Summary of Gregory Howell Lecture.docx

2
Summary of Gregory Howell lecture Traditionally construction industry focused more on implementation of the contracts. The procedure was to break up project into pieces and plan for it. Critical Path Method was one of the popular method but over the period people started to complain as CPM controls time but, not cost as to complete in time resources are increased. Productivity improvement was the next action. Howell and Glen looked into foremen weekly plan and found out the success rate, it turned out to be 54% and this was observed all over the world. They move on to describing the development of Toyota way or Pull Planning, he describes engineer Ohno’s observation of inventory being a waste. They figure out that why sometimes while increasing the productivity of a crew the project was going worse. This is because the work has been messed up. In order to improve the productivity, the productivity of the work flow must be improved. The general barriers to delay were illustrated with example as the change in the design, material being shipped late etc. these works could be sorted if there was enough communication between workers and the management team. An example illustrated were the MRI had to installed and there was no way the team could have done it in that time frame but the MRI Company had an incentive in completing the work in time so they have done partially, shows that unexpected things could have turn up if things are more informed. In the Last planner system is the person executing the work plans out giving an informed plan and shows the interdependencies of the crew. In lean construction we are optimizing the project not each piece of work. The speaker talks about the phases of work which starts with a Request and forms a commitment which when performed, can be declared and then declare satisfaction. To improve project performance there must be impeccable coordination as discussed earlier and production system design should be done for optimum project benefits not task wise and lastly collective enterprise and this has to be done with everyone and planning this way will help try to make better decisions to reduce the time, cost and complexity. Another important point to note is to eliminate contingencies but at the same time there presence gives more safety hence there is a tradeoff. The next topic was about contracts, the first LCI meeting agreed that present contracts do not obstruct Lean construction nor do they support. Relational contracting was discussed. In traditional practice the persons who know why, what and how are separated but modifying we bring people together in an integrated team with core and the peripheral group. This would increase the scope for optimization and participants are better informed about the project. It is observed that the project become more safer after implementation. There should more thought in where to apply this method as people have invest their time in it. Target value design is a method which gives a challenge to the design team to work out innovative ways to meet the target. Integrated Project delivery system was discussed with an overview template. Concluding it with by saying that fundamental practices, conceptual foundation and having a common language are very important and leading edge would be target value design and choosing by advantage. Lean construction is now being applied at various places in the world and concluded it by an example of block building contract in Nigeria which was very successful. Wrapping up with differentiating features of lean construction and tradition methods

description

summary of the video lecture

Transcript of Summary of Gregory Howell Lecture.docx

Page 1: Summary of Gregory Howell Lecture.docx

Summary of Gregory Howell lecture

Traditionally construction industry focused more on implementation of the contracts. The procedure

was to break up project into pieces and plan for it. Critical Path Method was one of the popular method

but over the period people started to complain as CPM controls time but, not cost as to complete in

time resources are increased. Productivity improvement was the next action. Howell and Glen looked

into foremen weekly plan and found out the success rate, it turned out to be 54% and this was observed

all over the world. They move on to describing the development of Toyota way or Pull Planning, he

describes engineer Ohno’s observation of inventory being a waste. They figure out that why sometimes

while increasing the productivity of a crew the project was going worse. This is because the work has

been messed up. In order to improve the productivity, the productivity of the work flow must be

improved. The general barriers to delay were illustrated with example as the change in the design,

material being shipped late etc. these works could be sorted if there was enough communication

between workers and the management team. An example illustrated were the MRI had to installed and

there was no way the team could have done it in that time frame but the MRI Company had an incentive

in completing the work in time so they have done partially, shows that unexpected things could have

turn up if things are more informed. In the Last planner system is the person executing the work plans

out giving an informed plan and shows the interdependencies of the crew.

In lean construction we are optimizing the project not each piece of work. The speaker talks about the

phases of work which starts with a Request and forms a commitment which when performed, can be

declared and then declare satisfaction. To improve project performance there must be impeccable

coordination as discussed earlier and production system design should be done for optimum project

benefits not task wise and lastly collective enterprise and this has to be done with everyone and

planning this way will help try to make better decisions to reduce the time, cost and complexity.

Another important point to note is to eliminate contingencies but at the same time there presence gives

more safety hence there is a tradeoff.

The next topic was about contracts, the first LCI meeting agreed that present contracts do not obstruct

Lean construction nor do they support. Relational contracting was discussed. In traditional practice the

persons who know why, what and how are separated but modifying we bring people together in an

integrated team with core and the peripheral group. This would increase the scope for optimization and

participants are better informed about the project. It is observed that the project become more safer

after implementation. There should more thought in where to apply this method as people have invest

their time in it. Target value design is a method which gives a challenge to the design team to work out

innovative ways to meet the target. Integrated Project delivery system was discussed with an overview

template. Concluding it with by saying that fundamental practices, conceptual foundation and having a

common language are very important and leading edge would be target value design and choosing by

advantage. Lean construction is now being applied at various places in the world and concluded it by an

example of block building contract in Nigeria which was very successful. Wrapping up with

differentiating features of lean construction and tradition methods

Page 2: Summary of Gregory Howell Lecture.docx