Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of...

51
Bartlett Nuclear, Inc. -- May 2007 1 Survey Meter Reading Primer –

Transcript of Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of...

Page 1: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 1

Survey Meter Reading Primer –

Page 2: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 2

Introduction (1 of 2)During the spring 2007 outage season there were several locations where a timed “meter reading” exercise was given.The following exercise is designed to allow you to “practice” your meter reading & interpretation skills before you report to a site & potentially encounter a “timed” exam.

Our thanks go to Ray Hock and the Training Staff at Susquehanna for providing the meter face images

.

Page 3: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 3

Introduction (2 of 2)

As you work through the examples remember that the objective is just to read the meter (not subtract background, etc.)

If you have any questions please contact Jerry Hiatt (x1286) or Fred Campbell (x1287) in the Bartlett Home office

Page 4: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 4

The following Instruments are

Count Rate Meters

Page 5: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 5

Example 1Ludlum Model 177count rate meter

Page 6: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 6

ANSWER Example 1

3,200 cpm

SCALE = x10 Needle is on the 320 marking (320 x10 = 3200)

Page 7: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 7

Example #2Ludlum Model 177count rate meter

Page 8: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 8

ANSWER Example 2

10,000 cpm

SCALE = 100xNeedle is on the 100 marking (100 x 100 = 10,000 cpm)

Page 9: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 9

Example #3 Eberline RM-14 count rate meter

Page 10: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 10

ANSWER Example 3

22,000 cpm

SCALE = 100xNeedle is on the 220 marking (220 x 100 = 22,000 cpm)

Page 11: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 11

Example 4Ludlum Model 3count rate meter

Page 12: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 12

ANSWER Example 4

300 cpm

SCALE = 0.1xNeedle is on the 3K (3000) marking (3000 x 0.1 = 300 cpm)

Page 13: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 13

Example #5 Ludlum Model 3count rate meter

Page 14: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 14

ANSWER Example 5

20,000 cpm

SCALE = 10xNeedle is on the 2K (2000) marking (2000 x 10 = 20,000 cpm)

Page 15: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 15

The following Instruments are RO-2, RO-2A, or

RO-20’s

Page 16: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 16

Example 6Eberline RO-2A

Page 17: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 17

ANSWER Example 6

400 mR/h

Scale setting = 500 mR/hNeedle is on the 4 indicating 400 mR/h

Page 18: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 18

Example 7Eberline RO-2

Page 19: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 19

ANSWER Example 7

3.6 mR/hr

Scale setting = 5 mR/hrNeedle is on the 3.6 marker

Page 20: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 20

Example #8Eberline RO-2

Page 21: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 21

ANSWER Example 8

2500 mR/hr

SCALE = 5000 mR/hrNeedle is midway between the 2000 mR/hr and 3000 mR/hr scale

Page 22: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 22

Example #9Eberline/Thermo RO-20

Page 23: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 23

ANSWER Example 9

8.5 R/hr

SCALE = 50 R/hrThe 1 represents 10 R/h. The needle is between the 8 R/hr and 9 R/hr markings

Page 24: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 24

The following Instrumentis a BC-4Record only the counts, ignore the count time.

Page 25: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 25

Example #10 Eberline BC-4

Page 26: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 26

ANSWER Example 10

502 counts

The instrument read-out is directly in countsNote: As an added bit of information -- the count time is set for 20 minutes. This would equate to ~25 cpm.

Page 27: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 27

The following Instruments are

ASP-1’s

Page 28: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 28

Example 11Eberline ASP-1

Page 29: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 29

ANSWER Example 11

48 mR/hr

SCALE = x100 Needle is on the 0.48 marking (0.48 x100 = 48)

Page 30: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 30

Example 12Eberline ASP-1

Page 31: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 31

ANSWER Example 12

7.3 mR/hr

SCALE = x10 Needle is on the 0.73 marking – clearly between the 0.72 and 0.74 markings

(0.73 x10 = 7.3)

Page 32: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 32

The following Instruments are

Telepole’s

Page 33: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 33

Example 13 MGP Telepole

Page 34: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 34

ANSWER Example 13

30.6 mR/h

As configured, the instrument read-out is directly in mR/hNote: you can also “read” the response from the scale that circles the digits expressing the value

Page 35: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 35

Example 14 MGP Telepole

Page 36: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 36

ANSWER Example 14

35.7 R/h

As configured, the instrument read-out is directly in R/hNote: you can also “read” the response from the scale that circles the digits expressing the value

Page 37: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 37

The following Instruments are EC-4’s

(portable Area Radiation Monitors)

Page 38: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 38

Example 15 Eberline EC-4

Page 39: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 39

ANSWER Example 15

1.0 mR/h

As configured, the instrument read-out is in mR/hThe needle is pointing directly towards the “1”

Page 40: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 40

Example 16Eberline EC-4

Page 41: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 41

ANSWER Example 16

300 mR/h

As configured, the instrument read-out is in mR/hThe needle is pointing at the “300” marking (between the 100 and 1000 markings)

Page 42: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 42

The following Instruments are

AMP’s

Page 43: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 43

Example 17MGP AMP-100

Page 44: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 44

ANSWER Example 17

1.169 R/h

As configured, the instrument read-out is directly in R/h

Page 45: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 45

Example 18MGP AMP-50

Page 46: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 46

ANSWER Example 18

89.7 mR/h

As configured, the instrument read-out is directly in mR/h

Page 47: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 47

The following Instruments are RO-20’s

Page 48: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 48

Example 19Eberline RO-20

Page 49: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 49

ANSWER Example 190.9 R/h

SCALE = 5 R/hThe 1 represents 1 R/h. The needle is between the 0.8 R/hr and 1 R/hr markings

Page 50: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 50

Slide #20Slide #20

Page 51: Survey Meter Reading Primer - NukeWorker · Bartlett Nuclear, Inc. -- May 2007 2 Introduction (1 of 2) During the spring 2007 outage season there were several locations where a timed

Bartlett Nuclear, Inc. -- May 2007 51

ANSWER Example 2036 mR/h

SCALE = 50 mR/hThe “3” represents 30 mR/h and the “4” represents 40 mR/h. The needle is on the 36 marking.