Sudhagad Tank Cleaning 2009
Tank 1 Cleaned in
2008
Tank 2 Cleaned in
2009
Ready to start
Day 1
• Session 1 – Removed water from tank 2, first 2 hours of haphazard work.
• Session 2 – Learnt from mistakes, more structured and fast work. 2 chains worked in the tank. 40 % work done
Tank 1 Tank 2
Chain 1 Chain 2
Day 2
• Session 1 – Good start, fast work for first 3 hours• A short break of half an hour before lunch, this really
helped us a lot• Session 2 – Powerplay……… The fastest and most
energetic work, we threw out all the mud in 20 min….. And then all the giants came and piled up the boulders in an hour, about 50 boulders……
• Saturday evening 5 pm, we did the wind up…….. Tremendous efforts by the team
• Saturday evening 5 pm, we did the wind up…….. Tremendous efforts by the team
Kshitiz, Durgamitra and Girimitra Pratishthan
The forts stood for us for centuries, now its our turn
Its one life friends, and we are the only ones who care for forts
Lets come together and do this, just as we do on Sudhagad
Team
• Jayesh, Minal, Varada, Rahul, Kedar, Kiran, Nikhil, Umesh, Aniket, Shatrughna, Kiran, Jui, Jayesh, Deepak, Atul, Vivek, Saurabh, Pradeep, Dipankar, Sachin, Yatin, Amit, Mangesh, Mahesh, Vaibhav, Phulaji, Bhushan, Mr. Mhatre, Isha, Santosh, Saurabh, Abhinav, Deepa, Parag, Ajay, Amey
• Gaurav, Mr. Bhuskute, Puranik Sir (background work)