Subsea Standardisation Project Adopting a Fit for...

23
Subsea Standardisation Project Adopting a Fit for Purpose and Optimised Approach Oil & Gas UK Efficiency Task Force Share Fair 2016 – Innovation Hub Sessions Steve Duthie – ETF Subsea Standardisation Project Industry Lead 2nd November 2016 Aberdeen AECC

Transcript of Subsea Standardisation Project Adopting a Fit for...

Page 1: Subsea Standardisation Project Adopting a Fit for …oilandgasuksharefair.co.uk/wp-content/uploads/2016/11/Share-Fair... · Subsea Standardisation Project Adopting a Fit for Purpose

Subsea Standardisation ProjectAdopting a Fit for Purpose and Optimised Approach

Oil & Gas UK Efficiency Task Force

Share Fair 2016 – Innovation Hub Sessions

Steve Duthie – ETF Subsea Standardisation Project Industry Lead

2nd November 2016 Aberdeen AECC

Page 2: Subsea Standardisation Project Adopting a Fit for …oilandgasuksharefair.co.uk/wp-content/uploads/2016/11/Share-Fair... · Subsea Standardisation Project Adopting a Fit for Purpose

2

Contents

Introduction

Literature Review

Standardisation Themes

UKCS Case Studies

Strawman Theoretical Exercise

Efficiency Scope Selection

Summary of Research Findings

Prospect Review – Centrica Pegasus West

Oil & Gas UK – Efficiency Task Force

Page 3: Subsea Standardisation Project Adopting a Fit for …oilandgasuksharefair.co.uk/wp-content/uploads/2016/11/Share-Fair... · Subsea Standardisation Project Adopting a Fit for Purpose

3Oil & Gas UK – Efficiency Task Force

The Oil & Gas UK executive formally launched the Efficiency Task Force (ETF) in September 2015, to drive a pan-industry improvement in efficiency – with the aim of creating a sustainable industry in a lower oil price world.

While recognising that some behavioural change will be company-specific, Oil & Gas UK is taking the lead to help drive pan-industry initiatives to achieve efficiency improvements and transformational change, formalising those initiatives under the ETF.

The task force is taking a three pronged approach under the themes:

Business Process

Co-operation, culture and behaviours

Standardisation

Compression Systems Inventory Management Procurement Logistics Maintenance

Industry Behaviours Charter Rapid Efficiency Exchange Efficiency Roadshows

Subsea Technology

Valves Well Plugging & Abandonment

Overall Project Objectives Summary

Page 4: Subsea Standardisation Project Adopting a Fit for …oilandgasuksharefair.co.uk/wp-content/uploads/2016/11/Share-Fair... · Subsea Standardisation Project Adopting a Fit for Purpose

4Oil & Gas UK – Efficiency Task Force

Industry Driven

Key Stakeholder and Companies Involved

Page 5: Subsea Standardisation Project Adopting a Fit for …oilandgasuksharefair.co.uk/wp-content/uploads/2016/11/Share-Fair... · Subsea Standardisation Project Adopting a Fit for Purpose

5

Working GroupAlan Black

Graham Whitehead

Guy Trumper

Matt Corbin

Martin Fowlie

Neil Kirkbride

Patrick Duggan

Rebecca Borresen

Richard Hinkley

Stuart Buchan

Stephen Marco Jones

Steve Duthie – Industry Lead

Detailed Design Pre-Commissioning

Fabrication SPS

Flexibles Survey

IVB Trenching, Backfill & Rockdump

Installation Umbilicals

Pipelines, LinePipe & Coatings Valves, Flanges & Fittings

12 Sub Groups from across Industry

Literature Review

Case Studies

ProspectReview

Strawman Theoretical

Exercise

Efficiency Scopes

Oil & Gas UK – Efficiency Task Force

Input from:

Scopes

Dev

elo

p T

heo

ryA

pp

ly

Theo

ry

Organisational StructureSubsea Standardisation Project

Page 6: Subsea Standardisation Project Adopting a Fit for …oilandgasuksharefair.co.uk/wp-content/uploads/2016/11/Share-Fair... · Subsea Standardisation Project Adopting a Fit for Purpose

6Oil & Gas UK – Efficiency Task Force

1. UKCS Prospects economically challenging

2. “Here and now” solutions required to stimulate investment and developments

3. Need to make a difference today !

4. Majority of Small Pools are within tie back range –new technology not essential

5. Industry led initiative with voluntary support

OutputIndustry Review Previous Initiatives

Industry Review Behaviours Cultures and Practices

Key ConsiderationsLiterature Review

Literature Review

Page 7: Subsea Standardisation Project Adopting a Fit for …oilandgasuksharefair.co.uk/wp-content/uploads/2016/11/Share-Fair... · Subsea Standardisation Project Adopting a Fit for Purpose

Optimisation and Alternative MethodsThese could include: Field layout optimisation Pre-commissioning philosophy Alternative designs, fabrication, manufacturing

and installation methods and technology. Hot Taps to Host Pipeline Schedule optimisation, Vessel Sharing and

cluster development strategy (Mass Centralisation).

Simplified Process These could include: Reducing documentation requirements, Acceptance of contractor documentation. Reduced inspection requirements, Acceptance of contractor quality control procedures. Reduces reporting Interface management. Risk Review Profile Industry Proforma documents

Functional vs PrescriptiveThese could include: Working to industry standards as opposed to

prescriptive customer specification requirements, Use of pre-qualification and testing information, Material requirements and traceability Simplified design and installation analysis

Standardised Hardware.These could include: Catalogue of Components Re-Use of Equipment Envelope for Design Components Standard Classifications Interchangeability Standard Interfaces Plug and Play Modularised and building block approach

Alternative Methods and Technologies

HardwareProcess

Codes, Standards

and Specifications

7Oil & Gas UK – Efficiency Task Force

Standardisation Themes

Page 8: Subsea Standardisation Project Adopting a Fit for …oilandgasuksharefair.co.uk/wp-content/uploads/2016/11/Share-Fair... · Subsea Standardisation Project Adopting a Fit for Purpose

Early indication of the potential savings that could be realised

Four previously executed projects revisited applying the standardisation themes

8

Case Study 2Subsea pipeline tieback

Total Savings: £13m = 18%

Case Study 1FPSO riser system

Total Savings:£7.75m = 25%

Case Study 3Subsea manifold & bundle

Total Savings:£26m = 15%

Case Study 4Subsea pipeline tieback

Total Savings:£14.5m = 28%

Oil & Gas UK – Efficiency Task Force

UKCS Case Studies - Results

Page 9: Subsea Standardisation Project Adopting a Fit for …oilandgasuksharefair.co.uk/wp-content/uploads/2016/11/Share-Fair... · Subsea Standardisation Project Adopting a Fit for Purpose

9

Strawman Exercise

Define Theoretical Strawman

Scope

Define Reference

Case

Define Metrics

and Score

Produce Time/ Cost/

Complexity Diagram

16 Scopes

10 Sub Groups

Oil & Gas UK – Efficiency Task Force

UKCS Operator:Cost - £1,712,000 (7%)

Schedule – 56 Weeks (8%)Complexity – 27 (225%)

Global Operator:Cost - £2,232,000 (40%)

Schedule – 84 Weeks (62%)Complexity – 54 (450%)

Strawman Theoretical Exercise

Page 10: Subsea Standardisation Project Adopting a Fit for …oilandgasuksharefair.co.uk/wp-content/uploads/2016/11/Share-Fair... · Subsea Standardisation Project Adopting a Fit for Purpose

90%

100%

110%

120%

130%

140%

150%

160%

170%

90% 110% 130% 150%

10

Note: Impact of duration on project development cycle is not reflected in costs.

% Cost

% Duration

17%38%

57%

26%Global Operators

UKCS Focused Operators

High

Medium

Low

Complexity

Reference Case

Oil & Gas UK – Efficiency Task Force

Strawman Theoretical Exercise – Overall Results

Page 11: Subsea Standardisation Project Adopting a Fit for …oilandgasuksharefair.co.uk/wp-content/uploads/2016/11/Share-Fair... · Subsea Standardisation Project Adopting a Fit for Purpose

7%

24%9%

18% 12%21%

4%14%

7% 12%2%

10% 12%

31%40% 46%

17%

40%29% 23%

15% 16%

14%

48%

17%

39%

22%29%

22%

120%

28%

37%32%

51%

40%

62%

46%

86%

59%

120%

65%

47%

69%

41%

0%

20%

40%

60%

80%

100%

120%

140%

UKCS Focus

Global

11

2% 5

%8%

11%

14%9

%6%

6%

12%

27%

Co

st

Sch

edu

le

Co

st

Sch

edu

le

Co

st

Sch

edu

le

Co

st

Sch

edu

le

Co

st

Sch

edu

le

Co

st

Sch

edu

le

Co

st

Sch

edu

le

Co

st

Sch

edu

le

Co

st

Sch

edu

le

Co

st

Sch

edu

le

Co

st

Sch

edu

le

Trenching Installation Fabrication Survey Flexibles Design ValvesControl Systems

(SPS)

Trees (SPS)

Pipelines Umbilical

Reference Case

%

Oil & Gas UK – Efficiency Task Force

Strawman Theoretical Exercise – Cost and Schedule Impact

Page 12: Subsea Standardisation Project Adopting a Fit for …oilandgasuksharefair.co.uk/wp-content/uploads/2016/11/Share-Fair... · Subsea Standardisation Project Adopting a Fit for Purpose

Simplified Process Applied Inspection and Test Plan Savings

Witness and hold points tied to milestones

Approved Vendor Savings

Using only supplier approved vendors

Removal of independent verification and certification for safety critical equipment.

Documentation

Accepting standard supplier documentation, reduced review cycles

Reduce documents due to providing only functional requirements

o 10,000+ man-hours reduced to 2,850 hours.

13% overall cost and 18% schedule savings were achieved

12Oil & Gas UK – Efficiency Task Force

Through a series of workshops held by the Sub Groups, projects were selected that identified potential costs and schedule benefits

55 projects selected overall from 11 Sub Groups

X

X

X

SPS Sub Group applied one of their projects to a current subsea tree supply scope

Efficiency Scope Selection – Case Study Example

Page 13: Subsea Standardisation Project Adopting a Fit for …oilandgasuksharefair.co.uk/wp-content/uploads/2016/11/Share-Fair... · Subsea Standardisation Project Adopting a Fit for Purpose

The reviews and exercises undertaken to date have identified the potential for achieving significant efficiency savings when applying the Standardisation Themes to Subsea Developments: Four UKCS case studies indicated 15-28% cost savings

The theoretical Strawman exercise identified potential savings in the range of 6 – 38%

Applying a simplified approach to the Process’s as part of a subsea tree manufacture demonstrated actual savings of 13%

The overall savings and individual weighting of the standardisation themes will vary from project to project as influenced by the development and operators behaviours & culture where: Codes, Standards & Specifications are generally influenced by the level of prescriptive requirements.

Process is influenced by the level of control applied and level of detail and information requested.

Alternative methods and technologies are influenced by the scope and level of early engagement from the supply chain.

Hardware standardisation offers limited savings in the short term but offers potential for achieving significant savings in the longer term – this will also be influenced by proprietary knowledge and commercial sensitivity.

13Oil & Gas UK – Efficiency Task Force

Case Study 2UKCS subsea pipeline

tieback

Total Savings: £13m = 18%

Case Study 1FPSO riser system

Total Savings:£7.75m = 25%

Case Study 3Subsea manifold &

bundle

Total Savings:£26m = 15%

Case Study 4UKCS subsea pipeline

tieback

Total Savings:£14.5m = 28%

Summary of Research Findings

Page 14: Subsea Standardisation Project Adopting a Fit for …oilandgasuksharefair.co.uk/wp-content/uploads/2016/11/Share-Fair... · Subsea Standardisation Project Adopting a Fit for Purpose

Industry Review Previous Initiatives

14

Research Findings

Centrica West Pegasus

Oil & Gas UK – Efficiency Task Force

Potential efficiencies that could be applied to subsea developments by adopting a fit for purpose and a more simplified approach to projects.

Objective:To establish what cost savings could be realised when applying the findings identified to date to an existing prospect considered ‘economically challenging’.

Industry Review – Cultures, Behaviours and Practices

Standardisation Themes

Prospect Review

Applying the Theory to a Real Life Case Study

Page 15: Subsea Standardisation Project Adopting a Fit for …oilandgasuksharefair.co.uk/wp-content/uploads/2016/11/Share-Fair... · Subsea Standardisation Project Adopting a Fit for Purpose

15Oil & Gas UK – Efficiency Task Force

Centrica was the first operator to offer a prospect for review. In this case, the West Pegasus field development, a potential three well gas tie-back in the Southern North Sea.

Manifold Structure

Manifold Structure

1km8” Infield Pipeline

80km 12” Export Pipeline

Pegasus North Well

Andromeda Well

6km 8” Infield Pipeline

6km 8” Infield Pipeline

End of Scope12km

KP – 6.27

KP – 46.90

KP – 55.73KP – 53.64

KP – 59.30

Pegasus West Well

Key:Rigid PipeUmbilicalCrossing

Several options with different “Host” Facilities were considered.

Centrica Pegasus West Prospect Review

Page 16: Subsea Standardisation Project Adopting a Fit for …oilandgasuksharefair.co.uk/wp-content/uploads/2016/11/Share-Fair... · Subsea Standardisation Project Adopting a Fit for Purpose

16Oil & Gas UK – Efficiency Task Force

Substantial savings through material & manufacturing selection Further savings were realised through applying only the ISO

standards Savings were also identified through reducing the level of

documentation and accepting only manufacturer documentation.

Standard DesignsThrough measuring flow at the

host rather than adopting a multiphase flow select meter.Opting for a single SEM with a dual

power source realised substantial cost savings

SPS Controls

Field layout optimised by introducing a co-mingling manifold to replace the well daisy chain configuration this reduced the number of valves including number of actuated valves.

Simplified pipework at trees avoided protection structure plus reduced dewatering methodology.

Revised Field Layout

Key Efficiencies Identified

Umbilical Optimisation

Page 17: Subsea Standardisation Project Adopting a Fit for …oilandgasuksharefair.co.uk/wp-content/uploads/2016/11/Share-Fair... · Subsea Standardisation Project Adopting a Fit for Purpose

17Oil & Gas UK – Efficiency Task Force

By trenching into the 500m zone there is an area between the dropped object cone and the boundary of the 500m zone where no matts would be required.

Through applying the above, 208 matts were no longer required .

The reduction of matts also has a significant cost and schedule saving from vessel duration.

Reduced rock quantities and subsequent installation time, through challenging specification and applying industry standards

Dropped Object and Over-trawlability

Crossing Design

Rigid PipeUmbilical

Seabed

Combining the umbilical and the pipeline in the same trench realised significant savings.

Single Pipeline and Umbilical Trench

Pipelines

Use of High Frequency Induction Line Pipe & optimised Wall Thickness

ECA and AUT replaced with radiography Removal of Field Joint Coatings Optimised pipeline fabrication and lay rates

Key Efficiencies Identified continued

Page 18: Subsea Standardisation Project Adopting a Fit for …oilandgasuksharefair.co.uk/wp-content/uploads/2016/11/Share-Fair... · Subsea Standardisation Project Adopting a Fit for Purpose

Application of standard designs for: Valves SPS Manifold

18Oil & Gas UK – Efficiency Task Force

Optimised pipeline fabrication and lay rates Optimised line pipe WT for reel lay Application of HFI Line Pipe Single Trench for Pipeline and Umbilical Revised field layout and co-mingled manifold with simplified

tree pipework, valves and necessity for protection cover. Simplified de-watering philosophy Combined leak and strength test Multi-phase flow meter selector to single flow selector. Crossing Design – Concrete plinths used Replace steel tubes with thermoplastic hoses for Umbilicals Overall installation schedule optimisation

Apply contractor documentation Inspection Review cycles Interface and sub contractor management Reporting Combined FEED and detailed design

Dropped object and over-trawlability Crossing design – rock quantities SEM redundancy Reduce trench transition from 75m to 50m Remove ECA and AUT requirements Pre-qualified welding and welder qualifications No FJC 22%Cr instead of 25%Cr Duplex for valve bodies Part cladding instead of full cladding for valves Pre-qualified valves Manufacturers standard FAT for valves 3.1 certification for valves Apply industry standards (ISO – Umbilicals/ API – Valves/

ASME – Fabrication) Umbilical hose and cable dimension optimisation Manufactures SIT applied to manifold Epoxy paint coatings for spools and structures

1.0%

65.7%18.9%

14.4%

Overall Efficiencies linked to Standardisation Themes

Page 19: Subsea Standardisation Project Adopting a Fit for …oilandgasuksharefair.co.uk/wp-content/uploads/2016/11/Share-Fair... · Subsea Standardisation Project Adopting a Fit for Purpose

19Oil & Gas UK – Efficiency Task Force

Range*

Project Management and Engineering 20.4% 24.7%

Procurement, Manufacture and Fabrication

14.8% 28.3%

Transportation and Installation 16.3% 33.6%

The above % indicates the savings achieved within these groupings.

Overall Percentage Savings 20.4% 24.7%* Dependant on Field Option

Overall Efficiency Savings

Page 20: Subsea Standardisation Project Adopting a Fit for …oilandgasuksharefair.co.uk/wp-content/uploads/2016/11/Share-Fair... · Subsea Standardisation Project Adopting a Fit for Purpose

20Oil & Gas UK – Efficiency Task Force

Sustainable Savings of 20-24% were achieved applying the Standardisation Themes

The overall savings & individual weighting of the Standardisation Themes will vary from project to project and by the cultures and behaviours adopted by the Operators and Supply Chain

The prospect review has highlighted that applying a functional and non-prescriptive approach will provide an optimised solution

Early engagement of the supply chain will increase the potential to apply alternative methods & technology

Savings attributed to improvement of the overall prospect delivery schedule have not been determined within this work but expected to provide further cost savings

This unique industry driven initiative, supported by a large number of companies applying collective behaviours, has demonstrated that cost savings of 20-24% were achievable.

Wider adoption of the Standardisation Themes to other prospects including the “small pools” will provide “Sustainable Savings” going forward.

Conclusion

Page 21: Subsea Standardisation Project Adopting a Fit for …oilandgasuksharefair.co.uk/wp-content/uploads/2016/11/Share-Fair... · Subsea Standardisation Project Adopting a Fit for Purpose

21

Centrica Feedback

‘Pegasus West’

The Centrica Pegasus project team is very pleased with the positive outcome achieved from the ETF work group subsea review and standardisation study case;

Identified a series of optimisations in the base case subsea concept,

led to noticeable potential cost reductions, which increased our confidence in the economically viability of the prospect.

The ETF work group demonstrated a high level proactive approach and professionalism;

An excellent level of collaboration between the Pegasus project team and ETF work group with one-team spirit maintained at all times.

Pegasus partners (Centrica and Third Energy) remain optimistic with regard to achieved results at the given level and look forward towards further improvement opportunities.

Pegasus partners will evaluate in more detail before a decision on whether and how we progress with Pegasus.

Page 22: Subsea Standardisation Project Adopting a Fit for …oilandgasuksharefair.co.uk/wp-content/uploads/2016/11/Share-Fair... · Subsea Standardisation Project Adopting a Fit for Purpose

22

12 members of the Working Group

57 members involved across 12 Sub GroupsDetailed Design Fabrication Installation

Adrian Ledingham Wood Group Kenny Craig Jamieson Isleburn (GEG) Neil Shand * TechnipFrank Smith Xodus Graeme Gray Isleburn (GEG) Sean Magee Subsea 7Gordon Tough Technip David McCann Wood Group Kenny

Flexibles Independent Verification Bodies Valves, Flanges and FittingsAndrew Roberts * Wellstream GE Claudia Scragg DNV GL David Gallagher Bel ValvesHelle Mortensen NOV Sean Murray Lloyds Register Claudio Ripamonti TechnipRon Mackinnon Technip Sam Mathew DNV GL Debbie Wyness Technip

Umbilicals Pre-Commissioning SurveySteve Marjoram * Technip Umbilicals Malcolm Harris * Enermech Mike Clark * Subsea 7Ian Probyn Technip Umbilicals Mark Rasmusen IKM Scott Winning Subsea 7Jonas Peterson Technip Umbilicals Phil Roberts Atlus Martin Skinner TechnipJoao Melo Oceaneering Shaun Main Haliburton Lewis Smith Technip

Derek Walker TechnipDamian Ling Chevron

Pipeline, Line Pipe and Coating Subsea Production Systems Trenching, Rock Dump and BackfillAlan Black * Subsea 7 David Benison Aker Solutions Willie Ross * TechnipHerve Quintin Subsea 7 Stephen Wood OneSubsea Trevor Pugh TechnipStuart Ward Subsea 7 Craig Johnstone GE Oil and Gas Alasdair Maconochie TechnipLee Miller Subsea 7 Iain Knight Wood Group Kenny Andrew Small XodusJosip Micak Technip Bruce Stuart ProServ Mike Wilson EcosseSameer Patil Subsea 7 Phil Ashley Siemens Toby Powell Subsea 7Duncan Graham Subsea 7 Gerard Gillespie Siemens Ian Stewart ChevronSimon Dewey Bredero Shaw Peter Blake Chevron Jon Machin UTECNeil Patrick Bredero Shaw Mike Tierney FMC Technologies

Working GroupSteve Duthie Technip Matt Corbin * Aker Solutions Rebecca Borresen Oil and Gas UKGuy Trumper Technip Martin Fowlie * DNV GL Richard Hinkley ChevronAlan Black Subsea 7 Neil Kirkbride * Bel Valves Stephen Marco Jones Oil and Gas UKGraham Whitehead EnQuest Patrick Duggan Apache Stuart Buchan * Genesis

* Sub Group Sponsor

Oil & Gas UK – Efficiency Task Force

Acknowledgements

Page 23: Subsea Standardisation Project Adopting a Fit for …oilandgasuksharefair.co.uk/wp-content/uploads/2016/11/Share-Fair... · Subsea Standardisation Project Adopting a Fit for Purpose

[email protected]#oilandgasuk

© 2016 The UK Oil and Gas Industry Association Limited, trading as Oil & Gas UK

Thank You