Transcript of Successful Program Execution Center for Systems and Software Engineering (CSSE) Executive Workshop...
![Page 1: Successful Program Execution Center for Systems and Software Engineering (CSSE) Executive Workshop 15 March 2006 Center for Systems and Software Engineering.](https://reader035.fdocuments.us/reader035/viewer/2022062516/56649d3f5503460f94a1892e/html5/thumbnails/1.jpg)
Successful Program Execution Successful Program Execution
Center for Systems and Software Engineering (CSSE)
Executive Workshop
15 March 2006
Center for Systems and Software Engineering (CSSE)
Executive Workshop
15 March 2006
Marilee J. WheatonGeneral Manager
Systems Engineering Division
Marilee J. WheatonGeneral Manager
Systems Engineering Division
©2006 by The Aerospace Corporation ©2006 by The Aerospace Corporation
![Page 2: Successful Program Execution Center for Systems and Software Engineering (CSSE) Executive Workshop 15 March 2006 Center for Systems and Software Engineering.](https://reader035.fdocuments.us/reader035/viewer/2022062516/56649d3f5503460f94a1892e/html5/thumbnails/2.jpg)
2
•People and teamwork
•Controlling risk
•Processes
•Accountability
•Cost and schedule estimating
•Stability
•Industrial base
Key Attributes of Successful Program Execution
![Page 3: Successful Program Execution Center for Systems and Software Engineering (CSSE) Executive Workshop 15 March 2006 Center for Systems and Software Engineering.](https://reader035.fdocuments.us/reader035/viewer/2022062516/56649d3f5503460f94a1892e/html5/thumbnails/3.jpg)
3
People and Teamwork
•Contractor execution team and PM should be first line of defense for mission success
– Second line is contractor functional organization check and balance
– Third line is government, FFRDC and SETA team
– Government is not staffed to be the first line of defense
•Space Quality Improvement Council (SQIC)
![Page 4: Successful Program Execution Center for Systems and Software Engineering (CSSE) Executive Workshop 15 March 2006 Center for Systems and Software Engineering.](https://reader035.fdocuments.us/reader035/viewer/2022062516/56649d3f5503460f94a1892e/html5/thumbnails/4.jpg)
4
What Is The SQIC?
•Space Quality Improvement Council– An industry forum with government sponsorship– Identifies and addresses common problems and
solutions
•Executive-level engineering and quality control leadership from the NSS contractor community– Mission assurance processes– Product quality issues that affect all (Example: FPGAs)– Acquisition policy affecting quality
•Facilitated by The Aerospace Corporation– Carries forward consensus industry recommendations
to government sponsors– Not for attribution
![Page 5: Successful Program Execution Center for Systems and Software Engineering (CSSE) Executive Workshop 15 March 2006 Center for Systems and Software Engineering.](https://reader035.fdocuments.us/reader035/viewer/2022062516/56649d3f5503460f94a1892e/html5/thumbnails/5.jpg)
5
Space Quality Improvement Council (SQIC)Key Accomplishments
•Contractor data sharing
– New SQIC/GIDEP NSS Advisory Forum, operational Sept. 2005
– Anomaly/mission failure investigations
• Standardized MOU developed and ready when needed
•Selective specs and standards reintroduction
– Industry representatives on all standards committees
– Industry consensus on specs and standards to put on contract
• SMC and NRO requiring that these be on new contracts
– Common playing field in bidding executable contracts
– Key element in assuring mission success
•Helps government be a “smarter buyer”
![Page 6: Successful Program Execution Center for Systems and Software Engineering (CSSE) Executive Workshop 15 March 2006 Center for Systems and Software Engineering.](https://reader035.fdocuments.us/reader035/viewer/2022062516/56649d3f5503460f94a1892e/html5/thumbnails/6.jpg)
6
Smart Buyer 1
•Helping System Program Directors (SPDs) and acquisition executives become smarter NSS buyers
– Be aware of the demands and expectations placed on your industry counterparts
Smart Buyer 2
•Now that the buyer understands the contractor environment…
The buyer must formulate an executable plan and maintain an executable baseline.
![Page 7: Successful Program Execution Center for Systems and Software Engineering (CSSE) Executive Workshop 15 March 2006 Center for Systems and Software Engineering.](https://reader035.fdocuments.us/reader035/viewer/2022062516/56649d3f5503460f94a1892e/html5/thumbnails/7.jpg)
7
How Do We Control Risk?
•Four variables in project management: cost, schedule, performance, and risk
•Need to define risk rigorously and cap it at an acceptable level
• If you cap the other three variables, risk grows continuously– Example: 1990s NASA
Mars missions, which failed
Assertion: Capping risk and driving schedule hard leads to best cost performance
![Page 8: Successful Program Execution Center for Systems and Software Engineering (CSSE) Executive Workshop 15 March 2006 Center for Systems and Software Engineering.](https://reader035.fdocuments.us/reader035/viewer/2022062516/56649d3f5503460f94a1892e/html5/thumbnails/8.jpg)
8
How Do You Cap Risk?
•Use standards for engineering and manufacturing
– Appropriate test program, robust QA, PMP, etc.
•Rigorous system engineering and test
– Example: JPL Mars Rover “incompressible test list”
– Test like you fly, fly like you test
•Manage risk at a sufficiently senior level on a program
– Allowing lower levels to trade mission success for cost and schedule leads to unbounded risk
![Page 9: Successful Program Execution Center for Systems and Software Engineering (CSSE) Executive Workshop 15 March 2006 Center for Systems and Software Engineering.](https://reader035.fdocuments.us/reader035/viewer/2022062516/56649d3f5503460f94a1892e/html5/thumbnails/9.jpg)
9
How Do You Cap Risk? (Cont.)
•Government/industry team manages risk incrementally
– Robust mission assurance tailored to risk assessment
– Contractor uses “buildup” process in design and test to define and manage risk
– Establish confidence at each major step—not just at the end of the program
– Find and fix defects early
•Establish environment that encourages problem reporting
– Example: Weekly Watchlist (“No Ambushes”)
![Page 10: Successful Program Execution Center for Systems and Software Engineering (CSSE) Executive Workshop 15 March 2006 Center for Systems and Software Engineering.](https://reader035.fdocuments.us/reader035/viewer/2022062516/56649d3f5503460f94a1892e/html5/thumbnails/10.jpg)
10
Processes
•Use validated processes that ensure predictable, repeatable results– Processes represent lessons learned and best
practices from past experiences– Help prevent repeating mistakes
•Rigorously manage the baseline implementation•Fund and manage disciplined, validated technology
insertion•Require credible independent assessments prior to
program initiation and at key milestones
![Page 11: Successful Program Execution Center for Systems and Software Engineering (CSSE) Executive Workshop 15 March 2006 Center for Systems and Software Engineering.](https://reader035.fdocuments.us/reader035/viewer/2022062516/56649d3f5503460f94a1892e/html5/thumbnails/11.jpg)
11
Processes (Cont.)
•Use standards and measure performance against those standards– Put core specs and standards on contract
– Examples: PM&P, SE, test– Government program office and FFRDCs ensure
that “best practices” are being used
•Independent flightworthiness and mission assurance certification
– Rigorous EELV mission assurance process has 2000 verification tasks prioritized against risk assessment
– Underpins “thumbs up” in Flight Readiness Review (FRR)
![Page 12: Successful Program Execution Center for Systems and Software Engineering (CSSE) Executive Workshop 15 March 2006 Center for Systems and Software Engineering.](https://reader035.fdocuments.us/reader035/viewer/2022062516/56649d3f5503460f94a1892e/html5/thumbnails/12.jpg)
12
Accountability
•Nearly every failure in space systems resulted from a breakdown in accountability
•Need clear definition of accountability on government/contractor team– At every organization level and flows down to
individuals executing program
– Key program people remain in the job long enough to ensure they are accountable for their decisions that affect mission success
![Page 13: Successful Program Execution Center for Systems and Software Engineering (CSSE) Executive Workshop 15 March 2006 Center for Systems and Software Engineering.](https://reader035.fdocuments.us/reader035/viewer/2022062516/56649d3f5503460f94a1892e/html5/thumbnails/13.jpg)
13
Accountability (Cont.)
•Key roles of government– Define requirements– Set risk level and assure responsible risk management– Ensure that proper practices are used– Incentivize contractor team and assess performance
•Contractor balances holistic enterprise perspective and tailored program needs
– Line organizations are accountable for the product
– Functional organizations are accountable for the processes
– Prime takes accountability for the quality of output by subcontractors and vendors
•Streamline government-industry decision-making process: In-plant representation
![Page 14: Successful Program Execution Center for Systems and Software Engineering (CSSE) Executive Workshop 15 March 2006 Center for Systems and Software Engineering.](https://reader035.fdocuments.us/reader035/viewer/2022062516/56649d3f5503460f94a1892e/html5/thumbnails/14.jpg)
14
Cost and Schedule Estimating
•Recognizes that best value is not necessarily lowest cost bid
•Government must place value on non-deliverables essential to mission success (Examples: SE, MA, QA,…)
– Then industry will also value them
– Exclude “name-that-tune-in-three-notes” bids
•Has a well-established Independent Cost Estimating (ICE) and program control function
•Budget program to 80% confidence, including a management reserve sized by risk
– Expend reserves to execute unforeseen elements of baseline program—not new requirements
![Page 15: Successful Program Execution Center for Systems and Software Engineering (CSSE) Executive Workshop 15 March 2006 Center for Systems and Software Engineering.](https://reader035.fdocuments.us/reader035/viewer/2022062516/56649d3f5503460f94a1892e/html5/thumbnails/15.jpg)
15
Stability
•Stable, manageable baselines—requirements, budget, and schedule
– Manage necessary but unplanned changes
– Rigorous systems engineering process for assessing impact of new requirements
– New requirements must come with new funding
•Allows trade spaces vs. “cast-in-concrete” requirements
– Capabilities, cost, and schedule
•Architectures that allow right-sized programs (can be executed in about 5 years)
– Regulates appetite of user community
![Page 16: Successful Program Execution Center for Systems and Software Engineering (CSSE) Executive Workshop 15 March 2006 Center for Systems and Software Engineering.](https://reader035.fdocuments.us/reader035/viewer/2022062516/56649d3f5503460f94a1892e/html5/thumbnails/16.jpg)
16
Industrial Base
•Compete when in the best interests of the government– Government should recognize the need for stability,
longevity, and performance of industrial base
•Government aligns contract and fee structure to balance risk between government and contractor– Example: Titan IV contract
•A world-class supplier base– Multiple sources, particularly at sub-vendor level
•Government should require and enforce subcontract management plan– Put it on contract (How do we evaluate and enforce?)
![Page 17: Successful Program Execution Center for Systems and Software Engineering (CSSE) Executive Workshop 15 March 2006 Center for Systems and Software Engineering.](https://reader035.fdocuments.us/reader035/viewer/2022062516/56649d3f5503460f94a1892e/html5/thumbnails/17.jpg)
17
Knowing When We Are Turning the Corner
•Effective programs that meet user demands with 100% mission success
•Efficient execution—meeting cost, schedule, and performance baselines
•Retirement of program risk as a function of time is measurable and visible
•Government and contractor teams meet their commitments
Attributes of World-Class Industry/Government Acquisition Team
Promises Made = Promises Kept