Summer training (civil engineering)-Ramp construction
-
Upload
vivek13 -
Category
Engineering
-
view
158 -
download
2
Transcript of Summer training (civil engineering)-Ramp construction
HINDUSTAN INSTITUTE OF TECHNOLOGY AND MANAGEMENT
NAME _VIVEK KUMAR SINGH ROLL NUMBER_1300300058
PROJECT TITLE_ RAMP CONSTRUCTION
<DETAILS><Calculation of slope of ramp>
<Construction of ramp>
<CONTENTS>
• Comparison b/w ramp & stairs• Theory• About
<Comparison>
Stairs Ramp
<theory>
• The maximum recommended slope of ramps is 1:20.
• Steeper slopes may be allowed in special cases depending on the length to be covered.
• Simple mathematics is used for calculation of slope.......
Meaning of 1:20
<recommended standards>
<About >• OPD BLOCK & OTHER ASSOCIATED SERVICES• Project:-OPD Block & other Associated Services • Client:-The Director AIIMS C/O M/S HSCC (India) Ltd. • Location:-AIIMS Campus, Ansari Nagar, New Delhi • Architect:-The Genral Manager (CIVIL), HSCC (India) Ltd.E-6 (A),
Sector-1, Noida-201301• Project Highlights:-Rcc Frame structure building (3B+G+8) Cilvil,
Plumbing, Electrical, HVAC, Lift, Fire Alram, external development, drainage etc..
<AHLUWALIA CONTRACTS LTD.>
• Project cost -251 crore• Project duration-09 months • My training duration-25 days
<Memories>
<Notes>
• Circular and round slope can not be construct.