Substantial Completion Blues

download Substantial Completion Blues

of 8

Transcript of Substantial Completion Blues

  • 7/31/2019 Substantial Completion Blues

    1/8

    SUBSTANTIAL COMPLETION BLUES

    Every owner and general contractor is generally familiar with the concept

    of Substantial Completion. From a scheduling standpoint, it is the

    focal point of everyones attention from the very beginning of a project

    until well, when the project is substantially completed. Despite this

    intense focus, disputes about whether substantial completion is actually

    achieved on a given date abound across the construction landscape.

    These disputes often turn into litigation for no reason other than the par-

    ties were not very clear on what they meant by substantial completion

    when they signed the construction contract.

    From the standpoint of courts and judges, substantial completion is

    important in deciding whether a party has breached a construction con-

    tract, and when relevant statutes of limitation begin to run with respect

    to defective work. Most courts use the same denition utilized in most

    construction contracts, namely that substantial completion occurs when

    the owner is able to use the project for the purpose intended, or some-

    thing similar to that. Most construction contracts, including the AIA

    forms, have that kind of generic description of substantial completion.

    Of course, there are many other contract provisions that are tied to

    substantial completion, including liquidated damages, delay damages,

    payment of retainage and similar matters.

    However, despite the signicance of substantial completion to owners,

    contractors and subcontractors alike, it is quite apparent to construc-

    tion litigators that very little attention is paid to the actual denition of

    substantial completion used in a construction contract, or the unique

    circumstances of a particular project. This is surprising, given that all

    construction projects are clearly not alike. In many cases, the generic

    denition referenced above simply does not get the job done for any of

    the parties involved. It rarely works for the owner.

    Properly dening substantial completion is critical from the standpoint

    of meeting expectations and avoiding disputes. The concept of ben-

    ecial occupancy, the standard contract formulation, can be subject to

    many different interpretations. A contractor might say that a certicate

    of occupancy (whether temporary or permanent is a debate all by itself)

    is dispositive as to the determination of a substantial completion date.

    An owner might construe the situation more strictly, and say that the

    CONSTRUCTION LAWREVIEW

    November 2004

    www.alston.com

    Inside:

    Announcement 3

    Case and Legislative 3

    Updates By State

    Florida 3

    Georgia 3

    Mississippi 4

    New York 4

    South Carolina 4

    Virginia 5

    Federal Case Update 5

    Mark Your Calendar 5

    In the News 6

    Construction Tips: 6

    Lien Waivers: What Do

    They Really Mean?

    http://www.alston.com/http://www.alston.com/
  • 7/31/2019 Substantial Completion Blues

    2/82

    owner should be allowed to occupy and enjoy the building without any further disruptions (with punch

    list items conned to the exterior of the building, for example).

    The benecial occupancy denition certainly makes perfect sense if one is talking about a brand new,

    vanilla ofce building in the suburbs with one tenant. However, it makes absolutely no sense when

    talking about a hotel or residential project. On a residential or hotel project, the idea of punch list work

    being performed in an occupied hotel room or an occupied apartment is unthinkable to the developer

    and the resident. If the owner cannot turn the hotel room or apartment over to the resident to be enjoyed

    without plumbers doing punch lists, then the project cannot generate revenue for the owner. Being able

    to occupy the project, or receiving a certicate of occupancy, has no particular relevance to this owner

    or developer.

    Other projects pose similar problems. If the issue is the construction of retail shell space, how much

    work has to be completed by the landlords contractor in order for the tenant to accept the premises for

    xturing? If the issue is interior retail tenant space, how much work has to be completed by the contractor

    for the retailer to open for business? What does the lease say about the work that has to be completed,

    and when? In these circumstances, that may be the most important question. All of these questions

    mustbe answered if the denition of substantial completion in the construction contract is going to be

    accurate and useful in preventing a dispute at the end of the project.

    For some of our clients that develop or construct many different types of projects, we often suggest that

    they leave the substantial completion denition blank in their form contracts. The hope is that the project

    manager will look at this issue along with all of the other business terms, and come up with a denition

    that makes sense for the particular project involved.

    This denition may need to be very detailed and contain a laundry list of items bearing on the issue of

    substantial completion. This could include specic site work items (site lighting, paving, etc.) that have

    nothing to do with the building itself, but which bear on the issue of substantial completion, at least a

    substantial completion that meets the expectations of the developer. In the apartment example, one

    should determine what common area work has to be completed in order to achieve substantial comple-

    tion, above and beyond completion of the residential units.

    As noted above, the difculty of determining when substantial completion has been achieved can have

    enormous consequences. Delay damages, payments and retainage releases are almost always tied to

    substantial completion. As a result, a lot of money is riding on whether substantial completion has been

    achieved on a particular project, and by what date. It is therefore critical that the parties to the contract

    avoid, if at all possible, arguing about the denition of substantial completion and what has to be done

    to achieve that status on the project.

    Deborah Cazan

  • 7/31/2019 Substantial Completion Blues

    3/83

    CASE UPDATES BY STATE

    Florida

    Subcontractors Failure to Separately Register and License Its Fictitious Name Did Not Invalidate

    Its Subcontract

    In Martin Daytona Corp. v. Strickland Const. Services, Floridas Fifth District Court of Appeals ruled tha

    a subcontractors failure to separately register and license the ctitious name under which it entered

    into a subcontract did not invalidate the subcontract. In this case, the subcontractor sued to collec

    amounts allegedly owed by the general contractor at the end of a project. The subcontract contained

    an arbitration clause and the contractor moved to stay or abate arbitration arguing that the clause was

    unenforceable because the subcontractor entered the subcontract under a ctitious name, without sepa-

    rately registering and licensing the name, in violation of Floridas contractor licensing laws. The Fifth

    District ruled that the subcontract is enforceable, notwithstanding the subcontractors failure to registe

    and obtain a separate license. The court determined that a recent amendment to the contractor licens

    ing requirements claried that a contract is not invalid for the contractors failure to register or obtain a

    license under its ctitious name. 881 So. 2d 686 (Fla. App. 5th

    DCA Aug. 27, 2004)

    Georgia

    Georgia Legislature Enacts General Contractor Licensing Statute

    The Georgia Legislature recently enacted a contractor licensing scheme designed to cover both resi

    dential contractors and general contractors. O.C.G.A. 43-41-1 et. seq. The law will go into effec

    when appropriations are budgeted for the licensing board, which did not occur during the 2004 legislative

    session. The denition of contracting is very broad and includes not only performing the construction

    or the management of the construction of improvements to real property for an owner, but also merely

    offering to undertake such services for, or submitting a bid to, an owner. The denition also includescontracting work performed by a construction manager at risk. Generally, residential contractors mus

    obtain a license if they contract directly with an owner for a value over $2,500 or receive a fee over

    $2,500. However, no minimum dollar amount appears in the statue for general contractors. The statute

    prescribes both criminal penalties and civil sanctions for failure to comply with the statue. Notably, like

    most jurisdictions, an unlicensed contactor may not enforce its contract. An unlicensed contractor also

    loses all lien and bond rights it may otherwise have had. Contractors who perform construction work in

    the state of Georgia should play close attention to the new contractor licensing requirements and should

    take steps to ensure they will be in compliance when the statute becomes effective.

    ANNO

    UNCMENT The Construction and Government Contacts Group is pleased to announce the relocation of one of

    its attorneys, Brook A. Clark, to the rms New York ofce where she will join partner Daniel J. ONeill

    as the second attorney from the Construction and Government Contracts Group in that ofce. For

    many years, Alston & Bird has represented national and international clients who have engaged our

    services to handle transactional and adversarial matters throughout the Northeast. The relocation of

    Ms. Clark allows the Construction and Government Contacts Group to enhance its ability to providelocal support to clients who need business and adversarial advice on construction and government

    contracts matters in New York City and throughout the Northeast.

  • 7/31/2019 Substantial Completion Blues

    4/84

    Mississippi

    Mississippi Supreme Court Requires Contractor to Prove Objective and Subjective Impossibility

    to Prevail on Defective Design Claim

    In Evan Johnson & Sons Constr., Inc. v. State, the Mississippi Supreme Court held that the state and

    its architect were not liable on the contractors defective design claim because the contractor failed to

    prove the impossibility of constructing the building according to the design. The contractor believed that

    it could not build the roof in accordance with the plans and specications. Despite the contractors objec-

    tions, the state instructed the contractor to install the roof as designed. After the contractor attempted

    to build the roof in a manner contrary to the plans and specications, the state rejected the contractors

    work. The contractor sued the state and the architect alleging defective design. The court rejected the

    contractors defective design claim because the contractor failed to prove both subjective and objective

    impossibility. Because [the contractor] failed to prove any other contractor was unable to comply with

    the original design and specications and because [the contractor] failed to attempt to construct the

    roof according to the original design and specications, the contractors claim for defective design was

    without merit. 877 So. 2d 360 (Miss. 2004)

    New York

    Failure to File Notice of Lending Costs Bank $1.9M

    The New York Court of Appeals recently reminded banks of the importance of ling a Notice of Lending.

    InAspro Mechanical Contracting Inc. v. Fleet Bank, N.A., 7, the court ordered Fleet to pay a group of

    subcontractors $1.9 million dollars that it had applied to its mortgages on a residential housing project.

    Fleet loaned Berry Street Corporation $12 million dollars secured by the assignment of Berrys rights in

    a development contract with the New York City Housing Authority (NYCHA). Fleet applied NYCHAs

    payments to its outstanding mortgages on the property. Several unpaid subcontractors (including

    Aspro) sued Fleet, alleging that the Bank had diverted trust assets in violation of the states lien law.

    The court found that Fleet was a trustee of the funds received from NYCHA, and had a duciary duty

    to use those funds to pay for improvements to the property. Fleet breached that duty by using trust

    funds to repay its own mortgages and was therefore liable for the subcontractors claims. Fleet could

    have avoided liability entirely if it had led a Notice of Lending with the county clerk. By doing so, it

    would have notied trust beneciaries that trust assets were being used to discharge Berrys debt. 805

    N.E.2d 1037 (N.Y. 2004)

    South Carolina

    Right to Compel Arbitration Not Waived By Delay, Pre-Trial Activity and Litigation Costs

    In Patten Grading & Paving, Inc. v. Skanska USA Building Inc., two attorneys from Alston & Birds

    Construction and Government Contracts Group successfully argued an appeal before the U.S. Court of

    Appeals for the Fourth Circuit. The appellate court reversed the lower courts ruling that the contractor had

    waived its contractual right to compel arbitration when it waited eight months after commencing litigation

    before moving to compel arbitration. In reversing, the court of appeals assessed several facts raised

    by the subcontractor and relied upon by the district court, including the contractors alleged eight-month

    delay in moving to compel arbitration, limited pre-trial activity and discovery, and the subcontractors

    incursion of $5,800 in litigation costs, and concluded that taken in isolation and together, these facts did

  • 7/31/2019 Substantial Completion Blues

    5/85

    not constitute actual prejudice sufcient to demonstrate waiver of the right to compel arbitration. 380

    F.3d 200 (4th Cir. 2004)

    Virginia

    Suretys Notice of Claim Against Principal, Coupled With Right and Opportunity to Defend, Suf

    cient to Bind Surety To Judgment by Default Entered Against Principal

    InAmerican Safety Casualty Ins. Co. v. C.G. Mitchell Construction, Inc., the Supreme Court of Virginia held

    that a judgment by default entered against the principal on a payment bond as a discovery sanction was

    binding and conclusive on the surety for purposes of summary judgment. Relying on the Eleventh Circui

    Court of Appeals decision in Drill South, Inc. v. International Fid. Ins. Co., 234 F.3d 1232 (11th Cir. 2000)

    the Virginia Supreme Court announced that a general rule has emerged whereby a surety is bound by

    any judgment against its principal, default or otherwise, when the surety had full knowledge of the action

    against the principal and an opportunity to defend. 601 S.E.2d 633 (Va. 2004)

    FEDERAL CASE UPDATE

    Expiration of One-Year Limitations Period on Appeal of Contracting Ofcers Decision Precludes

    Claim Where Contractor Failed to Retrieve Decision from Post Ofce Box

    In Riley & Ephriam Constr. Co. v. United States, the Court of Federal Claims dismissed the contractors

    appeal of the contracting ofcers denial of its $300,000 claim. Under the Tucker Act, a contractor mus

    le an appeal of a contracting ofcers nal decision in the Court of Federal Claims no later than one

    year after the date of the contractors receipt of that nal decision. Here, the contractor received notice

    in its post ofce box that a package sent by certied mail was received by the U.S. Post Ofce, but

    failed to retrieve the package before it was returned to the sender after 29 days. The contracting ofce

    also sent the decision via facsimile to the contractors attorney and received conrmation of receipt, bu

    the attorney claimed never to have received the facsimile. The court found that the facsimile, combined

    with evidence suggesting successful transmission, constituted receipt by the contractors agent. The

    court also found that receipt by the Post Ofce was sufcient as well, so that the contractors suit in the

    Court of Federal Claims, led over a year after both the post ofce box receipt and the facsimile, was

    untimely. 61 Fed. Cl. 405 (2004)

    MARKYOURCALENDAR

    Stephen M. Reams is speaking on Construction Project Finance and the Impact of NAFTA at

    the Trilateral Symposium at Universidad Pan Americana, November 10-11, 2004, Guadalajara,

    Mexico.

    Brian K. Fielden is presenting Managing Risk in Hotel Development and Construction at the

    Academy of Hospitality Industry Attorneys November 2004 Meeting, November 11-13, Dallas,

    Texas.

    Robert L. Crewdson and Brian K. Fielden will present Managing Risk in Hotel Development

    and Construction at the Americas Lodging Investment Summit, January 18-20, Los Angeles,

    California.

  • 7/31/2019 Substantial Completion Blues

    6/86

    INTHENEWS

    Partners John I. Spangler III, William H. Hughes, Jr., and Robert L. Crewdson were all recognized in

    Best Lawyers in America 2005-2006in the area of construction law.

    Robert L. Crewdson presented Construction War Stories II -- Another Year, More Stories at the 2004

    ICSC U.S. Law Conference in Hollywood, Florida.

    Jonathan D. Crumly, Sr. presented Evidence in the 21st Century: a Construction Lawyers Guide at the

    May 2004 American Bar Association Forum on the Construction Industrys Annual Meeting in Scottsdale,

    Arizona.

    William H. Hughes, Jr. presented A Practical Course of Action for Claim Prevention and Avoidance at

    the national conference of the Construction Management Association of America (CMAA) in San Antonio,

    Texas on September 13, 2004.

    Robert L. Crewdson and William H. Hughes, Jr. made presentations at the Institute for Continuing

    Educations Construction Law for the General Practioner seminar in Atlanta on October 14, 2004. Mr.

    Crewdson also chaired the seminar. Associate John S. Ducat III co-authored written materials.

    Jonathan D. Crumly, Sr. co-authored Preventing War Over Mold Claims, an article appearing in the

    July 2004 New York Law Journal.

    Jonathan D. Crumly, Sr. was quoted extensively in a front page article in August 30, 2004, edition of

    the South Carolina Lawyers Weekly reporting on the Patten Gradingdecision (see Case Updates for

    details of the decision).

    CONSTRUCTION TIPS: LIEN WAIVERS: WHAT DO THEY REALLYMEAN?

    Lien waivers are a staple of construction projects. Everybody knows the importance of obtaining a lien

    waiver, although many owners and contractors never bother to collect them. But where do the waiver forms

    themselves come from? And what do they really mean? Unfortunately, many owners, contractors and

    subcontractors cannot really answer these questions, and the consequences are often devastating.

    The most generic form of lien waiver simply waives a contractors right to assert lien claims on a project.

    For interim pay applications, this waiver of lien rights might extend through the date of the waiver, or

    might be effective only to the extent of payment. This is an important distinction with a difference. From

    the owners perspective, it is preferable to use a lien waiver form that waives lien rights through the date

    of the waiver, as this may serve to waive lien rights for as yet unresolved claims for extras or delay. A

    contractor, however, will want to limit the lien waivers coverage to the payment that is being received.

    Owners can obtain additional protection by including language that waives contract claims as well as

    lien claims on the project, through the date of the lien waiver. The purpose of this additional language

    is to bring the project current and give the owner comfort that no hidden or unknown claims exist at

    the time of each progress payment, or at the time of nal payment.

  • 7/31/2019 Substantial Completion Blues

    7/87

    In these cases, it is important that a contractor read the waiver form, and understand the difference

    between a lien waiver and a claim waiver. When the waiver releases contract claims as well as lien

    rights, the company signing the waiver will have released its right to recover costs or damages for

    pending change orders or delay claims that are otherwise being submitted or processed on the project

    The waiver could result in an inadvertent and unintentional release of claims under the contract that are

    otherwise entirely valid.

    These waivers are enforced according to their terms like any other legal document, particularly because

    waivers are sworn documents. Courts are loath to allow an attack by a contractor on its own sworn

    lien waiver. Therefore, when signing a waiver that includes a release of contract claims (as well as lien

    rights), a contractor should carefully list and exclude those claims and matters that are still pending. Mos

    owners nd the list of excluded claims to be acceptable, as their main intent in using the claim waiver is

    to obtain information on claims that might be in the ofng. Owners should ensure that this list of claims

    is as specic as possible to preclude any argument as to what is included in that claim at a later date.

    Another issue regarding lien waivers that requires careful attention is the issue of whether the state in

    which the project is located has restrictions on the type of waivers that can be used. For example, in

    the South, Georgia and Florida have statutory lien waiver forms, and the statutes generally provide that

    all waivers must be substantially in the form provided in the statute to be effective. In the West, Arizona

    and California have very strict requirements on the form of a lien waiver. There are a few other states

    with similar requirements. If a waiver contrary to the terms of these statutes is used, it will be deemed

    unenforceable.

    Most of the statutory waiver forms are merely waivers of lien, and not claims. While these statutes often

    do not speak to the issue of whether claim waivers can be included in a waiver form (and there are no

    cases bearing on this issue at the present time), Arizona and California do, in fact, prohibit claim waiv-

    ers. Other states, like Florida and Georgia, do not seem to prohibit claim waivers, although there are

    no cases that would permit a nal answer to this question. Additional states will likely pass lien waive

    form provisions in the future, and a contractor going into any state for the rst time should always check

    to make sure their form complies with any statute that exists.

    Owners and contractors should pay careful attention to the lien waivers used on every project they under

    take. If statutory lien waivers are required, the parties should ensure they have the proper forms. They

    should read and analyze the lien waivers to obtain a clear understanding of what rights and claims are

    being waived every month. If owners and contractors pay close attention to statutory requirements, and

    the contents of lien waivers, they can avoid unintended and potentially devastating consequences.

    Aubrey B. Wadde

  • 7/31/2019 Substantial Completion Blues

    8/8

    Jeffrey A. Belkin

    404-881-7388

    [email protected]

    Deborah Cazan

    404-881-7667

    [email protected]

    Brook A. Clark

    212-210-9462

    [email protected]

    Robert L. Crewdson404-881-7291

    [email protected]

    Jonathan D. Crumly, Sr.

    404-881-7336

    [email protected]

    ATLANTAOne Atlantic Center1201 West Peachtree Street

    Atlanta, GA 30309-3424404-881-7000

    CHARLOTTEBank of America Plaza101 South Tryon StreetSuite 4000Charlotte, NC 28280-4000704-444-1000

    NEW YORK90 Park AvenueNew York, NY 10016-1387212-210-9400

    RESEARCH TRIANGLE3201 Beechleaf CourtSuite 600Raleigh, NC 27604-1062919-862-2200

    WASHINGTON, D.C.601 Pennsylvania Avenue, NNorth Building, 10th FloorWashington, D.C. 20004-260202-756-3300

    www.alston.com

    If you would like to receive future Construction Law Reviews electronically, please forward

    your contact information including e-mail address to [email protected]

    Be sure to put subscribe in the subject line.

    MEMBERS OF ALSTON & BIRDS CONSTRUCTIONAND GOVERNMENT CONTRACTS GROUP

    Alston & Bird LLP 2004

    Daniel F. Difey

    404-881-4703

    [email protected]

    John S. Ducat III

    404-881-4934

    [email protected]

    Brian K. Fielden

    404-881-7496

    [email protected]

    J. Andrew Howard404-881-4980

    [email protected]

    This Construction Law Reviewis published by Alston & Bird to provide a summary of

    signicant developments to our clients and friends. It is intended to be informational

    and does not constitute legal advice regarding any specic situation. This material

    may also be considered advertising under the applicable court rules.

    John I. Spangler, III

    Practice Group Chair

    404-881-7146

    [email protected]

    William H. Hughes, Jr.

    404-881-7273

    [email protected]

    Daniel J. ONeill

    212-210-9522

    [email protected]

    Stephen M. Reams

    404-881-7731

    [email protected]

    Aubrey B. Waddell404-881-4932

    [email protected]

    http://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=4215mailto:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=4101mailto:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=4102mailto:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=3340mailto:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=4163mailto:[email protected]:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=3891mailto:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=4394mailto:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=3264mailto:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=4212mailto:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=3567mailto:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=3422mailto:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=3945mailto:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=3795mailto:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=4386mailto:[email protected]:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=4386mailto:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=3795mailto:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=3945mailto:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=3422mailto:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=3567mailto:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=4212mailto:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=3264mailto:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=4394mailto:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=3891mailto:[email protected]:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=4163mailto:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=3340mailto:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=4102mailto:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=4101mailto:[email protected]://www.alston.com/index.cfm?fuseaction=attorneydirectory&attyid=4215