Surging to a Smarter Future · 8.4. Training Need Assessment and Content Development 66 8.4.1....

80
www.pwc.com World Bank Surging to a Smarter Future Detailed Project Report for World Bank “ICT Enabled Integration for Green GrowthJune 2016

Transcript of Surging to a Smarter Future · 8.4. Training Need Assessment and Content Development 66 8.4.1....

www.pwc.com World Bank

Surging to a Smarter Future

Detailed Project Report for World Bank

“ICT Enabled Integration for Green Growth”

June 2016

PwC 2

Table of Contents

1. Overview 4

1.1. Sectional Overview 4

1.2. Intended readers 4

1.3. Approach adopted for the document 4

1.4. Executive Summary 5

1.5. Objectives of the Project 6

2. Shimla – City Profile 7

2.1. City Snapshot & Projection 7

2.2. Geographical Overview 8

2.2.1. Climate and Rainfall 8

2.2.2. Land Use Pattern 8

2.2.3. Tourism and Industry 9

2.2.4. Industrial Scenario 9

2.2.5. Economic Features 9

2.3. Existing Scenario 10

2.3.1. General 10

2.3.2. Source 10

2.3.3. Distribution System 12

2.3.4. Service Coverage 12

3. Design Considerations 14

4. Water Value Chain 16

5. Architecture& Solution Elements 19

5.1. Water Collection and Treatment 19

5.1.1. Architecture of Water Distribution System Automation 19

5.1.2. Detailed analysis of Process Monitoring and Control 20

5.1.3. Detailed Analysis of Plant Wide SCADA 24

5.1.4. Detailed Analysis of Plant Automation 41

5.1.5. RTU’s for Distribution & Intake networks 46

6. Estimated Cost 54

6.1. Summary 54

7. Service Level Agreement 56

7.1. Purpose of this Agreement 56

7.2. Problem Severity Levels 57

7.3. Breach of SLA 58

7.3.1. Monitoring and Auditing 58

7.3.2. Reporting Procedures 58

PwC 3

7.3.3. Issue Management Procedure 58

7.3.4. Change Management: 59

7.3.5. Service Continuity 59

7.3.6. Security Management 59

7.3.7. SLA Change Control 59

8. Capacity Building and Change Management 61

8.1. Need for Change Management 62

8.1.1. Identification of Stakeholders 63

8.1.2. Description of Roles and Responsibilities 63

8.1.3. Participation by Stakeholders 64

8.2. Staffing and Deployment Strategy 64

8.2.1. Staffing and Deployment Plan 64

8.2.2. Staffing and Deployment Process 65

8.3. Training Strategy 66

8.4. Training Need Assessment and Content Development 66

8.4.1. Capacity Building 66

8.4.2. Training 66

9. Monitoring and Evaluation 68

9.1. Monitoring and Evaluation Framework 68

9.1.1. Clearly Defined Objectives 69

9.2. Define Organization’s Roles and Responsibilities 69

9.3. Approach for Monitoring and Evaluation Process 69

9.3.1. Monitoring 69

9.3.2. Evaluation 70

10. Assumption and Risk Management 73

10.1. Process for Risk Assessment 73

10.1.1. Risk Identification 73

10.2. Risk Mitigation Strategy Based on Risk Evaluation Matrix 74

10.2.1. Risk Mitigation Strategy based on Risk Evaluation Matrix 74

10.3. Risk Monitoring 74

11. Project Implementation Strategy and Sustainability Plan 75

11.1. Stakeholder’s Involvement 75

11.2. Tendering and Bid Process Management 75

11.3. Project Implementation Strategy 75

11.4. Project Phasing Strategy 76

11.4.1. Exit Plan 76

11.5. Sustainability Plan 76

12. Project Implementation Schedule 78

PwC 4

Overview 1.1. Sectional Overview

This document is divided into following broad sections and sub sections:

1. Section 1: Overview & Executive Summary – This section provides a brief overview of entire

document on what is contained in the document, the target audience, the approach adopted etc.

This section also has an Executive Summary and states clearly the Objectives of the Shimla project

as well as a bit of background about it.

2. Section 2: Shimla – This section is meant

to give a clear background and history about

the Shimla city to the readers

3. Section 3: Water Scada– This section

forms the major portion of the document.

This includes the following subsections

under it

Smart city guiding principles:

Detailing of the PwC Smart City Local

Governance Framework which is an overview

on the Services offered as part of the project,

KPIs for each of the services, Desired

Objectives & Outcomes, Functional areas &

services of each of the Govt. departments

under the scope of the project.

Detailing of the Regulatory Framework which explains about the regulating body, their functions

etc.

Detailing of the Technology Framework which includes the guiding principles for the technological

framework, a brief description on the technical aspects of each of the services offered etc.

Section on the essential financials which details about the Bill of Material, estimated cost etc.

1.2. Intended readers

Target audience of this document is following stakeholders:

1. Process Owners: Process owners for each of the business function would be required to read this document primarily from application stack perspective. They would be able to understand how the IT requirements of their individual function would be catered and through which application and provide feedback on it.

2. Senior Management/ Policy Maker who are responsible for Strategy design and implementation and have detail statistics about the cost utilization on projects.

3. Other Stakeholder includes all stakeholders of the project for transformation of Shimla to a Smart

City would be encouraged to read the document especially for the functions which are not matured in

Producer Companies.

1.3. Approach adopted for the document

The aims and objective that are initially envisaged for formulation of any water supply plan are related to

population of the area, socio-economic status of the people inhabiting the area, investigation of sources,

PwC 5

their capacity and dependability on long term basis, future Development Plan of the region, existing and

proposed level of water supply, its quality and history of epidemnicity of water borne diseases.

The approach to achieve these goals is governed by the following methodologies

• Examination of decadal population of the project area and estimation of future population to the

end of the planning period.

• Total daily requirement of water for the present and future estimated population.

• Exploration of capable and dependable sources within or outside the project area.

• Ascertaining the raw water quality viz physical, chemical and bacteriological.

• Determination of treatment process consistent with raw water quality.

• Planning and designing of collection and distribution system considering the topography and

location of settlements of the project area.

1.4. Executive Summary

Objectives of Water Supply Plan for any region should be conceived and conceptualized consistent with

broader perceptions related to socio- economic structure of the inhabitants, their needs and requirement

of adequate potable water and involvement of capital investment as well. The strategy of planning should

therefore aim at formulation of general programmes directed to specific results and conceptual frame work

for action.

Provision of drinking water to communities is not only the basic amenity but it should be viewed as an

integral part of the major public health programme aimed at prevention of water borne diseases which will

result in better health, happiness and well being of the community. It has been proved by epidemiological

studies that all fatal enteric diseases like cholera; Diarrhea, typhoid etc. are caused due to intake of

contaminated water. It therefore, implies that purity of drinking water conforming to prescribed standard

of purity should be primary concern of any water supply system and hence the planning and design of

water supply projects should address not only the technical features but the public health aspect too. The

planned strategy shall take into account the identification of source of supply, collection, transmission,

distribution and other related aspects. Keeping in view the aforesaid concept and objectives formulation of

water supply plan of Shimla M. C. Area should be governed by the following considerations:

• Identification of dependable source on long-term basis

• Potentiality and environmental conditions of the source

• Examination of raw water quality

• Assessment of degree of treatment required

• Per capita daily water requirement

• Total requirement of water for ultimate designed population

The planning should be so framed that it would not only integrate the existing system of water supply but

would also envisage a strategic plan consistent with future overall development of the project area. The

planning should also be streamlined to fit into the regional development plans, long-term sector plan, land

use plan and other open space planning. The planning scenario may also include the supporting activities

like health, education, staff training and infrastructural improvements etc.

The present scale of water to rural or urban population is generally inadequate all over the country hence

the MC, Shimla is no exception. Increasing demand of rising population, non-availability of potential

source, inadequacy of infrastructure etc all lead to scarcity of drinking water in the project area.

Beginning as a feeder of paltry population of 16000 souls in year 1875 AD, Shimla city water supply grew

to larger proportion augmented and improved over the years. Despite the improvements carried out so far

PwC 6

as aforesaid, scarcity of water prevails in many pockets of the city particularly in special areas

amalgamated within the municipal boundary and the areas that are likely to be amalgamated. Depletion of

yield of sources during lean period cause further increase in demand and supply gap resulting in much

hardships and miseries to the inhabitants of the city. City Development Plan (CDP) proposed under

JNNURM identifies water supply and sanitation as a major priority area to be tackled in order to lessen

the growing gap between demand and supply. To provide adequate quantum of portable water to the

citizens, the CDP has envisioned a rate of 135 lpcd water supply to the city. The plan has estimated total

quantity of water required till the end of planning year of 2047 as 71.11 MLD. Further the plan reiterates

availability of about 30 MLD of water, which falls too short of present requirement of the city causing

acute shortage. To tide over the crisis, the state administration conceived a plan to bring water from

Koldam Reservoir (Lift Water Supply Scheme from Koldam Reservoir)

1.5. Objectives of the Project

The primary objective of this initiative is real time remote monitoring of Water treatment to distribution

network of Shimla on parameters like Flow, Pressure, UGR & SUMP Levels, Energy Consumption and Water

Quality.

The objectives of this initiative are following:

Timely availability of real time operating parameters

Real time assessment of water supply situation

Real time data on water quality

Readily available on-line information of distribution data in command areas periphery network

Reliable real time data for service level parameters

To provide alert in case of deviation to set parameters

To bring in accountability into the system and the services

To use latest technology effectively and efficiently to yield significant improvements in

efficiency, productivity, profitability and competitive advantage to Shimla

To enable better decision making by providing real time data and a technological platform

for effective integration with other communications and information management

technology

To provide significant opportunities for item-based process improvement and innovation

in the functioning of Water network

Establishment of the Water SCADA will result in accurate and automated data in continuity for pressure,

flow, energy consumption monitoring, and water quality monitoring including complete water audit for

the transmission mains. Current project is aimed at

Real time Dash board view of Overall system on healthiness

Efficient utilization of water

Ease of coordination for maintenance activities from the plant to the consumers-end

Water SCADA would enable Centralized control and monitoring of distribution and collection system

which would in turn provide data for water modelling and energy use optimization, as well as predictive

maintenance of distributed equipment. The central control room which would be established for

automation of water Distribution ensures constant communication from the server to the remote units.

The system will have configuration to support fail safe design for round the clock monitoring.

PwC 7

2. Shimla – City Profile

2.1. City Snapshot & Projection

The city was spotted as a tiny agglomeration of hamlets inhabited by 16000 persons more than 130 years

back. As the time passed by, it grew in importance on account of its salubrious climate and surrounding

beautiful natural landscape till it became the capital city of Himachal Pradesh. It continues to grow in shape

and size amalgamating more and more adjoining urbanize able areas. Presently MC, Shimla covers an area

of 51.30 sq.km comprising Shimla Municipal Corporation recently merged special areas of Dhalli, New

Shimla, Tutu and Kasumpti etc. The major land uses are located on the southern face of Shimla due to

gradual slope and sunny side. The city sprawls over spurs of central Himalayas south of river Satluj. The

average height of the city is 2130.0 m above MSL. Geo-climatic setting of the town is mainly characterized

as a place having heavy monsoon, cold winter, rugged topography, steep slopes, deep valleys and elongated

mountain spurs. The total population as recorded in 2001 census is 1,56,127 souls (1,44,975 for Shimla +

11,152 souls for merged area as per gazette notification in 2006). Detailed features of the project are given

in succeeding chapter.

Earlier Detailed Project Report for Rehabilitation for Water Supply distribution system of Shimla City was

approved amounting to Rs. 72.36 Crores in the meeting held on 20.02.2009 under the Chairmanship of

Secretary, Ministry of Urban Development, Govt. of India under JNNURM. The funds allocated of Rs.

1447.20 Lacs against the approved project under JNNURM has not been utilized so far. Thus, the Govt. of

India has been withdrawn the funds allocated.

The Irrigation and Public Health Deptt, Govt. of Himachal Pradesh has allowed the work of consultancy

services for updating the earlier approved Project of Rehabilitation of distribution system through

WAPCOS Ltd. which is empanelled with the JNNURM and consultancy jobs.

Section 2

Proposed

Solution

PwC 8

2.2. Geographical Overview

Geology of Shimla indicates sub Himalayan characteristics. The rock found in the project area have

undergone three distinct generations of deformations resulting in variation of altitude of formation.

Carbonaceous, Phyllite, local bands of quartzite and lime stone forming Jutog group of rocks occupy main

Shimla area and extends from Annadele – Chura Bazar-prospect hill-Jakhoo-U.S. club and high land area

whereas shales, slate, greywacke quartzite, local conglomerates and dolomites forming Shimla group of

rocks are found in Sanjaulli and Dhalli area.

2.2.1. Climate and Rainfall

Shimla is on the map of international tourist centres on account of its being hill station with salubrious

climate and extraordinary natural and scenic landscapes. It maintains a pleasant climate during summer

month from April to mid June followed by monsoon up to end of September. The city experiences winter

from September to March and cold spells between the month of December and February when temperature

ranges between -4o C to 17oC. The temperature in summer month varies between 18oC and 32o C. Average

annual rainfall is recorded as 1179.8mm. The maximum and minimum annual rainfall recorded so far is

1897mm in the 1995 and 456.37mm in the year 1987. Most of the rainfall occurs in the month of June, July,

August and September, which accounts for 70% of annual rainfall.

2.2.2. Land Use Pattern

The extent of MC, Shimla is 9950 ha that includes Shimla Municipal Corporation with its added areas of

Dhalli, Tutu and New Shimla and Kasumpti. Area under urban uses is 1475.6 ha as mentioned in

Development Plan (Source: Town and Country Planning Dept., HP), which accounts to 15% of total planning

area. Existing land use plan of SPA is given in the following Table:

Sl.

No.

Land Use Area in ha % of planning area

1. Residential 963.13 9.07

2. Commercial 25.22 0.25

3. Industrial 9.00 0.07

4. Tourism 21.70 0.22

5. Public and Semi Public 138.78 1.39

6. Park and other spaces 6.00 0.06

7 Traffic and Transportation 371.73 3.75

8. Agriculture 2174.75 21.85

9. Forest 6080.15 61.12

10. Water bodies and Barren land 219.34 2.20

Total 9950.00 100%

PwC 9

2.2.3. Tourism and Industry

Tourism is an important revenue earner to the state Govt. It employs nearly 4049 numbers of workers.

Shimla is an attractive destination for tourist from all over the world through out the year. Topography of

the town is characterized by interlocking spurs, narrow and deep valley with high peaks and thick forest. Its

salubrious climate and beautiful scenic location attract large number of foreign tourists. It is easily accessible

through Chandigarh-Shimla National Highway No 22, Kalka-Shimla narrow gauge toy train and by air from

Delhi, Chandigarh and Kullu. Tourist population grew from 9,12,528 in 1998 to 21,97,795 in 2007.

2.2.4. Industrial Scenario

The city has small scale and service industries. Factors prohibitive to industrialization are the inhospitable

geographical features, inadequate and high cost of transport facilities and the absence of market in the near

vicinity. Industrial growth is almost stagnant since late 1960. Nevertheless the traditional small-scale

industries like wool spinning, weaving, basket making and metal work that use local resources are making

tardy progress. There are about 450 small scale and service industries operating in SPA. Description of

existing industries is given in the following table.

Sl.No. Category of Industries No. of units. No. of workers

1 Textile 18 60

2 Manufacturing 110 494

3 Communication 44 154

4 Auto repairs 52 228

5 Food products 63 294

6 Service Industries 117 384

7. Other 45 686

Total 449 2300

2.2.5. Economic Features

Natural resources play a key role in economic survival of the town as tourism and agriculture are the main

stay of the economy. The shift from agriculture to horticulture has changed the economic pattern of the

region as the city has become major centre for collection and distribution. Per capita income is estimated

to be Rs. 27486.0 per annum. The key drivers of economic sectors for MC, Shimla are tourism, health area,

education, agri processing, trading hub etc.

PwC 10

2.3. Existing Scenario

2.3.1. General

Pure drinking water free from physical, chemical and biological contamination is the basic necessity for

health and happiness of any community. Epidemiological investigation has amply proved that fatal

intestinal diseases like cholera, diarrhea etc. are transmitted through intake of contaminated water. Urban

communities in absence of inadequate and scarce availability of pure drinking water may be compelled to

consume water of doubtful quality falling prey to such health hazards.

Water supply facilities were introduced in Shimla more than 130 years ago by pumping water from nearby

spring sources. The city grew over the years increasing its boundary as well as population with subsequent

augmentation of water supply to match the needs of the growing population. With the commissioning of the

last augmentation scheme of water supply in the year 1992 the total installed capacity of the system rose to

29.50 MLD.

2.3.2. Source

The water, which is received from different sources for Shimla Town for distribution, is detailed as under:

2.3.2.1. Dhalli Catchment

An average of 0.45 MLD water is received from this source under gravity condition at Dhalli filter. This is

the source based on spring sources of the dense protected forest known as Dhalli catchment.

2.3.2.2. Cherot & Jagroti

From this source an average of 3.50 MLD of water is received which is collected at Dhalli Filter. Part of this

water is distributed in the adjoining area of Dhalli Zone and balance is received at Sanjauli reservoir

through gravity main from Dhalli filter.

2.3.2.3. Chair Nllah

From the source, an average of 1.70 MLD water is received which is pumped from Chair source to storage

tank at Lambidhar from where water is distributed to Kufri under SPA Shimla.

2.3.2.4. Source at Gumma at Nauti Khad

This is the main source of water supply, which provides approximately 16.75 MLD of water. This quantity

of water is pumped from Gumma & received at Carignano reservoir from where it is gravitated to the

Sanjuli reservoir. From Sanjauli this water is further gravitated to the Ridge reservoir and also to Mans

field reservoir. In addition to this, some of the sectoral tanks are also fed through feeder line from Sanjuli

reservoir. These setoral tanks are Engine Ghar, North Oak, Bharari, Advace Study, Sandal Chakkar and

Totu.

2.3.2.5. Source at Gumma at Nauti Khad near Bridge

From this source, about 4.54 MLD of water is pumped and received at Carignano reservoir from where it

is gravitated to the Sanjuli reservoir. From Sanjauli this water is further gravitated to the Ridge reservoir

and also to Mans field reservoir. In addition to this, some of the sectoral tanks are also fed through feeder

line from Sanjuli reservoir. These setoral tanks are Engine Ghar, North Oak, Bharari, Advace Study,

Sandal Chakkar and Totu.

2.3.2.6. Ashwani Khad

From this source, about 7.60 MLD of water is pumped through two stages and received at Kasumpti

reservoir from where part of the water is distributed in the adjoining area and sectoral tanks located at

PwC 11

sector-1, 3 & 4 New Shimla are filled-up. The balance water is again pumped from this reservoir to Mans

field tank. From Mans field tank the water is distributed in the adjoining area and sectoral tank at Knolls

wood is also connected with this water tank. In addition to this the sectoral tank at Tuti Kandi and sump

well of Kamna Devi Pump house is also fed.

2.3.2.7. River Giri

From this source, about 20.00 MLD of water is pumped into Dhalli Treatment Plant and further water is

distributed in the adjoining area of Dhalli Zone and balance is received at Sanjauli reservoir through

gravity main from Dhalli filter.

Surface water is drawn from five main sources occurring as springs and streams. The following Table

shows the name of source and quantities of water drawn from them.

Sl.

No.

Name of source Quantities drawn in MLD

(Average)

1 Dhalli catchment 0.45

2 Churat Nallah 3.50

3 Nauti Khad 16.75

4 Nauti Khad near Bridge 4.54

5 Ashwani Khad 7.60

6 River Giri 20.00

Total 52.84

The water available i.e. 1.70 MLD from Chair Nallah is being supplied to Kufri under SPA Shimla.

Water from the sources are treated and pumped barring Dhalli catchment source, which operates under

gravity conditions. Water thus pumped or gravitated are stored in 10 number of service reservoirs located

at suitable sites covering the MC, Shimla as given in the following Table:

Sl. No. Reservoirs Capacity in ML Type

1. Carignano 3.01 UG

2. Sanjaulli 8.78 UG

3. Ridge 4.63 UG

4. Mans field 3.63 UG

5. Kasumpti 2.00 UG

6. Kasumpti 0.227 OH

7. Viceregal lodge 0.23 OH

8. Jakhu 0.32 OH

9. Boileaugunj 0.24 UG

PwC 12

10. Balancing Reservoir at Masobara 3.00 UG

Total 26.447

The total capacity of existing reservoirs as shown above is 26.447 ML. The reservoirs located at Sanjaulli is

largest one having a capacity to store 8.78ML and the smallest one is situated at Kasumpti having a capacity

of 0.223 ML. Newly developed areas of BCS, Chakkar, Tohu etc. do not have separate service reservoirs

instead they are fed from existing ones causing considerable loss in pressure at the tail end of the network.

2.3.3. Distribution System

The city has fourteen delineated water zones based on topography and location of feeder reservoirs as shown

in the following Table:

Sl.

No.

Name of zone Area covered

1. Sanjaulli Sanjaulli Bazaar, Engine Ghar, Nav Bahar, Snowdown, Jakhoo, Pumping Station, Grand Hotel, Shankli, Scandal, Sangti

2. Bharari Bharari, Harvington, Kuftu, Anu, Bermu, etc

3. Ridge Telegraph office, Krishna Nagar, Sabzi Mandi, Ripon, Lalpani, Western Command, Ram Bazaar, Middle bazaar

4. High Court Lower High Court area, Paradas Garden, Kanlog, Talland

5. BCS BCS, Khalini, Forest Colony

6. AG office Kaithu, Annandale, Kavi, AG Office, Ram nagar Vidhan Sabha, Chaura Maidan, Tuti Kandi, Kumar House, Raj Bhavan, Ava Lodge, Labour Bureau, Kenndy House, Win Gate

7. Vice Regal lodge Institute of Advanced Studies, Tilak Nagar, Ghora Chowk, Hanuman Temple

8. Mansfield Mansfield to Marina, Secretariat, Chotta Shimla bazaar, Brock Hurst upto Govt. School

9. Kasumpti Kasumpti Colony, Lower Brock Hurst, Patti Rehana, Patina Mehli, Pantha Ghati, Patelog

10. University University Complex, Summer Hill, Govt. Quarters, Shiv Mandir

11. Kamna Devi Hill Spur of Kamna Devi, Forest Colony

12. Chakkar Sandal Hill, Tara Devi, Shoghi

13. Tutu Tutu Bazaar, Jutogh, Dhamida, Fatenchi

14. Dhalli Dhingu Devi Mandir, Dhalli Bazar, Indira Nagar, Part area of Mashobra

2.3.4. Service Coverage

At present 27765 consumer connections have been provided by the Deptt. The details of private and public

services are detailed below:

PwC 13

Sl. No. Head No. of connections

1. Domestic 21276

2. Commercial 5161

3. Street hydrants /Construction connection 900

4. Govt. Buildings/ Institutions/ Religious 428

Total 27765

Water is supplied to the consumers during non-lean season from 60 to 90 minutes on daily basis and during

lean season around 60 minutes on alternate day basis.

PwC 14

3. Design Considerations

Key design considerations taken into account are as follows –

System is designed for projected population of 3.24 Lakhs by 2047

There are 7 Sources of water, major sources being River Giri, Nauti Khad, Ashwani Khad.

System designed for 24x7 water supply system and water requirement of 71.11 MLD by year 2047

Reduced chance of contamination

Distribution pipeline is pressurized for 24 hrs. hence, lower chance of foreign

contamination

No tank at consumer end (except for high rise building). Hence, bacterial / virus

contamination through tank is eliminated

Continuous on-line monitoring of water quality at water treatment plant

Water meters :

Electromagnetic flow meter : In Main Pipelines ( Intake, WTP, MBR & UGRs)

On-line monitoring of production of water, quality of water, distribution status, and demand

management.

System should be flexible, scalable , support open protocol and distributed architecture design

Centralized Water SCADA in line with Smart city concept envisaged for monitoring and controlling

of WTPs , Water Supply & Distribution system spread across city

Revenue management system for metering, billing and collection

The primary objective of this initiative is real time remote monitoring of Water treatment to distribution

network on parameters like Flow, Pressure, UGR & SUMP Levels, Energy Consumption and Water Quality.

The objectives of this initiative are following:

Timely availability of real time operating parameters

Real time assessment of water supply situation

Real time data on water quality

Readily available on-line information of distribution data in command areas periphery network

Reliable real time data for service level parameters

To provide alert in case of deviation to set parameters

To bring in accountability into the system and the services

To use latest technology effectively and efficiently to yield significant improvements in

efficiency, productivity, profitability and competitive advantage to Shimla Municipal

Corporation

To enable better decision making by providing real time data and a technological platform

for effective integration with other communications and information management

technology

To provide significant opportunities for item-based process improvement and innovation

in the functioning of Water network

Establishment of the Water SCADA will result in accurate and automated data in continuity for pressure,

flow, energy consumption monitoring, and water quality monitoring including complete water audit for

the transmission mains. Current project is aimed at

Real time Dash board view of Overall system on healthiness

Efficient utilization of water

PwC 15

Ease of coordination for maintenance activities from the plant to the consumers-end

Water SCADA would enable Centralized control and monitoring of distribution and collection system which

would in turn provide data for water modelling and energy use optimization, as well as predictive

maintenance of distributed equipment. The central control room which would be established for automation

of water Distribution ensures constant communication from the server to the remote units. The system will

have configuration to support fail safe design for round the clock monitoring.

PwC 16

4. Water Value Chain

Objective is to maximize their asset management & utilization, reduce capital expenditures, improve

reliability and enhance service delivery to Shimla City citizens, business and industries.

Shimla Water Value Chain involves two components as shown below:

Water collection and treatment- This component involves the collection of the Raw water from

different Sources and then treating the water by passing it through the Water Treatment Plant where it

is Coagulated , Flocculated, Chlorinated and then backwashed to distribute it into the MBR.

Water supply and distribution- After the treatment from treatment plants water is distributed to

the 11 major reservoirs and 28 minor reservoirs from where it reaches to the consumers through internal

sector pipelines.

A smart water system is proposed and designed looking at current requirement that will help the authority

to gather meaningful and actionable data about the flow, pressure and distribution of a city's water and help

in better city water management and operations.

Distribution & Supply

Distribution to 11 major reservoirs and 28 minor reservoirs

Supply to consumer

Water Collection &

Treatment

Collection of freshwater

Raw water treatment

1 2

PwC 17

SMART WATER MANAGEMENT SYSTEM

PwC 18

Shimla Smart Water Management Integrated View

PwC 19

5. Architecture& Solution Elements

5.1. Water Collection and Treatment

In this section, we will discuss in detail the first component of Water Supply Chain i.e. Collection of Water

and its treatment of the collected water through Water Treatment Plant (WTP) and pumped to storage

reservoir

5.1.1. Architecture of Water Distribution System Automation

The three major components of automation of Water Distribution System are:

1) Process Monitoring and Control

2) Plant Wide SCADA

3) Plant Automation

Process Monitoring and Control: This includes primary instrumentation, including pressure, level,

flow and analytical instruments, primary control devices such as valve actuators and solenoids and electrical

equipment, including motor control centers, variable frequency drivers and packaged control panels. The

types and quantities of devices needed at this level are dependent on the plant processes and capacity and

to some extent the physical layout of the plant

Process Automation: The process automation Category includes area control panels, local indicators,

Programmable Logical Controllers, Remote Terminal Units (RTUs), Distributed Control Units (DCUs),

dedicated operator interface devices, panel mounted recorders, indicators, single loop controllers. Many of

these devices are considered instruments but the intent here is to show generally where they would be

located in the plant. Like the process monitoring and control category, the types and quantities of these

devices depend on the plant processes, the level of unattended operation, plant capacity and physical

capacity.

Plant Wide SCADA: This category constitutes Operator Interface Workstations, computer networks,

printers, SCADA software applications, reporting application, Alarming Systems Firewalls, communication

processors and network storage devices. Many of these devices and systems are similar for any water

treatment plant and the equipment costs are only moderately affected by the type of processes and physical

size of the plant. Software development including graphic displays, PLC programming and report

PwC 20

development are directly related to the processes used, field equipment count, no. of SCADA computers and

plant capacity.

5.1.2. Detailed analysis of Process Monitoring and Control

5.1.2.1. Water Treatment Functional Architecture

PwC 21

1) Raw Water Pumping-

Raw water pumping involves moving raw water from the source to the treatment plant. Surface water

treatment plant intakes are typically equipped with screens or rakes that remove large objects from the flow

before it enters the plant that convey it to the head of the treatment plant. The automation of raw water

pumping includes the automatic controls, valve actuators, variable frequency pump drives and flow and

level monitoring instruments

Potential benefits of the automation of raw water pumping are:

Reduced energy cost as a result of off-peak operation

Automatic startup and shutdown in response to emergencies or water demands

Reduced Labour costs and improved water quality as a result of more uniform flow rates

2) Coagulation-

Coagulation removes dirt and other particles suspended in water. Alum and other chemicals are added to

water to form tiny sticky particles called “floc” which attract the dirt particles. The combined weight of the

dirt and the alum (floc) become heavy enough to sink to the bottom during sedimentation. Coagulation

involves the addition of chemicals to influent raw water to form particles large enough to be removed by

settling. Typical coagulants are:

Alum

Ferric Chloride and Coagulant Aids

As raw water pH can interfere with the coagulation process, pH control is often included.

Control Modes for Coagulation Process:

Manual Control - A common method of controlling coagulant dosages is manually adjusting the

coagulant , coagulant aid and acid and caustic feed rates based upon observation, jar testsand

instrument readings. Jar testing is performed on a scheduled basis with increased frequency when

the quality of source water fluctuates.

Some of the instruments needed in the limited automation of Coagulation process:

Raw water flowmeters

Raw water turbidity monitors

Raw water pH meters

Settled water turbidity monitors

Automatic Control

Automatic control - It adjusts coagulant feed rates and dosages in response to variation the

plant flow and/or source water quality. Automatic shutdown of the plant should also shut down

the coagulant feed. Automatic pH control may be required at some plants. Feedback control of

the coagulant dose is accomplished using streaming current detectors and controllers. The use

of streaming current detectors may not be suitable with some source waters

Some of the instruments needed for automatic control of Coagulation process:

Raw water flowmeters

Raw water turbidity monitors

Raw water pH meters

Settled Water turbidity monitors

Controller for streaming current detectors

pH controllers

Potential Benefits of automated Coagulation Process:

Adding stream current detectors can include improved coagulant dosing resulting in chemical cost

savings ,

More consistent treated water quality and fewer process upsets

PwC 22

3) Flocculation/sedimentation - Flocculation refers to water treatment processes that combine or

coagulate small particles into larger particles, which settle out of the water as sediment. Alum and iron

salts or synthetic organic polymers (used alone or in combination with metal salts) are generally used

to promote coagulation. Settling or sedimentation occurs naturally as flocculated particles settle out of

the water. The heavy particles (flocculation) settle to the bottom and the clear water moves to filtration.

4) Filtration and Disinfectors – Many water treatment facilities use filtration to remove all particles

from the water. Those particles include clays and silts, natural organic matter, precipitates from other

treatment processes in the facility, iron and manganese, and microorganisms. Filtration clarifies water

and enhances the effectiveness of disinfection.

The majority of the surface water treatment utilizes granular media filtration, gravity fed to remove

suspended solids.

Controlling Methods to automate the filtration Process:

There are two primary methods for the control of gravity filters:

Constant Rate

Declining Rate

With constant rate filtration, the influent channel water level is maintained at a constant level as

flow is split equally between all on-line filters.

There are three main approaches used for controlling constant rate filters including:

Constant Rate with filter effluent rate of flow controller

Constant rate with constant water level and influent flow splitting

Constant rate with variable water level and influent flow splitting

Automatic Control: A certain level of automated control is required for filtration; completely

manual control is not utilized. The most common indicator of filter performance is Turbidity. Each

filter’s effluent should be monitored and recorded continuously. Automation of a typical filter

configuration and typical instrumentation includes:

Individual filter turbidity

Combined filter effluent turbidity

Filter effluent Flow Rate

Filter influent channel level

Filter Head loss

Filter level or level switches

Backwash Flow rate

Filter Effluent particle Counts

Flow Controller- using Modulated discharge control valves to vary effluent flow rate

5) Declining rate filters- These filters are typically equipped with effluent weirs or fixed position

effluent valves rather than effluent rate of flow controllers. The declining rate filters collect solids; the

flow through the filter begins to drop off. Solid begins to accumulate in the filter media bed, porosity

decreases and the head loss across the bed increases. To avoid head-loss increases beyond a desired level

of turbidity breakthrough of the filter media the filter needs to be backwashed or cleaned.

PwC 23

6) Backwashing- Backwashing is the cleaning of filters after the water is treated through their medium

i.e. effluent wires. There are four basic Backwash Methods:

Up flow of wash water through the filter bed without auxiliary scour

Up flow of wash water through the filter bed with air scour

Up flow of wash water with surface wash

Continuous backwash

Control Methods for Automated Backwashing: Backwash is typically initiated manually with

operator intervention or automatically based on filter head loss, filter run time or turbidity levels

of the filter water exceeding a certain set point. Backwash sequencing typically is configured to

minimize filter bumping by gradually increasing backwash flowrate or having a low rate and High

rate backwash. Backwashing is typically completed based on the duration of backwash cycle or on

backwash

The components needed to automate the backwashing are:

1) Turbidity Analyzers

2) Turbidity Recorders

3) Pressure Sensors

7) Chlorination – This is the final step of water treatment. After the filtration the chlorine dose is

given to the water for the end purification. Chlorine dose is given in a controlled and it is controlled

through the chlorine sensor and the residual controller and analyzer. Some of the typical instruments

needed to automate the chlorination are: Chlorinator with pacing signal input – Flow Pacing and

Residual feedback Controller

PwC 24

5.1.3. Detailed Analysis of Plant Wide SCADA

5.1.3.1. Functional Overview of a Plant Wide SCADA

In this section we have covered the indicative Functional Overview of SCADA & its Reporting Application

Software with brief description of each application/services planned to be implemented through Water

SCADA

The services of the department, both information and transactional, shall be delivered to the

stakeholders through multiple service delivery channels including portals (for both internal and external

stakeholders mobile communication (SMS services)

For all users / stake holders the portal is envisaged to deliver information services about the processes

and allow to control based on authorization and access rights. The portal shall also facilitate

transactional services both for water delivery and energy use

The portal shall be accessed through secure intranet and all services shall be delivered through the

internet

The access shall be extended through secure VPN connectivity

The proposed system shall also provide the mobile application/SMS services for facilitating

communication for alarm / alerts /intervention required

Process Instruments Needed for the Automation of Process

Raw Water Pumping Raw Water Flow Meters

Influent Channel Level Sensor

Raw Water l Level Sensor

Flow Controller

Speed and Valve Controls

Valves and Actuators

Variable frequency Drives

Coagulation/Flocculation/

Sedimentation

Raw Water Flow Meters

Raw Water Turbidity Monitors

Raw Water pH meters

Settled water pH Meters

Controller for streaming current detectors- coagulation dosage

control

pH controllers

Backwashing Turbidity Analyzer

Turbidity Recorder

Pressure Sensor – for measuring head loss

Chlorination Flow meters for filtered water

Residual Analyzer

Residual Recorder

Residual Controller- Configured for one of the following modes:

Flow paced

Residual control or compound close-loop control

Chlorinator with pacing signal input

Finished Pumping Flow Meter- for finished water flow

Level Sensor- for checking reservoir level

Chlorine Sensor- checking Chlorine Level

Pressure Sensor- to check the distribution system pressure

Flow Controller – using modulated pump discharge control valves

Variable Frequency Drives for the adjustment of pump speed

PwC 25

Ethernet Ring network

WMSOWS - 1 OWS - 2

PRIMARY/

SECONDARYUPS Reporting Printers

City Control Room

DSL IP WAN NETWORK

SMS functionality

on critical alarms

Web

Client

Leak

DetectionPSU CPU COMCOM

+-

Data

Concenrator

PSU COM

+-

DI DO AI AO

PSUCOM

+-

DI DO AI AO COM

Ethernet Ring network

PSU CPU COMCOM

+-

WTP Controller

ClariflocculatorBuilding

PSUCOM

+-

DI DO AI AO

P

L

A

N

T

C

O

N

T

R

O

L

N

E

T

W

O

R

K

CWPH

EWSOWS - 1 OWS - 2

PRIMARY/

SECONDARYUPS Reporting Printers

PSU COM

+-

DI DO AI AO

Chemical Building

SwitchGear Panel

PSU COM

+-

DI DO AI AO

Chlorination BuildingPSU COM

+-

DI DO AI AO

BackwashPSU COM

+-

DI DO AI AO

Filter House

Modbus Serial

Modbus Ethernet

Fiber Optic

WTP Control RoomDSL IP WAN NETWORK

PSU CPU COMCOM

+-

SMS functionality

on critical alarms

5.1.3.2. SCADA & Reporting Application Software

The task of the SCADA shall be to collect all process-related data from the processing units into the process

database. The process database shall reflect the real-time image of the process. The collected information

shall further be distributed, e.g. for displays, historical archiving, calculations, printing, reports generation

and further transmission to other systems.

The Objectives of reporting software are:

• Continuous system self-supervision

• Display of events & alarms

• Storage of time stamped events

• Trend reports

• Display of station Network Diagram with status of all process objects

• Alarm and event reports

PwC 26

• Automatic printout of fault reports

• Parameter settings of event & alarm

SCADA system should be capable of being configured to various predefined users so that each user defined

in the system can be given access rights for various features. The hierarchies of authorization should take

due care of protecting the system from unnecessary configuration changes. The Suggested users are

following but not limited to

• System Administration

• Engineering

• Maintenance

• Operation

The access rights shall be in the form of passwords & user ID both, Only the system administrator should be

authorized to add / remove users and change access rights. It is desired that the system should prompt the

password change after first log-in so that default password will be overwritten. It is desired that the WMS

software should support multiple instances of software on the same personal computer simultaneously of

the same make. It is desired that the software should have the functionality to alert the system operator

about the event in a specific station by pop up or colour change of the minimized software instances for a

particular station .

A feature of sending the SMS message to field crew is also desired. It shall able to send disturbance & fault

event to the field crew. The WMS shall possess the following additional functionality.

• Features to add new graph, display& reports

• Features of web view only access

• Data exporting to other system in the XML format.

Ethernet Ring network

PSU CPU COMCOM

+-

WTP Controller

EWSOWS - 1 OWS - 2

PRIMARY/

SECONDARYUPS Reporting Printers

WTP Control RoomDSL IP WAN NETWORK

PSU CPU COMCOM

+-

SMS functionality

on critical alarms

RTU

RTU

RTU RTU RTU RTU RTU

RTU

RTU

RTU’s installed at remote locations for reservoir

monitoring & Control

Typical Telemetry Achitecture

PwC 27

5.1.3.3. Functional Requirement of SCADA System

5.1.3.3.1. System Display

The Display system should be based on the principle of communicating to the operator through visual aids

like mimics/ screen videos like Single line diagrams of individual distributors. The operator should be able

to use pictures to communicate with the process and the control system:

• Pictures should visualize the controlled process with industry standard symbols and Specified

colors

• The operator should be able to select the object by using the mouse and issuing the command

by double click. The operator should also able to issuing the command on selected object by

using the functional keys. The keys should be standard for all the installation of a specific

manufacturer

• Pictures should inform the operator about alarms and events by specified color changes

• Pictures should illustrate process data

5.1.3.3.2. Trends Display

A trend is a time-related follow-up of process data. The major parameters to be considered for trends are:

• Flow

• Pressure

• Turbidity

• Energy

• Chlorine levels

• Ph

• Ammonia

• Water Levels

• BOD, SS/SS

The trend display shall be available in graphical mode as a line graph. Trends shall be available on a two

dimensional co-ordinate system that consists of horizontal time (X) axis and vertical value (Y) axis. Trends

shall have minimum following characteristics:

• The curve can be scrolled in both direction, X and Y

• The time axes shall be scalable on minute, hours , day and monthly basis

o It should be possible to get the value of parameters at any instance by clicking the trend

o minimum eight parameters trends should be visible in one screen at one point of time

sharing the same process data

o The graphic window shall be resizable & maxim sable

5.1.3.3.3. Reports Display

The system shall collect the data from the database and able to produce report & produce printout on the

operators request. The system shall have the capability of displaying minimum 10 reports on a single window

simultaneously The system shall able to generate reports based on the user selected values on the basis of

time interval of Day/ Week/ Month/ Year However system should be capable of generating reports on the

basis of:

• Predefined time intervals

• when a predefined event occurs

• Day (mean, peak)

• Month (mean, peak)

• Year (mean, peak)

• System should provide functionality to produce user defined reports

5.1.3.3.4. Event Display

The event list presents the process events from the monitored process in pre-defined way whenever there is

change in status or change in limiting values. Each event shall normally be presented by displaying a

predefined event text line, which describes the event in the process. Event text lines shall consist of a time

PwC 28

stamp, object identification, a single text indicating status and data value. The events should be printed with

WTP/UGR ID, Distributor ID & equipment wise segregation. The events shall be presented in chronological

order so that the latest event appears on the top line of the first page. The event list shall contain keys for

browsing the list forward and backward. Configured of event log file for day, week, month and year wise

shall be possible. Events shall be stored in the history buffer in the computer’s RAM memory, and also stored

on the computer hard disk. The length of the history may be 10,000 events. The 10000 events shall be stored

on the basis of First in First out Principle (FIFO). User configurable prioritization of event shall be possible.

The system should have the functionality for user configurable prioritization & filtration of events.

5.1.3.3.5. Alarm List

The alarm list shall display the present alarm situation of the supervised process. All data Acquisition &

control malfunctions including no responses from field devices and Check- back –verification errors on

control selections, should be reported as alarms. Each alarm message should clearly indicate the type of

malfunction that caused the failure in the operation sequence. Each alarm shall have the time stamp (date

& time), object identification (WTP name & Distributor name), a signal text and a text indicating alarms

status. The alarms will be shown in chronological order. Alarms will have different colors on the basis of

priority and operator shall be in a position to view in archives category wise. Occurrence of alarm will be

noticed by popup in screen with sound. Alarm sound will be different on the basis of priority. The alarm data

can be exported to external system as per the requirement of the operator.

5.1.3.4. System Level Functions

5.1.3.4.1. Status Supervision

The position of each equipment shall be supervised continuously. Every detected change of position shall be

immediately displayed in the single-line diagram on the station of SCADA screen, recorded in the event list

and a hard copy printout shall be produced. Alarms shall be initiated in the case of spontaneous position

changes. The positions shall be indicated by two auxiliary switches, normally closed (NC) and normally open

(NO), which shall give ambivalent signals. An alarm shall be initiated if these position indications are

inconsistent or if the time required for operating mechanism to change position exceeds a predefined limit.

The SCADA shall also monitor the status of auxiliaries. The status and control of auxiliaries shall be done

through separate one or more IED and all alarm and analogue values shall be monitored and recoded

through this IED.

5.1.3.4.2. Measurements

Analogue inputs shall be connected via PLC / RTU with/without intermediate transducers. The measured

values shall be displayed locally on the station monitoring system and in the control center. The abnormal

values must be discarded. The analogue values shall be updated every 10 minutes. Threshold limit values

shall be selectable for alarm indications

5.1.3.4.3. Event and Alarm Handling

Events and alarms that are generated by the sensor unit shall be recorded in an event list in the station

Monitoring System .Alarms shall be recorded in a separate alarm list and appear on the screen. All, or a

freely selectable group of events and alarms shall also be printed out on an event printer. The alarms and

events shall be time-tagged

5.1.3.4.4. Presentation and Dialogues General

The processor shall be a redundant with hot standby and shall provide basic functions for supervision and

control of the equipment. The operator shall give commands to the equipment on the screen via mouse clicks

or keyboard commands. The SCADA monitors shall give the operator access to alarms and events displayed

on the screen. Aside from these lists on the screen, there shall be a printout of alarms or events in an event

log. The following standard pictures shall be available on the monitors of Control Center - Single-line

diagram showing the status and measured values. Control dialogues with interlocking and blocking details.

This control dialogue shall tell the operator whether the device operation is permitted or blocked.

Measurement dialogues Alarm list, station / bay oriented Event list, station / bay-oriented System status

PwC 29

5.1.3.5. SCADA Monitoring System Design Principles

Consistent design principles shall be adopted with the monitoring system concerning labels, colors,

dialogues and fonts. Non-valid selections shall be dimmed out.

The object status shall be indicated using different status colour for: Selected object under command

Selected on the screen Not updated, obsolete values, not in use or not sampled Alarm or faulty state Warning

or blocked Update blocked or manually updated Control blocked Normal state

• Process Status Displays and Command Procedures

• The process status of the WTP/Distribution System in terms of actual values of analog as well

as the positions of valves, circuit breakers, motors, pumps shall be displayed in the WTP single-

line diagram

• In order to ensure a high degree of security against undesired operation, a "select-before-

execute" command procedure shall be provided. After the "selection" of a switch, the operator

shall be able to recognize the elected device on the screen, and all other equipment shall be

blocked. As communication between control Centre and device to be controlled is established,

the operator shall be prompted to confirm the control action and only then final execute

command shall be accepted. After the “execution” of the command the operated switching

symbol shall flash until the switch has reached its new position. The operator shall be in a

position to execute a command only, if the equipment is not blocked and if no interlocking

condition is going to be violated. The interlocking statements shall be checked by the

interlocking scheme implemented at bay and WTP level

• After command execution the operator shall receive a confirmation that the new switching

position has been reached or an indication that the switching procedure was unsuccessful with

the indication of the reason for non-functioning

5.1.3.5.1. WMS Supervision & Display

The Water Management System (WMS) shall be comprehensively self-monitored such that faults are

immediately indicated to the operator, possibly before they develop into serious situations. Such faults are

recorded as a faulty status in a system supervision display. This display shall cover the status of the entire

WTP and Distribution Network including all sensors, communication infrastructure and remote

communication links, etc.

5.1.3.5.2. Event List

The event list shall contain events that are important for the control and monitoring of the

WTP/Distribution System. The event and associated time (with1 ms resolution) of its occurrence has to be

displayed for each event. The operator shall be able to call up the chronological event list on the monitor at

any time for the whole WTP/Distribution System or sections of it. A printout of each display shall be possible

on the hard copy printer.

The events shall be registered in a chronological event list in which the type of event and its time of

occurrence are specified. It shall be possible to store all events in the computer for at least one month. The

information shall be obtainable also from a printed event log.

5.1.3.5.3. Alarm List

Faults and errors occurring in the WTP/Distribution System shall be listed in an alarm list and shall be

immediately transmitted to the control Centre. The alarm list shall substitute a conventional alarm table,

and shall constitute an evaluation of all station alarms. It shall contain unacknowledged alarms and

persisting faults. The date and time of occurrence shall be indicated. The alarm list shall consist of a

summary display of the present alarm situation. Each alarm shall be reported on one line that contains:

• The date and time of the alarm

• The name of the alarming object A descriptive text

• The acknowledgement state

Whenever an alarm condition occurs, the alarm condition must be shown on the alarm list and must be

displayed in a flashing state along with an audible alarm. After acknowledgement of the alarm, it should

appear in a steady (i.e. not flashing) state and the audible alarm shall stop. The alarm should disappear only

if the alarm condition has physically cleared and the operator has reset the alarm with a reset command.

PwC 30

The state of the alarms shall be shown in the alarm list (Unacknowledged and persistent, Unacknowledged

and cleared, Acknowledged and persistent). Filters for selection of a certain type or group of alarms shall be

available as for events.

5.1.3.5.4. Object Picture

When selecting an object such as a valve or other equipment in the single-line diagram, the associated bay picture shall be presented first. In the selected object picture, all attributes like Type of blocking Authority Local / remote control etc., shall be displayed.

5.1.3.5.5. Control Dialogues (In future)

The operator shall give commands to the system by means of mouse click located on the single-line diagram.

It shall also be possible to use the keyboard for command activation. Data entry is performed with the

keyboard. Dedicated control dialogues for controlling at least the devices shall be available:

5.1.3.5.6. User-Authority Levels

It shall be possible to restrict activation of the process pictures of each object (bays, apparatus...) within a

certain user authorization group. Each user shall then be given access rights to each group of objects, e.g.:

Display only Normal operation (e.g. open/close) Restricted operation (e.g. by-passed interlocking) System

administrator

For maintenance and engineering purposes of the station WMS, the following authorization levels shall be

available:

• No engineering allowed Engineering/configuration allowed Entire system management

allowed

• The access rights shall be defined by passwords assigned during the log-in procedure. Only the

system administrator shall be able to add/remove users and change access rights

5.1.3.5.7. Reports

The reports shall provide time-related follow-ups of measured and calculated values. The data displayed shall comprise:

Trend reports: • Day (mean, peak)

• Month (mean, peak)

• Semi-annual (mean, peak)

• Year (mean, peak) Historical reports of selected analogue Values:

o Day (at 15 minutes interval)

o Week

o Month

o Year

It shall be possible to select displayed values from the database in the process display on-line. Scrolling

between e.g. days shall be possible. Unsure values shall be indicated. It shall be possible to select the time

period for which the specific data are kept in the memory.

Following printouts shall be available from the printer and shall be printed on demand:

• Daily voltage and frequency curves depicting time on X-axis and the appropriate parameters

• On the Y-axis. The time duration of the curve is 24 hours

• Weekly trend curves for real and derived analogue values

• Printouts of the maximum and minimum values and frequency of occurrence and duration of

maximum and minimum values for each analogue parameter for each circuit in 24 hrs. period

• Provision shall be made for logging information about breaker status like number of operation

with date and time indications

• Equipment operation details shift wise and during 24 hours

• Printout on adjustable time period as well as on demand

• Printout on adjustable time period as well as on demand

• Reports in specified formats which shall be handed over to successful bidder

PwC 31

5.1.3.5.8. Trend Display (Historical Data)

It shall be possible to illustrate all types of process data as trends - input and output data, binary and

analogue data. The trends shall be displayed in graphical form as column or curve diagrams with a maximum

of 10 trends per screen. Adjustable time span and scaling ranges must be provided.

It shall be possible to change the type of value logging (direct, mean, sum, or difference) on-line in the

window. It shall also be possible to change the update intervals on-line in the picture as well as the selection

of threshold values for alarming purposes

5.1.3.6. Software Requirements

5.1.3.6.1. WMS Software

WMS software can be divided into three categories:

• Operating system software

• Application software that includes any application loaded on the computer (SCADA Software

)

• Configuration file(s) for the settings, displays, and database of the WMS application (Reporting

Application Software)

Note that the WMS computer may have other applications that also have configuration files.

The WMS application typically runs on computers requiring the latest version of Windows, Linux, or some

other operating system. Design tradeoffs can occur when certain requirements are made. For example, the

Designer/Specifier may require a certain operating system to meet a corporate standard, which may limit

WMS selection. The behavior of the operating system software during and after power failures may help to

prevent unexpected WMS performance and must be determined prior to deployment. In addition to the

WMS software, the Designer/Specifier should also consider other software applications to be loaded on the

computer. Examples of such applications include software that configures WTP/Distribution System

devices, monitors network traffic, retrieves data from WTP/Distribution System devices, views different

files, web browsers, and other applications that may be important to personnel working in the

WTP/Distribution System. These applications may or may not be directly linked in the WMS application.

The Designer/Specifier should also consider whether the actual configuration files should have backup files

located on the WTP/Distribution System computer or if the files should be stored elsewhere. Due to

availability, security, and redundancy, this determination may not be trivial and should engage all of the

impacted parties

5.1.3.6.2. Issues

Patches and updates to all WMS software will be issued at various times during the life of the system.

Coordination of the various updates is essential and may require a maintenance contract or licenses that the

Designer/Specifier should include in the WMS specification. This may increase software costs. The

Designer/Specifier may require that all vendors provide copies of all WMS software. The Designer/Specifier

should consider whether multiple copies are required, which may increase software costs due to licensing

issues. The Designer/Specifier should also address process issues that most likely should not be included in

the WMS specification. The Designer/Specifier should provide a means to provide a version control process

that records all WMS software. These records should include compatibility relationships between the

various software. A backup process should also be put in place.

5.1.3.7. SCADA Software Requirements

5.1.3.7.1. Architecture of SCADA software

• Client / Server architecture based on TCP/IP networking and report-by-exception (RBE) technology

• Standalone single server operation

• Symmetric main-standby & capacity for triple standby server functionality

• Additional servers for client load sharing and remote locations

• Permanent Standby Server designed to be placed outside corporate firewalls providing a read-only

access to the server while ensuring corporate security

PwC 32

• Fully automated data transfer between servers to provide complete server redundancy. This transfer

shall include configuration, real-time data, historic data and event lists. Database updates shall be

on an incremental basis with tunable parameters

• A scalable fully distributable architecture providing:

a. Unlimited number of server systems

b. Unlimited number of display clients

• Where multiple servers are deployed, the system shall be capable of being configurable from a single

client

• All redundancy shall be handled by the database, with the operational state of systems preserved

through a server changeover. The system shall not rely on driver redundancy for data transfer where

providing redundant server. The system shall present a uniform view of data including

communication status after a fail over

• Forced changeover between main and standby allowing seamless changeover between main and

standby servers without shutting down either server

• Clients to connect to a synchronizing server as soon as the configuration and current data in the

database has synchronized. Incomplete data sets as per clients request on event or trend provide

indications that the synchronization is still in progress to ensure that conclusions are not drawn

from incomplete data sets

• Configurable compression of data communications between client/server and server/server to allow

optimization of communications performance over WAN networks

• Change reporting on Client/Server and Server/Server links rather than polled communication to

permit operation on WAN networks

• Capable of operating Client/Server and Server/Server links over low to medium speed channels

depending upon database size

• Application shall be native 32-bit and 64-bit versions and supported on Windows® Server and

Workstation operating systems including Windows 2000, Windows XP, Windows 2000 Server,

Windows 2003 Server, Windows 7 (32 and 64 bit) and Windows Server 2008 R2 and later.

5.1.3.7.2. Database

The SCADA database shall be of true relational database design and optimized for real-time SCADA

operation. The database shall be object oriented and organized in a hierarchical structure. It shall support

user-created “Templates” that allows management of common configuration from a single point in the

database. Instances of templates shall be used for repetitive, standard configuration. Templates of standard

configuration shall support multiple object types including, but not limited to:

• Point / Tag objects

• PLC / RTU or PLC / RTU objects

• Mimics or Graphic display objects

• Trend objects

• Logic programs

• Schedules

• Link objects

The SCADA database shall allow users to extend the database schema to store custom data, in either the

Configuration or data stream. These changes can be performed online without need for server restart.

5.1.3.7.3. Operator Interfaces

• SCADA software shall provide the ability to support multiple local and remote display clients

• Display facilities shall be available via LAN, WAN and dial-up connection

• Display clients shall be supported as Rich Clients without the requirement of a database resident at

the display node

• Rich Clients shall support database management and configuration changes

• Rich Clients shall support multiple monitors (multi-head display), allow logon for all heads from a

single location. The system should also provide navigation facilities such that displays on each head

can be controlled from any head. (yoking)

• Integrated Web Sever capability shall be available, providing all display and operational facilities of

the Rich Client without the need for additional software to be installed.

PwC 33

• Web Clients shall allow users to view Mimics, Trends, Database Objects, Reports as well as perform

control functions using a standard web browser.

• Changes made to the SCADA server shall require no additional steps to be performed in order for

those changes to be available to Rich Clients and Web Clients.

• Each full function Rich Client shall be configurable to connect to one, or multiple server systems

• Full function display clients shall automatically fail-over & reconnect to a redundant server node

when server change-over occurs.

• Current generation Windows® look and feel shall be provided by the SCADA system operator

interfaces, including provision for “favourites lists” comprising links to any server object. This

includes, but is not limited to: Mimics, Graphs, List Queries

5.1.3.7.4. Mimics / Graphics

SCADA system Mimics shall support a wide range of graphical facilities. Scalable Vector Graphics are

required in order to permit operation of the SCADA system with different resolution clients operating

simultaneously. Fixed resolution bitmap graphics are not acceptable. Mimics shall be multi-layered, object

oriented and permit mimics to be embedded in other mimics. Other objects that must be available for

embedding in a mimic include:

• Button objects

• Hyperlinks

• Disk images (e.g. JPG, motion JPEG)

• Remotely updated images

• Hyperlinks with embedded queries (for generating filtered lists directly from a mimic)

• Object menus

Graphical facilities within a mimic must also be object oriented including the ability to manipulate attributes

of embedded objects in real time, supporting animation including but not limited to:

• Fill factors

• Fill colour

• Rotation

• Position

5.1.3.7.5. Line thickness

• Text attributes

• Transparency

• Alpha blending

• Multi-rate Flashing

A suite of Graphical Symbols shall be provided for integration with configuration templates and embedding

within other mimics. Import of mimics shall be supported from DXF format, including integration of multi-

layered DXF drawings in to native SCADA mimics.

Adding Custom database fields dynamically to Metadata where the server does not have to be restarted after

adding or modifying.

Mimics shall support the ability to specify OPC data source information to display directly on the mimic.

This permits data from other systems to be seamlessly integrated in to the SCADA display. Other facilities

required to be supported by mimics includes:

• Context sensitive object menus available from mimic

• Accept an alarm from a mimic

• Issue a control from a mimic

• Operator Notes (as a native feature)

• ToolTips

• Hyperlinks to external documents (e.g. HTML, PDF, MS Office® suite documents)

Objects embedded and displayed on any mimic shall be viewable through both the full function client and

web client displays.

PwC 34

5.1.3.7.6. Start-up

The SCADA system shall startup unattended, and without compromising system security. The SCADA server

process shall operate as a Windows® Service. The SCADA server shall start without the requirement for an

HMI client to start. Windows® logon shall be available prior to display client RTUs which must provide

additional security. Shutting down a display client (including on the server node) shall not affect other users

or the server. Administrative privilege shall be required to shut down a SCADA server.

5.1.3.7.7. Configuration

The SCADA software shall provide full seamless On-line configuration of all database parameters including

but not limited to:

• Communication channels

• PLCs and PLC / RTUs

• Points / Tags

• Sequences

• Schedules

• Alarm redirection

• Mimics / Graphics

• Trends/graphs

• Reports

Configuration changes shall be capable of being made from local and remote workstations using Rich

Clients, with appropriate privilege. Configuration changes are to be applied to the Main SCADA server and

seamlessly applied to Standby server and other SCADA server nodes such as user performance sharing

SCADA nodes.

Further, configuration changes made to mimics and other display objects shall be immediately available to

local and remote Rich and Web display Clients without any manual intervention. Changes should be updated

automatically in local caches where appropriate. This facility shall be a native feature of the product and not

require external scripts or customization.

All aspects of the look and feel of the SCADA system, including default field values, shall be configurable. It

is not acceptable for colour regimes, communication parameters and other aspects of the system to be

hardcoded.

It shall be possible to add user defined fields to the SCADA database. These fields should be accessible both

internally and externally to the SCADA system; being exposed via OPC, ODBC, OLE Automation,

XML/SOAP, etc.

The SCADA server shall provide detailed diagnostics concerning its internal operation. The diagnostics shall

be available through capture to a log file as well as online locally on a server and remotely via Telnet and

Web interface.

The SCADA software shall provide the ability to perform a complete audit trail of all database changes down

to the individual property level of objects to ensure complete system integrity and safe system operation.

These details shall be provided as a built-in integrated part of the system and shall include, but not be limited

to the following:

• Time of change

• Object on which change was performed

• Property of the object that was modified

• Property value before and after the change

• User that made the change

• Reason for the change

Stored configuration records should be maintained in the historic database for a configurable time period,

support redundant SCADA server configurations and allow access from standard database interfaces such

as queries and simple mechanisms for displaying and filtering the configuration records

PwC 35

5.1.3.7.8. Alarm Management

The alarm system shall provide facilities where actions can be triggered by alarms. These facilities shall be

provided as a built-in integrated part of the system and shall include, but not be limited to the following:

• Configuration criteria for alarm actions

• Escalate Alarm priority

• Delivery of alarm to users via SMS

• Delivery of alarm to users via E-mail

• Trigger other actions including sequences

• Integrated paging facilities shall be provided without the need for additional software.

• The paging facilities shall include calendar operation for roster based user lists with flexible

interface for reconfiguration of alarm management

Tracking of alarms shall provide as a minimum:

• Alarm activation including point name, state, timestamp, priority

• Alarm de-activation

• Alarm acceptance including time, user responsible, optional comment

• Custom alarm fields for display of additional or operations specific information

Where a full function Rich Client is connected to multiple SCADA systems, alarms from all systems shall be

combined and filtered, based on user privilege and areas of responsibility.

System administrators shall be able to configure user accounts with default filters so tha operator alarm lists

can be confined for users to those areas where they assume responsibility.

Full function Windows & Web clients shall provide indication of alarm condition, with the ability to change

alarm tone, color, and other attributes based on alarm priority.

Full page and window display of the current alarm list to be shown. It shall also be possible to modify the

background color of alarm lists.

Alarm display, acceptance, query and comment entry shall be available via an integrated product Web

interface.

Alarm limit time profiles allowing analog setpoint levels to vary over the course of a day to account for

conditions at the site.

Consequential alarms to allow one (or more) alarms to be suppressed as the result of another alarm

occurring.

Suppressed alarms will be received and processed by the SCADA Server and recorded in the event journal

for future auditing, however the operator shall not be forced to take an action on an alarm where the cause

is known

5.1.3.7.9. Event Journal

The system shall provide, as a built in feature and without the requirement for custom or external software,

facilities for event logging. These facilities shall be separate from the alarm list and include the capability to

insert user comments at any place in the event list.

Event lists shall be obtainable through query or filtered through user entry on a forms-based display.

Event data is to be stored in a time-series relational database. Each event record shall comprise a timestamp,

responsible user, point name, message, and reason for event log.

The event journal shall support the following:

• ODBC / SQL interface to event data

• Filter and browse via full function display client

• Filter and browse from Web client interface

PwC 36

5.1.3.7.10. Historical Data

The SCADA system shall provide a built in data historian with the following facilities as standard features.

These shall be provided without the addition of external software modules:

• Time-series relational database

• ODBC / SQL interface to historical (trend) data

• Historical data to be stored with time-stamp, point quality, alarm status

• Historic storage is to be based on configurable criteria including time between samples,

alarm state change

• Compression capability

Historical files supporting fixed interval sampling only will not be accepted. Where historic data can be

retrieved through communication devices such as PLC / RTU/PLC / RTUs, the

Historic data sub-system shall natively provide the capability to backfill this data in to the historian. No loss

of data or gaps in data as a result of communication or server failure shall be accepted. The vendor must

demonstrate its ability to ensure data integrity and history data recovery. An API shall be included to provide

interface capability with the SCADA database. This shall be based on OLE Automation and/or .NET

The historic data subsystem shall provide fixed and user configurable views of the historic data tables. These

views are required to provide SQL pre-processing and present historic data in aggregate format.

The SCADA server shall provide Historian functions including the capability to validate historic data prior

to exposing it externally to the SCADA system, selectable archiving rates, point-by-point storage

compression regimes, annotation on history samples for tracking comments on operational conditions,

modification of historic data for normalization and correction (tracks previous value and modifying user

and is subject to user privilege), auditing of modified or annotated history.

5.1.3.7.11. System Security & Access

The SCADA system shall provide a high level of inherent security. To this end the SCADA software shall

provide security access down to data point level, and support individual Users, User Groups and a matrix of

system capability and access to any level of the SCADA database.

Full function Rich & Web client interfaces shall require explicit administrative configuration to valid

connection to the SCADA server.

Web interface facilities shall provide the capability to operate the Web interface using SSL and encrypted

data. The Web functionality shall be provided in an integrated way with the web server facility tightly

coupled with the SCADA database. It is not acceptable for the system to utilize IIS or similar external web

interfaces, or require web pages to be “published” from the SCADA system. Changes in configuration to the

SCADA system shall not require additional steps in order to provide modified information to the SCADA

Web interface.

The SCADA system security shall provide the ability to be integrated with Windows domains to authenticate

logon attempts against a trusted domain. Validation should occur across all client interfaces, ensuring that

users utilizing all types of clients are subject to the built in system security policies.

5.1.3.7.12. Open Connectivity

To provide easy access for customized reports and external data manipulation the SCADA software shall

provide inherent OPC and ODBC database connectivity without the need for additional software options or

modules. Integration with standard desktop computer products is essential

The following Open interfaces shall be provided as integrated components of the SCADA system are

required:

• OPC Data Access (OPC-DA) to the SCADA server real-time and configuration database

• ODBC and OLE-DB to the SCADA server real-time database, historian, event / parameter

journal and configuration database

• OPC Historic Data Access (OPC-HDA) to historian

• OPC Alarm & Event (OPC-AE) to event sub-system

PwC 37

• OLE Automation interface to the SCADA server database

5.1.3.7.13. Reports

An integrated reporting package shall be able to generate, print and export reports:

• Triggered by SCADA events

• On user demand

• On timed schedules

Report generation shall use latest technology in database access and be capable of combining data from

multiple databases via ODBC/SQL. This shall include SCADA and non-SCADA databases. Reports shall be

able to be generated in a number of formats including:

• HTML for viewing via Web interface

• PDF format

• CSV format

• MS Office® suite format

Generated reports shall be able to be:

• viewed in Rich Clients and Web Clients

• printed on a local or network printer

• stored on disk file, locally or remotely

• e-mailed to assigned users

5.1.3.7.14. Standard Drivers

• The SCADA system shall provide native support for fully integrated Wide Area SCADA PLC

/ RTU protocols.

• This shall include the capability for supporting all protocols in redundant SCADA server

configurations and support

• redundant communication paths.

• All drivers shall provide the ability to monitor communication statistics, log driver

diagnostics, and provide online

• access to driver and channel diagnostics remotely via Telnet or similar mechanism.

Captured diagnostics shall be able

• to be translated to HTML for analysis in clear human-readable format.

• Apart from PLC / RTU and PLC / RTU communication drivers, the system shall also

support as standard the following drivers:

a. SMS (with TAP and UCP service) to mobile phones and pagers with a GS or

CDMA modem connected directly to the SCADA server.

b. a full function system is required including calendar based rosters

c. SNMP – monitoring of network devices such as routers, computers, UPS, etc.

d. NTP – time server monitoring and alarming

e. ODBC – query data from other databases

f. Windows Performance Monitoring

g. OPC-DA driver

Wide area PLC / RTU protocols shall support:

• local serial port communication

• terminal server serial port communication

• Ethernet LAN communication via TCP and UDP ports

• time synchronization

• presetting output configuration points where configured

• fully integrated incorporation of events from a PLC / RTU

• unsolicited exception reporting

• Where PLC / RTUs utilize the DNP3 communications protocol, those devices must support

the DNP3

• Secure Authentication standard.

PwC 38

All drivers shall support capability to update SCADA database point value / alarm state / point quality /

timestamp. PLC / RTU protocol drivers shall support the ability the backfill time-stamped data into Event

Logs, Historic Data to maintain data integrity in the event of communication failure

The driver architecture shall support user accessible interfaces to access major driver functions. This shall

include, but not be limited to:

• enable / disable PLC / RTU communications

• trigger an integrity poll

• alter communication parameters

Drivers shall maintain current state of target device information, and when used in redundant server

architecture shall retain state information and be able to receive solicited and unsolicited information from

the PLC / RTU immediately following a server transition. It is not acceptable for the system to indicate

communication failure or not be able to receive communication from a remote device during the period of

transition from one server to another

The following protocols shall be supported and integrated with the product:

• Modbus Master serial protocol

• Modbus Slave serial protocol

• Open Modbus/TCP Master protocol

• Open Modbus/TCP Slave protocol

• OPC-DA client driver (for connection to OPC Server driver)

The OPC-DA interface shall include as a minimum, integration with SCADA database value / state / quality

/ timestamp data, support OPC-DA 1.0 and 2.0 specification interfaces, polled and exception modes, tag

browsing.

5.1.3.7.15. Logic

The SCADA system shall support logic sequences with full access to all SCADA system services at run time.

Programming of sequences shall be to the IEC61131-3 international standard and support as a minimum the

following languages:

• Ladder Diagrams

• Function Blocks

• Structured Text

• Sequential Function Charts

Sequences shall be able to me modified and started and stopped online. Sequence changes shall be a native

part of the database and replicated to redundant SCADA servers. Special scripting languages to perform the

control strategy will not be accepted.

5.1.3.8. Process Historian

The historian software should be based on open, standard technologies. The Historian software should help

the plant and IT personnel to optimize operational efficiency by providing a powerful, enterprise-wide

reporting tool that collects, historizes and delivers meaningful reporting data from multiple, disparate

systems. By using the information provided by the Historian, one should be able to make more effective

decisions toward optimizing operational performance.

The package comprising of historian and portal functionalities, should enable the user to accurately store

data for long-term reporting while also giving the user the option of visualizing and accessing the

information through the Historian portal, Excel or Reporting Services.

5.1.3.8.1. Software Details

i. The software should improve production reporting and ad-hoc analysis by connecting, aggregating

and presenting real-time information from multiple disparate systems throughout the enterprise,

allowing corporate, IT, plant and production managers to make more informed and timely

decisions.

PwC 39

ii. The historian should collect all changes in the process tag values, as well as alarm activity, from

within each control system. Each change should be saved with a timestamp and an OPC quality

stamp. Data should be acquired at user-definable rates, including sub-second data acquisition rates.

iii. The historian should support redundant control system links. In the event that one link fails, the

historian should request the data from the other link to the control system. In the event that the

network link to the historian fails, the historian should backfill from the control system’s trend and

alarm systems to acquire data that it could not acquire in real time. Quality flags should be stored

using the OPC status and sub-status definitions in conjunction with customized high-byte sub-

statuses to accurately reflect the status of the SCADA system data at any point in time.

iv. The historian should compress data by saving only changes in values. The data should be stored

directly into tables in the database Server; so that the large number of applications that have

DATABASE connectors can access the data and bring it into various applications. The historian

should leverage the security of the DATABASE Server to enable the user to secure each table, view

and function within the DATABASE Server. The user should be able to utilize Standard DATABASE

audit tools to see if any unauthorized editing of databases has occurred.

v. The Historian should be able to acquire data from SCADA systems via OPC V2 and OPC V3 servers

at sub-second retrieval rates.

vi. The Historian should be provide easy configuration like simple drag-and-drop techniques for

selecting data to be logged from SCADA systems, and a user-defined folder structure for organizing

logged data. Customization of individual tag parameters should be provided through easy-to-use

forms that identify aspects of the data to be logged.

vii. The Historian should offer web functionality. The Web Client should provide maintenance

engineers with a fast way to analyze trend and event data and to compare real-time and historical

data within one interface.

viii. The historian should comprise a Microsoft Excel Client which provides engineers and operations

managers with the calculation tools they need to model and analyze production. It should provide a

high quality reporting system using Reporting Services to build custom reports for any process

application where data be presented graphically, with the ability to drill down for more detail into

any results that may appear out of the ordinary.

ix. The Historian software should connect to one or more plant control systems via OPC. The software

should automatically import the tags, trends and alarms, making them available for immediate

publication. It should support bi-directional data transfer allows data to be read from, or written to

(with security privileges), plant control systems.

x. The historian software should support connections to all type of databases. Once the database data

source is created, it should automatically load the table structure. The software should be designed

to handle both

Data archiving

Plant control system connections integrating plant floor data with existing third-party applications or ERP systems.

xi. Operation of the software with Enterprise Edition of DATABASE Server 2008 R2 should also be

supported, so that users wishing to use the Enterprise Edition can also benefit from data

compression.

xii. The software should use OPC HDA Server as standard protocol for freely connecting to

manufacturing execution systems (MES) delivering a fully integrated solution allowing the

movement of information vertically from the factory floor throughout an enterprise with multi-

vendor systems.

xiii. The software should support OPC DA Client, an industry standard protocol, for connectivity to any

third-party SCADA system. The Historian software should provide direct access to tag alarm and

PwC 40

trend information from within the SCADA systems. This data can be transferred to business

applications or visualized within the Historian’s Web and Excel Clients, enabling data from multiple

SCADA systems to be compared and analyzed or histories to the historian for long term storage and

greater analysis options.

5.1.3.8.2. Reports & Alarms

i. The historian software should use the graphical query builder and report generation capabilities of

Reporting Services to deliver drag-drop-and-click reporting of any data from the historian. The user

should be able to schedule to run the reports based on an advanced scheduler. The functionality to

send scheduled reports to managers by email or recorded in a file share should be provided. In either

case, the user should be able to select to receive the report as HTML, PDF or an Excel spreadsheet.

ii. Alarm management is a set of procedures, practices, tools and systems that jointly assist in making

sure a plant’s alarm system is effective throughout the life of the plant. The historian should provide

pre-configured alarm rationalization reports based on the EEMUA (Engineering Equipment &

Materials Users Association) 191 alarm management guidelines.

iii. The historian software should contain ready-to-use energy reports that can facilitate energy

consumption assessment and potential savings across the equipment level, production lines, an

entire plant or multiple sites.

iv. The package should contain an intuitive visualization tool that allows operators and process

engineers to analyze the cause of process disturbances by bringing together trend and alarm data

on a single integrated display. The user should be given complete flexibility with regards to the ways

in which the pens can be displayed. For example, they can be overlaid or stacked or even moved to

different panes to reduce clutter and make the display simpler and easier to read.

v. The Analysis tool should include features such as true Daylight Savings Time support, accuracy to

millisecond resolution, and individual time axis per pen, customizable toolbars, rich printing and

saving of display settings for easy recall.

PwC 41

5.1.4. Detailed Analysis of Plant Automation

Plant Automation component includes the systems which are needed to automat a Water Treatment Plant.

The major part of this component is Programmable Logical Controller and Area Control Panel.

5.1.4.1. CPU specifications

The processors must have an internal non-volatile memory to store application and data. Processor must also have a reserved slot for a removable cartridge so that the application and data backup can also be performed also on a mobile device.

A program written for one CPU can be executed by another CPU in the range as long as it has sufficient capacity.

It must be possible to connect a PC (programming terminal) or a human-machine interface via a USB port integrated in the processor.

Embedded web server must provide CPU diagnostic, including detailed information on Ethernet system networking.

The Embedded web server must display application variables and advanced diagnostics features (rack viewer, alarm buffer, complete PLC application)

Each processor should have a savable real-time clock which manages:

o The current date and time

o The date and time of the last application shut-down

o The date and time should be managed even when the processor is switched off for 20 days.

NTP server must be provided within the CPU.

The processors must be equipped with ground connection contacts without additional cabling.

The performance capacities of the various processor models are to be expressed in terms of execution time for 1K List-equivalent instructions for the two application profiles defined below: Most powerful controller must process at least:

50 Kinstructions / ms for Boolean application

40 Kinstructions / ms for Numerical application

The PLC must be able to load the program without the use of programming software, just with the use of the memory cartridge.

It must be possible to add modules or add remote I/O islands in the configuration without stopping the controller, as well as changing the application or variables.

Processor must provide cyber-security features, such as real-time memory integrity control, access control…

The complete environmental footprint of the product must be known, such as equivalent CO2 consumption during each phase of product life.

The operating system (OS) must be capable of multitasking with up to 4 periodic tasks and more than 60 event or I/O tasks.

The I/O and channels (counter, etc) of the various modules can be assigned to each task.

The PLC RUN/STOP functions can be remotely controlled by setting the parameters of an input channel.

It must be possible to assign a chosen physical input to prohibit any modification or downloading of the program.

It must be possible to maintain the outputs or set them to fallback position when the PLC switches to STOP mode via channel by channel parameter entry.

Execution of the warm and cold restart procedures is available by system bits which are accessible by the program and terminal.

It must be possible to perform a functional update of the processor by simply downloading the firmware through the dedicated software or the programming software platform. However, it must

PwC 42

also be possible to use a more recent version of the programming software without having to update the firmware of the processor.

To help in debugging applications, it must be possible to set breakpoints and watch points in application so that customer can check all system and data when executing his application. System must also provide Step-by-Step running feature to execute all operations one by one in the application.

Engineering tool must provide a trending tool embedded to display variables at a minimum of 1ms sampling rate

Hot standby synchronization signal link should not be more than 10ms and failure detection time should not be more than 20ms in the worst case.

The processor should be provided with 16MB as minimum of integrated non-volatile memory to save whole application and data, even in redundant configurations. A Removable memory cartridge must provide up to 4 GB of memory capacity

Operating system running on this removable memory cartridge must insure a high level of reliability to be compliant with industrial constraints to support for example extraction of the cartridge during execution.

It must be possible to store the program, comments and symbols in the PLC to enable connection of the programming tool without having the application on it. The "empty terminal" functionality must be possible whichever IEC language is used. It must be also possible to use the memory extension to back up files (production data, recipes, etc)

It must be possible to secure access to application stored on the cartridge to prevent the run of application from any controller

All products must be designed with eco-design requirements (Green Premium)

5.1.4.1.1. Distributed & Remote configurations

The communication functions of IP20 remote I/O modules must be independent of the input and output interface functions. It will therefore be possible to connect any module to the main field bus standards (multi-bus openness) including, amongst others:

o Ethernet 10/100Mbps

o Serial links

o AS-i

System must also support in remote configuration expert modules, such as counting, and weighing functions.

System must support in same network a mix of synchronized and unsynchronized drops and equipment with PLC scan.

Connection to synchronized or unsynchronized drops must be provided through ring topology to insure quick recovery (<50ms) in case of one cable failure.

Supplier must provide an opened system where it must be possible to integrate third party device based on standard technologies.

The supplier must have an IP67 offer. The IP67 dust and damp proof remote I/O modules, equipped with a fast connection system using M23/M12 type connectors, must be able to provide a remote power supply to the modules via a single cable.

5.1.4.1.2. Input and Output Modules

The I/O module assembly will consist of a mounting base, I/O module, and field wiring connector(s).

The I/O module will plug into the base, allowing “Hot Swap” capability where the modules can be inserted and removed without removing power or shutting down communications.

The plug-in connectors will plug into the front of the I/O modules and can be removed without the need to disconnect the wiring.

There must be a locating device for the modules, and automatic checking of conformity with the system software configuration to ensure that errors are avoided during module replacement.

PwC 43

All modules have a display block for identifying module and channel faults: input, output, bus device, axis, etc. These diagnostics are performed without using any special tools.

The modules are fully configurable by setting parameters in the development and runtime software. The parameters are stored in the PLC application and are automatically reloaded by the CPU if a module is exchanged.

All I/O modules should include a front mounted LED status indicator each input or out point to indicate the state of the inputs and outputs.

All modules shall be enclosed in rugged plastic housings with an environmental rating of IP20.

The catalogue should offer high density digital I/O, 64 I/O minimum, on one slot width module.

The high speed communication backplane of the I/O drop will be used to communicate the I/O states, data, and status information between the I/O modules and the communication network interface module for the I/O drop.

The I/O modules shall be capable of connecting directly to 2 and 3 wire devices and is capable of providing the power for the field mounted sensors and actuators.

The digital I/O modules should include versions that will connect to 24 VDC, 120 VAC and 240VAC field devices.

The 24 VDC digital input modules should be able to interface with either IEC type 2 or type 3 field devices

The digital output modules should include protection against reverse polarity, short circuit, and overload of the outputs, with automatic recovery.

The digital input modules should include the option for user selectable input filter time and input polarity.

The digital output modules should include the option for the user to select modes for fault recovery, output polarity, and fallback states.

The digital input modules should be available in versions that have 16, 32 & 64 points that will allow the user to select the number of I/O points that are required at each location.

The analog input modules shall have a maximum of 8/16 channels per module and shall accept 4 -20 mA signals inputs from field mounted transmitters. Input signal conversion shall be a minimum of 12-bit resolution.

The analog output modules shall have a maximum of 8 channels per module and shall convert 12-data bits into proportional 4-20 mA analog output signal.

For temperature measurements the I/O sub-system should include a multi range module of maximum 8

channels of thermocouple input that directly connects to Thermocouples, type B, E, J, K, R, S, and T. There

should be a multi range module of maximum 8 channels of RTD input to connect to RTD’s type Pt. 100, Pt.

1000, Ni 100, Ni 1000, and Cu 10, as well as a mill volt input,± 80 mV.

5.1.4.1.3. Ethernet communication

System must integrate in its communication layers standard Ethernet.

Synchronized and unsynchronized drops with PLC scan can be managed over standard and open Ethernet communication.

Communication network must be the same everywhere in the system, from control level to field level insuring network continuity from top to bottom.

Offer catalog must offer in rack Ethernet modules to build the entire integrated architecture. For example, offer must provide in-rack switches, Wi-Fi access point, and fiber optic converter.

Two types of exchanges of variables must be provided:

o Explicit exchanges (via function blocks integrated in the application)

o Implicit exchanges (Using cyclical variables generated by the single declaration of the device)

No prior declaration or configuration of the transmission or destination device is necessary for using communication function blocks.

PwC 44

A set of dedicated function blocks can be used for the simple setup of communication, doing away with the need for coding communication requests specific to each protocol.

The range must offer processors which have multiple integrated Ethernet connections with at least one Web server for diagnostic purposes, and one service port.

The range must offer separate Ethernet module that extends Ethernet connections with at least one Web server for diagnostic purposes or advanced web server services to control application, local configuration or complete system. System must accept a maximum of 4 of these Ethernet modules.

The PLC must be able to connect to the Ethernet network via integrated ports modules on a shielded twisted pair via an RJ45 connector.

The Ethernet connection must support SNMP agent functions for the standard MIB II base (RFC 1213).

The PLC must be accessible via Ethernet (from a remote site) using a standard Internet browser (Microsoft Internet Explorer type), or any other platform (android, iOS). A Web server must be installed in the PLC. It must provide functions for Ethernet communication diagnostics. These functions must not require any prior configuration or special software. In addition, the use of these functions must have no effect on the PLC scan time.

Variables or animated objects in the Internet browser’s web pages must be refreshed automatically from the PLC using a standard Internet protocol, without having to update the entire page.

The offer must have a solution to enable remote I/O exchanges on Ethernet TCP/IP or EtherNet / IP without any programming in the application. A device must be reconfigured automatically after replacement

There must be a mechanism for checking the bandwidth in order to simulate the load on the connection when it is configured.

5.1.4.1.4. High Availability

The range must at least include a processor designed to be part of a redundant architecture, obeying a principle of redundant controllers which guarantees a switchover without loss of control of the process on occurrence of a failure.

In case of a redundant processor configuration, the system is designed to have a bump less transition (no unattended spike on the IO during switchover)

The processors shall have to be dedicated to the services of the redundancy, and won't have to be associated with any specific coupler, configuration, nor specific programs. The implementation of the redundant solution shall be "plug & play" by design.

The data exchanges between the two redundant processors (Primary and Standby), are using a very high speed link of 1 Gbps.

The whole redundant variable database must be exchanged during each scan time, with a minimal impact on the cycle time of the system.

The user is able to select which variables are redundant in the application

The two processors can be distant up to 15 km. The dedicated redundant connection between the 2 processors can either be using fiber optic or copper RJ45 cable

The application logic program can be modified while the system is running, and without compromising the redundancy function

The redundant system must be seen by the SCADA as a single PLC (one IP address). The system manages in all transparency and automatically the IP address swapping of the Ethernet couplers.

The redundant controllers have their own IP addresses that never swap, in order to connect the engineering tool continuously

The system components internal firmware can be updated while the system is running without losing the redundancy function

The redundant power supplies used must provide a transparent status of their redundancy without extra hardware or wiring

The redundant power supplies must provide natively information about their ageing, to be able to be replaced before failure (preventive maintenance)

PwC 45

The redundant power supplies must use a true redundant technology (one active at a time, the other ready to take full load if needed), not using load sharing technology

5.1.4.1.5. Cyber Security

The system must be compliant with IEC – 62443 standard

The system MUST be Achilles level 2 certified

The system must have passed successfully the CSPN test

The system must be able to secure communication between PLC and engineering workstation providing authentication and integrity of data

The system must be able to secure communication between PLC and SCADA providing authentication and integrity of data

The system must be able to log any PAC security events into any SYSLOG database

The internal firmware of the CPU must be digitally signed and encrypted

The integrity of the firmware must be checked before any application download and at startup of the system

The integrity of the engineering software must be checked on demand

The user must be able to disable the following Ethernet services : FTP/TFTP/HTTP/EIP/DHCP/BOOTP/SNMP

The system provides an access control list for each protocol and each connected IP address

Any modification of the operating mode of the system (Run / Stop / Program modifications . . . . ) must be authenticated

5.1.4.1.6. Standards and certifications

The PLC must conform to the main national and international standards covering electronic equipment for industrial control systems:

a. CE marking according EN 61131-2

b. CSA 22-2 N° 142 (Canadian Standards Association)

c. UL 508 (Underwriters Laboratories)

d. C-Tick ACA (Australian Communication Authority/Australia)

e. CSA 22-2 N° 213 Hazardous Location (CSA)

f. FCC Part 15 – Class A

g. GOST CEI

The PLC must conform to the main certifications relating to marine classification:

a. BV (Bureau Veritas/France)

b. DNV (Det Norske Veritas/Norway)

c. GL (Germanischer Lloyd/Germany)

d. LR (Lloyd’s Register/United Kingdom)

e. RINA (Registro Italiano Navale/Italy)

f. ABS (American Bureau of Shipping / USA)

g. RMRoS (Russian Maritime Register of Shipping / Russia)

The PLC must conform to Ethernet robustness certification :

a. Achilles Level 2

b. Be compliant with IEC – 62443 standard

PwC 46

5.1.5. RTU’s for Distribution & Intake networks

Automation component includes the systems which are needed to automat a Intake & reservoirs. The major

part of this component is Remote terminal Unit and GPRS connectivity modem.

5.1.5.1. RTU Technical Specification

5.1.5.1.1. Major Functionality of RTU

• Functionality to map the field devices

• Provide communication connectivity to the all the slave devices through Serial

Communication or TCP/IP communication

• Provide a communication facility to the field devices through serial communication through

RS232 port via a serial communication device viz. modem etc.

• Should have a ability to collect data from all connected devices, regardless of protocol and

make it available to the control centers & WMS using a LAN,WAN connectivity

• Should act as a protocol translator to ensure interoperability with the protocols defined in

the communication principle section

• Should be capable of handling real time data exchange services to publish or subscribe

information for defined master and slave protocols

5.1.5.1.2. Specifications of RTU

The PLC shall be non-redundant, modular. The controller shall at least include the following base I/O and

further expansion shall be possible using expansion modules .The RTU shall be as per the following

specifications:

• Digital Inputs: 16 (24 VDC)

• Digital outputs: 10 (24 VDC Transistor/ Relay)

• Analog Inputs: 8 (Min.12 Bit resolution)

• Analog Outputs:8 channels/ Module

5.1.5.1.3. Communication protocol for RTU

• The RTU shall possess a minimum of three built-in communication ports with the

following characteristics:

• Two serial port (DTE) jumper-configurable to RS-232 (full or half duplex RTS/CTS

control) or RS-485 (two-wire half-duplex) with operation to 115,200 baud

• One USB 2.0 ports, Type “B” Peripheral

• The RTU shall support asynchronous operating mode, half and full duplex transmission

• The RTU shall support the industry standard DNP3 protocol, with the following minimum

features:

DNP3 Level 2 conformant with most features from Level 3 refer to the Device Profile for additional information

Local and remote configuration via DNP3 and file transfer Peer-Peer communications Routing - serial-serial communications Issue controller commands remotely (file, application, event management,

diagnostic capture, etc.) Reporting to up to 3 independent DNP3 Masters

• The RTU shall support the industry standard Modbus protocol, with the following

minimum features:

Allows up to 65,535 stations in one system.

Ability to transfer complete programs and data over the communication network.

Support high data security techniques such as Cyclic Redundancy Check CRC16

PwC 47

Proprietary protocols will not be allowed.

5.1.5.1.4. Power Distribution Modules

The power distribution modules will provide the power for the sensors and actuators connected to

the Input and Output modules. The power connections to the modules will be through the internal

connections on the I/O drops communication bus to reduce the amount of external wiring.

The power distribution module should include versions that are capable of directly connecting to

120/ 230 volts ac line power in the frequency range from 47 to 63 Hz, or 24 vice power, to provide

the voltage to the sensors and actuators connected to the I/O modules.

The power distribution module shall have separate power connectors to provide dedicated power to

the input sensors and the output modules actuators. This will allow the user to disconnect the power

to the output devices during servicing while maintaining power to the inputs.

5.1.5.1.5. LOCAL HMI for PLC/ RTU

The purpose of Local HMI is to indicate current status of the level, pressure, flow, energy data and water

quality etc.at the field stations.

The HMI shall also act as an aid to facilitate Pop up alarms, enter time delays, and operate the necessary

equipment. The HMI shall have 1 printer port and 1 USB port as a minimum. The HMI shall be Touch screen

with minimum diagonal screen size of 6”

5.1.5.1.6. Programming Software:

The programming software shall allow downloading of Relay Ladder Logic and/or standard C++ programs

from within one package. The software shall allow the user to develop and download the application and

system configuration over communication network via radios, Ethernet, leased and dial-up lines. The PLC

/ RTU shall allow Ladder and/or C++ applications to run concurrently. Any failure in the Ladder application

shall not affect other applications.

The Relay Ladder Logic shall include the following functions:

• Data logging function with time & data

• Modem dialing and control.

• Timers, counters, mathematical functions, memory functions.

• Standard Ladder Logic functions such as coils and contacts.

• Boolean logic functions.

• Bit transfer functions.

• Block transfer functions.

• Scaling function

• Totalizing function

• Flow function

On-line monitoring of Relay Ladder Logic power flow shall be included to facilitate start-up and debugging

of programs.

Relay Ladder Logic program shall be up to 12K words in size, with no fixed limit on the number of networks.

The programming software shall support on-line monitoring and forcing of any register in the protocol

database when utilizing the built-in protocol. Forcing shall write a value to the register and prevent

modification of the register content by the communication protocol or the application software. A global

command to remove all forcing must be included.

In addition to forcing, the software shall be capable of writing a value to any register in the protocol database

but continue to allow the protocol or application software to modify the contents of the register

PwC 48

5.1.5.1.7. Data Logging Functionality

The Controller shall support Data Logging via Removable USB Mass Storage devices which include:

• USB Flash Memory Stick

• USB External Hard Drive

• Log to USB Mass Storage

• USB mass storage device remains connected to controller

• Multiple data logs may be configured to write data to USB storage (Data is buffered to non-

volatile RAM and written once per minute.)

• At some point in time when the USB storage device is removed, the data continues to be

logged, but is stored to internal non-volatile memory.

• When a USB storage device is re-inserted the buffered data is copied to the USB storage

device

The unit must also support IEC 61131-3 programming using Sequential Function Chart (SFC), Functional

Block Diagram (FBD), Ladder Diagram (LD), Structured Text (ST), Instruction List (IL), Flow Chart (FC)

languages using a separate programming tools

5.1.5.1.8. Managed Ethernet Switches

General

Managed Ethernet Switches are considered as key components to ensure system performance and

must be furnished by the same vendor who is supplying the other system hardware and software to

insure compatibility and interoperability.

The Managed Ethernet Switches must be designed to operate in industrial environments with

specifications and MTBF figures that are consistent with the rest of the system.

Switch Features

The system must support a range of Managed Ethernet Switches that includes models that have 4

Ethernet ports up to models that include 24 Ethernet ports.

The basic models of the Switches will support for communications over copper cable distance up to

100 meters. The range must include models that have Fiber Optic communication ports supporting

Multimode fiber optic cable lengths up to 5000m for multi mode or single mode fiber optic cables

lengths up to 30,000m, for long distances and for use in high electrical noise environments.

All models must have loadable firmware that is stored in non-volatile memory. This will allow for

firmware upgrades in the field to take advantage of any new features or capabilities.

The Switches must use an RJ 45 connector for the ports supporting copper wire cables and uses

duplex SC connectors for ports supporting Fiber Optic cable.

The ports of the Switches must support 10/100 Mbps communication rate with an option for ports

that will support 1000 Mbps communications. All ports will include auto negotiation capability for

the communication rate and for half/full duplex modes of operation. Auto crossing (MDI/MDI-X)

must be supported when auto negotiation is active, and there must be a configuration option to

manually set cable crossing (MDI/MDI-X), and communication rate.

The Switches must include as a minimum, front mounted LED Indicators for correct supply voltage

level, communications status, faults, and standby status.

For Ethernet/IP applications, the Switches must have the ability to function as an Ethernet/IP

adapter. This will use the Common Industrial protocol (CIP) for implicit real-time I/O messaging

and explicit messaging to obtain switch information and make limited configuration changes that

are not time critical. The Switches must have the ODVA Declaration of Conformity.

PwC 49

The Managed Switches must support Fast Device Replacement as a method of handling the

configuration of a replacement switch and minimizing downtime in the event of a failure. The

switch configuration can be downloaded from a server to the switch.

Flow control capability in accordance to the IEEE 802.3 standard must be included as a standard

feature of the Switches providing message overload protection during periods of high traffic.

Message priority capability must be included as a selectable feature of the Switches. They must

support 4 priority levels to insure that high priority message traffic is not disrupted by other traffic

during busy periods. The switch will send all data packets with a higher priority level before sending

data packets with the next lower priority level.

Port based VLAN (Virtual Local Area Network) capability in accordance with IEEE 802.1Q must be

available for the Switches to offer the option for the user to create a logical subgroup of devices

within a larger network.

Traffic Limiter capability on a per port basis must be available as a selectable feature to improve

data exchange reliability during periods of high rates of traffic. Traffic limiting must include the

ability to configure a rate limit for all types of data packets transmitted or received.

The Managed Switches must support GMRP (GARP Multicast Registration protocol) and

IGMP/IGMP Snooping for multicast filtering.

To provide synchronization of the system time on the network, NTP (Network Time Protocol) must

be supported, including both the server and client functions.

The Managed Switches must offer RSTP support in at least 2 of the ports to allow the creation of

fast-healing rings.

The Managed Switches must support full LLDP (i.e. transmit, receive and MIB)

Diagnostics

The Managed Ethernet Switches must include diagnostic capability that will enable the user to

monitor the operation of the switch locally as well as from a remote location.

The diagnostic capabilities of the switch should include:

i. Product information, such as model number and manufacturer, Hardware and Firmware

versions, and device capabilities.

ii. Port mirroring that copies all communication traffic passing through one port (source) to

another port (destination).

iii. SNMP Trap that is user configurable, for selected device parameter statuses

iv. Connected device status log

v. Port diagnostics and statistics

vi. Event Logs with up to 2000 events with time stamping

vii. External alarm contact de-energized on fault that can be an input to the controls system.

The Switches must include standard remote monitoring capability that enables network

information to be gathered at a single workstation. The type of information gathered includes

packets sent, bytes sent, packets dropped, statistics by host, by conversations between two sets of

addresses, and selected events.

Switch Configuration

The manufacture must have available all of the product documentation covering the installation,

configuration, redundancy capability, and Web Management interface for remote monitoring.

PwC 50

The configuration of the switch can be performed with either a local direct connection to the

switch or through a network connection. The local connection enables the switch to be

configuration before installation and the network connection will enable configuration of Switches

already installed.

The switch configuration data can be stored remotely on a server connected to the network or

locally backed up to a USB memory backup adapter that would directly plug into the Managed

Ethernet Switch. In the event of a switch failure the configuration can be downloaded from either

storage device to the replacement switch to reduce downtime.

The configuration software will have the ability to detect all of the Switches connected on the

network and display their IP Parameters information.

To protect against access by unauthorized personnel to the switch configuration data, the software

must offer the capability for a user selected password set in the Log In screen of the configuration

software.

Security

To protect against unauthorized access the Managed Ethernet Switch must include security

capability that includes the following:

Port security that is based on the IP address or MAC address that protects every port on the switch

from unauthorized access, by only allowing assigned users access to the port. The settings for port

security are made via a Web based software tool for ease of use that can be accessed from the

engineering station.

SNMP V3 security capability for the Web based user interface that provides encryption for the

access password with a complex calculation for keystrokes, making it difficult to use brute force to

gain access.

Standards and Approvals

The Managed Ethernet Switches should include the following agency approvals:

UL – 508 and 1604

CSA – 22.2 No. 142

CE Mark per EN61131-2

FM Class 1, Div 2

UL1604 Class 1 Div2

C-Tick for Australia

Substation IEC 61850 EMC levels tested

Maritime approval (GL)

5.1.5.1.9. Network Firewalls

General

An Industrial Ethernet Firewalls provides a wide range of security tools for creating secure

zones within an industrial automation environment. Firewalls operate on the basis of rules

established by the process owners, specifying the network actions that will be allowed or

blocked by the device.

Industrial Firewalls are an essential device and the first line of defense in cyber security.

Industrial Firewall Features

Firewalls will provide Ethernet connectivity through on copper cables and fiber

The firewalls will be able to operate in Layer 2 mode, as a switch; in Layer 3 mode, as a router; or

in PPPoE (Point to Point Protocol over Ethernet).

The firewalls will be equipped with Access controls, including:

PwC 51

SNMP v1/v2/v3 password

SSH (Secure shell protocol) access

External authentication

Packet Filter for creating Firewall rules that includes:

Incoming IP packets from device connected to external port

Outgoing IP packets from device connected to internal port

Incoming MAC packets

Outgoing MAC packets

Incoming PPP packets received at serial port

NAT (Network Address Translation) that includes:

P Masquerading

1:1 NAT (network address translation)

Port Forwarding

Network security capabilities that include:

IP Masquerading

1:1 NAT (Network address translation

Port forwarding

DoS (Denial of Service)

Multiple user firewall entries (maximum 32)

VPN (Virtual Private Network) connection capability with up to 256 active VPN connections on

the external port with names assigned.

Firewall Learning Mode (FLM) that analyzes communication traffic and creates firewall rules

Redundancy capability that allows the Firewall and its communication connections to operate in a

redundant configuration for higher availability. Two modes are required:

Network Transparent mode, where one Firewall is connected each into the paths of two

redundantly coupled networks.

Router mode, where a Firewall is used to install a redundant line and a redundant Firewall

for an existing connection between two networks, the Firewall must be configured in the

Router Mode.

Time Protocols available to synchronize the time in the network using SNTP or NTP.

The Firewall Diagnostic capabilities include:

Ports – Utilization, Statistics, and ARPS

Topology Discovery

Device Status

Alarms (traps)

Reports – System Information

Firewall list – MAC and IP address

PwC 52

5.1.5.2. RTU/ Data Logger for Intake & UGR’s

HMI: Graphics Touch Screen Panel

Modems :

Ethernet or serial radios, GSM/GPRS modem,

Third party modems used (PSTN, 3G modems, DSL modem/routers , ,..)

System Security:

RTU should support DNP3 Level 4 subset features, providing both

DNP3 secure authentication

AGA12 encryption of DNP3 protocol

These authentication and encryption services can be used concurrently in the same system

Other Components :

PS, Battery : DC power supply + backup battery ctrl module + battery

Energy : Connection to Utility meter

Motor control : DOL , starter , Soft Starter , Variable frequency drives

Security :. Door switch, key contact

Lightning prot. : PRC / PRI surge protector for telecom/signal

PwC 53

PwC 54

6. Estimated Cost

6.1. Summary

I. Underground Reservoir Cost - 39 locations

S.No Expenditure item Units Unit Price (INR)

CAPEX (INR) AMC No. of year

Total AMC (INR)

Total Cost (INR)

1 Remote Terminal Unit along with enclosure, SMPS+ Relays+ Terminal Box

39 453000 17667000 5% 6 5300100 22967100

2 Local LCD displays (7" Colour) 39 50000 1950000 5% 6 585000 2535000

3 GPRS Modem 39 40000 1560000 5% 6 468000 2028000

4 Online Non-Redundant UPS - 1 KVA with SMF battery

39 150000 5850000 5% 6 1755000 7605000

Total 27027000 35135100

II. WTP Location – considered 1 No WTP

1 PLC (Working and Redundant) with REMOTE I/O PANEL with I/O module, power supply module communication module, etc

1 2000000 2000000 5% 6 600000 2600000

2 Ethernet Switch for connection between PLC and HMI

1 300000 300000 5% 6 90000 390000

3 Online Non-Redundant UPS -5 KVA with SMF battery for WTP Plant

1 1300000 1300000 5% 6 390000 1690000

4 Communication Cable (WTP) 1 500000 500000 5% 6 150000 650000

Total 4100000 5330000

III. Intake Plant Cost - Considered 7 (6 Intake Plants + 1 Clearing Pump House)

PwC 55

1 PLC (Non-Redundant) REMOTE I/O PANEL with I/O module, power supply module communication module, etc complete

7 4120000 28840000 5% 6 8652000 37492000

2 Ethernet Switch and Cable for communication 1 300000 300000 5% 6 90000 390000

3 Online Non-Redundant UPS -3 KVA with SMF battery for In take plants

7 500000 3500000 5% 6 1050000 4550000

4 SCADA & Engineering PC for plant operation 7 500000 3500000 5% 6 1050000 4550000

5 Modem – GPRS/ GSM 7 40000 280000 5% 6 84000 364000

Total 36420000 47346000

IV. Master Control Centre – 1 No

1 SCADA Server with SCADA Software suitable for project requirement ( 1 Main Server + 1 Standby)

1 4000000 4000000 5% 6 1200000 5200000

2 Database Server and PC 1 2000000 2000000 5% 6 600000 2600000

3 Large LED Display – 50” 1 350000 350000 5% 6 105000 455000

4 Operating Station & Engineering station (Workstation)

4 900000 3600000 5% 6 1080000 4680000

5 SCADA Application Software 1 7000000 7000000 5% 6 2100000 9100000

6 Modem – GPRS/ GSM With M2M Gateway

1 550000 550000 5% 6 165000 715000

Total 17500000 22750000

Grand Total (I+II+III+IV)

11,05,61,100

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 56

7. Service Level Agreement

7.1. Purpose of this Agreement

The purpose of this SLA is to clearly define the levels of service to be provided by System Integrator to the

Purchaser for the duration of this contract or until this SLA has been amended. The benefits of this SLA are

to:

a. Trigger a process that applies Purchaser and Supplier management attention to some aspect of

performance only when that aspect drops below an agreed upon threshold, or target.

b. Makes explicit the performance related expectations on performance required by the Purchaser

c. Assist the Purchaser to control levels and performance of services provided by Supplier

d. This SLA is between Supplier and Purchaser

Availability quarter

Deduction as % of the apportioned price of total FMS for SCADA portion of the contract applicable for that site

> 99% NIL

Less than 99% Deduction of 2% of the apportioned price of the apportioned quarterly AMC for every 1% or part there of decrease in availability under 99%.

>98% NIL

Less than 98% Deduction of 2% of the apportioned price of the apportioned quarterly AMC for every 1% or part there of decrease in availability under 98%.

While calculating Availability following shall be considered: The Overall SCADA/DMS System shall be

considered as available if

a. All SCADA applications are available b. All SCADA functions described in the specification are executed at periodicities specified in the

specification. without degradation in the response times c. Information Storage and Retrieval applications are available d. Data exchange with other system is available e. One of the redundant hardware is available so that all the SCADA applications are functional to ensure

the design and performance as envisaged in the DPR Further, Non-Availability of RTU/Data Concentrators shall not be considered for calculating Overall SCADA

Availability.

However each device, including RTU and Servers etc. shall individually exhibit a minimum availability of

98%. Further, the non-availability of following Non-Critical functions shall not be considered for calculations

of SCADA System availability; however these functions should be available for 98% of the time.

a. Database modification and generation b. Display modification and generation c. Report modification and creation

The computation of Availability / Non-availability would be rounded up to 2 decimal places at each Contract Co-

ordination Site on quarterly basis and any deduction in the maintenance charges thereof would be calculated

as stated above on pro-rata basis.

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 57

Availability would be on per quarter basis

The formula to be used for availability computation would be as under:

Availability per quarter (per site) = THQ- (S1 x 1+S2 x0.4+S3 x 0.1) x 100%

Where:

THQ is total hours in the quarter

S1 is the total non-available hours in Severity Level-1

S2 is the total non-available hours in Severity Level-2

S3 is the total non-available hours in Severity Level -3

7.2. Problem Severity Levels

Category Definition

Severity 1 – Urgent Complete system failure, severe system instability, loss or failure of any major subsystem or system component such as to cause a significant adverse impact to system availability, performance, or operational capability

Severity 2 – Serious Degradation of services or critical functions such as to negatively impact system operation. Failure of any redundant system component such that the normal redundancy is lost Non-availability of Manpower at control center during working hours

Severity 3 – Minor Any other system defect, failure, or unexpected operation

Severity 4 – General/Technical Help

Request for information, technical configuration assistance, “how to” guidance, and enhancement requests.

Severity-1 (Urgent support)-The entire WMS system is down, In this case the maximum time to

acknowledge the issue is 30.00 Min (between 6:00 Hrs. to 22:00 Hrs.) and maximum time to respond is 1:00

hrs. (Between 6:00 a.m. to 10 p.m.). In case the problem is reported during lean period (22:01 Hrs. to 5:59

Hrs.) downtime will be calculated from the next day. This unplanned downtime will not be considered as a

part of the SLA down time.

Severity-2(Serious)- Services to more than 50% and up to 75% of the WMS system are affected. In this case

the maximum time to acknowledge the issue is 30:00 Min (between 6:00 hrs. to 22:00 hrs.) and maximum time

to respond is 2 hrs. (between 6:00 Hrs. to 22:00 hrs.). In case the problem is reported during lean period (22:01

Hrs. to 5:59 hrs.) downtime will be calculated from the next day. This unplanned downtime will not be considered

as a part of the SLA down time.

Severity-3 (Standard support)-Services to more than 25% and up to 50% of the WMS system are affected.

In this case the maximum time to acknowledge the issue is 30:00 Min (between 6:00 hrs. to 22:00 hrs.) and

minimum time to respond is 3:00 hrs. (between 6:00 hrs. to 22:00 hrs.). In case the problem is reported during

lean period (22:01 hrs. to 5:59 hrs.) downtime will be calculated from the next day. This unplanned downtime

will not be considered as a part of the SLA down time.

Severity-4 (General Technical Help) - Services to up to than 25% of the WMS system are affected. In this

case the maximum time to acknowledge the 30:00 Min (between 6:00 Hrs. to 22:00 Hrs.) and maximum time to

respond is 4:00 hrs. (between 6:00 Hrs. to 22:00 Hrs.). In case the problem is reported during lean period (22:01

Hrs. to 5:59 Hrs.) downtime will be calculated from the next day. This unplanned downtime will not be considered

a part of the SLA down time.

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 58

7.3. Breach of SLA

In case the Supplier does not meet the service levels for three (3) continuous time-periods as specified in the

relevant clause, the Purchaser will treat it as a case of breach of Service Level Agreement. The following

steps will be taken in such a case:-

Purchaser issues a show cause notice to the Supplier.

Supplier should reply to the notice within three working days.

Exclusions

The Supplier will be exempted from any delays or slippages on SLA parameters arising out of following reasons:-

a. Delay in execution due to delay (in approval, review etc.) from Purchase’s side. Any such delays will

be notified in written to the IT Team.

b. The network links will be provided by a third party and the Supplier will monitor and report any

problems on behalf of third party. If Supplier notifies and Purchaser approves that the delay or fault

was due to the third party link services then such loss will not be considered for tracking Supplier’s

SLA parameters (Also reduced from total service time).

7.3.1. Monitoring and Auditing

Purchaser will review the performance of Supplier against the SLA parameters each month, or at any

periodicity defined in the contract document. The review / audit report will form basis of any action relating

to imposing penalty or breach of contract. Any such review / audit can be scheduled or unscheduled. The results

will be shared with the Supplier as soon as possible. Purchaser reserves the right to appoint a third-party auditor

to validate the SLA.

7.3.2. Reporting Procedures

The Supplier’s representative will prepare and distribute SLA performance reports in an agreed upon format

by the 10th working day of subsequent month of the reporting period. The reports will include “actual versus

target” SLA performance, a variance analysis and discussion of appropriate issues or significant events.

Performance reports will be distributed to the Purchaser’s IT Team.

7.3.3. Issue Management Procedure

7.3.3.1. General

This process provides an appropriate management structure for the orderly consideration and resolution of

business and operational issues in the event that quick consensus is not reached between Purchaser and

Supplier. It is expected that this pre-defined process will only be used on an exception basis if issues are not

resolved at lower management levels.

7.3.3.2. Issue Management Process

Either Purchaser or Supplier may raise an issue by documenting the business or technical problem,

which presents a reasonably objective summary of both points of view and identifies specific points of

disagreement with possible solutions

Purchaser and the Supplier’s representative will determine which committee or executive level should

logically be involved in resolution

A meeting or conference call will be conducted to resolve the issue in a timely manner. The documented

issues will be distributed to the participants at least 24 hours prior to the discussion if the issue is not an

emergency requiring immediate attention

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 59

Management of Purchaser and Supplier will develop a temporary, if needed, and the permanent solution

for the problem at hand. The Supplier will then communicate the resolution to all interested parties.

In the event a significant business issue is still unresolved, the arbitration procedures described in the

Contract will be used

7.3.4. Change Management:

These metrics are necessary for tracking and reviewing all change activities related to the WMS environment from time to time, ensuring quality of the system is maintained

7.3.5. Service Continuity

These metrics are necessary to ensure that critical CMS components and services can be recovered within

required and agreed time lines as per the Service Continuity plan

Time taken for reestablishment replacement of services and/or components in case of failure . In case of a failure, the services will be re-established / components replaced as per Service Continuity Management Plan developed by the Implementing Agency The IA is responsible for developing and implementing a Service Continuity (Business Continuity Plan) Management plan to ensure that critical WMS components and services can be recovered within required and agreed time scales. It will provide appropriate contingency management plans containing appropriate resilience strategies, recovery and crisis management, based on minimum service requirements, following an interruption to the WMSservice delivery. The Service Continuity (Business Continuity Plan) Management will be approved by Shimla.

7.3.6. Security Management

Security compromises and exploited vulnerabilities or threats and resolutions, in relation to the WMS solution

infrastructure.

Security compromises and exploited vulnerabilities or threats and resolutions, in relation to the WMS solution

infrastructure. The implementer will design and implement appropriate ISMS (Information Security

Management System) for the CMS in accordance with the code of practice for information security management

provided in ISO 27001. The ISMS shall be approved by the CMS Acceptance agency before “Go-live”. As part of

implementing the ISMS, the IA will provide an analysis of the risks and vulnerabilities to which the CMS will be

subjected to and the counter measures proposed. Security related exploits & resolution etc. will be measured on

a weekly basis and reported monthly.

Every breach of security, and every attempt to breach security or exploit a vulnerability or risk, will be reported in the Service Management process.

7.3.7. SLA Change Control

General

It is acknowledged that this SLA may change as Purchaser’s business needs evolve over the course of

the contract period. As such, this document also defines the following management procedures:

A process for negotiating changes to the SLA

An issue management process for documenting and resolving particularly difficult issues

Purchaser and Supplier management escalation process to be used in the event that an issue is not

being resolved in a timely manner

Any changes to the levels of service provided during the term of this agreement will be requested,

documented and negotiated in good faith by both parties. Either party can request a change. Changes

will be documented as an addendum to this document and consequently the contract.

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 60

7.3.7.1. SLA Change Process

Both the parties may amend this SLA by mutual agreement in accordance. Changes can be proposed by either

party. Normally the forum for negotiating SLA changes will be Purchaser’s monthly review meetings.

7.3.7.2. Version Control

All negotiated SLA changes will require changing the version control number. As appropriate, minor changes

may be accumulated for periodic release (e.g. every quarter) or for release when a critical threshold of change

has occurred

Management Escalation Procedures

The purpose of this escalation process is to provide a quick and orderly method of notifying both parties that

an issue is not being successfully resolved at the lowest possible management level. Implementing this

procedure ensures that purchaser and Supplier management are communicating at the appropriate levels.

Escalation should take place on an exception basis and only if successful issue resolution cannot be achieved in

a reasonable time frame.

All issues would be raised to the project management team, which is completely responsible for the day to day aspects of the implementation. The project management team shall classify the issues based on their severity level and resolve them within appropriate timelines.

If project management team is unable to resolve an issue, the issue would be escalated to the top management with options/ risks detailed for decision. Top management will make decisions based on the options/ risks presented by the IT team.

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 61

8. Capacity Building and Change Management

The objective of Change Management in this context is to ensure that standardized methods and procedures are

used for efficient and prompt handling of all changes to control Smart Street Lights and its respective IT

infrastructure, in order to minimize the number and impact of any related incidents upon service. Changes in

the infrastructure may arise reactively in response to problems or externally imposed requirements, e.g.

legislative changes, or proactively from seeking improved efficiency and effectiveness or to enable or reflect

business initiatives, or from programs, projects or service improvement initiatives. Change Management can

ensure standardized methods, processes and procedures which are used for all changes, facilitate efficient and

prompt handling of all changes, and maintain the proper balance between the need for change and the potential

detrimental impact of changes.

Change management is responsible for managing change process involving:

• Hardware

• Communications equipment and software

• System software

• All documentation and procedures associated with the running, support and maintenance of live systems.

Based on the project implementation strategy, and proposed modules to be implemented, this section

provides details about the Change Management and Capacity Building based on the existing capacity of

ULB.

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 62

8.1. Need for Change Management

Deciding to choose the method of organizational change management for the change process within business

comes with many benefits. Organizational change management uses the type of structure that prevents

resistance, and, therefore, prevents failure of the project itself. All too often business implement change without

any type of plan or communication to the parties affected by the change. This, in turn, is the major cause of a

project lacking in the significant factors needed for success.

What Causes the Project to fail?

Several things have to be in place for organizational change management to work. Many projects fail when

certain things do not line up. Some of the major reasons for failure include lack of communication, inexperience

and complexity, technical issues, management problems, and lack of definitive objectives. When change is not

communicated to all parties affected by the change, resistance becomes a huge problem. When you have

employees who are not willing participants, the main thing to suffer is the business itself. Organizational change

management can create a structured model to outline the change process for a successful outcome.

The complexity of the project is another major cause for failure of a project. You can have everyone on board

and willing to participate, but there has to be an understanding involved for the change to take place.

Organizational change management can offer the understanding to be effective. The end result will be an

effective project for everyone to move forward with. Many resources are available regarding organizational

change management that can help simplify the more complex projects.

Project Sponsorship

Project sponsorship usually is defined as the person who actually saw a need for change, and then took the

action needed to implement the change process. With organizational change management, many people can

hold the project sponsorship role collectively. A sponsorship map can be created to show who holds what role,

and what is involved to participate.

When major change is at hand, many parts of the organization will be involved in the process. Specific

departments in the workplace are going to be responsible for tasks that pertain to them individually. For

example, the IT department will not be responsible for changes being made in the finance department, and vice

versa. Sometimes, with organizational change management, a cascade of project sponsorship is involved. This

basically means that leadership will send messages to the departments involved.

The Right Change Style

The right change style is needed to implement the organizational change management process. Different types

of change include collaborative, consultative, directive, and coercive change. With collaborative change, the

target population is involved in the change process. Consultative change targets the population whose views are

sought regarding the change. Directive change is informing the workplace about the changes and why they are

needed. Last, but not least, coercive change is basically telling the workplace that change is taking place, and the

new rules must be obeyed.

Organizational change management may provide various types of change styles, but defines a specific outline

that is easy to follow for the future success of the company or entity involved.

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 63

8.1.1. Identification of Stakeholders

Before starting of project stakeholders are identified. Key stakeholders for Smart Water Management project

are;

• Shimla Municipal Corporation

• World Bank

• Project Management Consultant

• The Implementation Agency

• Citizens

• Business Users

8.1.2. Description of Roles and Responsibilities

The roles and responsibilities of the stakeholders involved are mentioned below;

• Shimla Municipal Corporation: The SMC will be the owner of project and will be responsible for

successful implementation of the project. SMC will provide right of way to the implementation agency

for a smooth implementation and issue the necessary Governmental notification/ by-law

• World Bank: The World Bank will be the funding agency and will supervise the project implementation.

• Project Management Consultant: SMC will appoint Project Monitoring Consultant, who will

provide end to end Consultancy assistance to them- right from assistance in selection of Implementation

Agency (IA), to monitoring the services of the IA till the end of contract period. The PMC will undertake

the field works, comprehend the requirements, document the observations, prepare roadmap, redesign

the processes, and help build capacity for the staff and executive resources of the department.

The PMC so appointed/engaged for may be required to design new business strategy and process flows

for various selected services. They will carry out the field study in order to understand the project

requirements, existing mechanism, the present challenges, document the understanding and redesign

an efficient and effective delivery structure, understand the capacity building requirements and help in

creating a facility for development of capacity.

• The Implementation Agency: The Implementation Agency will be responsible for design, develop

and implement the entire project.

• Citizens: Citizen will avail the services that will become live after the project execution

• Business Users: Business users will get associated with SMC for the business purpose and will actively

take part in the tendering process.

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 64

8.1.3. Participation by Stakeholders

Participation of stakeholders is mentioned in the table below;

# Stakeholder Group/ Name

Roles and Responsibilities

Level of Influence

Communication Strategy

1 Shimla Municipal Corporation

Define Policies

Approval of works/projects

Monitoring of its departmental functions

Strategic decision making

High Communicate the policy changes, to enable the working group to define and frame work plan.

Awareness creation and sensitization through training programme

2 The World Bank Monitor the overall progress of the project

High Awareness creation for the project being implemented

3 Project Management Consultant/Implementation Agency

Perform duties as per the RFP

Monitoring of progress of the project and submitting its report to MCS

High Written/Verbal communication with other stakeholders on the project execution

4 Citizen Should keep themselves informed about governmental policies

Participate in defining policies & projects

Medium Seek information from SMC for the project being implemented

8.2. Staffing and Deployment Strategy

The staffing and deployment strategy is mentioned here under;

8.2.1. Staffing and Deployment Plan

The resources at data Command & Control centre will be deployed as per below.

I. Water Management Engineer

Responsible for overall water scada management. 5-10 years minimum experience in ICT enabled

Water Scada System with Btech-BE (Civils).

Strong background in designing of the overall water distribution system

II. Centre Manager

Responsible for overall command and control centre management, user SLA commitments,

performance, availability, response time, and problem resolution etc. 5-10 years minimum

experience in facility and/or data center operations/planning/project management with

MCA/Btech-BE (Computers).

Strong background in facilities design with a focus on command & control centre/data centers

Significant project management experience required

Project management certification (PMP) a plus

III. System Administrator

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 65

Responsible for database configuration, scalability, performance, load balancing, OS

administration/management, troubleshooting & Debugging and monitoring of server(s). The

Systems Administrator will provide in-depth technical support and effective problem solving for all

employees.

The desired profile should be minimum B.E (CSC/ECE/EEE)/MCA preferably MBA with 3-4 years’

experience in system administration of RDBM data (Oracle/ MSSQL). Sys admin, win2k, UNIX,

Solaris, etc., server programmer of Java, C, C++, SQL, PLSQL, CORBA etc. Technical certification on

the above is desired. Required for only one shift.

IV. Network Administrators

Responsible for network uptime, security, User and Group Administration, including password

management. Assisting with building and supporting servers. Administering server-side antivirus

protection

The personnel should be well versed with routing and switching devices and technology like AM,

MPLS, wireless, broadband and protocol analysis tool.

3 – 5 years’ experience with server administration.

Working knowledge of server hardware.

V. Maintenance staff (Electrician, Cabling, House Keeping etc.,) – As Required (A/R)

Operate, monitor, maintain, and respond to abnormal conditions in facilities systems. Areas include:

Electrical, Mechanical and Building Monitoring and Control.

Tracking and trending operational characteristics

VI. Technical Support Services (System and Network Engineers)

Responsible for L2 support, H/W & S/W support and would provide help to the control centre

operations and management.

Core team in quick resolution of problems in the technical support team would work on shift basis

and ensure uptime of services.

The desired personnel should be min diploma with 2-3 years exp in technical support services,

operations, IT infrastructure managing and updating customer database with pleasing personality

and good communication skills. Technical certification like CCNA etc. is preferred. Required for 3

shifts.

VII. Facility Management Services

Facility Management Services is required for all the offices.

8.2.2. Staffing and Deployment Process

SMC can opt either of the following below mentioned process to hire the resources:

• Creating vacancies within the department and hire them as government officials

• Or hiring the resources for specific period of time on contract basis.

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 66

• Outsourcing the process to the third part recruitment agency. The selection of agency can be done

through tendering process.

8.3. Training Strategy

It will be a crucial task to be handled by SMC in imparting training to all its stakeholders. The SMC should

ensure putting forward their tentative agenda in the subject of Awareness Creation that will ensure both

internal and external stakeholders are made aware of the changes envisaged due to the project.

8.4. Training Need Assessment and Content Development

Implementation agency will impart necessary training to users on ICT enabled water scada. A detailed training

schedule will be made in consultation with the SMC. This training program will include classroom sessions with

hands on sessions and on-the-job training for the ULB employees. Training on different modules would be

imparted in batches of a maximum of 25 trainees per training program.

# Target Stakeholder Mode of Awareness Frequency 1. SMC Users Department wise Training mainly on the

use, benefits and problem solution process.

Monthly for first one year and thereby refresher course quarterly for next one year.

2. Other Government Department officials

Seminars and workshops with the top and middle level officials of different state Government official from city level

Quarterly for first one year

3. Business Users Online training Once in a quarter for first year

Adequate activities should be undertaken seamlessly by the Training Service Provider (TSP) at all concerned

locations to ensure the successful implementation of the smart street light solution. The TSP can be a training

institute/implementation agency or SMC staff etc.

8.4.1. Capacity Building

TSP shall assess the change readiness of the organisation & based on it shall define change management

approach to manage various stakeholder groups on an ongoing basis.

The TSP shall define structure of the leadership as well as execution team to drive the change with clearly

assigned roles & responsibilities.

The TSP shall define measurement tools to measure the impact of change initiatives and track the

ongoing corrective & preventive action.

The TSP shall obtain a sign off on the proposed change management team structure, change management

approach & the measurement tools from the purchaser.

The TSP shall all carry out the periodic review of the training imparted.

8.4.2. Training

The TSP agency shall carry out the Training Needs Assessment.

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 67

Based on the assessment, the TSP shall prepare detailed Training and Capacity Building plan for

providing Training to the different stakeholders of SMC.

The Capacity Building & Training Plan would indicate the schedule, scope, resource requirement &

participant details of all the training sessions, training categories & user groups.

The Capacity Building Plan would also indicate tools to track the skill & knowledge of different

stakeholders. The TSP shall obtain a sign off from SMC on the proposed Capacity Building Plan.

The TSP shall carry out the different Capacity Building Trainings for the stakeholders as per the schedule

provided in the approved Capacity Building Plan.

The TSP shall submit the course materials, presentations & any other material used in the Training

programmes to SMC. Hard copy of the training material to be provided to each participant during the

Training session, while soft copy is to be mailed to the participants.

The TSP shall use various predefined forms for gathering data regarding the satisfaction of end users

with the training delivered.

Detailed report regarding each training session (for e.g. attendance levels, proficiency levels of the

participants etc.) is to be submitted to the SMC management.

Exact Reporting formats will be decided and agreed upon by the TSP after approval from SMC.

The details of proposed training to be conducted shall be indicated by the TSP in the Technical Proposal.

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 68

9. Monitoring and Evaluation

9.1. Monitoring and Evaluation Framework

Having detailed out all components of the project as provided in the previous sections, it is essential to have

details about controlling of the project at various stages of the project. Thus Monitoring and Evaluation (M&E)

will help in the process of measuring, recording, collecting, processing and communicating information and

assist in project management decisions making. Hence a well-designed, properly functioning project M&E

system would be in place to provide updated information and right time and right frequency in order to

envisage that work is progressing in right direction as per plan and with time limit and budget. The main

feature of monitoring and evaluation is measurement and verification of variables/ indicators for input,

process, output and outcomes/ impact.

A diagrammatical representation of the M&E process has been given in figure shown. M&E will play a critical

role in all the phases’ viz. of the overall project implementation.

INPUTS

Project Plan

Resources

Reporting

Processes

ASP selection

S/w Dev and Testing

OUTPUTS

Online Services

Service Delivery

Trained Staff

OUTCOMES

Improved Process

Revenue

Citizen

IMPACTS

Timelines

Efficiency

Transperancy

MONITORING

EVALUATION

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 69

9.1.1. Clearly Defined Objectives

Following table illustrates the objectives at project and program level M&E;

Stakeholder Illustrative Objectives

World Bank Program Level

Identify state coordinator for Monitoring and Evaluation of ULB

Define scope of M&E for ULB in line with the project requirement

Create M&E plan and oversee its roll out (Physical and Financial progress) ULB level

Design standard reporting templates for Monitoring for capturing data

Provide guidance to involved stakeholders as and when required

World Bank/SMC Project Level

Collect information (progress report) in specific interval

Analyse and monitor the overall growth of project

Identify and address challenges, deviations and risks

Make interventions as and when required and make policy level decisions

9.2. Define Organization’s Roles and Responsibilities

Following table illustrates roles and responsibilities;

Role Illustrative Responsibilities World Bank Oversee the overall progress in terms of physical and financial progress Shimla Municipal Corporation

Co-ordinate with PMC at for determining the overall status

Co-ordinate with implementing agencies at ULB for status update

Oversee the fund utilization

Solve issues and deviations in timely manner

Collect status reports from implementing agencies and report to financing authority

Project Management Consultant

Monitor progress at a day-today basis

Conduct reviews of team

Report timely status to ULB

Report issues and deviations in timely manner

9.3. Approach for Monitoring and Evaluation Process

9.3.1. Monitoring

During the monitoring process, the milestones for the various indicators would be monitored at regular

intervals to determine the status. If any deviations found, control mechanism would be put into place to take

corrective actions at the minimal required period to achieve the desired output. In case of any change in the

project plan the same would be communicated with the output. An approach for Monitoring process has been

presented in the figure below;

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 70

9.3.2. Evaluation

Evaluation would be carried out at Pre and Post implementation Stage of the program. Evaluation performed at

the Pre-implementation stage is Base-Line Survey and one performed Post implementation is End-Line Survey.

Evaluation would also be carried on continuous basis after Program Implementation as Ex-Post

Implementation survey for continuous improvements till achievement of desired goals.

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 71

A suggestive approach for M&E would be divided into various sub-activities as mentioned below.

• ‘WHAT’: Identifies what needs to be monitored and evaluated? Various variables/ indicators have been identified for input, process, output as a part of monitoring process and outcome/ impact as a part of evaluation process. The identified indicators would be measured/ verified (in terms of Progress, Timelines, Resources allocated, Deviations, Risks and Funds utilised) against pre-defined plan. Illustrative list of variables/ indicators for input, process, output and outcomes/ impact would be as follows in Table

Phases Variables/ Indicators Input Define plans and schedules

Define framework Process Empowered committee formed

Process mapping and Standardisation

Process of identification of stakeholders

Vendor selection process

Software application requirement gathering

Software development

Testing and integration

Implementation

Capacity building

Risk Management Output Number of personnel trained

Number of existing lights replaced, new poles implemented etc Outcome/ impact Turnaround Time

Percentage increase in revenue

Customer satisfaction level

Customer awareness

HOW: Answers the various modes to be undertaken for Monitoring and Evaluation process.

Monitoring: ULB would take various modes for carrying out the monitoring process

o Framework defined at city level (Monitoring)

o Schedule and Resource Plan defined in the planning phase

o Online Tools developed at city and ULB level

o Quarterly Progress Report formats developed at ULB Level

o Standard formats developed at ULB level

o Team meeting, project review, feedback

o Audit by third party agencies

Evaluation: ULB would use the Performance Report cards to report the progress to carry out the Baseline and End line Survey. The various modes would be

o Reports generated through the developed system

o Feedback from the Citizens

o Surveys

o Questionnaire

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 72

o Engagement of 3rd party

o Usage of self-assessment forms

WHEN: Defines the frequency of the Reporting the Monitoring and Evaluation results. ULB would

determine frequency for reporting and would be appropriately spaced, so that the data collection is not

repetitive or cannot be interpreted to obtain accurate results.

‘WHO: Identify key resources for carrying out the monitoring process. Following table illustrates the same;

Process Persons Responsible Timelines

Develop criteria for selection of Implementation Agency

ULB/Project Management Consultant

2 weeks

Float RFP and Answer to queries

ULB/Project Management Consultant

1.5 weeks

Evaluate Proposals and publish final list

ULB/Project Management Consultant

2 weeks

Meeting with Vendors and final selection

ULB 2.5 weeks

Action Daily Weekly Monthly Quarterly

Informal discussions with team

Staff meetings with managers

Project review meetings with team

Status report

Team building activity

Report to management etc.

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 73

10. Assumption and Risk Management

Risk management is important because it gives the ability to figure out methods for which events can be

managed, especially those events that may have an adverse impact on the financial or human capital of the

organization.

Risk management should always be thought of as a process which is continuous. Not only does it allow one to

assess risk, but it also gives us the ability to identify risk as well. By being able to assess and identify risk, it

becomes easier for one to prevent it from occurring, or to quickly address adverse events if and when they do

occur

10.1. Process for Risk Assessment

Vision on Smart City is backed by large budgetary and time commitments and there by expecting large benefits

in service delivery for various stake holders. However, there may be a short fall due to lack of clear

identification, understanding and management of issues/ risks/ barriers related to in various spheres at

appropriate time, which in turn leads to time and cost over-run or project failure. It therefore becomes

imperative to identify and contain the possible reasons for failure or delays in appropriate time and at

appropriate cost. This is where the need of Risk Assessment and Management comes into play and has a

significant role.

10.1.1. Risk Identification

Risks can broadly be classified into:

• Strategy Level Risk: This deals with risks resulting from a strategy level decision or change.

• Project Level Risk: This deals with risks related to the ability to understand and manage the project

complexities and project environment. Not addressing them will result in not delivering the expected

results that can bring in desired benefits.

• Operational Level Risk: These risks will arise out of day-to-day activities and management of the

project from inadequate or failed processes, people, and systems or from external events. The Project

Manager or the Team Leader appointed by ULB would manage these risks on a day-to-day basis.

Following table illustrates the types of identified risks;

Risk Factor Project Risk Title Project Risk Area

Medium

Lack of political will Stakeholder Commitment No decision making power of project implementation committee

Project Management

Lack of technical expertise at project locations Resource Risk Resistance to use Smart Solutions/IT Change Management Risk Legal changes for supporting BPR Functional Risk Parallel manual delivery of services Functional Risk Unavailability of up-to-date MIS Functional Risk ICT applications for smart street lights not implemented

Technology Risk

Low

Resistance to Business Process Engineering Functional Risk Lack of interoperability among systems Technology Risk Lack of Smart infrastructure Technology Risk Lack of ICT resources (quality, quantity, timeliness) Technology Risk Lack of training programs for the department staff Change Management Risk

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 74

Lack of planning of resources and funds Resource Risk Progress of data digitization Functional Risk

10.2. Risk Mitigation Strategy Based on Risk Evaluation Matrix

Risk Mitigation strategy along with Risk Monitoring is explained below;

10.2.1. Risk Mitigation Strategy based on Risk Evaluation Matrix

The risk mitigation communicates how specific risks will be dealt with and the action steps that are required to

carry them out. It gives team members a clear sense of the actions that they are expected to take and provides

management with an understanding of what actions are being taken on their behalf to ameliorate project risk.

The following methods can be taken for mitigating the risk

• Avoidance: Not performing an activity that could carry risk

• Reduction: Methods that reduces the severity of the losses

• Retention: Accepting the loss when it occurs

• Transfer/ Share: Transfer or share the risk with various partners involved

10.3. Risk Monitoring

Risk monitoring is the last major element of risk management - but certainly not the least important! Risk

monitoring is a process of organizing and planning - just as important as strategic, financial, marketing and

human resources planning. Like any good planning, the process should be continual or on-going.

Once the basic risk management plan is in place, monitoring risk means to review it and update it continuously.

• Identify new risks as soon as possible

• Decide where and how to handle that risk

• Look for other risks that might be reduced or eliminated and no longer need coverage

During risk monitoring meetings, existing risks as well as new risks are reviewed and discussed in details by the

Project Team. Through Risk Monitoring, the project team will Implement and direct risk mitigation actions,

Monitor the risk mitigation actions to determine their effectiveness, and revise the risk mitigation strategies as

needed, if required. The team will also assess

• Assess Mitigation Effectiveness - After implementing the Risk Mitigation Plan, the project team will

assess the effectiveness of the risk mitigation actions.

• Reassess Exposure - Evaluating the project's current risk status on a regular basis will address the

dynamic realities of the project. Project team meetings can be venues to raise and report project risk and

risk mitigation actions and results.

• New risks: The project team will also identify the potential new risks and plans to mitigate them.

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 75

11. Project Implementation Strategy and Sustainability Plan

Following are the essentials for successful project implementation:

• Adequate formulation

• Sound project organization

• Proper implementation planning

• Advance action

• Timely availability of funds

• Better contract management

• Effective control and monitoring the progress of the project

11.1. Stakeholder’s Involvement

Following table illustrates the benefit of stakeholder’s involvement in the project execution;

Stakeholders Benefit The World Bank Ease of process

Better Project Monitoring

Less paper work & no cumbersome manual processes etc

Shimla Municipal Corporation

Citizen & Business Users Benefits in terms quality & cost of services, provision for customer care, jobs, involvement, environmental issues, etc

Value perceived Project Management Consultant & Implementation Agency

Generation of revenue

Increase of credentials

11.2. Tendering and Bid Process Management

Post the approval of DPR ULB/World Bank will publish the RFP for selection of Project Management

Consultant/Implementation Agency for implementing Smart Water Management in the city of Shimla.

11.3. Project Implementation Strategy

The implementation of the application has been subdivided into two parts – pilot implementation and Roll Out

of the tested application

Pilot Phase

The details of the various activities under the piloting phase of the implementation of the Project are listed

below:

• Study: The Implementation partner will have to understand the city’s As-Is situation, with respect to

existing water management, by doing a detailed site survey of the area.

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 76

• Implementation: Design, Develop, Implement, Manage, Operations and Maintenance of identified

services to improve SMC operation and delivers benefits to citizens and provide seamless integration of

smart services and solution

• Testing: Testing is a process of technical evaluation of functionality, operability, scalability and

modularity along with quality of the product. During this period unit testing, integration testing, system

testing, regression testing, performance testing etc will be done. The wok-flow determined in

consultation with the ULB should also be tested for all the applications

• Piloting: Once the implementation and testing is done the pilot location would be ready for go-live.

Roll Out

Any bugs in the system, gaps in functionalities, system inconsistencies and other problems found during the

pilot phase will be fixed prior to a full roll-out. After the go-ahead from the ULB, the implementation will be

rolled out to all the project sites. The activities in this phase are detailed below:

• Infrastructure Supply: The infrastructure will be supplied and installed in sync with the roll-out plan

at all the identified locations

• Implementation: The entire implementation in line to the pilot will be rolled out to the other site

within the city and the connectivity will be established with the command centre.

11.4. Project Phasing Strategy

11.4.1. Exit Plan

The Implementing agency will provide a detailed exit management plan to the ULB before the commencement

of project implementation. The Exit Management Plan to be provided to the department shall deal with the

following aspects of exit management in relation to Project Implementation and the operation & maintenance;

• A detailed program of the transfer process that could be used in conjunction with replacement

implementer including details of the means to be used to ensure continuing provision of the services

throughout the transfer process or until the cessation of the services and of the management structure to

be used during the transfer

• Plans for the communication with such of the implementers sub-contractors, staff, suppliers, customers

and any third party as are necessary to avoid any material detrimental impact on operations as result of

undertaking transfer

• Plans for provision of contingent support to department and replacement implementer for a reasonable

period after transfer

• During the exit management period , the implementer shall use its best efforts to deliver the services

11.5. Sustainability Plan

Procedural, staffing, budgetary and contractual arrangements that will ensure sustainability of project and its

outcomes during and beyond the mission period are mentioned below:

• Procedural Sustainability: The procedures that ensures the smooth functioning of project are:

o Strong decision making power of management authorities like SMC, World Bank etc

o Adequate amount of budgets

o Adequate technical expertise

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 77

o Capacity building at the end of the project

• Resource Sustainability: Adequate amount of human resource will be deployed with diversified

experience.

o The SMC is the Appointing Authority of the staff to be engaged for the project

o The authority have the power to sanction, add, create, abolish such posts as in their opinion are

necessary to manage the project

o No person shall be appointed to any post unless he/she is eligible for the same as per the

qualification prescribed by the ULB

o All the appointment made in the are either on contract basis or full time

• Financial Sustainability: The revenue will be generated by the project during implementation phase

• Contractual Sustainability: Contract agreement will be signed between SMC and other private firms

during the project execution.

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 78

12. Project Implementation Schedule

T=Data of Signing of Contract

Si.No. Project Activity Deliverables Responsibility Timelines

1 Supply of Hardware / Software/equipment etc from the date of signing the Contract

• Delivery Challan

• Invoice Copy

• Inspection report from authentic third party

• Warranty certificate issued by respective OEMs for each hardware / software (back to back, in the name of Authority also)

• License in case of software

MAF

Implementation Agency

T+20 weeks

2 Installation, Configuration Integration of Hardware/ Software/ systems

• Device wise Configuration report stating IP Schema

• Routing details

• In case of Software, the report should consist of

• Software Installation Guide and checklist.

• Complete set of Technical/ Operation and Maintenance Manual.

• Report formats for approval of Authority UAT/testing report

• Helpdesk and SLA compliance report

• Configuration change report

• Inventory Reports

Implementation Agency

T+30 weeks

3 UAT and Commissioning of entire system as per scope of work

• UAT Report and Successful Commissioning

• Certificate/ Rectification activities

Implementation Agency

T+32

4 Rectifications based on UAT

• Test reports and configurations

Implementation Agency

T+34

5 Go-Live • All project locations working successfully

Implementation Agency

T+35

6 Operations Phase Satisfactory Working Inspection

• Inspection to be done by Authority followed by submission and approval of Satisfactory Working Inspection Report

SMC T+36

7 Operation & Maintenance All project locations in working condition (after satisfactory inspection)

• Quarterly SLA compliance reports

• Quarterly Preventive Maintenance reports

• Quarterly Configuration change reports

• Quarterly location wise Inventory reports

• Other reports as desired

Implementation Agency

Quarterly after Go-live period

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 79

• Quarterly user report- Location wise

• Quarterly bandwidth utilization report- Location wise

• Quarterly report indicating daily uptime-Location wise

• Quarterly user feedback reports- Location wise

• Quarterly report user complaint- Location wise showing complaint, complaint time & date, solution given, complaint clear time & date

The aforementioned schedule is only indicative.

Detailed Project Report for ICT Enabled Water SCADA for Shimla

PwC 80

Thankyou