SUPPLEMENTARY TO FOCUSED PRESENTATION TO THE SELECT COMMITTEE ON APPROPRIATIONS SUPPORT PROVIDED TO...
-
Upload
zoe-potter -
Category
Documents
-
view
219 -
download
0
Transcript of SUPPLEMENTARY TO FOCUSED PRESENTATION TO THE SELECT COMMITTEE ON APPROPRIATIONS SUPPORT PROVIDED TO...
SUPPLEMENTARY TO FOCUSEDSUPPLEMENTARY TO FOCUSEDPRESENTATION TO THE PRESENTATION TO THE SELECT COMMITTEE ON SELECT COMMITTEE ON
APPROPRIATIONSAPPROPRIATIONS
SUPPORT PROVIDED TO MUNICIPALITIES AND SUPPORT PROVIDED TO MUNICIPALITIES AND MUNICIPALITIES PLACED UNDER ADMINISTRATION MUNICIPALITIES PLACED UNDER ADMINISTRATION UNDER SECTION 139 OF THE CONSTITUTION, 1996UNDER SECTION 139 OF THE CONSTITUTION, 1996
28 January 2014Parliament, RSA, Cape Town
1
OUTLINE OF THE SUPPLEMENTARY PRESENTATION
To provide additional information on the following:
1.MIG Support Initiatives
2.Operation Clean Audit
3.Section 139 Interventions
4.Local Economic Development
5.MISA Support2
1. MIG support initiativesChallenge Initiative
Underspending on the MIG programme primarily as a result of lack of adequate planning or planning related challenges. In certain instances lack of filling of Municipal Manager and critical section 56 manager posts as well as lack of timely communication and follow-up between municipalities and sector departments regarding submitted technical reports where there are issues that require compounded the planning challenge.
In Mpumalanga: The DCoG in partnership with the Mpumalanga Department of Local Government, MISA , DWA and Department of Public Works held intensive focussed advisory support sessions with each of the following municipalities to which solutions to the challenges were provided:
• Mbombela Local Municipality• Dr JS Moroka Local Municipality• Bushbuckridge Local Municipality• Dipaleseng Local Municipality• Mkhondo Local Municipality• Lekwa Local Municipality• Thaba Chweu Local Municipality
MIG support initiativesChallenge Initiative
Underspending on the MIG programme primarily as a result of lack of adequate planning or planning related challenges. In certain instances lack of filling of Municipal Manager and critical section 56 manager posts as well as lack of timely communication and follow-up between municipalities and sector departments regarding submitted technical reports where there are issues that require compounded the planning challenge.
In Limpopo: The DCoG in partnership with the Limpopo Department of Cooperative Governance, Human Settlements and Traditional Affairs (COGHSA), Provincial Treasury, MISA and DWA held intensive focussed advisory support sessions with each of the following municipalities to which solutions to the challenges were provided:
• Capricorn District Municipality• Polokwane Local Municipality• Sekhukhune District Municipality• Mogalakwena Local Municipality• Lephalale Local Municipality• Greater Giyani Local Municipality• Mopani District Municipality• Greater Tzaneen Local Municipality
MIG support initiativesChallenge Initiative
Underspending on the MIG programme primarily as a result of lack of adequate planning or planning related challenges. In certain instances lack of filling of Municipal Manager and critical section 56 manager posts as well as lack of timely communication and follow-up between municipalities and sector departments regarding submitted technical reports where there are issues that require compounded the planning challenge.
In Northern Cape: The DCoG in partnership with the Northern Cape Department of Cooperative Governance, Human Settlements and Traditional Affairs (COGHSTA) , the Northern Cape Provincial Treasury, Namakwa District Municipality, Pixley Regional Office COGHSTA, Frances Baard Regional Office COGHSTA, DWA and the South African Local Government Association (SALGA) held intensive focussed advisory support sessions with each of the following municipalities to which solutions to the challenges were provided:
•Karoo Hoogland Local Municipality•Hantam Local Municipality•Richtersveld Local Municipality•Khai Ma Local Municipality•!Kheis Local Municipality•Mier Local Municipality•Kamiesberg Local Municipality•Kareeberg Local Municipality•Siyathemba Local Municipality•Emthanjeni Local Municipality•Umsobomvu Local Municipality•Thembelihle Local Municipality•Joe Morolong Local Municipality•Gamagara Local Municipality•Magareng Local Municipality•Kai-Garib Local MunicIpality
1. Background2. Milestones3. Status of outcomes4. Support Initiatives5. Key challenges affecting Municipal Financial
Management and audit outcomes6. Capacity of provinces to support
municipalities
6
2. Operation Clean Audit
Operation Clean Audit
Background
Operation Clean Audit 2014; was launched in 2009 as a specific response programme within the Local Government Turnaround strategy.
At the time 86 of the municipalities audited obtained disclaimers for the 2007/8 financial year and another nine municipalities adverse audit opinions.
7
Operation Clean Audit milestones
The guiding vision for Operation Clean Audit is that by 2014 all municipalities will achieve unqualified audit opinions in their Annual Financial Statements. The programme milestones to realise the 2014 vision for municipalities were fixed as follows:
– Between 2010 and 2011, no municipality and municipal entity will obtain adverse and disclaimer audit opinions.
– At least 60% of municipalities and municipal entities will achieve unqualified audit opinions by 2012.
– There will be an increase in municipalities and municipal entities achieving unqualified audit opinions to at least 75% by 2013.
– 100% of municipalities and municipal entities will achieve unqualified audit opinions by 2014. 8
Current status of audit outcomes• The latest audit outcomes for Local Government that have been
released by the Auditor General (AG) pertain to the 2011/12 financial year. The AG is finalising the 2012/13 outcomes for release later this year.
• The 2011/12 outcomes reflect that 48% of municipalities and municipal entities achieved unqualified opinions against the 75% target of 2013 . In addition; the adverse audit opinions and disclaimers have not been eliminated. These were set to be eliminated by 2011.
• Only 3 provinces have managed to reach the 75% target for 2013 ; these are Gauteng, KwaZulu Natal and Western Cape at 84%, 77% and 85% respectively.
• The tables in the next 2 slides illustrate the status.
Current status of audit outcomes
AUDIT OPINION 2013 MILESTONE 2013 STATUS 3013
VARIENCEUnqualified Audit opinions
Minimum 75% 48% 27% Below target
Qualified Audit opinions and outstanding audits
Maximum 25% 52% 27% Below target
The Qualified Audit opinions & outstanding audits represent the following: Qualified Audit opinions
Maximum 25% 21% n/a
Disclaimers 0 24% Should be nilAdverse Opinions 0 1% Should be nilOutstanding Audits
0 6% Should be nil
10
Status of audit outcomes per province
11
PROVINCE Unqualified Audit opinions Qualified Audit opinions and outstanding audits
2013 MILESTONE
2013 STATUS 3013
VARIENCE
2013
MILESTONE
2013
STATUSEastern Cape Minimum 75% 31% 44% below
targetMaximum 25% 69%
Free State Minimum 75% 30% 45% below target
Maximum 25% 70%
Gauteng Minimum 75% 84% 9% ahead Maximum 25% 16%
KwaZulu Natal Minimum 75% 77% 2% ahead Maximum 25% 23%
Limpopo Minimum 75% 6% 69% below target
Maximum 25% 94%
Mpumalanga Minimum 75% 34% 41% below target
Maximum 25% 66%
Northern Cape Minimum 75% 22% 53% below target
Maximum 25% 78%
North West Minimum 75% 34% 41% below target
Maximum 25% 66%
Western Cape Minimum 75% 85% 10% ahead Maximum 25% 15%
Operation Clean Audit Support
• On an annual basis after the release of the Local Government audit outcomes by the Auditor General; the Department co-ordinates the development of a standard integrated support plan for Operation Clean Audit. (OPCA)
• The OPCA plan is developed after the analysis of the annual financial statements and audit outcomes of municipalities; in response to Section 131 of the MFMA.
• Accordingly; the attached 2013/14 plan (see ANNEXURE A) has been developed and approved by the CoGTA MINMEC for implementation in response to the 2012/13 Local Government Audit outcomes.
• The provinces share municipal finance support responsibilities which include the activities in the OPCA plan between the Provincial Treasuries and Provincial CoGTA’s
• The reporting on the implementation of the plan is quarterly to the Premier Co-ordination Forums / Committees; the Provincial MUNIMEC’s as well as a consolidated report to the CoGTA MINMEC.
12
Operation Clean Audit SupportThe key areas of focus in the attached 2013/14 OPCA plan are the following:• Actions to ensure that quality Annual Financial Statements (AFS) submitted timeously.• Actions to ensure that key controls are in place and that corrective measures are
implemented to address key control deficiencies.• Actions to improve the efficient use of service providers• Actions to ensure the development and implementation of audit remedial plans• Actions to improve leadership involvement in guiding and directing the
implementation of OPCA initiatives• Actions to create a platform for consequence management, politically and
administratively.• Actions to improve performance reports• Actions to improve asset management, Records management, Supply Chain
Management, Unauthorised, irregular, fruitless and wasteful expenditure.• Actions to improve Information Technology Controls,• Actions to ensure improved HR practises• Actions to improve the capacity of DCoG and Provinces to support municipalities.• Actions to ensure effective governance - Audit and Public Account Committees
Key challenges affecting Municipal Financial Management and audit outcomes
Although progress has been made within the municipal finance arena, municipalities face a number of historical challenges. These include:
• A history of receiving qualifications and inability to turn them around due to unresolved historical transactions (legacy issues) that affect the opening balances.
• The instability within the municipality, both at a political level as well as administratively.
• The high vacancy rate of CFO’s and other key personnel due to the suspensions and resignations.
• Lack of funds for asset management to facilitate a complete disclosure of infrastructure assets.
• Non functional MPACs as well as MPAC chairpersons being changed regularly which affect the committee’s stability and progress.
• Lack of capacity in Internal Audit units and inadequate functionality of Audit Committees.
• Inadequate information communication technology (ICT) systems to support financial management.
Capacity of provinces to support municipalities
• The capacity of certain provinces to support municipalities is of great concern.
• There seems to be a direct correlation between the provinces with substantive support programmes, dedicated personnel to support municipalities as well as funds for support interventions and the level of improvement in the audit outcomes over the OPCA period.
• Gauteng, Western Cape and KwaZulu Natal clearly demonstrate this correlation; of the 9 provinces whose support plans were analysed; they have the most comprehensive provincial CoGTA support programs for OPCA.
• These are also the provinces who currently meet the 2013 OPCA target of 75% unqualified audit opinions.
1. Nature of the Challenges2. Support Initiatives3. Detailed and other S139 initiatives4. Development of Intergovernmental Support
and Monitoring Bill (IMSI).
16
3. Section 139 interventions
PROVINCE: KZN
DATE OF INVOCATION
DATE OF TERMINATION
REASONS
Indaka Local Municipality
March 2010 Renewed – Still in progress
Governance: Lack of institutional leadership amounting to poor performance;Weaknesses in performance reporting directly affecting the oversight role of council over the executive and management.
Financial: Continuous financial irregularities resulting in the municipality receiving an audit disclaimer;Continuous failure to respond to audit findings and implement audit recommendations.
17
S 139 - Nature of the Challenges
PROVINCE: KZN
DATE OF INVOCATION
DATE OF TERMINATION
REASONS
Umvoti Local Municipality
July 2013 Still in progress Governance: Continuous struggle and instability due to political differences of elected councillors which also permeated to staff members; Unlawful removal of elected office bearers and unlawful election of new office bearers, including the Speaker; Disruption of council meetings, including the passing of the budget, rendering the meetings in-quorate as a result of walkouts;State of dysfunctionality had forced the presence of members of the SAPS at council meetings and the closure of the municipal offices.
18
PROVINCE: KZN
DATE OF INVOCATION
DATE OF TERMINATION
REASONS
Imbabazane Local Municipality
January 2013 Still in progress Governance: Political instability impacting on various aspects of administration and resulting in unstable governance;Tensions and disagreements in council resulting in various walkouts by political parties; Irregular decisions by council, such as continuing employing the Municipal Manager although his contract had terminated by operation of law ;Non adherence to policy, principles and frameworks applicable to council and the administration, such as instances where not all councillors were notified of meetings.
19
PROVINCE: KZN
DATE OF INVOCATION
DATE OF TERMINATION
REASONS
Abaqulusi Local Municipality
March 2013 Still in progress Governance: Municipality was without a municipal manager from 31 January to 05 March 2013 and other senior positions remained vacant;Council was failing to fulfil its executive obligations;Council failed to accept an offer of support from the provincial government.
Financial: Municipality received a disclaimer audit opinion for the 2011/12 financial year for various reasons, such as high levels of unauthorised expenditure;Municipality’s annual report not compliant with section 121 of the MFMA.
20
PROVINCE: KZN
DATE OF INVOCATION
DATE OF TERMINATION
REASONS
Umzinyathi District Municipality(MFMA S136)
April 2013 Still in progress Governance: Appointment of staff was not conducted in line with the recruitment policy, resulting in non-suitably qualified staff being employed and the appointment of a consultant as CFO ;Failure to comply with the section 139(1)(a) directive issued by the Provincial Executive in relation to the municipality’s obligations to Uthukela Water.
Financial: Lack of budgetary control which was evident from the income and expenditure statement for the 2011/12 financial year , reflecting over-expenditure;Material discrepancies between section 71 reported figures for the 2011/12 financial year and figures in the financial statements;Non-payment for services rendered by Uthukela Water.
21
PROVINCE: KZN
DATE OF INVOCATION
DATE OF TERMINATION
REASONS
Uthukela District Municipality(S136)
May 2013 Still in progress Financial: Disclaimer audit opinion in the 2011/12 financial year which highlighted significant deficiencies in financial management including insufficient cash to cover operations, under-budgeting, discrepancies between section 71 reported figures and figures in the financial statements; unspent conditional grants of R126,3 million, irregular expenditure amounting to R14, 6 million and weak budgetary control which resulted in unauthorized expenditure of R62,147 million;Disaster Relief Fund of R4 million not spent for the purpose; inability of the municipality to pay its creditors.
Governance: Failure to ensure that the municipality was structured and organised in a manner suitable to undertake its constitutional obligations. 22
PROVINCE: KZN
DATE OF INVOCATION
DATE OF TERMINATION
REASONS
Ugu District Municipality(MFMA S136)
May 2013 Still in progress Financial: The Auditor General’s report for the 2011/2012 financial year highlighted that the municipality regressed from an unqualified audit opinion to a qualified audit opinion; Unauthorised expenditure of R45, 4 mil, an irregular expenditure of R18, 4 mil, current liabilities exceeded current assets and conditional grants were not cash-backed.134 cases of deviations of the SCM regulations, high salary and overtime costs; the ratio of current assets to current liabilities was below the norm of 2:1; failure to pay creditors within 30 days, and loans totalling an amount of R285, 5 mil.
Governance: Numerous changes in top management with middle managers acting in critical posts. 23
24
PROVINCE: NW
DATE OF INVOCATION
DATE OF TERMINATION
REASONS
Maquassi Hills Local Municipality
April 2013 Still in progress Governance:Poor governance and management of council matters by council;Infighting in council, which grossly affects administration and service delivery (Poor relationship between Mayor and Speaker);Poor leadership and oversight by Council;Breach of code of conduct by Councillors;Poor relations between council and the administration;Deterioration of service delivery resulting in sporadic service delivery protests;Poor administrative leadership and lack of capacity.
25
PROVINCE: NW
DATE OF INVOCATION
DATE OF TERMINATION
REASONS
Ditsobotla Local Municipality
April 2013 Still in progress Governance: Poor governance and management of council matters by council (Infighting and divisions in council);Poor leadership and oversight by council (Appointment of the Municipal Manager was highly irregular);Breach of Code of Conduct by Councillors;Poor relations between council and the administration (Poor relationship between Mayor and Municipal Manager);Deterioration of service delivery;Poor administrative leadership and lack of capacity.
25
PROVINCE: NW
DATE OF INVOCATION
DATE OF TERMINATION
REASONS
Matlosana Local Municipality
April 2013 The council of Matlosana on 22 November 2013 accepted S139 intervention due to financial distress. At a meeting between the MEC and mayoral committee on 17 Dec 2013 it was resolved that the intervention team should immediately conduct an assessment on the financial status of the municipality to ascertain the areas of focus during the intervention. The report of the assessment will be presented to the MEC on the 17th January 2014, thereafter to the mayoral committee. Awaiting the response of the NCOP select committee on the letter from Province.
Financial: Financial crisis which had resulted in municipality not honouring its statutory obligations during the 2012/13 financial year;Non-payment of the bulk electricity and the bulk water accounts to Eskom and Midvaal Water Board;Failure to collect municipal rates resulting in the debtors book standing at about R960 million;Use of revenue from sale of electricity to subsidise other services for which the consumers were not paying;Poor administrative leadership and lack of capacity.Governance: Non-enforcement of debt collection and credit control policies; Lack of management and leadership capacity.
26
27
PROVINCE: MPUMALA-NGA
DATE OF INVOCATION
DATE OF TERMINATION
REASONS PROGRESS
Emalahleni Local Municipality
April 2013
Still in progress Four main findings- Infrastructure and service
delivery collapsed; Municipal capacity to
function disintegrated; Financially at the point of
collapse; Break down in trust
between communities and government.
Governance: Rrelationship between the
Mayor and Municipal Manager had deteriorated to such an extent that it had paralysed the functioning of the municipality;
LLF not functional; Interference of unions in
administrative functions; Deterioration of audit
outcome (Disclaimer).
Labour stabilised, agreements with unions and staff consultation process, LLF established.
Investigation into allegations of corruption, fraud and collusion initiated.
Performance management system being developed- aim to change culture to being performance orientated.
HOD forum launched. Members of mayoral committee
with directors pulled in as part of turnaround team.
Shift system reviewed and agreement signed.
Section 80 committees established.
Staff capacity strengthened. Audit Remedial Action Plan
Reviewed.
28
PROVINCE: MPUMALA-NGA
DATE OF INVOCATION
DATE OF TERMINATION
REASONS PROGRESS
Emalahleni Local Municipality
April 2013
Still in progress Restoring relations with communities :Series of public meetings. Programme from administration to visit wards to discuss issues.Open door to delegations from communities.Relationship with local press renewed, using news papers to convey messages.Social media employed as instrument to get immediate feed back and to give real time information. Extremely positive response.Weekly discussions by directors on issues on Emalahleni FM.Publishing challenges and programmes to communitiesIn process of developing new call centre to promote efficient communication. Funding from donors committed for this purpose.Engagement with key community groups on issues e.g. Planning forum to mobilise expertise. Mining sector/ organised business. Informal settlements – responded to
demands within time lines and agreed on a joint working committee.
Ensuring that personal attention to reported problems are provided and that teams respond immediately to service delivery reports.
29
PROVINCE: MPUMALA-NGA
DATE OF INVOCATION
DATE OF TERMINATION
REASONS PROGRESS
Emalahleni Local Municipality
April 2013
Still in progress
Service Delivery• Waste management sporadic and
severely impaired – only one truck out of 15 operating.
• Water provision poor and quality shocking – interruptions 3 out of every 7 days, at least 30% shortfall, water bursts daily.
• Road infrastructure disintegrating – not a street without potholes or with working robots.
• Electricity supply interrupted – every second day, 20% overload.
• Sanitation problematic –pollution levels high and sewage spillages daily.
• No law enforcement - Illegal activities escalating.
• Housing backlog – 27 informal areas.
• Maintenance of assets non existent.• No capacity for growth or for even
to service current population
The immediate provision of potable water has been stabilised through better system management.
Problems on network addressed with short turnaround times. Total wastage of water reduced with 60%.
Sanitation remains an issue and strategy has been in the short term to ensure quicker responses to problems. Turn around improved and long outstanding issues being addressed.
Waste removal back on track as the main problem of vehicles have been resolved.
Roads – pothole programme developed and own budget supplemented by Provincial Department of Public Works.
Electricity plans for improvements being made. Immediate focus on immediate problem solving as problems occur
Vehicle fleet management changed and fleet getting in shape. However, still a challenge.
30
PROVINCE: MPUMALA-NGA
DATE OF INVOCAT-ION
DATE OF TERMINATION
REASONS PROGRESS
Emalahleni Local Municipality
April 2013 Still in progress
Financial: Financial instability – Disclaimer:•Creditor payments – R346 million outstanding.•Debtors’ at 79%. Total outstanding R981 million.•Cash-flow estimated to be negative R93,7 million.•Total net negative R439,8 million.•Supply chain management waste full and severe issue.Income unsatisfactory:• Nearly R40 million under
recovery on water and electricity.
• 37 000 households not metered for water, 13 000 electricity not metered.
• Large scale illegal water and electricity connections.
•Expenditure out of control• Over utilisation of
contractors.• Overtime abused• Purchases inflated
Financial turn around strategy adopted. Audit plan developed and issues being
addressed. Aim at addressing all issues which led to a disclaimed audit.
Financial controls over supply chain strengthened.
Cash flow projections done daily. Cash flow still negative but improving. Debtor management improved. Clean up creditors, e.g. agreement with
Eskom. Over R20 million in long outstanding debt
paid to creditors. 60% of creditors paid within prescribed
dates to date. Additional financial expertise employed. Programme launched to ensure all are
metered. Need to replace and install 37 000 water meters and 13 000 electricity meters.
Addressing illegal connections. New tariff structure approved. Indigent
population’s plight relieved. Fines being imposed and enforced . More
than R1 million already levied. With above initiatives aims at improving
revenue stream with R25 million per month and reduce expenditure with R5 million per month.
31
PROVINCE: MPUMALA-NGA
DATE OF INVOCATION
DATE OF TERMIN-ATION
REASONS PROGRESS
Bushbuck-ridge Local Municipality
April 2013 Still in progress
Governance: •Critical vacancies in municipality•Disclaimer Audit OutcomeFinancial: •Inability of the municipality to honour its financial commitments to the Bushbuckridge Water Board, resulting in the latter cutting off its water supply. • The outstanding debtors was an
amount of R993mil and the outstanding creditors amounts to R351mil. The R351mil is unconfirmed and might increase.
• The Municipality billed consumers up to March 2013 a accumulative amount of R298mil and only collected an amount of R50,6 mil for the same period. The MIG allocation for the year was R286mil of which all was transferred to the municipality. Only R93mil spent.
• The balance of R192 mil was not cash backed.
• SCM unit not functional.
Technical Director Appointed
Audit Remedial Action Plan Developed
National, Prov. Treasury and COGTA developed financial turn around strategy
Tariff structure reviewed Data Cleansing exercise in
process IT environment audited
and support provided to link cash offices electronically
SCM units established and trained
MIG projects prioritised and service providers appointed
Systems developed and implemented.
The Municipality’s financial position is steadily improving.
32
PROVINCE: MPUMALA-NGA
DATE OF INVOCATION
DATE OF TERMINATION
REASONS PROGRESS
Bushbuck-ridge Local Municipality
April 2013
Still in progress
Service Delivery:•municipality was unable to discharge its responsibility of providing its communities with constant water, refuse removal and electricity.•The failure to provide water to its communities has been the low point in terms of its financial capability.•Failure to provide water is as a result of a crisis in its financial affairs; it is in serious or persistent material breach of its obligations to provide basic services and is unable to meet its financial commitments.•Bushbuckridge Water Board cut water supply to the municipality as from the 23 November 2012 due to municipality admitting to be unable to honour its commitments.•After several meetings the water supply has been restored for few days with no end in sight.
The Minister and the Premier have intervened in accelerating the implementation of the water reticulation programme by engaging Rand Water to become an implementing agent.
The tri-partite agreement is about to be signed, but Rand Water has already begun with the construction process.
The Acornhoek bulk line has been completed
The rest of the water bulk infrastructure will be completed this financial year
Dedicated maintenance teams are being set up. The existing municipal water tankers fleet is being overhauled and about 4 new trucks will be procured the next two month.
32
33
PROVINCE: MPUMALA-NGA
DATE OF INVOCATION
DATE OF TERMINATION
REASONS PROGRESS
Bushbuck-ridge Local Municipality
April 2013
Still in progress As far as Bushbuckridge Water Board is concerned, the Municipality is concluding a negotiated process to repay BWB over a period of time in such a way that the cash flow situation of BBR does not deteriorate further, and the debt does not escalate at the same time.
PROVINCE: WESTERN CAPE
DATE OF INVOCATION
DATE OF TERMINATION
REASONS
Oudsthoorn Local Municipality
34
Challenge Initiative
S 139: Access to provincial data and information (e.g. Administrator reports, close-out reports, correspondence and performance data)
The Joint support initiative; deepen institutional systems and processes to manage monitoring and reporting on S139 interventions at national level
Enhance Financial and Governance Competences
Consolidate the provision of initiatives by provinces, National Treasury, Auditor-General, LGSETA, IMFO and determine areas not yet being addressed / the reason why impact is not yet requisite and put a inter-sectoral plan in place to address challenges.
DETAILED S139 INITIATIVES
Challenge Initiative
Imbabazane DM, Umvoti LM, Ditsobotla LM, Maquassi Hills LM, Mquma LM and Emalahleni LM: Challenges with council; political differences of the elected councillors which also permeated to staff members; unlawful election of office bearers, including the Speaker; disruption of meetings as a result of walkouts and poor governance and management of Council matters; poor leadership and oversight by council; breach of code of conduct by councillors; poor relations between council and the administration; deterioration of service delivery.
Two factions, one led by the Executive Mayor and the other led by the Speaker and the Chief Whip, were running two parallel administrations; contraventions of the provisions of the Local Government Municipal Structures Act of 1998 and the Council Rules of Order, respectively.
Governance: Develop comprehensive Councillor Handbook in collaboration with SALGA and Provinces. Conduct workshops to implement Councillor Handbook in collaboration with stakeholders Monitor implementation.
Mobilise political intervention where necessary.
OTHER S 139 SUPPORT INITIATIVES
Challenge Initiative
Ugu DM and Uthukela DM:Majority of staff have inadequate skills
SD: Governance:Mobilise support from LGSETA to determine whether municipal workplace skills plan is addressing the requisite skills gap. Mobilise additional financial resources to fast track skilling for critical posts.
Uthukela DM
IDP not credible and failure to approve the annual budget and the IDP for 2013, respectively.
Send a team to facilitate the address of IDP and SDBIP challenges.
Uthukela DM: Excessive amounts .spent on overtime
Using SALGA HR Policy Handbook and in collaboration with SALGA assist the municipality to develop an Overtime Policy that addresses the challenges they face. Monitor approval and implementation of the Policy.
OTHER S139 SUPPORT INITIATIVES
OTHER S 139 SUPPORT INITIATIVES
Challenge Initiative
Umzinyathi DM, Matlosana LM, Indaka LM, Emalahleni LM and Bushbuckridge LM:
Staff not having access to accounting systems and lack of monitoring of work as service providers get paid without having done the work and financial crisis resulting in municipality not honouring its statutory obligations;
Non-payment of bulk electricity and bulk water accounts to Eskom and Midvaal Water Board; failure to collect municipal rates resulting in the debtors book standing at about R960 million; use of revenue from sale of electricity to subsidise other services for which consumers were not paying; poor administrative leadership and lack of capacity; non-enforcement of debt collection and credit control policies, respectively.
Finance and Governance: Mobilise support from National Treasury and LGSETA to address capacity constraints.
Mobilise political intervention where necessary.
S 139 – Development of the Intergovernmental Monitoring, Support and Interventions Bill (IMSI):
39
Objectives of the Bill:To provide for support and intervention measures to strengthen the
capacity of each sphere to fulfil its executive obligations in respect to oversight and support of municipalities
Stabilise the interventions environment through:
a) Clearer procedures and processes for undertaking both S100 and S139 interventions;
b)To establish, together with DPME, a range of sector norms and standards for service delivery to better define executive obligations;
c)To ensure that interventions are used as a ‘last resort’ and prevent ‘conflictual interventions’ through providing pre-intervention measures for provision of support.
d)Providing for a consistent and uniform approach to the application of an intervention at both provincial and local level (and rationalising procedurally, re both S139 and S 100)
e) Section 139 (8) legislation would complement the provisions of the Municipal Finance Management Act, which provides a detailed framework for section 139 (4) and (5) ‘financial’ interventions.
An integral part of COGTA’s efforts to realise the objectives of LGTAS.
1.Accelerating service delivery 2.Enhancing Good Governance 3.Promoting sound financial management 4.Fighting corruption 5.Facilitating sustainable infrastructure development.
40
4. MISA Strategic Focus
Local Government Skills Challenges Findings from Empirical Studies
• Migration of older experienced Built Environment professionals out of local govt
• Replacement by younger relatively inexperienced officials (3 -5 years minimum average experience)
• Majority unregistered with statutory professional Body (unregulated)• High Vacancy Rates(35 -50%)• Increased Technical workloads & falling staffing levels • Municipal Technical departments unable to spend MIG allocations• Frequent budgetary rollovers of MIG • General inability to cope with the demands of municipal operations
and maintenance,• Frequent sewage spills, water quality problems and refuse non-
removal• Inability to cope with services for developments/ large housing
projects due to a lack of bulk services and support bylaws• High water / electricity losses• Poor Metering management• Poor revenue income streams and collection rates (growing indigents)• Increased service delivery protests
Designated Technical Profession/ Trade
Professional Registration Body
Engineers (Civil, Electrical, Mechanical, Electromechanical)
Engineering Council of South Africa (ECSA)
Quantity Surveyors SA Council for the Quantity Surveying Profession (SACQSP)
Construction Project Managers SA Council for the Construction Project Management and Construction Management Professions (SACPCMP)
Town and Regional Planners SA Council for Planners (SACPLAN)Water and Wastewater Practitioners
Department of Water Affairs (DWA) Water Institute of Southern Africa (WISA)
Artisans National Artisans Moderating Body (NAMB)Property Valuers SA Council for Property Valuers Professions (SACPVP)Natural Scientists SA Council for the Natural Scientific Professions
(SACNASP)
Key Technical Professions Targetted
42
Sub-Programme ObjectivesTo create a pool of Artisans for efficient operations and maintenance of
infrastructure in local government
Current Support Deployed – Total x231 Apprentices deployed (FET graduates)
+ New Deployments - Total x58 Apprentices deployed (graduates)
Total Deployments x289 Apprentices deployed
Municipal Officials Under Apprenticeship – x87 municipal officials
Current Skills SetsElectriciansBricklayers & PlumbersMotor and Diesel Mechanics Fitters & Turners
New Skills SetWater Process Controllers – (Water & Wastewater)Landfill Site operators
Artisans Development Programme
43
APPRENTICE DEPLOYMENTS TRADE
ProvinceDistrict Municipality
Local Municipality Electrician Plumber
Motor Mechanic
Diesel Mechanic
Bricklayers Fitter
Fitter and
turner Total
Limpopo Capricorn Blouberg 6 6
Capricorn Modimolle 3 3
Capricorn Polokwane 10 9 19
Vhembe Mutale 3 3
Vhembe Thulamela 3 3
TOTALS 19 15 0 0 0 0 0 34
Eastern Cape Joe Gqabi Maletswai 0
Joe Gqabi Senqu 3 1 4
King Sabata Dalindyebo OR Tambo 5 3 8
Amathole Mnquma 0
TOTALS 8 0 0 0 4 0 0 12
APPRENTICE DEPLOYMENTS TRADE
ProvinceDistrict Municipality Local Municipality
Electrician
Plumber
Motor Mechan
ic
Diesel Mechan
icBricklay
ers Fitter
Fitter and
turner Total
Northern Cape Francis Baard Sol Plaatjie 4 4
Namakwa Kamiesberg 1 1
Pixley Ka Seme Karreberg 1 1
Siyanda Kai Garib 5 1 3 2 11
TOTALS 11 1 0 3 0 0 2 17Western Cape Stellenbosch 0
Kannaland 0
Hessequa 0
TOTALS 0 0 0 0 0 0 0 0North West Rusternburg 1 1
Madibeng 1 1 2
Moretele 2 2
APPRENTICE DEPLOYMENTS TRADE
Province District MunicipalityLocal Municipality Electrician Plumber
Motor Mechanic
Diesel Mechanic Bricklayers Fitter
Fitter and
turner Total
KZN Mgungundlovu Msunduzi 25 2 0 0 0 0 0 27
Mpofana 1 1
Mandeni 4 4
New Castle 17 1 4 22
Illembe 6 6
Kwadukuza 22 2 24
TOTALS 69 9 0 2 4 0 0 84Mpumalanga Albert Luthuli 9 1 10
Emalahleni 1 1 Lekwa 10 5 4 19
Thaba Chweu 14 14
Umjindi 4 4 Bushbuckridge 6 6
Nkomazi 2 2
GRAND TOTALS 167 41 0 11 8 0 3 230
Technical Bursary Programme
• Established by Cogta in 2010• Transferred to MISA in 2012
• Bursary to fund undergraduate studies - National Diploma/ Bachelors degree studies in Civil, Electrical Engineering, Town Planning & Geographical Information Systems (GIS) disciplines.
• Historically disadvantaged candidates from poor background • Eligibility: Matriculants meeting minimum university entrance
requirements • Total graduates currently funded - x91 graduates
Graduating bursary holders contracted to municipal Technical departments for service delivery and skills pipeline
Technical Training Programmes
Core Technical Modules•Construction Management•Asset and Maintenance Management •Supply Chain Management •Road Traffic Engineering and Management•Water Resources Engineering and Management•Solid Waste Management•Environmental Management•Town and Regional Planning
Core Management ModuleStrategic Management and Leadership
Electives for Technical Managers (1 Module)Fleet Control and Management Infrastructure Strategic Project ManagementProject Quality and Risk Management
Certificate Programme in Infrastructure ManagementPost Grad Diploma / Certificate Level
To assist Technical Directors /junior/ middle managers without minimum academic qualifications
Programme to be delivered with full academic credits by all x7
Universities of Technology with common curriculum, full academic credits nationally, subsidized by
MISA
Technical Training short courses , subsidized by MISA, about to start in January 2014
x12 municipal officials trained in Japan through MISA-JICA partnership
Young Professionals (YP) & Experiential Learning Programmes
YP Programme
•3 year structured work-based internship development programme leading to professional registration•Focused on Civil Engineering & Town Planning graduates from Universities/ University of Technology with 1 year or more working experience•Professional registration + absorption for building municipal internal capacity.
•x40 graduates underway to register as Technician professionals with statutory professional bodies ECSA, SACPLAN
Experiential Learning Programme
•18 months structured work-based internship development programme for new built environment graduates•Focused on Civil Engineering, Electrical Engineering, Waste Management, Construction & Town Planning graduates from Universities/ University of Technology with less than 1 year work experience•Exposure for employability + absorption for building municipal internal capacity.•x151 graduates currently being deployed nationally
Mentoring Towards Registration
Providing mentoring support to municipal officials to ensure the professional registration with professional registering bodies(ECSA; SACPLAN; SACPCMP). MISA Investment-Direct Mentoring CostTechnical Training RequiredSecondment WorkplaceMunicipal InvestmentS & T Accommodation during Secondment
1. Minimum academic qualifications in line with statutory requirements (National Diploma/ B. degree) 1. Five years or more relevant working experience 2. Eligibility for registration as Candidate 3. Existing professional registration (candidacy) with relevant statutory body
will be preferred.
Province YP’s Mentoring Towards Professional Registration
Experiential Learning
Civil Planning Civil Electrical Construction Planning Civil Waste Management
Electric Planning
Gauteng 2 3 2 7
Limpopo 2 2 5 4 2 12 2 2
Mpumalanga 2 4 11 3 10 11 2 2 7
Kwazulu Natal 2 6 10 7 7 13 19 3 9 7
Free State 2 2 7 2 2 7 2 6
Eastern Cape 3 9 12 3 6 8
Northern Cape 3 4 1 2
North West 2 6 3 4 6 8 7
Western Cape 2 1 1
Total 20 20 48 13 16 30 74 10 29 38
Planned Deployments 2013/2014 FY
Local Economic Development
52
a) The role of local government in promoting economic development is derived in the Constitution (Sec 152c and 153a): local government must promote social and economic development; it must structure and manage its administration, and budgeting and planning processes to give priority to the basic needs of the community and to promote the social and economic development of the community.
b) The role is refined in the 1998 White Paper on Local Government. It is stated that the powers and functions of local government should be exercised in a way that has a maximum impact on, among other things, the growth of the local economy.
c) This responsibility is discharged through the Local Economic Development (LED) function of municipalities, and is a key component of the municipality’s Integrated Development Plan (IDP).
d) Although the White Paper states local government is not directly responsible for creating jobs, this sphere is still responsible for taking active steps to ensure that the overall economic and social conditions of the locality are conducive to the creation of employment opportunities.
e) The role of DCoG is to support municipalities in the design and implementation of their local economic development function and strategies.
DCoG Support Programmes in Local Economic Development
53
Programme Progress
Business Adopt A Municipality
A total of 12 municipalities have been supported by the private sector. SANTAM has assisted municipalities in disaster management (fire). Fire-fighting implements were procured and delivered to the municipalities, and training was conducted, following an extensive needs assessment. SAB Miller and the Rand Water Foundation have provided training in the area of waste water treatment works and water infrastructure management. Mercedez Benz has provided technical advice on ICT systems, using their own model, and Buffalo City is currently testing the implementation of the recommendations. Eskom has identified 18 municipalities to be supported together with MISA. Eskom has selected 27 municipalities to be supported mainly in, among other areas, maintenance and rehabilitation of existing infrastructure; revenue management and tariff setting and skills development.
Red Tape Reduction (with the dti & SALGA)
Municipalities have undergone red tape accredited training to build skills and capacity around identifying and dealing with Red. 10 of the 12 municipalities selected have developed red tape action plans following an extensive identification of Red Tape issues. Identified red tape issue include poor communication of information; lengthy decision making timeframes; Supply chain Management (e.g. lack of local procurement). National Guidelines for Red Tape Reduction were produced using the pilot study in 12 municipalities. A national roll-out programme led by provinces is currently underway.
Business Development Forums
Forums were supported in the West Coast DM, Sedibeng DM, Cacadu DM and Steve Tshwete DM. All the forums are at differing levels of functionality. Support provided entails facilitating the formation of the structure or facilitating ongoing engagement. Through engagement, the WC DM has identified three catalytic interventions (Skills Development and Agriculture). In Sedibeng, lack of waste water treatment has been identified by the forum as an impediment to business development. Cacadu DM will launch its forum in February 2014
Capacity Building (funded by the dti)
LED Assessments were done in 7 municipalities to determine their level of LED functionality. Two municipalities were assisted with economic profiling. 5 municipalities were assisted with leadership training and mentorship.
NDMC support initiativesNDMC support initiatives
54
Approved Limpopo MDG
Municipality Amount (Rm)
Vhembe District Municipality R 41 501 200
Mutale Local Municipality R 24 700 000
Thulamela Local MunicipalityR 20 000 000
Makhado Local Municipality R 1 460 000
Total R 87 661 200
55
Approved KZN MDG
Municipality Amount Ugu District Municipality Allocation R 9 177 230Vulamehlo Local Municipality R 2 900 000Umdoni Local Municipality R 2 000 000 Umzumbe Local Municipality R 8 200 000Emnambithi /Ladysmith Municipality R 8 486 000Okhahlamba Local Municipality R 1 860 800Ethekwini Metropolitan Municipality R 1 500 000Total R 34 124
030.00
56
Approved North West PDG
Items Amount Fodder R 35 000 000Water Reticulation Infrastructure R 8 630 000
R 43 630
000.00
57
MDRG
2013/14 (R’000)
Eastern Cape municipalities 111 350 Nelson Mandela Bay 71 961 Ndlambe 15 353 Kouga 4 477
Koukama 8 439
Makana 8 724
Sundays River Valley 2 396
Western Cape municipalities 6 688
Langeberg 104
Eden District 6 584
Limpopo municipality 264
Maruleng 264
KwaZulu-Natal municipality 38
Umvoti 38
Total 118 340
58
Sector Grants 2010/11
2013/14(R’000)
Comprehensive agricultural support programme grant 296 085
Northern Cape 264 000
North West 4 500
Limpopo 15 000
Free State 9 000
Eastern Cape 1 500
Gauteng 2 085
Education infrastructure grant 159 412
North West 4 208
Limpopo 20 405
Mpumalanga 1 945
Kwa Zulu-Natal 15 941
Free State 6 121
Eastern Cape 110 791
59
Sector Grants 2010/11
2013/14(R’000)
Provincial Roads Maintenance 369 103
Northern Cape 93 752
North West 8 120
Limpopo 61 382
Kwa Zulu-Natal 45 732
Free State 33 478
Eastern Cape 125 199
Gauteng R 1 439
Human Settlements Development Grant 300 000
Northern Cape 17 250
North West 26 400
Limpopo R35 790
Mpumalanga R 600
KwaZulu-Natal 51 900
Free State 73 500
Eastern Cape 94 500
Gauteng 60
60
Sector Grants 2011/12 & 2012/13 2013/14(R’000)
Comprehensive agricultural support programme grant 4 295Limpopo 2 475Mpumalanga 303Western Cape 1 517
Education infrastructure grant 12 603KwaZulu-Natal 7 574Mpumalanga 4 866Limpopo 163
Health facility revitalisation 274KwaZulu-Natal 62Mpumalanga 212
Provincial roads maintenance 41 565KwaZulu-Natal 1 615Limpopo 4 462Mpumalanga 18 315Western Cape 17 173
Human settlements development grant 44 454KwaZulu-Natal 40 156
Limpopo 1 368
Mpumalanga 1 764
Western Cape 1 166
Total 103 191
61
THANK YOU.THANK YOU.
62