DIVERSIFYING YOUR SOLAR BUSINESS THROUGH
INNOVATIVE ROOF-TOP SOLUTIONS
Manu KaranDistributed Generation Biz. Dev. Head
![Page 2: Sun Edison](https://reader030.fdocuments.us/reader030/viewer/2022013118/5540097e550346b0758b4976/html5/thumbnails/2.jpg)
2
Top: 25 MW, Solar Park, Charanka, Gujarat Bottom: Narmada Canal 1 MW, Gujarat, India
Top: 72 MW Plant in Italy Bottom: 350 kWs Kohls Rooftop Installation
![Page 3: Sun Edison](https://reader030.fdocuments.us/reader030/viewer/2022013118/5540097e550346b0758b4976/html5/thumbnails/3.jpg)
SunEdison
First Private Solar Rooftop PPA in India – 100 kW at StanC
� First Rooftop Solar Private PPA in India (Standard Chartered Bank, Chennai)
� Thin Film PV Modules with Fixed Tilt
� Elevated Structures were used to ensure roof usage is not curtailed
� Central Inverter
![Page 4: Sun Edison](https://reader030.fdocuments.us/reader030/viewer/2022013118/5540097e550346b0758b4976/html5/thumbnails/4.jpg)
SunEdison
Education Institutes – 50kW at Shivalik Public School
� Rooftop Installation at Shivalik Public School, Punjab
� MonoCrystalline Modules
� Fixed Tilt
� String Inverters
![Page 5: Sun Edison](https://reader030.fdocuments.us/reader030/viewer/2022013118/5540097e550346b0758b4976/html5/thumbnails/5.jpg)
Distributed Solar Energy is a Key Feature of Developed Solar Markets
SunEdison
Source: Federal Network Agency, BSW-Solar (2011)
![Page 6: Sun Edison](https://reader030.fdocuments.us/reader030/viewer/2022013118/5540097e550346b0758b4976/html5/thumbnails/6.jpg)
Solar Energy Generation Peak Coincides with Afternoon Demand Peak
SunEdison
Solar Energy Generation Vs. Office Demand
Energy Demand
Solar Energy Generation
![Page 7: Sun Edison](https://reader030.fdocuments.us/reader030/viewer/2022013118/5540097e550346b0758b4976/html5/thumbnails/7.jpg)
SunEdison
Actual Peak Load Shavings from one of our solar power plants
Plant Size – 1.16 MWp in California, US
Peak Load Shaving, A Case in Point
Grid / Diesel Genset 1
Diesel Genset 2
![Page 8: Sun Edison](https://reader030.fdocuments.us/reader030/viewer/2022013118/5540097e550346b0758b4976/html5/thumbnails/8.jpg)
Hurdles to Adoption
� Subsidy turn-around time / uncertainty
� Upfront Large Capital Investment
� Roof-top usage for other purposes
� Limited free Roof-top Space
![Page 9: Sun Edison](https://reader030.fdocuments.us/reader030/viewer/2022013118/5540097e550346b0758b4976/html5/thumbnails/9.jpg)
Roof-top Solar Solution Innovation
� Business Model Innovation
• Non-subsidy System Sale
• Energy Sale
• Multiple Customer Energy Sale
� Mounting Structural Innovation
• Car Park roofing
• Elevated Semi-Roofing on terrace
![Page 10: Sun Edison](https://reader030.fdocuments.us/reader030/viewer/2022013118/5540097e550346b0758b4976/html5/thumbnails/10.jpg)
Business Model Innovation
![Page 11: Sun Edison](https://reader030.fdocuments.us/reader030/viewer/2022013118/5540097e550346b0758b4976/html5/thumbnails/11.jpg)
Subsidy & Non-Subsidy business models
SunEdison
![Page 12: Sun Edison](https://reader030.fdocuments.us/reader030/viewer/2022013118/5540097e550346b0758b4976/html5/thumbnails/12.jpg)
Economics of a System Sale
SunEdison
* Depends on parameters such as level of irradiation, tilt & type of installation
COMMERCIAL SUMMARY : 100 kW SPV POWER PLANT
Description With Subsidy Without Subsidy
Cost of 100kW System Rs 130 Lakhs Rs 117 Lakhs
Effective Cost to Customer Rs 61.47 Lakhs Rs 79.03 Lakhs
Operation & Maintenance cost Rs 2.5 Lakhs (5% YoY increase) Rs 2.5 Lakhs (5% YoY increase)
System Life 25 Years 25 Years
Calculated Cost per unit
of electricity generated~ Rs 7.5* ~ Rs 8.5*
Rs. 13 - 16
Diesel Genset
![Page 13: Sun Edison](https://reader030.fdocuments.us/reader030/viewer/2022013118/5540097e550346b0758b4976/html5/thumbnails/13.jpg)
Cost Comparison : Solar V/s Diesel Generator
SunEdison
Payback Summary
Diesel Price Rs40 / litre (5% yoy inflation)
Liters of Diesel required to produce equivalent units (kWh) 53333 litres
Payback Period3 Years (with capital subsidy)
5 Years (without capital subsidy)
Investment in Solar PV will result in Payback in 5 Years and almost Free Electricity for 20 More Years !!!
![Page 14: Sun Edison](https://reader030.fdocuments.us/reader030/viewer/2022013118/5540097e550346b0758b4976/html5/thumbnails/14.jpg)
Economics of Energy Sale
SunEdison
With SubsidyWithout
Subsidy
System Sale
(Energy Cost)~ Rs 7.5 ~ Rs 8.5
Energy Sale ~ Rs 8.5 ~ Rs 9.5
16%
Investor
IRR
![Page 15: Sun Edison](https://reader030.fdocuments.us/reader030/viewer/2022013118/5540097e550346b0758b4976/html5/thumbnails/15.jpg)
Multiple Customer Energy Sale
Apartment Block
Apartment #2
Apartment #4
Apartment # 1
Apartment #3
PV Panels
• Owner: Builder
• Location: Rooftop
Inverter, Battery
• Owner: Resident
• Location: Apartment
15
![Page 16: Sun Edison](https://reader030.fdocuments.us/reader030/viewer/2022013118/5540097e550346b0758b4976/html5/thumbnails/16.jpg)
Structural Innovation
![Page 17: Sun Edison](https://reader030.fdocuments.us/reader030/viewer/2022013118/5540097e550346b0758b4976/html5/thumbnails/17.jpg)
Parking Lot Canopy
SunEdison
![Page 18: Sun Edison](https://reader030.fdocuments.us/reader030/viewer/2022013118/5540097e550346b0758b4976/html5/thumbnails/18.jpg)
Yet low cost
SunEdison
![Page 19: Sun Edison](https://reader030.fdocuments.us/reader030/viewer/2022013118/5540097e550346b0758b4976/html5/thumbnails/19.jpg)
Commercial & Residential Building structures
SunEdison
(Not a SunEdison installation)
![Page 20: Sun Edison](https://reader030.fdocuments.us/reader030/viewer/2022013118/5540097e550346b0758b4976/html5/thumbnails/20.jpg)
SunEdison
Think Different
Think Big
![Page 22: Sun Edison](https://reader030.fdocuments.us/reader030/viewer/2022013118/5540097e550346b0758b4976/html5/thumbnails/22.jpg)
![Page 23: Sun Edison](https://reader030.fdocuments.us/reader030/viewer/2022013118/5540097e550346b0758b4976/html5/thumbnails/23.jpg)
HT Customers : Pain Points
TNEB’s New Regulations on HT Customers:
� Reduction in sanctioned load by 40%– 60%
• Eg. 1000kVA sanctioned load, reduced to
400kVA quota
� 2 days of power holiday per week
� Restricted usage between 6PM to 10PM
(unless purchased from power exchange)
� Significant cutback of total number of units
(kWh) to be consumed
� Heavy Penalties for non compliance
SunEdison