Subsea Processing System Integration Engineering07121-1901Project Management Plan Rev 1
Project Management PlanFebruary 11, 2009
Project Plan
Microsoft Project Document
ID WBS Task Name PredecessorsDuration Start Finish
1 1 Task 1: Develop Integrated Process Simulator 57 wks Fri 1/2/09 Thu 2/4/10
2 1.1 Literature & Prior Work Survey (includes equipment vendor survey)7.9 wks Fri 1/2/09 Thu 2/26/09
12 1.2 Component Modeling 42.44 wks Thu 2/5/09 Tue 12/1/09
22 1.3 Integrated Process Simulator 57 wks Fri 1/2/09 Thu 2/4/10
35 1.4 Develop SSP Evaluation Methodology (Developed in parallel with Level 4)31 2.2 wks Fri 5/8/09 Fri 5/22/09
38 1.5 Milestone 1 Report-out: Simulator Prototype Presentation 37 0 wks Fri 5/22/09 Fri 5/22/09
39 2 Task 2: Laboratory Test and Mobilization 41.1 wks Fri 1/2/09 Fri 10/16/09
91 3 Task 3: Execute the Lab Scale Test Matrix 39 37 wks Fri 10/16/09 Fri 7/2/10
92 3.1 Validate/Develop Component Level Models 5 wks Fri 10/16/09 Fri 11/20/09
97 3.2 Validate SSP Simulator 30 wks Fri 11/6/09 Fri 6/4/10
98 3.2.1 Execute Test Matrix 94 14 wks Fri 11/6/09 Fri 2/12/10
99 3.2.2 Conduct Data Reduction 98 1 mon Fri 2/12/10 Fri 3/12/10
100 3.2.3 Analyze Data 99 1 mon Fri 3/12/10 Fri 4/9/10
101 3.2.4 Adjust Prototype Simulator 100 2 mons Fri 4/9/10 Fri 6/4/10
102 3.3 Write Technical Report 92,971 mon Fri 6/4/10 Fri 7/2/10
103 3.4 Database Raw and Analyzed Data 100 3 days Fri 4/9/10 Wed 4/14/10
104 3.5 Deliverable 1: SSP Simulator 0 wks Fri 10/16/09 Fri 10/16/09
113 3.6 Deliverable 3: Test Matrix Results Reporting 32 wks Fri 11/20/09 Fri 7/2/10
114 3.6.1 Test Report 32 wks Fri 11/20/09 Fri 7/2/10
121 3.6.2 Database of Raw & Analyzed Data 103 0 days Wed 4/14/10 Wed 4/14/10
122 3.7 Milestone 3 Report-out (Deliverables 1 & 3) 104,1130 wks Fri 7/2/10 Fri 7/2/10
123 4 Task 4: Technology Transfer 71.1 wks Fri 2/20/09 Fri 7/2/10
124 4.1 Develop Technology Transfer Plan w/ RPSEA 150 2 wks Fri 2/20/09 Thu 3/5/09
125 4.2 Conduct Training on Simulator Use (start after project Milestone 3)131 0 days Fri 7/2/10 Fri 7/2/10
126 4.3 Disseminate Project Results (start after milestone 3) 131 0 days Fri 7/2/10 Fri 7/2/10
127 5 Task 5: Program Mangement 87.2 wks Fri 1/2/09 Fri 9/3/10
128 5.1 Milestone 0: Project Kick-off 0 days Fri 1/2/09 Fri 1/2/09
129 5.2 Milestone 1: Task 1 (Develop Integrated Process Simulator) Complete37 0 days Fri 5/22/09 Fri 5/22/09
130 5.3 Milestone 2: Task 2 (Lab Test & Mobilization) Complete 79 0 wks Fri 10/16/09 Fri 10/16/09
131 5.4 Milestone 3: Project Completion 124,1130 days Fri 7/2/10 Fri 7/2/10
132 5.5 Monthly Reports 76.5 wks Fri 1/2/09 Tue 6/22/10
150 5.7 Technical Kick-Off Meeting 0.2 wks Thu 2/19/09 Thu 2/19/09
151 5.6 Quarterly reviews 77.8 wks Tue 3/10/09 Fri 9/3/10
5/22
Flow Loop Manager,Flow Loop Tech,Kristian SveenKristian Sveen,JD Williams
JD WilliamsJD Williams
10/16
4/147/2
Dave Anderson7/27/2
1/25/22
10/167/2
DecJanFebMarAprMayJun Jul AugSepOct NovDecJanFebMar AprMayJun Jul AugSepOct NovDecJan4th Quarter 1st Quarter 2nd Quarter3rd Quarter 4th Quarter 1st Quarter 2nd Quarter3rd Quarter 4th Quarter 1st Quarter
2008 2009 2010 2011
Project Management PlanFebruary 11, 2009
Project Team Organisation
Weekly team meetings; quarterly RPSEA meetings
Project DirectorChris Wolfe (GR)
GE Oil & Gas Business Program Manager
Amin Radi (GR)
Technology LeaderDan Friedemann (VG)Project Technical Quality
Principal InvestigatorDavid Anderson (GR)
Multi-Phase Flow Loop Lead
Kristian Sveen (VG)Test Facility Preparation
& Test Execution
Separation Modeling Lead Inge Wold (VG)
Simulator LeadMahadevan Balasubramaniam (GR)
Component model/Simulator Development
Statistical Analysis Lead James D Williams (GR)Probabilistic Performance
Evaluation; Experimental Design & Analysis
Software EngineerRoger Shisler (GR)
External Input for Component LibraryEquipment Suppliers
Simulator End-Users/Beta UsersOperators/Equipment Suppliers
GE DW1901 Team
Flow Loop Operation Flow Loop Team (VG)
GR: Global Research – NiskayunaVG: VetcoGray - Oslo
Project Management PlanFebruary 11, 2009
Baseline Project Cost
$0
$200,000
$400,000
$600,000
$800,000
$1,000,000
$1,200,000
$1,400,000
$1,600,000
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep Oct
Nov
Dec Ja
n
Feb
Mar
Apr
May
Jun
Cum
mul
ativ
e Sp
end
[$]
Task 5 Program ManagementTask 4 Technology TransferTask 3 Test MatrixTask 2 Laboratory MobilisationTask 1 Process Simulator
Total Project Cost: $1,511,448RPSEA Funding: $1,200,000GE Cost Share: $311,448
Project Management PlanFebruary 11, 2009
Technology Transfer Plan - Preliminary
Simulator technology transfer via demonstrations at:Quarterly RPSEA meetingCustomer workshops at GE – “Session T”
- Annual events with GE O&G customersConference presentations
- Target conferences to be determined
Start with simulator prototype – June Quarterly meeting
Develop detailed plan with RPSEA