Summary Highlights of License Application Plan Technical ... · Michael Lee NRC MPL nrc.gov...
Transcript of Summary Highlights of License Application Plan Technical ... · Michael Lee NRC MPL nrc.gov...
* ,*'-.*. � *- - -� - a' - -----
Summary Highlightsof
Ucense Application Plan Technical ExchangeNRCIDOE Videoconference T2B3
September 16, 1998
The meeting summary of the License Application Plan Technical Exchange between the U.S.Department of Energy (DOE) and the U.S. Nuclear Regulatory Commission (NRC) is comprisedof these signed summary highlights, the meeting agenda (attachment 1), the attendance list(attachment 2), and the presenters slides (attachment 3).
* The Yucca Mountain Project Office is being re-organized into the Office of Licensing andRegulatory Compliance (Steve Brocoum, Director) and the Office of Product Execution (D.Spence, Director)
* DOE indicted that Repository Safety Strategy, Revision 2 is currently being revised to clarifythe rationale for going from the hypothesis to principal factors. Revision 2 is current for thecurrent design and DOE hopes to have it out when the Viability Assessment is released. Inthe future, DOE expects to produce Revision 3 for LA design.
* DOE indicated that data available as of August 1999, will be incorporated in the next versionsof the process models and TSPA.
* DOE indicated their willingness to talk to NRC in more detail about qualification of data.
* The NRC staff indicated that It needed more confidence in DOE's implementation of the QAprogram and this will continue to be an area of concern.
* DOE indicated that the Working Draft License Application will be available in August, 1999,but will not contain the LA Design. The LA Design information will be available later in year,the exact dates are not available because DOE is In the process of finalizing FY99 planning.
* DOE indicated that the Site Recommendation Report will include all the information requiredby the NWPA, supported by technical documents.
Sandra L. Wastler tian E. EinbergHigh-Level Waste and Uranium Regulatory Coordination Dive
Recovery Projects Branch Office of Civilian RadioactiveDivision of Waste Management Waste ManagementOffice of Nuclear Material U.S. Department of Energy
Safety and SafeguardsU.S. Nuclear Regulatory Commission
901200173 990106PDR WASTEWMI-1 I FDR
V
S.-. I
Attachment I
I -. lm t
Technical Exchange
License Application Plan-Viability Assessment Volume 4
September 16, 1998
8:30-8:45
8:45-9:00
9:00-9:30
9:30-10:00
10-00-10:15
10:15-11:00
11:00-11:45
11:45-12:45
12:45-2:45
2:45-3:00
3:00-3:30
3:30-4:00
4:00-5:00
Introductions
Opening Remarks
Introduction
Organization and Rationale of License Application Plan
DOE
DOE
DOE
BREAK
Evolution of the Repository Safety Strategy and its Relationto PreclosurclPostclosure Safety Case DOE
Performance Allocation and Identification of NeededInformation DOE
LUNCH
Discussion and Examples of Remaining Technical Work DOESite InvestigationDesign (and Design options and Alternatives)Performance Assessment
BREAK
Status of Quality Controls on the Technical Program DOE
Regulatory Program and Path Forward DOE
Concluding Discussions NRC/DOE
4.i d: : A is,.e .,
" A; : At~C
< ;. :~~~~~~~~~~~~~~~~~
.!~~~~~~~~~~~Atcmn 2
. ., A :
, C) ' ; -: :.
W' '. ,'
1 ;%.
'4 ' , .. . ..
;ATTENDANCE,-Ucens Applicatlon .Plan Technical Exchinge
.NRC VIdeoconhernce T2B3September. 16, 1998
Name Affiliation Address E-Mail Address TelephoneNumber
Sandra Wastler NRC SLWt @nrc.gov 301-415-6724
Jim York Booz, Allen, Washington, DC Jim-york rw. 202-626-1067Hamilton doe.gov
Alan Brownstein DOE Washington, DC 202-586-4973
Jack Bailey OCRWMlM&O/ Las Vegas, NV jack.bailey@ 702-295-4251TRW ynp.go0V
Steven Kraft NEI 17761 Street NW spk~nei.org 202-739-8116Washington, DC
Ralph Anderson NEI 17761 Street NW rda~nei.org 202-739-8111Washington, DC
Tim McCartin NRC Washington, DC [email protected] 301-415-6681
King Stablein NRC Washington, DC NKSE nrc.gov 301-415-7282
Michael Bell NRC Washington, DC MJB20nrc.gov 301-415-7286
April Gil DOEIYMP/AMP 702-794-5578
Bill Belke NRC 702-794-5047
E. Von Clark County 702-455-5184Tiesenhausen
Steve Frishman NV NWPO _ 702-687 3744
Jut., Treichel NNWTF 702-248-1127
Bob Andrews M90-PA 702-295-5549
Mal Murphy Nye County 360-945-5610
Chad Glenn NRC 702-794-5047
Tim Gunter YMSCO/AML 702-794-1343
R. Gamble MTS 702-794-1440
English Pearcy CNWRA 210-522-5540
.. 0 "OPOIN", I '.
"ATTENDANCEMUcol Appication Plan Technical Exchange
NRC Vldeoconfencoe T2B3. September16, 1998
Ray Wallace USGS Reston, VA Ray.Wallace r (202)586-1244_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ ___ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ w .d o e.g o v
Holly Dockery M&O/SNL Albuquerque,NM hodocke@sandi (505)284-3413a.gov
RD Snell M&O/DOE Las Vegas, NV (702)295-5601
Thomas Bruno M&O/JKRA Washington, DC tjbruno @ aol.co (703)862-9400m,
Steve Hanauer DOE Washington, DC steve.hanauer 1 (202)586-3547@ rw.doe.gov
Marshall David Scientech Washington, DC MDAVID @ scien (301)258-1868tech.com
Steve Brocoum DOE Las Vega, NV SteveBrocoum@ yp.gov
Ted Carter NRC Washington, DC THC1@ nrc.gov (301)415-6684
James Firth NRC Washington, DC [email protected] (301)415-6628
Mike Scott DOE/M&O Las Vegas, NM michaeLscott@ (702)295-5556ymp.gov
Andy Campbell NRC Washington, DC acc @ nrc.gov (301)415-6897
Chris McKenney NRC Washington, DC cam1 @ nrc.gov (301)415-6663
John Trapp NRC Washington, DC jst nrc.gov (301)415-8063
Mysore Nataraja *NRC Washington, DC msn1 @ nrc.gov (301)415-6695
Manny Comar NRC Washington, DC mmcl @nrc.gov (301)415-6074
Tae Ahn NRC Washington, DC tma~nrc.gov (301)415-5812
NSridhar CNWRA San Antonio, TX (210)522-5538
WPatdck CNWRA San Antonio, TX (210)522-5158
GWittmeyer CNWRA San Antonio, TX (210)522-5082
MJarzemba CNWRA San Antonio, TX (210)522-6828
WMurphy CNWRA San Antonio, TX (210)522-5263
*.~~~~~*. _________ -.~~~~~~~~~111LI111
-ATTENDANCEUcenso ApplIcafton Plan Technical Exchange
. NRC Vldeoconfernce T2B3:September 16,1998
MMiklin CNWRA San Antonio, TX
JWeldy CNWRA San Antonio, TX
Gustavo Cragnolino CNWRA San Antonio, TX
RGreen CNWRA San Antonio, TX
AChowdhury CNWRA San Antonio, TX
SHsiung CNWRA San Antonio, TX
SMohanty CNWRA San Antonio, TX
RJanetzke CNWRA San Antonio, TX
BMabrito CNWRA San Antonio, TX
(210)522-5207
(210)522-6800
(210)522-5539
(210)522-5305
(210)522-5151
(210)522-5209
(210)522-5185
(210)522-3318
(210)522-5149
DTumer CNWRA San Antonio, TX (210)522-21394. .1
Tim Sullivan DOE Las Vegas, NV (702)794-3389
Carol Hanlon DOE Las Vegas, NV (702)794-1324
Mike Lugo M&OJTRW (702)794-4761
Buck Ibrahim NRC AKIQnrc.gov (301)415-6651
Jean Yonkers M&O Las Vegas, NV (702)794-5497
John Greeves NRC JTG1 @nrc.gov (301)414-7437
David Brooks NRC DJB @ nrc.gov (301)415-7284
Giorgio Gnugnoli NRC GNG Q nrc.gov (301)415-7135
K. Cline MTS/BA . (702)794-5481
Robert Johnson NRC [email protected] (301)415-7282
Michael Lee NRC MPL nrc.gov (301)415-6677
Chris Einberg DOE Washington, DC (202)586-8869
Howard Larson NRC/ACNW (301)415-6805
Michael Weber NRC MFW 0 nrc.gov (301)415-6708
Philip Justus NRC PSJ @ nrc.gov (301)415-6745
Sc Q2 ; - -- ~~* ; , .,EIf,>;ATT liANCE r ;K i.: ; .* . UconsApiIi Plmn TchnIcal Exchnge
'+ v . . '- . R CV ldT6fi m2B33
Jeff Weaver M&O Licensing (702)295-2094
Homi Minwalla M&O SE/I (702)295-4995
Michael Voegele M&O (702)295-5520
Dennis R. Williams DOE (702)794-1447
Ken Ashe M&O Licensing (702)295-3964
Dennis Richardson R&L (702)295-4392
Delia Gwyn M&O SE/ (702)295-3964
E.P. Stroupe M&O, SE/I (702)295-3944
Bob Price NV Legis. (702)642-5669
Roxana VanGillen WPO-FCF (702)295-4596
Michael Frankle WPO-FCF (702)295-4479
Bob Andrews M&O-PA (702)295-5549
Lee Shephard DOE Washington, DC (202)794-5526
Dan Wilkins TRW (702)295-5193
Al Eddebbarb M&O-NEPO (702)295-6606
James E. Clark OQA-QATSS (702)295-1629
Krishna R. Iyorgar M&O-R&L (702)295-4517
RobertaStambaugh M&O-SEII (702)295-3972
Joe Price DOE/OM (702)794-1441
Bill Seddon AECIJDOE (702)794-5422
Larry Hayes M&O-NEPO __ (702)295-5648
Phil L. Oberlander M&O-NEPO (702)295-3402
Hugh A. Benton M&O-WPO (702)295-4389
Abe Van Luik DOE (702)794-1424
Bernard J. Vema DOE _ (702)794-1374
Donald A. Nitti M&O-WPO (702)295-4587
Mark Tynap DOE _ _ (702)794-5457
4.
I
ii
:1
.r
I
I.I..16t
1,�It
T,
A, I. ;I�i
I-- I
I I
i '.�11
t,i� -
I . "! I,,- , 't-, " A. , .1 4' , �- ., )I' --
Attachment 3
!4�11MMMA I "-11:1 I- ~~~~~~~~~~~~~~~~~~~~~
YUCCA iMOUNTAIN
PROJECT I- _________ �4�SS�
Introduction
Presented to:DOE/NRC Technical Exchange onthe Technical Guidance Document for License Application Preparation
Presented by:Tim GunterLicensing Engineer, License Application TeamTYucca Mountain Site Characterization Office
.September 17, 1998 U.S. I)epartment of EnergyOffice of Civilian Radioactive
Waste Management
��
Purpose of the Technical Exchange
* Discuss the Technical Guidance Document forLicense Application Preparation (TGD)
- DOE's principal vehicle for building on NRCguidance for development of the LicenseApplication (LA)
* Describe TGD development process* Describe how the NRC's Key Technical Issues
(KTI) are being integrated into the TGD
OimfiOl796 pV12"~R=*~P96 2
-W iv ", 1.0 - I I 1-1 ",-A,
.I - , i
. - I I., � .1-1 , -- I_#
Purposes of Technical Exchange (continued)
* Address potential impacts of 1 0 CFR 63 on TGDcontent and schedule
* Describe planned organization of TGD and LA* * Discuss TGD content
* Seek NRC feedback on DOE's-approach
O~mwf"IM76WVIVWNRJS%9 3
I . - :. -M I ,
Technical Exchange AgendaTechnical Guidance Document for License Application
September 17, 1998
1:00 pm
3:00
5:00
Opening RemarksIntroductionRole of Technical GuidanceDocument in License ApplicationConsideration of Part 63 inTechnical Guidance DocumentDevelopmentBreakOrganization and Content ofTechnical Guidance DocumentNRC PerspectivesConcluding DiscussionsAdjourn
AllTim GunterApril Gil
Mike Lugo
Mike Scott
NRCAll
04abOOI 796 WV12MU~~~~~~CiS.PW 'I
YUCCAMOUNTAIN
PROJECT.a1 .ui.. I -
Role of the Technical Guidance Documentin the License Application
Presented to:DOE/NRC Technical Exchange onthe Technical Guidance Document for License Application Preparation
Presented by:April V. GilLicense Application Team LeadYucca Mountain Site Characterization Office
U.S. IXepanment of EncrgySeptember 17, 1998 Omanrce of Civilian RadioactiveSeptember 17, 1998 Wa2st Management
.4. .4~ ~ ~ ~ ~~ ~~~~~~* .'..- '. *44~. :4. :' an .4'1 As .' -V ' S.ttC t-
Purposes of the TGD
* Provide content and organization guidance toLA authors.
- LA development schedule requires guidance toauthors
* Serve as communication tool to ensure LA willbe as complete as possible at time of docketing
012-091790ppVI2SJHRClSeM9 2
Client I I In
Scope of the TGD
* TGD provides guidance for LA authors oncontent and layout of the LA
* Intent is to provide similar information to thatprovided in an NRC Standard Review Plan, butintended for author rather than reviewer
* TGD is a guidance and not a requirementsdocument
Gi12-09 1798PWI2SlNRCISe"8 3
. I"Q tIIII.%..nMII �' - .1, - 11 .
RNMORM"
Sources of Guidance for LA Authors
* TGD- Layout- Content- Acceptance criteria- Writers Guide (Appendix)
* LA Management Plan (Mechanics ofdevelopment process)
* Technical sources (by reference in TGD)
00*1 7UW t2S*WJS~ 4
TGD Development Approach
Using NRC standard review plans as models- NUREG-1567: Standard Review Plan for Spent
Fuel Dry Storage Facilities (draft)- NUREG=1536: Standard Review Plan for Dry Cask
Storage Systems* Unlike standard review plans, TGD audience is
LA author- Language differs, but layout is similar
0Q41?U M125"%W" S
"tt-q,. I I � M ---=
TGD Development Approach (continue
* High priority in determining where NRCguidance and industry codes and standards arepotentially useful or applicable
* Although previous guidance documents are nolonger current, technical criteria have been usedwhere considered likely to be appropriate (e.g.,LARP and FCRG)
* TGD contains placeholders for regulatoryguidance and industry standards not yetanalyzed
C. ~~~~~q9~~~ ~ ~ ~ 9I
-- -C ~ ~ ~ ~ ~~~~ ~ ~ ~ C.~~~~~fl..¶~~~~~~~j<V~~~~~l 'A.'.ifl' *~~~~~~~~~~~~~~~$*'U,~~~~~~~~~" ~.
TGD Development Schedule
* Rev 0 approved September 1998* Subsequent revisions will incorporate:
- Additional regulatory guidance as it becomesavailable
- Industry standards to the extent feasible andappropriate
- Part 63* Final Part 63 in summer 1999 essential to timely
development of TGD and LA
o~~ ew ?W ~~~/12~~ftd'~~C~~iW~~W V
a, .- > - - .> - '
TGD Development Schedule (continued)
FY98 FYOO
TGD RcvO1
Working Draft LAproduction begins I
rGD Rcv 2 Submit LA
WDLA compicte
Acceptance Draft LAproduction begins
TGD Rev I
GQOSW p~'2S~i~~iq~a
-. I..... .- - - -1. . . ". k-, -1 - 11 .. I I � .� - .1.1- 11 .11-... I �. .I I I. -
Key Technical Issues
* DOE recognizes role of KTls in helping defineresolution process for important issues
* KTI acceptance criteria being incorporated intoTGD as questions resolved or criteria clarified
* Incorporation of acceptance criteria in TGD- Rev 0 incorporates acceptance criteria about
which DOE has no questions- Subsequent revisions will incorporate additional
acceptance criteria after more comprehensivereview and clarification if needed
6.1209X 9 ppVl2S'RC 8eg 9
I
-11- .1 . Id. S.. &_,25
Summary
* DOE plans to use TGD to develop LA and makeuse of regulatory and industry precedents andguidance (including KTIs) to extent feasible andappropriate
* Close coordination with content of 1 0 CFR 63and IRSR acceptance criteria critical to ensureTGD contains correct and adequate criteria forLA development
* Feedback on approach presented todayrequested
GAW0G196 piMW12&%dnCjSM" 10
-o-g F:
YUCCAMOUNTAIN
PROJECT
Organization and Content of the TechnicalGuidance Document
Presented to:DOE-NRC Technical Exchange on the Technical Guidance Document for LicenseApplication Preparation
Presented by:Michael ScottLicensing SupervisorCRWMS Management & Operating Contractor
U.S. D)cparlntcnl of EnergyOffice or Civilian Radicoacive
September 17, 1998 Waste Management
Purpose of Presentation
* Provide overview of organization and contentof TGD chapters
* Discuss guidance related to codes,standards, and regulatory guidance
* Explain how KTIIlRSR acceptance criteria areaddressed
ScottOg I 7DSppV1 25tNRC/S&M9 2
* -4"jg&,AibgtAJg --. .L I. * ~ 'lJ"A ~ .r C , iv"- i ''~i'. f-ii,- i
TGD/LA Organization
* TGD chapter organization corresponds toplanned LA chapter organization
* LA organization based on:- Project Integrated Safety Assessment format- LARP/FCRG- Regulatory Guide 1.70, Standard Format and
Content of Safety Analysis Reports for NuclearPower Plants
* Format chosen is the one DOE believes mostclearly presents the information needed tosupport the safety case
SCfOW 1 798 PPIVl 25Jhi1C~sew 3
TGD/LA Organization (continued)
In addition to chapter layout corresponding toLA layout, TGD contains:
- Introduction that explains how to use thedocument and discusses issues pertinent toTGD and LA development
- Appendix showing cross-walk between currenthigh-level waste regulations and TGD/LAsections
- Appendix containing a writers' guide for LA
ScoflmcI g8 pwt2swnRCIS" 4
Overall LA Organization
* Per 10 CFR 60, LA includes generalinformation and safety analysis report (SAR)
* Chapter-1 contains general informationrequired by 10 CFR 60
* Chapters 2 through 14 comprise the SAR
SwUWoI 79.pptJ2WMNC/SePW 5
.-A 01 W#WI"fAITVXIO�v.?-."If-A-w
LA Chapter Layout
Scflg 76 I744C/~pI~ 6
.- - wwwxb~~~~~~~~~~~~~~~~~~~~-.-..-. . '. ~ s .~.V
LA Chapter Layout (coninued)
Some topics will have brief discussions in theLA with more detail in separate documents,consistent with industry practice
- Quality assurance- Security and safeguards- Emergency plan- Proposed technical specifications
scof"In984wom25wRCs""g 7
--I ,,,,man kind. i 11 -11-��-IinL;-,16.,�wl '. - - 11 1-1 Our i W .,
I - - i
Chapter 1 - Introduction and GeneralInformation
* Contains general information per 10 CFR60.21
- General description- Material incorporated by reference- Schedules- Description of site characterization work and
changes from Site Characterization Plan- Security and safeguards (summary)- Agents and contractors- Statements of compliance
Scott I ,ga ppo marsCfepw 8
I ; -1---.1-1�1
Chapter 2 - Conformance WithDesign Criteria
* Chapter 2:- Ties together information from other design
chapters- Relates repository design to technical criteria in
10CFR60 Subparts E and F- Demonstrates how the design supports the
postclosure safety case- Identifies principal codes, standards, and
regulatory guidance applicable to repositorydesign and construction
Scot1O I 79a.ppV' 251NnC/Supga 9
,-- '.-k. -I -
Chapter 2 (continued)
* Chapter 2 (continued)-- Presents the classification methodology for
structures, systems, and components andsummarizes those important to radiologicalsafety and to waste isolation
- Summarizes how major design features complywith radiation safety and waste isolation criteria
* Recognize design criteria will likely not beincluded in Part 63
* Chapter 2 will remain a "rollup" of complianceinformation to show that the facility designsupports meeting repository performanceobjectives
Sco1O91 79B ppVi25,/NRCJSep9B 1 0
Chapter 3 - Site Characteristics
* Presents site description in terms of geology,hydrology, geochemistry, and other topics
* Basic layout similar to LARP but will notdiscuss compliance with site-relatedsubsystem performance objectives
* Site Description Document will be primaryreference
* Chapter will focus directly on site descriptioninformation to support licensing
ScotMO 1 798 ppVI 2SiNFC/Sep9fl 1 1
Chapter 4 - Repository Design
* Includes surface and subsurface repositorydesign excluding the engineered barriersystem
* Provides for each system:- Design bases- Design description- Design evaluation
ScoUWMS7~8ppJ12SMPVCSep98 12
Chapter 5- Waste Package Design
* Describes waste forms* Describes waste package
- General description- Material selection- Thermal design- Criticality design- Structural design- Shielding design
* For each component, provides design bases,design description, and design evaluation
ScoNogI 798ppl l 25NRC/Sep98 13
Chapter 6 - Engineered BarrierSystem (Excluding the Waste
Package) Design
* Describes engineered barrier system (EBS)excluding waste package (i.e., describes theunderground facility)
• Discusses the EBS environment* For each EBS component, provides:
- Design bases- Design description- Design evaluation
ScoftO91798 ppVI25/N~rC/eP9a 1 4
- - -. . . . I . . ... . .. I I .. .-- .~ i * -. a
Chapter 7 - Preclosure RadiologicalSafety Assessment
e Describes:- Approach- Source term- Design Basis Event definition- Potential releases- Atmospheric dispersion- Dose calculations
Swtong I M W ppf2SNRClSep98 15
Chapter 8 - Performance of theRepository After Permanent Closure
Describes:- Approach to performance assessment (PA)- Systems and subsystems input to the PA- Evaluation of undisturbed performance- Evaluation of disturbed performance,
ScotIog178wpVI2SwNRCI&ep 16
Chapter 9- Radioactive WasteManagement
Provides design bases, design description,and design evaluation for:
- Liquid low-level waste management systems- Solid low-level waste management systems- Gaseous low-level waste management
systems- Mixed waste management systems
* Describes source terms (low-level radioactivewastes of each type)
ScoftogI 798 ppVI 25JNRCJSeP98 17
Chapter 10- Radiological Protection
Describes:- Radiological protection program- ALARA design features
* Shielding* Ventilation* Instrumentation
- Dose assessments
ScontOg I ne.ppV1 25/RC/Sep98 18
Chapter 1 1 - Conduct of Operations& Related Topics
Chapter 1 1 contains various topics that donot clearly fall elsewhere. Discusses:
- Facility operations, testing, maintenance, etc.- Organization and staffing- Administrative controls- Procedures- Records and reports- Training
SCottW 9n8 pptll25NRC.?SeP98 19
-_.. __ -AM A-0JU.-W -_. _. -
Chapter 1 1 (continued)
* Chapter 1 1 discusses: (continued)- Site markers- Operating controls and limits- Emergency planning (reference)- Proposed technical specifications (reference)- Requirements for additional technical
information (1 OCFR60.21 (c)(1 4))
ScoUtO 1 7g8.ppVI25/NRC/Sep98 20
Chapter 12- PerformanceConfirmation
* Describes:- Performance confirmation plan- Performance confirmation for:
* Natural barriers• Repository structures, systems, and components* Waste package and EBS
- Radiation protection for above activities- Analysis of changes from performance
confirmation baseline
Scott=gi798.ppVl 2VlRC/Sep98 21
Chapter 13 - Land Ownership andControl
* Discusses:- Acquisition of the controlled area- Plans for regulating land use outside the
controlled area- Access controls for the repository
-mmume 79 ptlv25lmmsep9a 22
- . - N , -4?A � --�" r , ,, L'i � -". I-,' -� 1. _., -.4 . ".:.,
Chapter 14 -Quality Assurance
* Chapter will be brief, consistent with industrypractice
* Refers to Quality Assurance Requirementsand Description (QARD) for details on QAprogram
ScoftMOlIM ppV125#NRcmSp9 23
-011. .�AL� �t� I.- I i��
Basic TGD Format
* Each chapter contains five sections, similarto layout of NUREG-1567, Standard ReviewPlan for Spent Fuel Dry Storage Facilities(draft):
1: ObjectiveII: Guidance TopicsIll: Regulatory RequirementsIV: Acceptance Criteria and GuidanceV: References
5coMM0179a PPV125/N'RCISeP98 24
I -.I.- I.'I--1--II-- - -1. � - � t. --.. --
TGD Guidance* TGD tells author what information and
analyses need to be presented in the LA andwhat documents with which to statecompliance
* Provides acceptance criteria based onregulatory guidance (e.g., IRSRs, LARP whereconsidered appropriate)
* Similar level of detail to draft NUREG-1567* Prefer to use existing guidance and
standards where appropriate and applicableto reduce burden on applicant and regulatorand to take advantage of proven technology
Sc=IT"p 1~SMC~S" 25
.....
Level of Detail
* TGD Introduction contains general guidance- Level of detail is that needed to present safety case
and support NRC's "reasonable assurance" finding- Site description: More detail than for analogous
topics in site description in power plant final safetyanalysis report (FSAR)
- Design* Important to safety or waste isolation, unprecedented:
Similar to design detail in power plant FSAR* Important to safety, precedented: Similar or greater detail
than for similar topics in preliminary power plant SAR* Not important to safety: Much lower level of detail
Scotl Il798.ppt/12SJNRC/Sep98 26
Level of Detail (continued)- Performance assessment: No SAR analog and
crucial to assessing acceptability ofrepository; substantial detail
- Accident analysis: Similar to FSAR analysesTGD does not contain detailed, prescriptiveguidance on level of detail needed for LA
- DOE's Licensing staff will provide guidance totechnical leads and ensure detail needed tosupport NRC's reasonable assurancedetermination is provided
- Interactions with NRC during LA developmentand Project's QA classification process willalso help reach correct level of detail
Scoi1091798.ppV12W/NRC/Sep98 27
I.,��.i:.-..,.-��,�4.-�,�'..--�--71..�.-�,-�-.."-..�--� �6� -- - �
Sources of Guidance
* NRC Standard Review Plans* NRC Regulatory Guides* Industry codes and standardse Issue Resolution Status Reports* NUREGs* Staff Technical Positions
ScotiO91 n98.PPVI 25/NRCWSep91 28
�- �- -1-1- . --- -- - I . . '- ' -16- �'
Identification of Codes, Standards,and Guidance
e TGD Rev 0 provides guidance for use ofcodes and standards, as well as NRCguidance
- Relatively detailed, firm guidance- "Placeholders" (applicability not fully
determined)* Applicability being determined by systematic,
documented review of potential sources* Final form of the direction to be provided in
the TGD is under evaluationSco?109 I 798.ppt/l25NRC/Sep98 29
Treatment of NRC Key TechnicalIssues
* TGD (Section IV of each chapter) showswhere in LA to address each IRSRacceptance criterion
* Requires discussion in LA of:- NRC perspective on subissue status- DOE perspective- Demonstration that acceptance criteria are met- Description of information to be obtained and
provided after LA submittal if any aspects notfully resolved
Sco~ttO9 79B.pp Vt25NACrtep9B 30
Summary
* TGD provides relatively detailed guidance to LAauthors based on analysis of available regulatoryand industry information
* LA layout intended to most clearly presentinformation needed to support licensing case
* TGD layout corresponds to LA layout* TGD addresses NRC KTls at the subissue and
acceptance criterion level
ScoUngl 798.pptV1 2WNtRc/sePqe 31
-~~~~ ~ ~ ..-:- -11 ;-
..~-e I: -..S
YUCCAMOUNTAIN
PROJECT
II
i
iIk
I
Consideration of 10 CFR Part 63 Rule inTechnical Guidance Document Development
l'resented to:D)OIF'/NRC Te'cnical Exchange onthe Technical Guidance Document for Liccnse Application lPreparation
P'resented by:Migulel A. LugoLicensing ManagerCWMS Management & Operating Contractor
September 17, 1998I J.S. D)cp.1iilt'llnt oI Enriigy
O fIie of (:ivilian IHtadioa:ctive
Wazslt Mlanagelln-1Al
I �ll-H,;.�.1--l�:.,.,,,",.,L�,�.",-,.,.--�"--%'�.--� .... . - ,- -.A*aAw= i
Purpose of Presentation
* Describe general approach taken to address10 CFR Part 63 rule in TGD
* Discuss assumptions about 10 CFR Part 63changes reflected in TGD Rev 0
Lugao9l 798.ppI~l 2544RCISep98 2
I �'- 1 4-. ��! "WA; I '-I.... -�' .1--'r- .- - �-' �-- - . - - - -
I 0
Consideration of Part 63 in TGD
* Added a note to the beginning of eachTGD Rev 0 chapter
- Expected changes to regulations applicable toeach chapter
* Subsequent revisions of the TGD willPart 63 rule, as information becomes
addressavailable
LugoOg I 798.pp VI 25fIMCJSep96 3
Assumed Changes Noted inTGD Rev O
Postclosure CriteriaEmphasis placed on overall repositoryperformance and showing contribution ofindividual barriers
- Noted upcoming modification to compliance with§60.112 (total system performance objective)
- Deleted explicit compliance with §60.113(subsystem performance objectives)
- Deleted explicit compliance with siting criteria§60.122 (siting criteria)
- Deleted explicit compliance with design criteria inSubpart E
LugoO91 798.ppVl 25NRC/Sep98 4
.v . . - 0
Assumed Changes Noted inTGD Rev 0 (continued)
Postclosure Criteria (cont'd4The following potential changes were notexplicitly addressed:
- Performance assessment methodology- Reference biosphere and critical group- Stylized human intrusion analysis
Lugoog I 798.ppVl 25/NRC/Sep9B 5
. I � -. 1 - , _: -
.. .., - �r� ..--- I -1-._I____-, ---. 1.---
Assumed Changes -Noted inTGD Rev 0 (continued)
Preclosure CriteriaEmphasis placed on compliance with overallperformance (normal operations and accidentconditions)
- Deleted explicit compliance with preclosuredesign criteria in §60.130 thru §60.133
* Potential changes in emergency planning notexplicitly addressed
- TGD Rev 0 already invokes guidance from otherNRC regulations/regulatory guides
LugoO91 79a ppVI 25/NRC/Sep". 6
Assumed Changes Noted inTGD -Rev 0 (continued)
Other Provisions* Deleted direct references to NUREG-1323
(LARP) and DG-3003 (FCRG) -: Retained technical discussions as appropriate
.* No changes assumed to administrativerequirements
Ii
LugoO9179e.pptfl25MaCrepqe 7
,, . . . ..... . ....-. - .. " - p .S -ry
:; ~~Summary:
* Part 63 is being and will be implemented in TGDand LA as it becomes- available
*: The W~orkin'g Draft LA will reflect DOE's bestunderstanding oftPart 63,'based on'the,
- proposed rule- h . I
LugoO9I798.ppVlZ25MC4Sep9S5 8. t