Surviving the “Big Crunch” with insight-enabled decisions inside the plant gate
Surviving the Construction Crunch Wednesday 25 th March 2009.
-
Upload
solomon-owen -
Category
Documents
-
view
214 -
download
0
Transcript of Surviving the Construction Crunch Wednesday 25 th March 2009.
The construction crunch
contractual pitfalls
Richard WadePartner, head of Construction and Development
Blake Lapthorn
Turnaround Managers Association25 March 2009
Contract law – the basics
Some essential characteristics
Agreement Offer/acceptance Consideration Capacity Written or oral or by conduct Privity
OWNER
FUNDAB College (Developments
Limited) (Employer)
TENANTS
MAIN CONTRACTOR ARCHITECT M & E ENGINEER STRUCTURAL ENGINEER
Q.S
SUB-CONTRACTORS SUPPLIERS SUB-CONSULTANTS
The ‘Interested third parties’
Owner/purchaser
Tenant
Fund
Employer
Employer’s associated company
Ultimate client/owner
Present/future?
Protection of third parties’ interests
Warranties
Third party rights
Assignment
Future third parties
Importance of:
– underlying contractual agreement
– insurance
Warranties
Enforceable contractual promise
Remedy in damages
Express or implied
Written or verbal
Protects the third party’s rights in case of exclusion of Contract (Rights of Third Parties) Act 1999
The Paradox of modern developments:
Often the developer is not the end user/occupier
Linden Gardens Trust v Lenesta Sludge (House of Lords, 1993) (the St Martins Case); highlights the paradox and a possible solution
but …
McAlpine – Panatown (House of Lords, 2000)
OWNER
FUNDAB College (Developments
Limited) (Employer)
TENANTS
MAIN CONTRACTOR ARCHITECT M & E ENGINEER STRUCTURAL ENGINEER
Q.S
SUB-CONTRACTORS SUPPLIERS SUB-CONSULTANTS
Other methods of protection of third party interests
Bonds (performance/guarantee and ‘on demand’ or ‘conditional’)
Guarantees – must be written
Novation (not to be confused with assignment)
Disputes and how to avoid them
Why good contracts go bad
Legal problems
People and dispute resolution
Three useful tips
Why good contracts go bad
Misunderstanding the law
Terms and Obligations not defined
Rash decision making
Breakdown in the management of the contract or relationships
Failure to adequately deal with disputes
One off contracts – no perceived benefit in continuing relationships
Margins too tight
Legal problems
Misunderstanding the law (use of Letters of Intent, contract formation, suspension)
Lack of definition in terms and obligations (eg notice to correct breach, eg JCT SBC05 Clause 8.4)
Rash decision making (suspension and termination... repudiation?)
Breakdown in management of contract/relationships
Cashflow
Failure to plan
Failure to deal adequately with disputes
A Case Study in Rash Behaviour (and Proportionality):
Multiplex Construction (UK) Limited v Cleveland Bridge (TCC, 2008)
Judgment of Mr Justice Jackson 29 September 2008
Award of £6 million damages to Multiplex
Overall legal costs incurred ... £22 million
Award of legal costs to winner … 20%
Alternative dispute resolution (ie not litigation or arbitration)
“ADR”...
Mediation Dispute Resolution Board Early neutral evaluation ‘Med/Arb’ Adjudication Negotiation/collaborative working ‘clear’!
Three useful tips to take away
Ensure clarity of contract terms etc...
Effectively manage disputes
If in doubt ... take good advice!
And finally, a word about …
… Insolvency (some specific issues for construction projects)
Using the contract to your advantage – Melville Dundas v Wimpey (2007)
Retentions of Title
Novation
Keeping the project alive
The construction crunch
contractual pitfalls
Mark GordonPartner
Ridge and Partners LLP
Turnaround Managers Association25 March 2009
Heads of claim
Measured works
Variations
Prolongation and loss and expense
Disruption/acceleration
Remedial works
Contra-charges
Liquidated damages
Completion costs
Prolongation
Major source of disputes
Money flows with liability
Check Contract terms; notice provisions, method of analysis, long-stop dates etc
‘Black art’ – seek advice
Commonly over-stated
Disruption/acceleration
Out-of sequence working
Cause + effect demonstration
Common amongst subcontractors
Instruction required for acceleration
Remedial works
Common head of counter-claim
Not usually an issue until after termination
Betterment
Burden of proof
Liquidated damages
Employer / main contractor remedy for delay
Default position
Main contractor allocation
Withholding notice
Often applied toward end of works
Completion costs
Contract must be terminated
Market price
Emergency works
Betterment
Check contract terms – loss suffered?
Survey of work completed
Avoid paying twice (direct payments)
Common tactics
Unrealistic and inflated works completed
Inflated and spurious claims
Extensive contra-charges
Completion costs include betterment
Large value of management time claimed for completion
Invoices disputed on spurious grounds
Delayed payment
Ambush
Starve struggling companies
Actions
1. Secure site, materials and records
2. Commission detailed survey of works completed
3. Review account and prepare final account
4. Appoint professionals to advise on entitlements
5. Consider adjudication as means of quick-win
6. Check for collateral warranties and guarantees
7. Check withholding notices
8. Move quickly
9. Don’t be put off!
Our thanks go to the following:
To Blake Lapthorn for hosting the event
To Richard Wade and Mark Gordon for speaking
To our members and guests attending
All of our Sponsors, including our Foundation Sponsors: