha 2,764 1,581 1,049 5,394 65,340 0.08
2 Rainy season
rice Ha 2,084 1,159 854 4,097 23,905 0.17
3 Dry season rice Ha 212 192 118 522 1,106 0.47
4 Upland rice Ha 0 0 0 0 2 0.00
5 Other crops Ha 0 0 5.95 5.95 690.24 0.01
6 Cattle Head 944 3,847 573 5,364 26,236 0.20
7 Buffalo Head 2,973 2,830 749 6,552 41,381 0.16
8 Pig Head 1,239 1,589 382 3,210 17,370 0.18
9 Goat Head 173 456 190 819 3,670 0.22
10 Poultry Head 18,314 37,692 4,986 60,992 320,553 0.19
11 Fish Ha 0 0.08 0 0.08 1.34 0.06
12 No of population Person 9,544 3,300 12,844 92,130 0.14
13 No. of
household No. 1,953 3,098 602 5,653 23,121 0.24
14
No. of
Agriculture
household
No. 1,726 1,547 558 3,831 19,319 0.20
15
Women is owner
of agricultural
household
Person
s 1,738 39 17,77 3,138 0.57
Source: Statistics survey by PAFO, June 2011 and Attapeu PPO survey, June 2011.
87
CHAPTER 5: POTENTIAL ENVIRONMENTAL IMPACTS AND ASSESSMENT
The potential environmental impacts were identified and assessed through 1) classification of the subproject, 2) identify and 3) assessment with the use of impact checklist and matrix. In addition, the impact identification and assessment were conductedthrough stakeholder consultation. Based on similarity of subprojects type and aspects including impacts; subprojects were classified into three main groups: livestock and small scale agriculture development, infrastructure which includes irrigation and access road.The livestock and small scale agriculture subproject types areSVK COM 10, SVK PR1, SAL PR 1, SEK COM 10, CPA COM 9 and 10, ATP COM 1 and COM 2 while SAL COM1 is irrigation based/prominent subproject10 and SAL COM 4 is road based subproject11. The potential impacts were identified with the use of impact checklist for each type of the subproject.Inwhich the identification of impact covered three main phrases: pre-construction, construction and close or operation of the subproject and also covered most impact areas or targets such as physical, biological and social value. The impacts were assessed with help of impact matrix which looks at impact significance through assessment of types and scales of activities against ecological and social value and also impact duration.
5.1. Livestock and Small Scale Agriculture Development Subproject Type
As mentioned, theSVK COM 10, SVK PR1, SAL PR 1, SEK COM 10, CPA COM 9 and 10, ATP
COM 1 and 2 are livestock and small agriculture development type subproject. Although
impacts and scales might be slightly different especially because of different location
environment and context including different stakeholder involvement and implementation
style;such differencesare not significant or majority of impactsare similar and in overall, can be
one group. So the potential impacts of these subprojects were identified and assessed by use of
same set of impact checklist and matrix. Details of the impacts identification and assessment
forpre-, during and post construction phase of the subproject are as follows.
5.1.1 Environmental Impacts due to the location and Design
Overall there is no significant or direct negative impact at this stage. The key activities during this stage are only survey, selection of location and partnersforestablishing production centres andsmall facilities,livestock pens, maize or crops production areas,preparation of subproject detailed design including improvement options of subproject activities and bidding. These activities are unlikely to cause major impact. However, selection of location and design is crucial because if suitable location and design are not selected; negative impact can be anticipated. So the concern at this stage is that improper selection and/or change of subproject location and design which may result in changing the scope or scale of environmental impacts predicted in
10Irrigation rehabilitation is the main activities that is likely to cause the negative impact
11Road rehabilitation is the main activities that is likely to cause the negative impact
88
the IEE or locating production centres, facilities, livestock pens at inappropriate site such as un-approved areas, forest areas,or unstable or close to community.Another concern is exclusion of environmental management and mitigation measures in biding documents and contracts.
However, the concern or risk is avoidable and shall be addressed through consultation process and use of participatory approach including using appropriate criteria for considerations and selection of suitable sites/areas for the production and processing centres, demonstration, for maize production and include mitigation measures in the contract or agreement.
5.1.2 Environmental problems associated with construction stage
Overall livestock system and agriculture development such as livestock farming, processing and feed and fodder production can cause some negative impacts on physical, biological and social environment such as land and soil, water, air, forest, wildlife and aquatics, health, conflict and disturbance due to solid waste and waste water, odour, noise, forest encroachment and land use conflict due to expansion of maize or fodder production and so on. However, it depends on the type and scale of activities, location, design and implementation methods. As for the SNRMPRP’s proposed livestock and small scale agriculture development subprojects; its main activities in this stage are only establishing livestock producing centres (engaged with and increase production of existing livestock producing centres), demonstration, establish and provision of revolving fund and production group formulation; so only some impacts especially odour, unhygienic environment and health risk are likely to be key issues. The forest encroachment or land use conflicts resulted from maize production could be also issues if there is no appropriate measure in place. Apart from these impacts or risks, it is unlikely to occur or significant. However, such impacts are not significant because the activities are small scale and temporary; majority of livestock and maize production are on existing farming ones.Followings are description ofpotential impacts and impact assessment. 1. Potential impact identification The potential impacts were identified based on activity type, location and implementation mode; with the use of impact identification checklist, site observation and consultation;the results of the identification can be shown as in the Table 30 below.
Table 27: Potential impact from livestock and small scale griculture subproject type
ENVIRONMENTAL AND SOCIAL
ASPECTS
Yes (Likely)
No (Unlikely)
Description
PHYSICAL RESOURCES
Air Quality (GHGs) X
The livestock and agriculture development subproject type are subject to cause increase or change of Greenhouse Gases (GHGs) emission rather than impact on the other aspect of air quality e.g. methane and nitrous from enteric fermentation and manure; carbon dioxide and nitrous from land use change and soil disturbance.
Noise X
Especially at existing pig producing centers and larger farms (20 pigs)
Odor X
Existing pig producing centers, meat processing (slaughterhouse) and large farm where manure and waste water including odor are improperly managed
Erosion/Sedimentation
X In general, the erosion could occur due to maize cultivation especially in steep slope area and maize only cropping. However, in this case it is different maize is promoted on the
89
ENVIRONMENTAL AND SOCIAL
ASPECTS
Yes (Likely)
No (Unlikely)
Description
existing farm land which is plateau or not on steep slope. In addition, some applied intercropping techniques and erosion evident are not found. So it is unlike to occur.
Soil degradation/ Fertility reduction
X
Especially maize production where no intercropping and or rotation cropping is promoted.
Surface water/ Hydrology
X Most of the activity areas are not close to river;no use of huge water from river or cause a hugeland use change in the watershed area. So it could be free from hydrological impact.
Surface water Quality
X Most of the activity areas are not close to and no direct discharge to river.
Groundwater Quality
X
Ground water is perceived to be so deep in the ground (based on observation of wells) while waste water is stored in the concrete or soil packed pond especially producing centers and large farms. So no contact and impact to the ground water are anticipated.
BIOLOGICAL RESOURCES
Forest encroachment
X Producing centers, livestock facilities and processing, maize and fodder producing are mostly on the exiting area. In addition, forest in adjacent area is limited.
Terrestrial Fauna
X Limited forest, river-fauna habitat and fauna in or adjacent subproject activity areas
Aquatic Flora
X Limited forest, river -flora habitat and flora in or adjacent subproject activity areas
Aquatic Fauna
X No river-aquatic habitat and aquatic fauna in or adjacent subproject activity areas
Endangered species
X Irrelevant and no NBCAs, conservation ponds and endanger species in or adjacent areas
Protected areas/ NBCAs etc
X Irrelevant and no impact since no NBCAs in or adjacent areas
HUMAN USE VALUES AND QUALITY OF LIFE
Population and community (disturbance)
See odor and noise mentioned above
Settlements
X None
Infrastructures/Facilities
X No negative impact but positive impacts such as improvement of livestock and farming facilities.
Industries
No negative impact but positive impacts such as improvement commercialization of livestock and agricultural products
Trade and Commerce
No negative impact but positive impacts such as improvement commercialization of livestock and agricultural products
Agricultural Activities
X No negative impact but positive impacts such as improvement livestock health, productivity and commercialization.
Livestock X
Positive impact such as improvement livestock health, productivity and commercialization
Fisheries
X Irrelevant to negative impact but positive impacts (improve fish farming including feeds for fish and reduce feeds cost)
Education
X Irrelevant or no negative impact but positive impacts (improvement skills and knowledge)
Health X
- Positive: improvement of livestock health, sanitation, training and facilities
- Risk: odour, unhygienic livestock handing are existing although minor. Health risk could be anticipated due to someinappropriate management of livestock manures and animal health including techniques, facilities and labour.
Safety
X None/Irrelevant
90
ENVIRONMENTAL AND SOCIAL
ASPECTS
Yes (Likely)
No (Unlikely)
Description
Traffic
X None/Irrelevant
Land use X
Especially for maize and fodder production expansion. However, the subprojects also promote land use planning and preventing encroachment
Land taken/Grasping X
See land use
Tourism and recreational resources
X None/Irrelevant
Aesthetic values
X None/Irrelevant
Historical Treasures
X None/Irrelevant
Cultural Values
X None/Irrelevant
Conflicts X
See land use
2. Impact assessment The impact assessment intends to determine impact significance by considering the impact versus environmental values and scale of the impact. Based on the impacts or risked identified in the Table 28 above, the assessment and outcomes could be assessed and revealed as follows.
Table 28: Impact assessment from livestock and small scale griculture
ENVIRONMENTAL AND SOCIAL
ASPECTS
Intensity12 Extent13 Duration14 Scale or Significance15
Description
PHYSICAL RESOURCES
Air Quality (GHGs)
1 1 3 Low
Intensity: Low:CH4, N2O, CO2 emission from livestock and manure management, maize growing are small scale. In addition,promotion of biogas and intercropping in some areas could help minimizing the emission. Extent: Medium: although the GHGs or global warming is global concern; livestock and agriculture are for livelihood subsistence Duration:Long term: the livestock and agriculture development will be ongoing beyond the timeframe of the subprojects
Noise 1 1 1 Low
Intensity: Low:the disturbance or impact is low due to it couldjust happens only for animals and some cases e.g. when the animals are
12 Intensity: High =3, Medium=2, Low=1
13 Extent: Regional=3, Local (provincial and district)=2, Village or site specific=1
14 Duration: Long term=3, Medium term=2, Short term=1
15High=3, Medium=2, Low=1
91
ENVIRONMENTAL AND SOCIAL
ASPECTS
Intensity12 Extent13 Duration14 Scale or Significance15
Description
hungry and not timely feed, and removal. But it is quite common to local. Extent: village or site specific. Duration: short term: e.g. when the animals are hungry and not timely feed, and removal.
Odor 1 1 1 Low
Intensity: Low:the disturbance or impact is low due to it is small scale, there are some handlings (e.g. use of manure to produce fertilizer, use of EM, dry manure system. in addition, it is quite common to local. Extent: village or site specific:within village’s territory. Duration: short term: e.g. only when the manure is not entirely managed and wet season.
Soil degradation/ Fertility reduction
1 1 1 Low
Intensity: Low:the disturbance or impact is low due to intercropping and application of green manure is promoted. Extent: village or site specific: Duration: short term: during maize production only. Soil fertilizer is expected to recover once other crops and green manure are applied.
BIOLOGICAL RESOURCES
None or insignificant since far from or limited and or important flora, fauna and aquatics including ecosystem in the activity areas. HUMAN USE VALUES AND QUALITY OF LIFE
Health risk 2 1 1 Low
Intensity: Low:the disturbance or impact is low due it could only occur when the manure, waster water and livestock pens are poorly managed or unhygienic (due to shortage of labor) and seasonal disease outbreak. Since livestock health care or vaccination present disease is promoted, some applied biogas and produce manure fertilizer to minimize the manure and water waster, training on how to handle with livestock safely was promoted; it is expected that impact is low. Extent: village or site specific: Duration: short term: e.g. during poorly managed or unhygienic (due to shortage of labor) and seasonal
92
ENVIRONMENTAL AND SOCIAL
ASPECTS
Intensity12 Extent13 Duration14 Scale or Significance15
Description
disease outbreak.
Land use 1 1 1 Low
Intensity: Low:the disturbance or impact is low due to it is mainly promoted on the existing farm land. Extent: village or site specific:land use or expansion of the maize and other production are within each village’s territory or with agreement with other villages if land use is expanded into other village’s territory. Duration: short term: land use planning and allocation is under way. It is expected that land use conflict is minimized n is completed. Or land use conflict may happen only short-term (during land use plan is unclear).
Overall, the impact or risk are minor, however, shall be handled appropriately by performing following key mitigation measures: - Increase awareness/provision of information, include appropriate manure, waste water,
handling, disease prevention, sustainable agriculture and land use planning; - Promote application of manure and waste water or treatment forexisting and demonstration
farms; - Select suitable areas for maize production including promote integrate/rotation cropping and
application of manure while control chemical fertilizer use.
5.1.3 Environmental Problems during Operation
The key activities especially ones that are like to cause negative impacts are producing thousand of piglets, ducks, chicks and millions of fingerlings and especially at the producing centers. In addition, some potential impacts can be taken place due to household livestock raising, meat and fish processing centers. The key impacts or risks are solid waste from vaccination; waste water and odor discharge from livestock breeding centers, processing and pens; disease outbreak and health risk resulted from inappropriate livestock handling, overuse or misuse of manure which can cause water contamination, degradation, and unhygienic environment. These impacts or risks are unlikely critical but it is important to ensure that such impact are avoided or minimized. - Vaccinate livestock and disposal vaccination waste at the suitable area/landfill or otherwise
burning especially contagious waste; - Establish proper discharge and treatment system for treating waste water (waste water
pond, use for crops growing, use bio-extract liquid, risk husks or ash to cope with odor or use manures and waste as the input for biogas production;
93
- Provide training and information or awareness on the hygiene livestock handling practice.
Figure 28: Examples of Pig Farming Situation
94
5.2. Irrigation Development Subproject Type
5.2.1 Environmental Impacts due to the location and Design
The main activities for this stage are survey and detail design including improvement options of subproject irrigation scheme and procurement or bidding. Overall there is no environmental impact in this stage; there is no major change in the project design and location. In addition, majority of activities are not yet implemented. Although the rehabilitation of the irrigation schemes is taken place in the area of Sedone River, there is no valuable forest as well as endangered species of fauna and flora in and adjacent area. Impact on any protected areas and important flora or fauna are not anticipated.
5.2.2 Environmental problems associated with construction stage
Overall there could be negative impacts resulting from irrigation construction such as land grapping, land use conflict and forest encroachment due to expansion of cultivation areas resulted from irrigation expansion; soil salinity due to off and on irrigation;sedimentation; disturb aquatic and fisheries and water use conflict. However, since this irrigation is on the existing or just replace the soil packed canal, expand the concrete canal and repairing some damages of existing concrete canal; no major impacts are likely observed and foreseen. Details of potential impacts and impacts assessment are as follows.
1. Impact identification With the same approach and processes of the impact identification and assessment mentioned above, the potential impacts of the irrigation based subproject can be identified were presented in the Table 32 below.
Table 29: Potential impact from irrigation based subproject type
ENVIRONMENTAL AND SOCIAL
ASPECTS
Yes (Likely)
No (Unlikely)
Description
PHYSICAL RESOURCES
Air quality/Dust/ Pollution emissions
X
Dust and emission could generate from transportation and earth work. But it is so negligible and temporary.
Noise X
Only during use of equipment and construction but it is negligible and temporary
Odor
X No odor is anticipated
Erosion/Sedimentation X
- Erosion and sediment including damage of canal could be happened especially during flooding.
- Sediment could release into the paddy field especially during canal cleaning and flooding
Soil degradation/ Fertility reduction
X
Indirect impact. Improvement can increase cultivation area and frequency; leading to increase synthetic fertilizers.
Surface water/ Hydrology
X
Only small amount of water irrigated compare to discharge of the Sedone River.
Surface water Quality
X Only oil spill from pump repair can cause some impact on the quality. Pump repair is only conducted once a year and usually with care. So oil spill is rarely taken place.
Groundwater Quality
X Most part or project funded is concrete canal. Although irrigation is off (raining season) and on (dry season), it is unlikely to cause impact to ground water.
95
ENVIRONMENTAL AND SOCIAL
ASPECTS
Yes (Likely)
No (Unlikely)
Description
BIOLOGICAL RESOURCES
Forest encroachment
X
Irrelevant. Although there is mangrove forest along Sedone River, the constructions of canals are on the existing alignment or just replace the soil packed canals which are mostly lie down the paddy field.
Terrestrial Fauna
X See forest encroachment above
Aquatic Flora
X Irrelevant
Aquatic Fauna X
Indirect. Only small amount of water irrigated from the Sedone River. Important species of aquatics or fish are rarely found in the River at irrigation area.
Endangered species
X Irrelevant, see forest encroachment above
Protected areas/NBCAs etc
X Irrelevant, see forest encroachment above
HUMAN USE VALUES AND QUALITY OF LIFE
Population and communities/Migration
X None
Settlements
X None
Infrastructures/Facilities X
Existing canal passes through home garden, road and paddy field. Repairing of some damage canal or revitalize the canal could just impact some facilities such as road in the village. However, impact is not significant since it is only some areas, small scale and temporary.
Industries
X Positive but indirect. Improvement of the irrigation schemes could result in increase production and processing including commercialization of rice and rice products.
Trade and Commerce
X See industries above
Agricultural Activities
X See industries above
Livestock X
Open and deep canal could pose a risk to large livestock to fall down and trapped especially off cultivation season when livestock are released for free grazing in the paddy field where open irrigation located.
Fisheries X
- Positive. Irrigation provides fish farming in the rice paddy field
- Negative. Noise and irrigation of water could disturb fishery but it is small scale and temporary
Education
X Irrelevant or indirect positive impact. Improvement irrigation revitalize the water use group performance
Health X
- Risk of falling into the open canal and hurt especially kids. Some kids like playing or having a bath on the canal. Previously kids fell and hurt on the old open canalsin Khamthong and nearby village. However, village leaders already educated and encourage taking care of kids and be aware of such danger.
- No water born disease is anticipated. No water in dry season or off season. Although there is water in the canal during cultivation, raining and flooding period; there was no record.
- Indirect negative impact. Improvement irrigation could lead to increase production area and frequency including pesticide and chemicals use; leading to health risk.
Safety X
See health risk above
Traffic
X Irrelevant. Although there are sometimes transportation of construction materials, it does not cause or increase traffic
96
ENVIRONMENTAL AND SOCIAL
ASPECTS
Yes (Likely)
No (Unlikely)
Description
impact.
Land use
X
Although improvement of irrigation might lead to increase expansion of rice and other cultivation area, expansion is on household land or no land grapping. In addition, it did not happen in the past.
Land taken/Grasping
X See land use
Tourism and recreational resources
X Irrelevant
Conflicts (water use) X
Especially water use or allocation. Although water use conflict could occur e.g. the end or tributary canal rice field might not adequately access to water compare rice field that locate head or main canal. However, it is manageable and addressed by water use group which, from observation, perform pretty well so far.
Aesthetic values
X Irrelevant
Historical Treasures
X Irrelevant
Cultural Values
X Irrelevant
2. Impact assessment Based on the table above, only some environmental impacts or risks associates with those mentioned activities can be taken place but such impacts or risks are minor because activities and most of the impacts small scale, site specific, temporary and manageable.
Table 30: Impact significance of irrigation development
ENVIRONMENTAL AND SOCIAL
ASPECTS Intensity Extent Duration
Scale or Significance
Description
PHYSICAL RESOURCES
Air quality/Dust/ Pollution emissions
1 1 1 Low
Intensity: low disturbance due to temporary and far from community. Although transport of the construction materials on the soil packed road could generate dust and emissions but it temporary and short term. Extent: Site specific e.g. only in traffic road and irrigation construction sites. Duration: temporary e.g. during transport of material and construction of the earth bank canal of irrigation.
Noise 1 1 1 Low
Intensity: low disturbance due to temporary and far from community. Although transport of the construction materials and construction of irrigation release only low noise or common for local (for construction work). Extent: Site specific e.g. only in
97
ENVIRONMENTAL AND SOCIAL
ASPECTS Intensity Extent Duration
Scale or Significance
Description
traffic road and irrigation construction sites. Duration: temporary e.g. during transport of material and construction of irrigation.
Erosion/Sedimentation 1 1 1 Low
Intensity: low disturbance due to low erosions Extent: Site specific e.g. only irrigation back of canal Duration: temporary e.g. during transport of material and construction of irrigation.
Soil degradation/ Fertility reduction
1 1 3 Low
Intensity: low disturbance due to it is indirect impact. Extent: Site specific e.g. only paddy field Duration:Long term: rice growing will be continued for future
Surface water quantity 1 2 3 low
Intensity: only small amount of water irrigated compare to discharge of the Sedone River. Extent: Sedone river Duration: Long term: rice growing will be continued, irrigation is expected to maintain and support the production for future
Surface water Quality 1 1 1 Low
Intensity: only oil spill from pump operation and repair are likely minor Extent: Site specific or only pumping site and near by Duration: Long term: rice growing will be continued, irrigation is expected to maintain and support the production for future
Groundwater Quality 1 1 1 Low
Most part or project funded is concrete canal. Although irrigation is off (raining season) and on (dry season), it is unlikely to cause impact to ground water.
BIOLOGICAL RESOURCES
Aquatic Fauna 1 1 1 Low
Intensity: only small amount of water irrigated compare to discharge of the Sedone River. Extent: Sedone river Duration: Long term: rice growing will be continued, irrigation is expected to maintain and support the production for future
HUMAN USE VALUES AND QUALITY OF LIFE
Infrastructures/ Facilities/ Property
1 1 2 Low
Intensity: low disturbance: existing canal passes through home garden, road and paddy field. Repairing of some damage canal and expansion of concrete canal could just impact some facilities and pieces of rice field Extent: within village or local road and land
98
ENVIRONMENTAL AND SOCIAL
ASPECTS Intensity Extent Duration
Scale or Significance
Description
Duration: Long term or permanent: irrigation will cause the change land use permanently
Health and safety 1 1 1 Low
Intensity:although it is critical issues but fall and hurt are rarely happened. Extent:irrigation canal Duration:temporary
Conflicts 1 1 1 Low
Intensity: it is critical issues but there is rare possibility since water use group is quite strong with good solidarity. Extent:village or water use group Duration:could temporary since it can be solved from time to time
However, the main impacts or risks to be taken into account or monitoring are impact on property (road and home garden), risk of accident, and water use conflicts because if the construction and operation is proceed carelessly.
1) Impact on property Since the existing and damage canal is lined across some home garden and village road, construction/rehabilitation of the canal in these areas can result in damage of home garden and village road if the planning and construction are proceed carelessly, without stakeholder consultation and monitoring. However, these anticipated impacts are not significant because most impacts are small scale, temporary and only few sites. These impacts or risks can be manageable by especially consultation with villagers, road authorities and contractor-ensuring that these issues are included in the contract. In addition, monitoring of the rehabilitation and risks should be conducted regularly to ensure that the risks are addressed properly and timely.
2) Risk of accident The risk of accident is observable due to open deep canal which passes through villages. Kids and large animal could be accidentally fallen and trapped in some areas. In addition, risk of accident can be taken place at where irrigations canal meets road especially during construction of irrigation canal and local passing by. This kind of accident happened during construction of the existing canal. However, these are not major issues oravoidable. This subproject shall address these risks by especially provision of information and education for avoiding such risk or impact. Kids should be kept out of the canal. Good fencing or keep out animal can help preventing animal to access to and falling in the canal. Where possible, cover the canal with durable cover especially ones that are close to houses or community.
3) Water use conflict Although there is water use group which functions very well, due to the level of Sedone River and irrigated water change or so different in dry and raining season which could cause water shortage or flood including maintenance cost; leading to conflict or disruption of the water use group. So monitoring and supporting the water use group is necessary.
99
5.2.3 Environmental Problems during Operation
Improvement of the irrigation scheme could result in increase cultivation area; leading to increase use of chemical fertilizer or pesticides. Based on the current discussion with water users group, many farmers are using and/or intend to apply compostmade of manure instead chemical fertilizer because synthesis fertilizer is costly and while they needs to improve soil fertility. Awareness raising activities will be conducted to enforce appropriate use of agriculture chemicals in accordance with the environmental guidelines for application and control of fertilizer and pesticides developed by Department of Agriculture of MAF. There may be a possibility of overflow and breach of the canals system during flood season. Heavy rain and storm occurred every 3-4 years; causing Sedone River inundated the irrigation and farm land. In 2013, several sites of irrigation canals and pump were damaged. Without flood, the volume of water to be conducted through the system is small; the likelihood of breach is negligible. The water user association (WUA) exists and conducts regular maintenance; clogging and water use conflicts are manageable or unlike to occur.
Figure 29: Irrigation Area Situation
100
5.3. Road Development Subproject Type
5.3.1 Environmental Impacts due to the location and Design
Overall there is no environmental impact in this stage; however, since the design and location are key factors determining the significance of the impact; minimizing or avoiding negative impact can be addressed in this stage to certain extend.
The proposed road construction is located in the existing road where no rare or endangered species of fauna and flora in and adjacent area.Road rehabilitation and improvement will be within the existing Right of Way (ROW) and involves no major design changes in alignment but raising the surface of the road above the flood level. Due to the soil type of sandy and clay loam, there may a need to procure the soil from outside the village.Borrow pits will be located at sites that do not result in erosion. Only government approved quarry sites will be used for construction materials such as stone, sand, and gravel. In addition, compensation should be taken into account for the quarry site selection to avoid compensation or otherwise, compensation for loss of structures and affected persons should be considered.
The road improvement will be done through participation scheme in which villagers will contribute necessary labor for construction and minor regular maintenance (e.g. fill up pot holes, cleaning culvert and road sides) while major road work will be done by machinery of contractor. Some parts of the road pass through undulations with patches of forest areas. However, the forests are not categorized as protected areas and prior clearance from the forest department will be obtained before execution of works.
5.3.2 Environmental problems associated with construction stage
Overall road rehabilitation could bring about negative impacts such as impact on property including land, forest encroachment due to enlargement ofroad ROW, erosion and sedimentation, disturb wildlife, aquatic and fisheries, dust and emissions, health risk and accident etc. However, since this subproject’s road rehabilitation is on the existing or just replaces the soil packed roadwith gravel road. Followings are potential impacts and its significance.
101
1. Impacts identification Based on the similar approach of assessment; the potential impacts can be predicted as presented in the table below.
Table 31: Potential impact from road based subproject type
ENVIRONMENTAL AND SOCIAL
ASPECTS
Yes (Likely)
No (Unlikely)
Magnitude or size (if
yes)
Description
PHYSICAL RESOURCES
Air quality/Dust/ Pollution emissions
X
Moderate
Dust and emission could generate from transportation and earth work and especially during windy period and inadequate watering. However, it is temporary.
Noise X
Insignificant Only during use of equipment but it is negligible and temporary
Odor
X Or irrelevant
Erosion/Sedimentation X
Minor
- Erosion and sediment including damage of canal could be happened especially during flooding.
- Sediment could release into the paddy field especially during canal cleaning and flooding
Soil degradation/ Fertility reduction
X
Insignificant Indirect impact. Improvement road access might lead to increase cultivation area and use of synthetic fertilizers.
Surface water/ Hydrology
X
Insignificant Only a small stream cross the road and no major water work
Surface water Quality X
Insignificant
Only a small stream crosses the road and no major water work. Oil spill, erosion and sedimentation are rarely happened on the stream area.
Groundwater Quality
X Although there is quarry work but it is on soil surface, so it is unlikely to cause impact on ground water.
BIOLOGICAL RESOURCES
Forest encroachment X
Insignificant
Road rehabilitation is on the existing one or ROW, limited forest nearby or no forest on the ROW. However, it could be indirect impact; the improvement of road might lead to expansion agricultural land to forest area elsewhere or further area
Terrestrial Fauna
X See also forest encroachment above
Aquatic Flora
X Only a small stream in the road area, no or limited aquatic life and no major water work. So it is unlikely to cause negative impact.
Aquatic Fauna
X
See above
Endangered species
X See also forest encroachment and aquatics above
Protected areas/NBCAs etc
X See also forest encroachment above
HUMAN USE VALUES AND QUALITY OF LIFE
Population and communities/Migration
X
Insignificant - Especially migration, but it is likely small
scale and there is a control migration measures
102
ENVIRONMENTAL AND SOCIAL
ASPECTS
Yes (Likely)
No (Unlikely)
Magnitude or size (if
yes)
Description
- See dust and noise mentioned above
Settlements
X Irrelevant
Infrastructures/Facilities
X Irrelevant negative impact but positive impacts (improvement of road)
Industries
X
Positive but indirect. Improvement of the road could result in increase production and processing including commercialization of agricultural products such as sweet potato, banana and peanut.
Trade and Commerce
X See industries above
Agricultural Activities
X See industries above
Livestock
X
Irrelevant
Fisheries
X
-
Education
X
Irrelevant or see the impact from dust
Health X
Minor - Construction of road could lead to road
accident and work place accident
- See impact from dust
Safety X
Minor See health risk above
Traffic X
- Negative: Increase some congestion
- Positive: improve traffic in long term and bring about high benefits
Land use X
Minor
- Loss some pieces of land due to quarry sites. However, agreement could be reach with land owners and reciprocal practice is in place e.g. convert quarry site into fish pond.
- Improvement of road might lead to increase areas for crops and demand for land; resulting land grasping land use conflict
Land taken/Grasping X
Insignificant See land use
Tourism and recreational resources
X Irrelevant
Conflicts X
Insignificant Especially land use
Aesthetic values
X Limited or no change of landscape. Only dust, quarry and stock piling could impact on aesthetic value but these are small scale and temporary
Historical Treasures
X No important historical sites encountered
Cultural Values
X Although there is temple and cultural activities, it is unlikely to be impacted
2. Impacts assessment Apart from impact identification, it is important to determine significance of the impact. The significance of the impact, in general, assessed based on the important of the environmental values and degree of disturbance or impact which consider the intensity, extent and duration of the impact. However, presented below are only assessment of the key impacts which are required to be included in the management and monitoring plan.
103
Table 32: Impact significance from road construction
Major Potential Environmental
Impact
Intensity
Extent Duration Significance Description
Loss of land 1 1 3 1
Intensity: some pieces of land area could be lost due to quarry sites and expansion of ROW. However, recovery landscaping and/or convert into fish pond are practiced and likely acceptable by villagers. If consensus is reached by this reciprocal, it would low disturbance. Extent: site specific Duration:permanent
Accident (due to use of careless vehicles and equipment use, busy traffic or congestion, inappropriate construction material stock piling, dust, no use of warning sign and no use of safety equipment etc)
1 2 3 Low
Intensity: low risk since low traffic and local is quite aware of the accident. Construction rules of conduct are in placeand workers are aware of.
Extent:Entire road, camp and quarry site
Duration: long term since local will use road for long term
Health risk due to dust and emissions
2 1 1 Medium
Intensity: every day although watering dust is in place while low risk for exposure to other emissions
Extent: entire road
Duration: long term since road will be used for long term
Local disturbance (traffic, noise, dust etc)
2 1 1 Low
Intensity: it is about medium however it is temporary except dust may last for long since it is soil packed road.
Extent: entire road
Duration: long term
1) Loss of parcel of land As described in the matrix,quarry site and overall construction resulted in loss of some land area due to quarry sites are mostly on the village land. Some of farmers expanded their cultivation land close to ROW. While recovery landscaping and/or convert into fish pond were practiced and acceptable in the villages. So the impacts can beminor.
104
However, there is a need to ensure road construction is only limited to ROW and quarry areas approved by land owners and authorities. In addition, there may need a monitoring of impacted orchards andcompensation may need if monitoring found necessary.
2) Risk due to workplace accidents The accident can be occurred with workers, villagers and other and users. The accident with these groups can be due to use of careless vehicles and equipment use, busy traffic or congestion, inappropriate construction material stock piling, dust, no use of warning sign and no use of safety equipment etc.The accident can be happened especially during construction and quarry; windy, dusty and raining; busy traffic or congestion; transportation and stock piling construction materials. However, these risks can be reduced or avoided. Key mitigation measures are defined in the following table.
3) Health risk due to pollution emissions During construction, at the micro-level and temporary only, air quality may be degraded by generation of dust (SPM) and generation of polluting gases including SO2, NOX and HC (hydrocarbons) for short periods from vehicular movements, site clearance, earth filling and material loading and unloading. However, impact is minimal and manageable or reducible for instance by (i) regular check-up and maintenance of construction equipment; (ii) vehicles delivering loose and fine materials should be covered to reduce spills; (iii) disposal of solid and dangerous materials properly; (iv) train and ensure working safety, and (v) water the road regularly.Key mitigation measures are defined in the following table.
4) Disturbance of local living The disturbance can be occurred to especially four villages that situate on the road or passed by roadand particularly during construction.The disturbance usually are caused by busier traffic, dust, mud, improper stocking construction materials, noise, vibration, quarry and other construction works. However, these are temporary or short term impact and can be addressed by training of workers on the workplace safety, provide and use of safety equipments, create detour and installation of warning and or instruction signage,properly stocking construction materials, maintain vehicles and equipments, careful planning of machinery operation and the scheduling operations properly, provision information for local people and watering the road to reduce dust properly or not too much. Key mitigation measures are defined in the following table.
5.3.3 Environmental Problems during Operation
The key potential negative impacts are increase of emissions and accident due to increase of traffic volume, land and resettlement due to easy access. However, such impacts are not significant and there more positive more than negative impacts. Traffic flow may increase due to improved economic activities associated with better access but such increase is expected to be moderate since main vehicles will be tractors and light vehicles. The impacts such as emissions and accident are also likely minor.
105
The impacts on land use and settlement patterns are anticipated limited. Improved access will inevitably lead to increased in and out migration, but this is likely to occur gradually and over a prolonged period. There will be time for new residential areas to be established. There may, however, be a need to control ribbon development and increase awareness about safety drive.
Figure 30: Road Area Situation
106
CHAPTER 6: MITIGATION MEASURES AND ENVIRONMENT MANAGEMENT AND MONITORING PLAN
6.1. Mitigation Measures and Environmental Management and Monitoring Program
Environmental mitigation measures were included in the Environmental Management and Monitoring Plan (EMMP) which defined key activities that are likely to cause negative impactsduring pre-construction, construction and operation phase; mitigation measures and framework to address such anticipated impacts. Since the key areas of concerned are impacts that may results from three main types of subprojects namely 1) small livestock and agricultural development;2) irrigation development and 3) access road development;therefore, three types of EMMPs were proposed for those types of subprojects, Annex 1, 2 and 3 respectively. In addition, organizational arrangement for implementation of EMMP and grievance mechanism can be referred and/or translated from to what have been described in the section 6.2 below. However, to put theEMMP into practice, it is necessary to develop action plan which defines clearly how to, organizational structures and responsibilities, schedule and budget for implementation of the environmental management and monitoring activities in each phase of project. The detail of action plan will be developed once this IEE report is approved.
6.2. Institutional Arrangement forImplementation of EMMP
The Ministry of Agriculture and Forestry (MAF) is the Executing Agency (EA). Within its Department of Planning (DOP), there is Project Coordination Office (PCO). The PCO is responsible for day-to-day management of the Project. The Provincial Project Office (PPO) which was established within the governors’ office in the Province is responsible for day-to-day management of the Project in the province or field. The Project Steering Committee (PSC) which composed of relevant local agencies such as Provincial Agriculture and Forestry Office (PAFO), Provincial Agriculture and Forestry Extension Services (PAFES), Department of Public Works and Transport (DPWT), Department of Natural Resources and Environment (DONRE) is overall oversee implementation of the project including IEE and EMMP. Within PPO, a staff in the PAFO staff was assigned to responsible for support/coordinatingimplementation of EMMP with coordination with DONRE and DAFO staff charges of environment and reporting to the PPO and then PPO to PCO, DoNRE and the Steering Committee. At district level, A District Agriculture and Forestry (DAFO) staff who in charge of environment implement and reporting the EMMP to PPO with coordination with DoNRE, district natural resources and environment office (NREO) and irrigation constructor.
6.3. Grievance and Redness Mechanism
The grievance and redness mechanism is important tool to handle with complaints and disputes. The grievance and redness mechanism for the project mainly follow the dispute settlement principles and procedures defined in the Prime Minister’s Decree on Environmental Impact Assessment Decree 2010 and Compensation and Resettlement of People Affected by Development Projects 2009 and executed by DAFO/PAFO and under supervision of PCO and EA.
107
Overall, the dispute settlement recommended and agreed by stakeholders for this subproject is step by step approach: 1) pier to pier dispute settling or handling; 2) solved at village level, mediated or arbitrated by village authority; 3) solved at district level, mediated or arbitrated by district authority particularly the environmental management and monitoring authority and 4) or arbitrated by higher level and so on. This means the disputes, conflicts and complaints or problems should be addressed at early stage and as early and as much as possible. Otherwise, it can be brought to solve at higher leveland by third parties such as Economic Dispute Arbitration Organizations or even people court to adjudicate if consensus or even a compromised agreement cannot be reached. However, in any cases, step by step approach including consultation, negotiation and compromise should be the priority dispute settlement approach and channel.The dispute settlement proposal should be in writring and prepared in consultation with and agreed by village authorities. The proposal in words is also possible especiallyduring consultation meeting on IEE and project or IEE and project implementation. In most cases, all relevant evident, references should be recorded and annexed to the proposal. However, proposed through one channel or direct to the project committee-dispute settling committee or coordination points at village, district level etc respectively should be promoted although proposal could be made via national assembly and other organizations. The project committee-dispute settling committee, PCO or coordination points at village, district level etc should have both urgent and regular dispute settling mechanism. The urgent dispute settling mechanism could be an urgent consultation meeting and direct negotiation with disputes proposed body to address the urgent issues immediately or timely manner. Or otherwise, address the issues by using monthly and quarterly meeting as platform for sorting out the disputes. Results of the dispute solving should be communicated with concerned people or bodies efficiently and timely manner.
108
CHAPTER 7: PUBLIC CONSULTATION AND INFORMATION DISCLOSURE
The consultation and information disclosure are specifically stipulated in the Decree on Public Involvement 2012, Decree No. 112 on EIA 2010 and Decree No. 192 on Resettlement and Compensation 2009. The public consultation and information closure about the project and IEEor environmental safeguardsfor this project were conducted during feasibility study, IEE process namely:environmental screening, IEE preparation and finalization. In addition, it should be continued on regular basis through projectconstruction, operation and closure phrases and at various levels (village, district and provincial level) and forms. However, this IEE report focused on the consultation and information disclosure in the IEE processes. The consultation and information disclosure in the IEE processes were conducted mainly during data collection and validation,IEE draft report and IEE report finalization stage. The data collection and validation is an initial stage of IEE, which aims to understand socioeconomic, environmental baseline information and environmental impact or changeswhich may resulted from the subprojects including village level consultation. The activities conducted in this stage included visit subproject location, re-check and discussion with key stakeholders on the socioeconomic and environmental baseline information described in the Feasibility Report;key activities and its potential impactsincluding magnitudes.The visits to some key subprojects are on January 7-12th, 2013; February 19-25th, 2013, March 4-6th,2013and outcomes were briefed in the Table 34 below while met stakeholders from districts and villages were included in the Annex 5.
Table 33: Site visit to key activities during January, February and March 2013
No Subproject visited Summary of the outcomes or findings
1 SVK/COM/10: Promotion of service providers for the commercial production of Native Chickes, Ducks in Savanakhet province
Livestock is the key source of income of the targeted villages though it is small or household scale which livestock pens are located in the residential plots of lands of each household in community rather than separate farm area.Livestock especially pigs are mainly kept in pens while other livestock are mixed pen system and free-grazing. Overall, base on the scale and system of livestock rearing, it can be predicted that there will be no major concerns on the environmental impacts. However, once the farmers get supported by the subproject to expand their production, some environmental issues such as unpleasant odor, noise, unhygienic environment and expose to animal disease outbreak need to be taken into account. So, it was suggested that mitigation measures which may include regular cleaning and removal or use waste or produce manure fertilizer, apply Effective Microorganisms (EM)-where possible and provide knowledge and information about livestock disease prevention should be considered for the up-scaling the production.
2 SAL/COM/01: Integrated Organic Rice Based Farming for the commercialization of
Most of the villages in the SAL COM1 live along Sedone River and mainly growing rice for earning a living. Fishing in Sedone River is only sometimes now due to declining of fishes and aquatics. Electric pump irrigation systems which pump water from support dry season rice growing Sedone River were installed and been used since
109
organic rice cultivation in Khong Sedone district, Salavanh Province
1990s.Most irrigation schemes consist of irrigation head which are made up of concrete and canals which are mainly earth canal. Forest along the River bank and in the villages are limited and land is mainly used for resident, rice paddy and home garden. The proposed irrigation under this subproject is to rehabilitate and expand concrete canal to increase farm area especially in dry season. Based on the observation of the existing environment and proposed activities, it can be predicted that there will notbe major environmental impacts resulted from the activities. However, there are other concerns such cost of eclectic pump which as high as 600,000 LAK per ha per producer. In addition, there could be some risks and conflicts required to be monitored. 1) Risk due to open irrigation concrete canal (kids like to play in the area and water in the canal which is risky to fall on and hurt). 2) Conflicts due to extension of canal while line along with home gardens and paddy field; 3) conflict related to water use (end canal rice paddy may gain less water or water would not be reached especially during dry season.
3 SAL/COM/04: Integrated Commercial Cultivation of Sweet Potato, Peanut and Banana in Lao Ngyam district, Salavanh Province
There are about 9 villages along the existing soil-packed road which will upgraded by this subproject. Main activities in this area are growing and commercializing sweet potato, banana, maize, orchards. Rice paddy is limited. Forest and wildlife are limited in the area. There is a small river in the area but quite far from the road. Road traffic is quite low now but it would increase remarkably because of new road and increase trucks to load the production.So, construction of road (graveled road around 15km) is expected to cause some the environmental impacts and concerns such as 1) health risks due to dust; 2) increase traffic and may accompany with accident and 3) cost to maintain the road. In this regard, It was suggested that road should be watered regularly (1) at least road area in from of each household and (2) entire road by whole village watering scheme-rotation). In order to reduce accident; put a warning signs (slow down, community area, people pass the road etc) and also educate kids not to play on the road. Maintaining the road remains challenge since it involves with high cost and mush depends on government support. However, basically villagers support the road maintenance model which set by the government (30% by villagers versus 70% government).
SAL/PR/01: Bong wood planting in commercial & Improving farmer livelihood in the focus Kumban, Samouay & Taoy district, Salavanh province
Bong Tree caught in the trend and could be important option for income generation, replacing shifting cultivation and reduce collection of Bong Tree’s barks from natural forest that being practiced by targeted villages. Proposed Bong Tree plantation that will be promoted by this subproject are 1-3 ha per household up to 150-200 ha for whole targeted villages. The plantation is planned to locate at the existing shifting cultivation land and no chemical fertilizer is intended to be used. Demand for Bong Tree bark is rather high and good price (5-6,000 LAK/Kg of dry bark). However, only environmental concern is the expansion of the plantation and or expansion of upland rice to forest area especially during first 1-2 yearswhen Bong Tree have not yielded the barks or income from Bong Tree are not generated yet (to buy rice). So, alternative income earning is recommended. In addition, close monitoring is needed to ensure that forest is not converted for upland rice and or Bong Tree.
4 SAL/PR/03: Like other targeted villages that under this SNMPE project, the
110
Promotion of service providers for the commercial Pig, Poultries and Fish Raising in 6 Kumb Ban of Salavanh district of Salavanh province
targeted villages, livestock is a means of income earning and livestock keeping is traditional way and mainly for consumption with basic trading. So, base on the findings, there will not be major environmental impacts apart from unpleasant odor and health risk due to unhygienic circumstances which resulted from livestock waste and waste water. However, basic livestock waste and waste water management are in place such as direct use of manure to crops growing or fish feeding, produce manure fertilizer.
SAL/NRM/01 Integrated Forest Conservation by reducing the slash and burn in Tumlan, Ta Oy and Samouay district, Salavanh Province
The situation is quite similar to the SAL/PR/01 which one of the most concern is forest encroachment. Alternative income generation is also recommended during first 2 years. In addition, close monitoring is needed as well.
5 CPA/COM/10: Promotion of service providers for the commercial Pig in Champasak province
The mission found that, because of location of livestock centers and pens are close to communities, some impacts or risks like livestock activities elsewhere such as unpleasant odor, health risk due to unhygienic circumstances and noise are anticipated. Although impacts are unlikely to be significant but mitigation and monitoring are needed.
CPA/PR/01 Integrated Rice based farming system for food security in Bachieng district, Champasak Province
The subproject promotes agriculture development by mainly enhance the productivity of existing farming. So, no major environmental impact. However, the key concerns to be taken into account are allocation and certificate of 100ha of land for the production; and some impacts caused by irrigation such as water use conflict and irrigation maintenance.
6 SEK/COM/04: Promotion of service providers for the commercial Pig, Poultries, Goat and Fish Raising in 4 Kumb Ban of Thateng district of Sekong province
The site visit revealed that the livestock business is relatively small scale. Because of farmers located livestock pens close to houses and community; unpleasant odor and unhygienic circumstances are concerned people surrounding.Although it would not cause major troublebut mitigation measures are needed to avoid and reduce such foreseen nuisance.
SVK/COM/05: Promotion of Integrated Rice Based Farming System in DIDM Irrigated area Laha Nam-1 and Laha Nam-2 irrigation scheme in Songkhone district of Savannakhet Province
Like other subproject and activities; this subproject just enhances the existing production system which is unlikely to cause major changes and adverse environmental impacts. However, it needs monitoring the impact or conflicts that may arise from the irrigation scheme development, increase utilization of fertilizers and soil nutrients once the farming is expanded or more intensive.In addition, expansion of maize cultivation which may cause land use conflict.
111
The consultation and information disclosure with district and also village authoritiesduring preparation of the IEE was taken place during January 26-30th, 2014. The mission included consultation and soliciting feedback and concerns from key stakeholders and site visits. Table 35 briefed on the site visits and findings and participants in the visit and discussion are as in the Annex 5.
Table 34: Site visit for validation of impacts and stakeholders consultationJanuary 26-30th, 2014
No Date Subproject
1 January 27th, 2014
SVK/COM/10: Promotion of service providers for the commercial production of Native Chickes, Ducks in Savanakhet province
Overall, no major environmental impacts are anticipated. However, there could be some risks such as animal waste and waste water include unpleasant odor and unhygienic circumstances which could results in health risk. Mitigation measures suggested included regular cleaning and efficient use or removal of waste (produce manure fertilizer for home garden, rice growing, orchards and also sell to other producers). In addition, promote use of Effective Microorganisms (EM) to reduce the odor and for waste water treatment.
2 January 28th, 2014
SAL/COM/01: Integrated Organic Rice Based Farming for the commercialization of organic rice cultivation in Khong Sedone district, Salavanh Province
In general, there are only some environmental impacts to be addressed such as impact on property and home garden due to expansion of irrigation canal and risk due to open canal. However, there was also other concern such impact on irrigation due to flood apart from cost of eclectic pump. This is quite challenge since the irrigation design and construction have incorporated flood resilient techniques which was unforeseen. However, it was suggested that close monitoring is needed during flood season. In addition, use of sand packs to support the irrigation canal firmly could reduce the canal damage. And for long term there irrigation development should incorporate climate resilient infrastructure techniques.
3 January 29th, 2014
SAL/COM/04: Integrated Commercial Cultivation of Sweet Potato, Peanut and Banana in Lao Ngyam district
The site visit found that in general there is no major concerns on the environmental impacts by villagers and district stakeholders and no major impact are anticipated. However, dust is confirmed to be the issue. In addition, part from issues anticipated during first visit, the reduction of soil nutrient is likely to be other issue since the land use will be more intensive once road access is easy and farmers increase large production to respond to (sweet potato, banana, peanut etc) demand.
4 January 29th, 2014
CPA/COM/10: Promotion of service providers for the commercial Pig in Champasak province
Overall, although there will not be major concerns on the environmental impacts but unpleasant odor and unhygienic circumstances are needed to be addressed. In addition, traditional manure management such as direct use of manure to crops growing or rice husk to produce manure fertilizer, use of Effective Microorganisms (EM) should be enhanced. Biogas should be sought and applied where feasible.
5 January 30th,
SEK/COM/04: Promotion of service
The issues found and mitigation measures suggested are mainly similar to other livestock promotion
112
2014 providers for the commercial Pig, Poultries, Goat and Fish Raising in 4 Kumb Ban of Thateng district of Sekong province
subprojects.But the issues seem less serious for the subproject and effective monitoring could be sufficient.
Furthermore, the consultation and information disclosure will also be pursued during consultation meetings prior to approval of the IEE and post IEE approval.
113
CHAPTER 8: CONCLUSION AND RECOMMENDATION
10 Environmental Category B out of 70 subproject of the Sustainable Natural Resources Management and Productivity Enhancement Project (SNRMPEP), which promote commercialization of agricultural production, natural resources management and poverty reduction, can be classified as three subsectors or project types namely livestock and agriculture development, irrigation and road.
The impacts of these10 Environmental Category B subprojects were identified and assessed
through desk review, field works, stakeholder consultation and consensus and by using impact
identification and assessment matrix and quality assessment to help judging the significance of
the impacts. The assessment covers three aspects (physical, biological and social environment)
and project phases (pre-, during and post construction).
The mitigation measures for addressing the identified impacts were identified and presented in
the Environmental Management and Monitoring Plan (EMMP) matrix. In addition, institutional
arrangement grievance mechanisms were also recommended to enhance the implementation of
EMMP.
Although the IEE found that 10 category B subprojects are unlikely to cause major or significantenvironmental impacts; to ensure theimpacts are minimized to the possible extend and in appropriate ways,the EMMP may need to be translated in details or fit in to some specific context and effectively implemented.
114
ANNEX 1: ENVIRONMENTAL MANAGEMENT AND MONITORING PLAN OF LIVESTOCK INTERVENTION SUBPROJECTS
Key Activities (Likely to cause
negative impacts)
Potential Impacts and/or Risk
Location Mitigation and/or Enhancement Measures
Monitoring Responsible Institution
Design and Location Survey and design including improvement options of subproject activities and location
There is no or limited direct impact. However, change in subproject’s design especially activities and location options and scales may result in changing the scope or scale of environmental impacts
Entire project area
Consultation with stakeholders to select appropriate location, design with minimal negative impacts. Range of criteria shall be used for location and design assessment and selection.
Entire subproject design including activities, location and mode of implementation
PCO/PPO/ Consultant
Preparation of subproject detailed design and bidding
There is no direct impact. However, exclusion of environmental management and mitigation measures during contracting and construction may lead to increase impact scale and significance
Entire project area
Incorporation of all mitigation measures into the subproject detailed design as well as contract/bidding and also implementation
Incorporation of all mitigation measures into the subproject detailed design as well as contract/bidding and also implementation
PCO/PPO/ Procurement officer/Consultant
Construction Phase
Component 1: Support to Business Support Service Providers (BSSP) Establish 1 pig breeding center (2,000 piglets per year), 2 fish hatcheries (2 million fish fingerlings per year), 1 duckling production center (40,000 ducklings per year), 1 native chick production center (40,000 chicks per year), 1 meat processing center or modern
There is no major impact. However, selection and location of livestock facilities in inappropriate site (e.g. community areas, close to river etc) may cause unpleasant odour, unhygienic environment and other health impact and disturbance.
Target villagers and households
- Consultation with stakeholders to select appropriate sites (develop and use a set of environmentally and technically criteria or conditions for selection of livestock producing centers and pens location as well as service providers
- Monitoring environmental performance of the service providers
- No direct discharge to environment and support improvement the waste
- A monitoring of environmentally and technically criteria used for selection of suitable livestock location as well as service providers
- A quarterly monitoring of implementation od
PCO/PPO/ DONRE/ village authority/ Consultant
IEE SNRMPEP FINAL DRAFT
115
Key Activities (Likely to cause
negative impacts)
Potential Impacts and/or Risk
Location Mitigation and/or Enhancement Measures
Monitoring Responsible Institution
slaughter house and 1 feed production center to produce pig feed, fish and poultry feed.
management facilities. - Promote biogas where feasible.
mitigation measures
- The monitoring can be conducted separately or at anytime PPOs/DAFOs conduct field work or assessment
Support establishment of 100 ha maize production with the use of intercropping for animal feed
Land use conflicts associates with land allocation or expansion for maize production.
Entire villages
Consultation with provincial DONRE, DAFO/PAFO and villagers to identify appropriate land area or follow existing land use plan for maize production.
- A monitoring of land allocation and process and A quarterly monitoring of land use conflicts
PPOs in collaboration with Provincial DONRE and Department of Forestry-PAFO
Selection and location of inappropriate site (e.g. forest areas, cultural or spiritual site, unstable areas etc) may result significant environmental and social impacts.
Maize farm area
- Consultation with stakeholders to select appropriate sites and align with land use plan (develop and use a set of environmentally and technically criteria or conditions for selection of suitable area e.g. existing farm land, avoid expansion on to forest areas including engagement with producer group that encroach forest for cultivation expansion)
- Environmentally and technically criteria used for selection of suitable maize location as well as producer groups
- Suitability of the selected maize location as well as producer groups
PCO/PPO/ DONRE/ village authority/ Consultant
Increase chemical uses and soil degradation or ineffectiveness of the integrated cropping system
Maize farm area
- Follow the farming including best agriculture practice technical guidelines
- An annual monitoring of chemical uses and soil degradation or ineffectiveness of the integrated cropping system
PCO/PPO/ DONRE/ village authority/ Consultant
Operation Phase
116
Key Activities (Likely to cause
negative impacts)
Potential Impacts and/or Risk
Location Mitigation and/or Enhancement Measures
Monitoring Responsible Institution
Component 1: Support to Business Support Service Providers (BSSP) Establish 1 pig breeding center (2,000 piglets per year), 2 fish hatcheries (2 million fish fingerlings per year), 1 duckling production center (40,000 ducklings per year), 1 native chick production center (40,000 chicks per year), 1 meat processing center or modern slaughter house and 1 feed production center to produce pig feed, fish and poultry feed.
Livestock Waste and Outbreak - Increased and
appropriate use of manure could reduce risks
- Appropriate maintenance
of livestock (e.g., housing and animal welfare, waste) could reduce waste and animal and human diseases and nuisance due to odor
- Hygiene and environmental health will be included in training to improve management practices and enhance environmental benefits
- Implement other measures defined in thecontractor contract
- An semi-annual monitoring of disease outbreak/reduction and waste disposal
PCO/PPO/ DAFO/Consultant
Hygiene and Environmental Health - Disease control through
vaccination will improve the animal health and prevents outbreak
- If vaccination of large number of animal is needed, inappropriate disposal of vaccination pose some negative impacts
- - Introducing the guideline for disease control or regulation of ill livestock trading
- Provide training and information about hygiene practices, safety livestock keeping/handling including risk due to exposure or contagious diseases
- Regular monitoring and vaccination - Implement measures above (regular
cleaning, promote appropriate use of manures etc)
- Provide or ensure supply and use safety equipments
- Provided trainings and information (quarterly monitor)
- Vaccination (semi-annual)
- Cleaning and use of safety equipments (quarterly or anytime of field visit)
- Hygiene (quarterly or anytime of field visit)
PCO/PPO/ DAFO/Consultant
- Unpleasant odor generated from manures and waste water (due to increase production, aged waste water storage, treatment facilities and shortage of
- - Provide training and information of new techniques about odor elimination (e.g. development and application of BM, use of manure for producing fertilizer, design of the waste water storage/treatment facilities
- Regular cleaning (e.g. every day) and
A quarterly or anytime of field visit monitoring of: - Odor and odor
management - Villagers’ feedback
or petition (about
PCO/PPO/ DAFO/DONRE, Consultant
IEE SNRMPEP FINAL DRAFT
117
Key Activities (Likely to cause
negative impacts)
Potential Impacts and/or Risk
Location Mitigation and/or Enhancement Measures
Monitoring Responsible Institution
labor) removal of the manure to appropriate area, use for farming or sell to other producers/farms
- Promote use including commercialization of manure including waste water to produce gas through biogas digester or
- Enhance the traditional manure producing technique/ practice where appropriate (e.g. use of rice husk to mix and ferment with waste water and manure to produce manure fertilizer) including increase labor
- Promote and/or support improvement of the water storage/treatment facilities
odor)
Support establishment of 100 ha maize production with the use of intercropping for animal feed
Land use conflicts associates with land allocation or expansion for maize production.
- Consultation with provincial DONRE, DAFO/PAFO and villagers to identify appropriate land area or follow existing land use plan for maize production.
- Set up and apply appropriate redness and grievance mechanism
Negative impacts or conflicts due to land use change (A quarterly monitoring or as part of the routine work of project/DAFO/PPO)
PPOs in collaboration with Provincial DONRE and Department of Forestry-PAFO
Increase or otherwise stabilization in encroachment of forest or shifting cultivation (due to increased income, labor generated from feed and livestock production)
- Consultation with provincial DONRE, DAFO/PAFO and villagers to identify appropriate land area or follow existing land use plan for maize production.
- Avoid engagement with producers who encroach forest for expansion of the maize area or ensure the selection of suitable producer groups to participate in the project
- Change in the trend in shifting cultivation will be monitored through collaborating with the department of forestry to monitor the trend once a year (A quarterly monitoring or at anytime of field visit)
- A monitoring of
PPOs in collaboration with Provincial DONRE and Department of Forestry-PAFO
118
Key Activities (Likely to cause
negative impacts)
Potential Impacts and/or Risk
Location Mitigation and/or Enhancement Measures
Monitoring Responsible Institution
selection of suitable producer groups to participate in the project
UXO Risks - The existing land being
used for communal or other productive activities will be converted to forage and livestock production. Thus, very minor UXO risk is expected.
- Government clearance will be sought prior to implementation
- Consultation with provincial UXO authority and villagers to identify appropriate land area or follow existing land use plan for maize production.
A quarterly monitoring or at anytime of field visit or during accident
PPO, PCO and UXO authority
Soil, Water Degradation and Health Risk - A risk of declining
nutrients in the soil due to continual and long-term maize production or including erosion
- Potential soil, water contamination and health impacts due to overuse of manure and/or inappropriate handling of manure
- Through training, appropriate handling and application of manure to land will be promoted
- Improve soil fertility and discourage use of chemical fertilizer
- Reduce soil and water degradation by promoted integrated cropping and application of nitrogen fixation crops
- An or semi-annual monitoring of capacity building
- An annual soil and water quality monitoring will be conducted through (i) visual inspection by project and DONRE; (ii) annual soil and water quality sampling if deems necessary; and (iii) health (of targeted groups)
PPO, PCO in collaboration with Provincial DONRE and Department of Health
IEE SNRMPEP FINAL DRAFT
119
ANNEX 2: ENVIRONMENTAL MANAGEMENT PLAN FOR THE KONGSEDONE IRRIGATION INTERVENTION SUBPROJECT: SAL/COM/01
Intervention Stage/Activity
Potential Impacts Location Mitigation Measures Monitoring Responsible
party Preliminary Planning and Design Stage Survey and improvement options of subproject irrigation scheme
There is no or limited impact. However, major concern is the changes in design and/or location of the irrigation especially during the detailed design which may require adjustment of the scope and scale of impacts
Entire subproject length
Select best design option and alignments (e.g. existing alignment) which is avoidable widening or expansion on to agricultural land, other properties and fragile area
A monitoring of widening or expansion on to agricultural land, other properties and fragile area during selecting options
PCO/PPO/ Design Engineer/ Consultant
Preparation of subproject detailed design and bidding
There is no or limited impact. However, major concern is that environmental management and mitigation measures are not adjusted and incorporated in the final detailed design, bidding or prior to construction
- Revisit and adjust the IEE in accordance with the final detail design approved to ensure that all mitigation measures are incorporated into the final detailed design and contract bidding documents including contractors’ contracts
A monitoring of incorporation of revised measures in the final detailed design, contract bidding documents including contractors’ contracts
PCO/PPO/ Design Engineer/ Consultant
Construction Stage
Re- embankment (of canal) and construction of the concrete canals
- Disposal of silts or cut soil or canal bank erosion onto the paddy and home garden or inappropriate area nearby
Along the irrigation scheme, and especially along the rice paddy and home garden
- Disposal of silts or cut soil onto appropriate areas or for pack in the canal and avoid disposal which cause impact on the rice paddy and home garden
- Ensure the quality of embanking work, and use of bio engineering techniques (grass) to maintain or cover to stabilize canal slope.
A quarterly or at anytime or routines of PCO/PPO/ Contractor conducting monitoring of disposal of silts, erosion and its associated impacts including in place mitigation measures
PCO/PPO/ Contractor
- Accident due to Along the - Inform and educate the A semi-annual or at anytime
120
Intervention Stage/Activity
Potential Impacts Location Mitigation Measures Monitoring Responsible
party uncover canal irrigation
scheme, and especially deep and close or pass by village canal
villagers about the risk or danger about uncover canal (e.g. fall and hurt into the canal)
- Cover the canal with local materials where appropriate or high risk (fall and hurt)
of field work monitoring of awareness activities and accidents including made solutions.
Disturbance of cultivation Entire irrigation scheme
Inform the villagers construction period and avoid during cultivation period
A semi-annual or at anytime of field work monitoring of the disturbance, feedback and implemented measures
Contractor, PCO/PPO
Unexpected environmental problems/calamities (floods) during construction activities
Destruction of constructing irrigation canal/scheme
Entire irrigation scheme
- Avoid construction during rainy season and flooding period
- Ensure quality of the construction
- Where possible/appropriate, incorporate flood resilient techniques
- Undertake appropriate and immediate remedial actions in coordination with relevant government and local agencies.
A few monitoring during raining seasons or at anytime of field work monitoring of flood risk and damages and solution measures.
Contractor, PCO/PPO
Implementation of EMP during construction.
Inadequacy of environmental management measures or deviation from the EMP measures mentioned in the contract documents or during construction.
Entire irrigation scheme
Strictly following and implement the EMP measures mentioned in the contract documents or adopt suitable measures with consultation with relevant organizations
A semi-annual EMMP implementation assessment
PCO/PPO/ ADB /Contractor
Operation Stage
Water use/allocation Water use/allocation conflict
Entire irrigation scheme
Maintain effective water use mechanism
A quarterly or at anytime of field work monitoring of water use and conflicts or feedback from local
Water use group
IEE SNRMPEP FINAL DRAFT
121
Intervention Stage/Activity
Potential Impacts Location Mitigation Measures Monitoring Responsible
party
Increased use of agricultural chemicals
Increased use of agricultural chemicals (insecticide and fertilizers) and consequent pollution of groundwater and rivers due to increased intensity of irrigation.
Entire irrigated areas
- Awareness raising to enforce and promote IPM and the existing environmental guidelines on application and control of fertilizer and pesticides developed by Department of Agriculture.
- Train and promote application of green manure and herbicide
An annual or at anytime of field work monitoring of on chemical uses and impacts/risks
Provincial Department of Irrigation/ Producer group
PAFES
122
ANNEX 3: ENVIRONMENTAL MANAGEMENT PLAN OF THE LAO NGAM ROAD INTERVENTIONSUBPROJECT: SAL/COM/04
Intervention Stage/Activity
Potential Impacts Location Mitigation Measures Monitoring Responsible
party
1. Preliminary Planning and Design Stage
1.1 Improvement options of road
Location on agricultural land, dense forests, wildlife habitat, unstable sites and religious/ cultural sites.
Change in improvement options determined during the detailed design stage, which may result in changing the scope or scale of environmental impacts predicted in the IEE.
Entire road length
Avoid widening on to agricultural land, dense forests, wildlife habitat and unstable sites. Also avoid widening into religious/cultural sites.
Undertake additional environment studies for new alignments (if required).
A monitoring of road options, impacts and mitigation measures
PCO/PPO/ Design Engineer/
Consultant
1.2 Location of quarry sites and borrow pits
Location in un approved areas, forest areas,or unstable or village areas
Quarry sites Only government or local authority approved quarry sites should be used.
An monitoring of selected quarry sites
PCO/PPO/ /Supervision Consultant
1.3 Preparation of a detailed design and contract including bidding
Exclusion of environmental management and mitigation measures during construction
Incorporation of all mitigation measures into the detailed design and contract bidding documents
See the monitoring during construction and operation phase
PCO/PPO/ Design Engineer/ Consultant
1.4 Removal of encroachment /structures along the road.
Loss of livelihood and structures.
Locations where resettlement required
Compensation for loss of structures should be provided and affected persons should be rehabilitated as per the provisions of resettlement plan.
- Regular monitoring of the impact and solutions
- Quarterly or at anytime of field visit monitoring of affected people livelihood and feedback
PCO/PPO /Supervision Engineer/
Consultant
IEE SNRMPEP FINAL DRAFT
123
2. Construction Stage
2.1 Removal of tress and vegetation
Change in micro level habitat/environnent. Soil erosion, scarring of landscape.
Entire length with vegetation.
Removal of only necessary vegetation. Re-vegetation of the space available on left and right boundary of the road with suitable soil conserving plants immediately after earth removal activities.
Removal of trees should be avoided and/or compensated in consultation with the PAFO
A quarterly or at anytime of field visit/routine monitoring of tress and vegetation and implementation of measures
Contractor/Forest Department/
PCO/PPO (DPWT)
2.2 Quarry, crushing of stone and transport of stone and materials.
Dust pollution for construction labourers and local vegetation. Air pollution from machinery and vehicle exhaust. Noise pollution and disturbance to nearby wildlife.
Stone crushing sites and road construction
Water sprinkling of stone crushing site. Proper coverage of vehicle transporting stone and material. Regular maintenance of machinery and vehicles.
Stone crushers should be located away from settlements and forest stretches.
A semi-annual monitoring of quarry and pollutions, health impacts or feedback from surrounding communities
Contractor/ PCO/PPO (DPWT)/ /Department of Geology and Mining
2.3 Cutting of hill slope and earth removal from borrow areas
Soil erosion and landslides. Scarring of landscape due to improper disposal of debris. Dust pollution. Disruption of local drainage. Siltation in nearby water river bodies and hence negative effects on aquatic ecology.
Hilly section along the road, and location near rivers or streams
Use of cut and fill method. Disposal of debris at proper disposal site. Use of bio engineering techniques to maintain stability of slope above and below ROW. Avoid placing hairpin bends very close to each other as it enhances erosion. Proper re-vegetation of borrow areas. Provision of appropriate drainage structures/facilities.
A semi-annual or at anytime of field visit monitoring of erosion and prevention measures
Contractor / PCO/PPO (DPWT)
2.4 Operation of machinery and equipment and general activities of
Spillage/leakage of chemicals and oil and contamination of soil and water resources. Injury to labourers. Respiratory problems
Construction site
Proper storage and handling of chemicals and oil. Provision of adequate facilities such as construction hats, facemasks,
A annual or at anytime of field visit monitoring of waste handling and
Contractor / PCO/PPO (DPWT)
124
labourers from dust and machinery emissions. Hearing problem due to high level of noise. Traffic delays and congestion.
earplugs, gloves etc. Provision of well equipped First Aid Kit and health facilities. Preparation of traffic control plans, proper maintenance of road surface to allow smooth flow of traffic.
pollutions including impacts and enforced measures
2.5 Unexpected environmental problems/calamitie(egg. flash floods) during construction activities
Destruction of constructed road and road furniture, injuries, loss of lives and property,
Construction camp and sites
Undertake appropriate remedial actions in coordination with relevant government and local agencies.
A semi-annual or during raining seasons monitoring of such events, measures and readiness.
Contractor/PCO/PPO/
DPWT
3. Operation Stage
3.1 Movement of vehicles
Air pollution from emissions. Noise and vibrations causing disturbance to residents and wildlife. Contamination of soil and water resources due to poor drainage.
Along the road
Periodic cleaning of drains. A semi-annual or at anytime of field visit monitoring of pollutions, health impacts or feedback
Contractor/PCO/PPO/DPWT
/villagers
IEE SNRMPEP FINAL DRAFT
125
ANNEX 4: LIST OF KEY PARTICIPANTS OR CONTRIBUTORS IN IEE REPORT DEVELOPMENT
1. Central level
No Name Position Remarks 1 Mr.Vinoth Vansy National Project Director 2 Dr. Kulwant SINGH Project Team Leader 3 Dr. Sengkum Deputy Team Leader 4 Dr. Boundeth National Project Assistant 5 Mr. Buageun Khansabaph Procurement Specialist 6 Ms. Sisavanh Phanouvong, Senior Project Officer, ADB
LRM
2. Provincial, district and villager level
No Name Position Organization Remarks I Savannakhet province 1 Olavanh
SAMARTHMANIVONG PPD Savannakhet PPO
2 Ms. Xaysavath Technician, safeguard official
Savannakhet PPO
3 Mr. Phaysanh Technician, safeguard official
Savannakhet PPO
4 Ms. Chanthala Chansima Technician, safeguard official
Savannakhet, DONRE
5 Mr. Phouthone Vethtavong Subproject coordinator
Savannakhet PPO
6 Mr. Vixay Pig producer/ supplier
Private sector
7 Mr. Aek Pig producer/ supplier
Private sector
8 Mr. Vieng Manivong Village member, pig keeper
Phonesim village, Kaisonephomevihanh Disitrict
9 DPPO Attapeu DONRE 10 Technical staff Attapeu DONRE II Salavanh province 1 Sonemany DOUANGVILAY PPD Salavanh PPO 2 Khampeu PHAPHOUGEUN Provincial Land-
Use Planning Specialist
Salavanh PPO
3 Mr. Somechan Keomanivong
Technician DAFO of Kongseone, Salavanh
4 Mr. Khamsavai Keovongsack
DAFO of Kongseone, Salavanh
5 Mr. Kongchai Kongheungsy Villager member Khamthong Village, Kongsedone District
6 Mr. Samly Villager member Khamthong Village Kongsedone District
7 Mr. Bounchan Villager member Khamthong Village, Kongsedone District
8 Mr. Sing Villager member Khamthong Village, Kongsedone District
9 Mr. Lom Deputy head of Khamthong Village,
126
village Kongsedone District 10 Mr. Bounpone Villager member Beungkang Village,
Kongsedone District
11 Mr. Khamdy Villager member Beungkang Village, Kongsedone District
12 Mr.Hinphet Villager member Beungkang Village, Kongsedone District
13 Mr. Khaenchai Head of village Ngew village, Lao Ngam District
14 Mr. Dan Head of village Ngew village, Lao Ngam District
15 Ms. Koukeo Head of women union
Ngew village, Lao Ngam District
16 Mr. Khamveung Villager member Ngew village, Lao Ngam District
17 Mr. Singchalot Villager member Ngew village, Lao Ngam District
18 Mr. La Villager member Ngew village, Lao Ngam District
19 DPPO Attapeu DONRE 20 Technical staff Attapeu DONRE III Champasak province 1 Bounheng AMPHAVANH PPD Champasak PPO 2 Livestock and
fishery technical center
Pakse district
3 Ggoat rearing
center
Kahe Village
4 Mr. Bounchanh Fish hatchery owner
5 Mr. Somphoung Fish hatchery owner
Kang village, Pakse district
6 Mrs. Mekohum
Pig farm owner Khae village
7 Mr. Dang Pig farm owner Khae village 8 Mrs. Maikenthong
Pig farm owner Huein Teng village
9 DPPO Attapeu DONRE 10 Technical staff Attapeu DONRE IV Sekong province 1 Bounsong LAMMANGOTH PPD Sekong PPO 2 DDG of PAFO Owner of fish
hatchery, pig farm, slaughter house and a feed processing centre
HuaiKien village in Lamam district
3 Mr. Damang Livestock farmer/villager
Dang village
4 Mr. Wat Slaughter House Owner
5 Mr. Saiyasen Model Fish Farmer Moh village 6 DPPO Attapeu DONRE 7 Technical staff Attapeu DONRE V Attapeu province 1 Sengsoth MAIBOUNMANY DPPD Attapeu PPO 2 DPPO Attapeu DONRE 3 Technical staff Attapeu DONRE
IEE SNRMPEP FINAL DRAFT
127
4 Mr.Sombat
Technical staff PAFO Attapeu
5 Mrs. One Ta
Head of DAFO Samakhixai district
6 Mr. Vilaysack
Head of DAFO Xaysettha district
7 Mr. XayLamphan
Technical staff Pha Mouang Kumb Ban, Xaysettha district
Mr. Phouvieng
Village Head Vat Neu village, Xaysettha district
8 Mr.Phonthalay,
Technical staff Attapeu PPO
9 Mr.Chanthasone
Technical staff DAFO staff,
Samakhixai district
10 Mr.Thonmay
Technical staff DAFO staff,
Samakhixai district
11 Mr. In Pan Village Head Samakkhi village 12 Mr. Boua Li Villager Samakkhi village 13 Mrs. Phountone Fish Fingerling
Farm Napong village
14 Mrs. Vilaphone feed factory and pig farm
Village
15 Mr. Man
Piglet breeding farmer
Village
16 Mr. Sengphachanh Slaughter House Village
17 Mrs. Kon Chang, Slaughter House Village
18 Mr. Kampenyang, head of village Piyakeu village
19 Mr. Khamule Chicken Farm owner
Kheu village
20 Mrs. Kampaseu
Owner of piglet breeding center
Sapauthong village
21 Mr.Intnah Owner of piglet breeding center
Sapauthong village