SUBMARINE POWER CABLE CASE STUDY • Vessel: M/V Industrial Hedland • Client: Prysmian • Cargo: Spooled submarine power cable 6,500 meters in cable tank installed on deck. Total weight: 140 mt. Cable spooling system diagram for loading cable onto vessel in Pozzuoli, Italy. In February, 2015 the PRYSMIAN hired Intermarine to transport a spooled submarine power cable from Naples Bay, Pozzuoli-Arco Felice jetty, Italy, to Ho Chi Minh City-Phu Huu Port, Vietnam. Synopsis: 6,500 METERS OF CABLE WEIGHING 140 MT; ITALY TO VIETNAM

Transcript of SUBMARINE POWER CABLE -...

Page 1: SUBMARINE POWER CABLE - intermarine.comintermarine.com/wp-content/uploads/2018/01/CaseStudy_Submarine... · SUBMARINE POWER CABLE CASE STUDY • Vessel: M/V Industrial Hedland •

SUBMARINE POWER CABLE

CASE STUDY

• Vessel: M/V Industrial Hedland• Client: Prysmian• Cargo: Spooled submarine power cable 6,500 meters in cable tank installed on deck. Total weight: 140 mt.

Cable spooling system diagram for loading cable onto vessel in Pozzuoli, Italy.

In February, 2015 the PRYSMIAN hired Intermarine to transport a spooled submarine power cable from Naples Bay, Pozzuoli-Arco Felice jetty, Italy, to Ho Chi Minh City-Phu Huu Port, Vietnam.

Synopsis:

6,500 METERS OF CABLE WEIGHING 140 MT; ITALY TO VIETNAM

Page 2: SUBMARINE POWER CABLE - intermarine.comintermarine.com/wp-content/uploads/2018/01/CaseStudy_Submarine... · SUBMARINE POWER CABLE CASE STUDY • Vessel: M/V Industrial Hedland •

INTERMARINE, LLC 55 Waugh Dr. Suite 300, Houston, TX 77007 WEBSITE intermarine.com

EMAIL [email protected] +1 281 885 3500 FAX +1 281 872 4444

TWITTER @intermarine_llc LINKEDIN intermarine.com/linkedin YOUTUBE intermarine.com/youtube

© Intermarine, LLC 2016

INTERMARINE CASE STUDY: SUBMARINE POWER CABLE

WORLDWIDE OFFICESIntermarine maintains worldwide offices in key locations to serve your chartering needs:

Americas: [email protected]

Europe: [email protected] | [email protected]

Italy: [email protected]

Turkey: [email protected]

Malaysia: [email protected]

China: [email protected] | [email protected]

Japan: [email protected]

UK: [email protected]: [email protected]

Intermarine was charged with picking up the cargo from the client’s factory and spooling the power cable inside a pre-fabricated tank to be welded onto the ship’s deck hatch covers. Intermarine then provided sea transport to the final destination. The cargo was offloaded onto a barge with further delivery to the offshore site to be laid on the sea bed by a cable laying vessel.

Work Scope of Project:Good communication and collaboration between all parties involved were required in the transport process to ensure smooth execution of the project.

Main Goals:

Cargo was delivered safely and on time.

Results: