Sustainable Airport Master Plan (SAMP) Update · 20/06/2018  · SUSTAINABLE AIRPORT MASTER PLAN...

20
SUSTAINABLE AIRPORT MASTER PLAN (SAMP) UPDATE Public Open House and Presentation June 20, 2018

Transcript of Sustainable Airport Master Plan (SAMP) Update · 20/06/2018  · SUSTAINABLE AIRPORT MASTER PLAN...

Page 1: Sustainable Airport Master Plan (SAMP) Update · 20/06/2018  · SUSTAINABLE AIRPORT MASTER PLAN (SAMP) UPDATE. Public Open House and Presentation. June 20, 2018

SUSTAINABLE AIRPORT MASTERPLAN (SAMP) UPDATE

Public Open House and PresentationJune 20, 2018

Page 2: Sustainable Airport Master Plan (SAMP) Update · 20/06/2018  · SUSTAINABLE AIRPORT MASTER PLAN (SAMP) UPDATE. Public Open House and Presentation. June 20, 2018

2

WHY ARE WE HERE?• Why have a Master Plan?

o Responsibility to meet demando Without a plan, more congestion, traffic, flight delays

• What you’ll see todayo Phased approach to master plano Focus on near-term projects

• What happens after today?o Environmental scoping begins July 23o Official comments meetings week of Sept 10

Page 3: Sustainable Airport Master Plan (SAMP) Update · 20/06/2018  · SUSTAINABLE AIRPORT MASTER PLAN (SAMP) UPDATE. Public Open House and Presentation. June 20, 2018

3

SEA-TAC STATISTICS

• Ninth busiest passenger airport and 15th busiest for operations in the United States

• 69.4% of passengers began or ended their flight in Seattle in 2016

• Passenger numbers grew 2.6% in 2017 and 34.8% from 2013-2017

• Operations grew 1% in 2017 and 31% from 2013-2017

• Both Alaska and Delta are increasing service at Sea-Tac Airport

• Sea-Tac has 45 international services, with 22 airlines serving 27 international destinations

Page 4: Sustainable Airport Master Plan (SAMP) Update · 20/06/2018  · SUSTAINABLE AIRPORT MASTER PLAN (SAMP) UPDATE. Public Open House and Presentation. June 20, 2018

4

REGIONAL GROWTH & MARKET DEMAND

Page 5: Sustainable Airport Master Plan (SAMP) Update · 20/06/2018  · SUSTAINABLE AIRPORT MASTER PLAN (SAMP) UPDATE. Public Open House and Presentation. June 20, 2018

5

LOW UNEMPLOYMENT

0.0%1.0%2.0%3.0%4.0%5.0%6.0%7.0%8.0%9.0%

10.0%

Feb-12 Feb-13 Feb-14 Feb-15 Feb-16 Feb-17 Feb-18

King County Washington United States

King County unemployment remains low, at 3.7% in February 2018

Page 6: Sustainable Airport Master Plan (SAMP) Update · 20/06/2018  · SUSTAINABLE AIRPORT MASTER PLAN (SAMP) UPDATE. Public Open House and Presentation. June 20, 2018

6

ROBUST REGIONAL ECONOMY

Puget Sound is home to a wide range of employers that contribute to the vibrant growth in the region.

Page 7: Sustainable Airport Master Plan (SAMP) Update · 20/06/2018  · SUSTAINABLE AIRPORT MASTER PLAN (SAMP) UPDATE. Public Open House and Presentation. June 20, 2018

7

REGIONAL GROWTH & MARKET DEMAND

Puget Sound is home to a wide range of employers that contribute to the vibrant growth in the region.

SEA-TAC GROWTH TRACKS WITH REGIONAL GROWTH

7

Page 8: Sustainable Airport Master Plan (SAMP) Update · 20/06/2018  · SUSTAINABLE AIRPORT MASTER PLAN (SAMP) UPDATE. Public Open House and Presentation. June 20, 2018

8

SEA-TAC OPERATIONS OVER TIME

Source: Historical – Seattle-Tacoma International Airport recordsSAMP Forecast: LeighFisher, based on data available through September 2014

Page 9: Sustainable Airport Master Plan (SAMP) Update · 20/06/2018  · SUSTAINABLE AIRPORT MASTER PLAN (SAMP) UPDATE. Public Open House and Presentation. June 20, 2018

9

CONCURRENT STRATEGIES TO SERVE MARKET DEMAND

Current Projects (46.9M PAX Today)

Near-Term Projects SAMP(56M PAX by 2027)

Long-Term Vision SAMP(Demand Beyond 2027)

• North Satellite

• International Arrivals Facility

• Concourse D Hardstand Holdroom

• Baggage Modernization

• Airport dining and retail development

• Meet market demand

• 19 additional gates &second terminal

• Cargo facilities

• 30+ projects to improve safety, provide support facilities, improve efficiency, and access to the airport

• PSRC regional aviation baseline study

• Sea-Tac Airport airfieldand airspace study

• Additional environmental review

Page 10: Sustainable Airport Master Plan (SAMP) Update · 20/06/2018  · SUSTAINABLE AIRPORT MASTER PLAN (SAMP) UPDATE. Public Open House and Presentation. June 20, 2018

10

SUSTAINABLE AIRPORT MASTER PLAN (SAMP)

Master Plan stages

• Inventory

• Forecasts

• Facility requirements

• Planning alternatives

• Environmental review

• Implementation plan

• Plan of Finance• Airport Layout Plan approval

Page 11: Sustainable Airport Master Plan (SAMP) Update · 20/06/2018  · SUSTAINABLE AIRPORT MASTER PLAN (SAMP) UPDATE. Public Open House and Presentation. June 20, 2018

11

CONCURRENT STRATEGIES TO SERVE MARKET DEMAND

Current Projects (46.9M PAX Today)

Near-Term Projects SAMP(56M PAX by 2027)

Long-Term Vision SAMP(Demand Beyond 2027)

• North Satellite

• International Arrivals Facility

• Concourse D Hardstand Holdroom

• Baggage Modernization

• Airport dining and retail development

• Meet market demand

• 19 additional gates &second terminal

• Cargo facilities

• 30+ projects to improve safety, provide support facilities, improve efficiency, and access to the airport

• PSRC regional aviation baseline study

• Sea-Tac Airport airfieldand airspace study

• Additional environmental review

Page 12: Sustainable Airport Master Plan (SAMP) Update · 20/06/2018  · SUSTAINABLE AIRPORT MASTER PLAN (SAMP) UPDATE. Public Open House and Presentation. June 20, 2018

NEAR-TERM PROJECTS – MAJOR IMPROVEMENTS

12

Westside Maint. Campus

Hardstand - northNorth GatesHardstand - central

Second TerminalRoadway ImprovementsBusway & StationsFuel FarmExpansion

Taxiway A/B Extension

ARFF Relocation

Highspeed Exit

Taxiway D Extension

Airline Support

C4S Warehouse Redevelopment

Page 13: Sustainable Airport Master Plan (SAMP) Update · 20/06/2018  · SUSTAINABLE AIRPORT MASTER PLAN (SAMP) UPDATE. Public Open House and Presentation. June 20, 2018

13

CONCURRENT STRATEGIES TO SERVE MARKET DEMANDCurrent Projects

(46.9M PAX Today)Near-Term Projects SAMP

(56M PAX by 2027)Long-Term Vision SAMP(Demand Beyond 2027)

• North Satellite

• International Arrivals Facility

• Concourse D Hardstand Holdroom

• Baggage Modernization

• Airport dining and retail development

• Meet market demand

• 19 additional gates &second terminal

• Cargo facilities

• 30+ projects to improve safety, provide support facilities, improve efficiency, and access to the airport

• PSRC regional aviation baseline study

• Sea-Tac Airport airfieldand airspace study

• Additional environmental review

Page 14: Sustainable Airport Master Plan (SAMP) Update · 20/06/2018  · SUSTAINABLE AIRPORT MASTER PLAN (SAMP) UPDATE. Public Open House and Presentation. June 20, 2018

LONG-TERM VISIONAdditional planning to meet demand beyond 2027

14

Page 15: Sustainable Airport Master Plan (SAMP) Update · 20/06/2018  · SUSTAINABLE AIRPORT MASTER PLAN (SAMP) UPDATE. Public Open House and Presentation. June 20, 2018

15

PURPOSE OF ENVIRONMENTAL REVIEWNational Environmental Policy Act (NEPA)State Environmental Policy Act (SEPA)

• Objective analysis of potential cumulative environmental impacts according to established procedures

• Verification of existing conditions and planning forecasts

• Identify ways to avoid, minimize, or mitigate impacts

• Public disclosure of environmental impacts

• Transparency and engagement key to process

• Overlay of environmental laws

Page 16: Sustainable Airport Master Plan (SAMP) Update · 20/06/2018  · SUSTAINABLE AIRPORT MASTER PLAN (SAMP) UPDATE. Public Open House and Presentation. June 20, 2018

NEAR-TERM PROJECTS – ENVIRONMENTAL REVIEW

16

Page 17: Sustainable Airport Master Plan (SAMP) Update · 20/06/2018  · SUSTAINABLE AIRPORT MASTER PLAN (SAMP) UPDATE. Public Open House and Presentation. June 20, 2018

17

SAMP ENVIRONMENTAL REVIEW

A single NEPA and SEPA document and process (12-18 months)

• DRAFT NEPA Environmental Assessment (EA) anticipated*- Final form of document depends on results- NEPA EA allows for maximum Port of Seattle involvement- Analysis driven by issues and standards. FAA is lead agency

• DRAFT SEPA Environmental Impact Statement (EIS) anticipated- Maximizes agency and public engagement- Analysis driven by issues and standards. Port is lead agency

*NEPA EIS automatic triggers are new airport, runway, or major runway extension

Page 18: Sustainable Airport Master Plan (SAMP) Update · 20/06/2018  · SUSTAINABLE AIRPORT MASTER PLAN (SAMP) UPDATE. Public Open House and Presentation. June 20, 2018

18

ENVIRONMENTAL IMPACT CATEGORIES• Air Quality & Greenhouse Gases• Coastal Resources• Compatible Land Use• Construction Impacts• Public Land & Recreational

Impacts• Endangered and Threatened

Species• Essential Fish Habitat• Migratory Bird Act• Floodplains• Solid Waste Impacts• Cumulative Impacts• Hazardous Materials

• Historical & Archeological Resources• Light Emissions & Visual Impacts• Energy Supply & Sustainable Design• Noise• Induced Impacts• Socio-Economic• Environmental Justice• Environmental Health• Water Quality• Wetland• Transportation• Shoreline

Page 19: Sustainable Airport Master Plan (SAMP) Update · 20/06/2018  · SUSTAINABLE AIRPORT MASTER PLAN (SAMP) UPDATE. Public Open House and Presentation. June 20, 2018

1919

SAMP PUBLIC OUTREACH• Community Open Houses – identical content, multiple locations

• Report out on planning work (Q2-3, 2018)

• Ongoing engagement with tenants, operators, FAA, & TSA

• Targeted engagement with external stakeholders • Airport-area communities• Social justice community leaders• Airport-area business leaders• Regional business and labor leaders• Traveling public

• Environmental Review in Q3 2018• Coordinated outreach program between SAMP planning and environmental