SAUDI BINLADEN GROUP - ABCDPAYMENT CERTIFICATE DEPARTMENT
Project CORRECTIONAL FACILITIES P-1182, DammamSubject AS-BUILT QUANTITIESPeriod As of 18 Feb 2016
NO DESCRIPTION Unit Total CONCRETE & BLOCKS (Main Works)
1 Plain ConcretePlain Concrete 20Mpa-SRC Thick = 50mm
1 m3 2,117.21
1 m3 26.51
Plain Concrete 20Mpa-SRC Thick = 100mm
2 453 Benayat m3 1,616.81
2 m3 40.90
5% Micro Silica 0.00
Mass concrete > 100mm
4 m3 50.60
2 Sub-structure Concrete works 30 Mpa-SRC (w/o S.O.G)Isolated Footing
1 453 Benayat m3 4,016.75
1 m3 96.52
Strip Footing
2 453 Benayat m3 2,268.59
2 m3 76.72
Tie Beams / Grade Beams
3 453 Benayat m3 2,387.26
3 m3 126.01
Column Neck
4 453 Benayat m3 276.17
4 m3 8.51
Wall Neck
5 453 Benayat m3 827.61
Slab On Grade
6 453 Benayat m3 7,268.25
6 m3 168.67
Vapour Barrier 300 micron Polyethylene under slab on grade
7 453 Benayat m3 64,758.76
7 m3 804.09
Damp Proofing
8 453 Benayat m3 49,500.30
8 m3 2,403.46
5% Micro Silica
3 Super Structure Concrete Works - 30Mpa OPCColumn / Beams / Walls
453 Benayat526 Dar Anan
526 Dar Anan
526 Dar Anan
526 Dar Anan
526 Dar Anan
526 Dar Anan
526 Dar Anan
526 Dar Anan
526 Dar Anan
526 Dar Anan
![Page 2: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/2.jpg)
1 453 Benayat m3 6,327.00
1 m3 264.42
Column / Beams / Walls (with corbel)
2 453 Benayat m3 747.48
2 m3 17.57
Suspended Slab (Vary Thick)
3 453 Benayat m3 7,605.65
3 m3 132.91
Concrete Ramps, Step & Landing
4 453 Benayat m3 569.85
Fairface Finish or Concrete ramps, steps & landing 0.00
Concrete Screed
6 453 Benayat m3 444.49
6 m3 6.73
Concrete Parapet
Concrete Coping
8 453 Benayat Lm 8,502.87
8 Lm 1,443.42
1 Lm 220.50
Mechanical Pad
9 453 Benayat m3 9.07
4 Steel Reinforcement (3% allowable wastage) - Straight Reinforcement bars 8 & 10, 12, 14, 16mmSupply, Cut, Bend & Installation
1 453 Benayat ton 4,394.07
8 ton 140.02
Cut, Bend & Installation
Installation only
3 453 Benayat ton 11.12
5 Masonry WorksSupply & Installation of Blocks 200mm (CMU), Non fire rated
3.1 m2 6,470.4
1 m2 49,395.4
1 m2 98.6
Supply & Installation of Blocks 150mm (CMU), Non fire rated
3.2 295 Dar Anan m2 1,220.1
2 m2 14,809.7
2 553 Al Otaibi m2 85.2
Supply & Installation of Blocks 100mm (CMU), Non fire rated
3.3 295 Dar Anan m2 1,747.9
3 m2 20,890.9
3 553 Al Otaibi m2 56.8
3 m2 391.3
Additional Rate for Fire Rated Solid Block or / Filled Block
526 Dar Anan
526 Dar Anan
526 Dar Anan
526 Dar Anan
526 Dar Anan560 Nahedh Al Monshri
526 Dar Anan
295 Dar Anan453 Benayat553 Al Otaibi
453 Benayat
453 Benayat
526 Dar Anan
![Page 3: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/3.jpg)
3.4 295 Dar Anan m2 635.3
4 m2 2,496.9
4 553 Al Otaibi m2 85.2
Backing rod (3cm thick) & fire rated sealant above block walls
5 m2 793.5
6 Plastering WorksSupply & Installation of cement plaster (Interior)
m2 3,150.0
3.13 m2 17,271.4
1 m2 76,933.6
1 m2 18,256.4
1 m2 11,000.0
Elect/LC1 pcs 18.0
Supply & Installation of cement plaster (Exterior)
2.11 295 Dar Anan m2 7,837.2
2 m2 62,339.4
550 Marim Jalani m2 -
2 560 Nahedh Al Monshri m2 11,007.6
2 562 Awan Al Awarrd m2 6,317.0
Elect/LC2 pcs 21.0
Supply & Installation of G.I. groove 20mm in plaster (external)
2.15 295 Dar Anan Lm 5,388.3
3 Lm 26,703.6
2 560 Nahedh Al Monshri Lm 5,589.3
3 562 Awan Al Awarrd Lm 1,664.0
7 Concrete Works - ADDITIONAL WORKSExtra over for SOG from 20Mpa to 30Mpa
D1 m2 7,268.25
Supply & install precast lintel above openings
D2 Lm 8,183.18
6 Lm 1,102.36
Reinforced conc beams & post for blocks walls incl rebars
D3 Lm 1,066.02
Extra over for conc negative in walls for doors & windows
D5 pcs 730.00
453 Benayat
453 Benayat
214 Marim Jalani295 Dar Anan453 Benayat560 Nahedh Al Monshri562 Awan Al Awarrd
560 Nahedh Al Monshri
453 Benayat
560 Nahedh Al Monshri
453 Benayat
453 Benayat
453 Benayat526 Dar Anan
453 Benayat
453 Benayat
![Page 4: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/4.jpg)
Supply & install reinf conc architrave around openings
D6 Lm 2,077.50
Supply & install PVC waterstop 10mm & 15mm
D7 Lm 146.70
5 Lm 94.50
Bituminous high grade fiber filler bd joint 20mm
D9 m2 2,795.99
8 Lm 471.93
Supply & install filling tie rod holes w/ non-shrink grout
D10pcs 18,974.00
pcs 33,762.30
12 pcs 1,584.00
Supply & install concrete screed (finishing works)
1 m2 2,511.78
Supply & install broom finish (interior)
2 m2 0.00
Extra over for hardener (broom fin)
3 m2 2,352.81
Concrete window sill incl forms & rebars
7 Lm 493.03
8 Masonry Works - ADDITIONAL WORKSSupply & Installation of tie beams & post
A1 Lm 116.6
Supply & Installation of insulation board 50mm
2.5 295 Dar Anan m2 1,979.3
A2 Lm 6,203.6
553 Al Otaibi m2 -
Extra over for supply & install 200mm filled blocks - 1201 only bet prison cells
A3 m2 2,708.4
Extra over for supply & install 200mm non-filled blocks (all bldgs)
A4 m2 46,687.0
Extra over for supply & install 150mm
A5 m2 2,518.6
Extra works for blocks Scaffolding & handling works above 4.5M
2.10 295 Dar Anan m2 74.7
453 Benayat
453 Benayat526 Dar Anan
453 Benayat (around SOG)526 Dar Anan
453 Benayat (tie beams)453 Benayat (walls)526 Dar Anan
526 Dar Anan
526 Dar Anan
526 Dar Anan
526 Dar Anan
453 Benayat
453 Benayat
453 Benayat
453 Benayat
453 Benayat
![Page 5: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/5.jpg)
A6 Lm 1,349.2
Supply & Installation of Blocks 300mm (100+150+50 insulation), Non fire rated
2.2 295 Dar Anan m2 863.9
Supply & Installation of 200mm preinsulated blocks
2.9 295 Dar Anan m2 2,563.7
Extra over due to using load bearing blocks
E1 m2 85,096.0
Extra over for pre-insulated blocks walls
E2 m2 4,850.6
Supply & install rigid thermal insulation board for block walls
E3 m2 8,768.2
Blocks & plaster Ht=60cm around ducts open on roofs
9.4 Lm 2,511.6
Solid blocks for MH 60x60x80 incl plastering & waterproof
4 295 Dar Anan pcs 61.4
9 Plastering Works - ADDITIONAL WORKSSupply & Installation of cement plaster, (Exterior-parapet)
2.13 295 Dar Anan m2 1,903.9
Supply & install cement plaster to ceiling (external)
B4 m2 1,530.1
Extra over Scaffolding & handling works above 4.5M (interior plaster)
3.15 295 Dar Anan m2 530.6
B5 m2 387.3
Extra over Supply & Installation of G.I. groove 20mm in plaster (external)
C1 Lm 26,703.6
Extra over for supply & install for plaster to parapet coping (external)
C2 Lm 7,315.1
Extra over Scaffolding & handling works above 4.5M (exterior plaster)
2.14 295 Dar Anan m2 1,576.2
C4 m2 10,067.8
Extra over for slabs & beams for scaffolding & handling 4mtr and above
C5 m2 260.8
Supply & Installation of cement plaster to parapet coping (Exterior)
453 Benayat
453 Benayat
453 Benayat
453 Benayat
453 Benayat
453 Benayat
453 Benayat
453 Benayat
453 Benayat
453 Benayat
453 Benayat
![Page 6: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/6.jpg)
2.16 295 Dar Anan Lm 2,236.3
Cement plaster on circular col Ø300, Ht=2.5mm
3.16 295 Dar Anan pcs 12.8
Supply & Installation of cement linear plaster inside openings
11 295 Dar Anan Lm 4,292.9
10 EXTERIOR WORKSFence Type 2 (foundation)
1 Lm 169.33
Watch Tower (B2602)
1 pcs 2.00
pcs 3.00
Dome & Minaret
3.1 pcs 1.00
Guard Room (B2501)
4.1 pcs 5.85
Gates (along precast fence)
13.1 pcs 0.50
526 Dar Anan
526 Dar Anan562 Awarrd (blocks & plaster only)
453 Benayat
453 Benayat
453 Benayat
![Page 7: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/7.jpg)
100 201 202 400 500 601
108.35 135.81 83.50 87.49 35.47
104.82 143.92 49.75 21.95
456.57 644.09 612.03 145.12 51.52
171.18 202.10 112.26 115.87 54.22
22.58 32.27 13.62 16.50 5.04
12.92 10.67 10.49
380.50 493.50 299.70 232.88 101.33
3,710.08 4,794.93 1,764.61 2,450.90 1,294.48
2,726.83 2,088.40 2,353.95 1,438.11 796.27
![Page 8: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/8.jpg)
417.46 486.29 385.41 253.82 15.69
38.58
511.56 1,144.23 471.07 146.05 25.26
20.84 50.63 22.12 34.96 35.28
24.30
448.60 455.82 286.30 247.71 111.00
Steel Reinforcement (3% allowable wastage) - Straight Reinforcement bars 8 & 10, 12, 14, 16mm
275.57 414.60 288.51 139.52 43.84
3,136.5 5,991.1 3,398.7 1,043.3 852.7
1,350.0 2,065.2 1,595.4 767.8 120.8
1,547.1 2,147.7 1,601.8 356.6 174.5
![Page 9: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/9.jpg)
204.8 396.1 16.9 50.6
6,185.0 10,837.1 6,965.0 1,834.9 961.7
5,800.0
4,117.2 5,213.8 3,668.1 2,879.7 1,105.8
3,150.0
1,720.6 2,492.7 1,787.6 936.3 525.2
2,300.0
380.50 493.50 299.70 232.88 101.33
452.75 719.20 509.60 104.74 91.50
10.00 4.00 10.00 11.00
![Page 10: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/10.jpg)
153.49 145.77 113.86 65.72 31.77
1,147.00 1,218.00 766.00 565.00 290.00
580.00 513.00 908.00 15.00
86.48
1,309.2 1,795.2 1,484.5 120.8
Extra over for supply & install 200mm filled blocks - 1201 only bet prison cells
3,136.5 5,991.1 3,398.7 1,043.3 852.7
![Page 11: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/11.jpg)
94.5 63.7 12.2
Supply & Installation of Blocks 300mm (100+150+50 insulation), Non fire rated
6,033.6 10,204.0 6,595.9 2,167.7 1,148.0
306.6 167.0
88.8 69.1 43.4 10.6 24.7
122.6 75.8 82.3 15.7 10.0
Extra over Scaffolding & handling works above 4.5M (interior plaster)
8.8 83.6 6.0
Extra over Supply & Installation of G.I. groove 20mm in plaster (external)
1,720.6 2,492.7 1,787.6 936.3 525.2
Extra over for supply & install for plaster to parapet coping (external)
448.6 455.8 286.3 247.7 111.0
Extra over Scaffolding & handling works above 4.5M (exterior plaster)
791.2 2,169.2 1,583.7 662.2 48.6
Extra over for slabs & beams for scaffolding & handling 4mtr and above
53.8 181.7 25.3
![Page 12: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/12.jpg)
1.00
![Page 13: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/13.jpg)
602 700 800 901-1 901-2 901-3
25.94
18.00
44.71
55.79
5.02
97.09
815.49
647.55
![Page 14: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/14.jpg)
51.90
91.68
2.27
145.53
48.91
717.9
5.8
43.2
![Page 15: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/15.jpg)
1,808.5
1,186.1
678.8
849.2
530.9
436.32
97.09
98.90
![Page 16: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/16.jpg)
41.15
274.00
72.49
717.9
![Page 17: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/17.jpg)
766.8
370.3
12.5
149.2
436.3
145.5
384.9
41.99
![Page 18: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/18.jpg)
187.0
230.4
![Page 19: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/19.jpg)
901-4 901-5 902 903-1 903-2 1001
30.60
3.18
23.39
15.86
56.02
54.43
49.94
66.57
3.61
5.36
105.38
107.00
931.79
279.03
746.17
960.65
![Page 20: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/20.jpg)
44.89
36.69
17.57
79.70
56.71
17.90
6.73
113.00
116.12
44.36
42.76
409.0
559.0
33.2
258.6
1.3
246.5
![Page 21: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/21.jpg)
66.8
820.0
1,168.6
481.9
798.9
247.3
242.9
105.38
110.65
103.68
![Page 22: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/22.jpg)
32.42
303.01
247.00
747.00
80.10 167.91
80.10 167.91
23.52
246.5
559.0
![Page 23: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/23.jpg)
229.5
1,064.1
41.6
9.0
155.9
242.9
113.0
29.0
![Page 24: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/24.jpg)
109.7
259.9
![Page 25: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/25.jpg)
1002 1100 1201-1 1201-2 1201-3 1201-4
61.55 150.49 150.49 150.49 152.71
54.90 152.40 152.40 152.40 152.40
44.36 154.72 154.72 154.72 154.72
115.24 375.57 375.57 375.57 375.57
44.18 73.80 73.80 73.80 73.80
4.95 7.99 7.99 7.99 7.99
34.58 100.54 100.54 100.54 100.54
229.96 506.94 506.94 506.94 506.94
2,007.13 4,930.30 4,930.30 4,930.30 4,969.74
1,458.44 3,521.96 3,521.96 3,521.96 3,559.94
![Page 26: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/26.jpg)
191.66 504.52 504.52 504.52 504.52
128.95 128.95 128.95 128.95
236.67 448.83 448.83 448.83 448.83
30.28 30.28 30.28 40.37
54.06 100.98 100.98 100.98
323.90 468.91 625.21 625.21 625.21
110.29 314.09 314.09 314.09 315.07
1,642.1 2,325.4 2,447.8 2,447.8 2,447.8
243.5 609.5 609.5 609.5 609.5
477.9 1,770.3 1,770.3 1,770.3 1,770.3
![Page 27: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/27.jpg)
124.5 344.9 363.1 363.1 363.1
1,783.2 4,532.9 5,741.7 5,741.7
2,091.12 2,425.4 4,608.3 4,850.8 4,850.8
947.1 1,067.6 2,028.3 2,135.1 2,135.1
229.96 506.94 506.94 506.94 506.94
157.00 530.70 530.70 530.70 530.70
78.51 124.43 124.43 124.43 124.43
28.00 131.00 131.00 131.00 131.00
![Page 28: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/28.jpg)
71.20 287.22 287.22 287.22 287.22
82.68 232.85 232.85 232.85 232.85
396.00 1,278.00 1,278.00 1,278.00 1,278.00
1,166.00 4,561.00 4,561.00 4,561.00 4,561.00
6.6 22.0 22.0 22.0 22.0
499.6 525.9 525.9 525.9
1,642.1 1,825.8 1,921.9 1,921.9 1,921.9
124.5 329.7 329.7 329.7 329.7
![Page 29: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/29.jpg)
285.0 294.0 300.0 300.0
2,363.5 4,705.2 4,827.6 4,827.6 4,827.6
409.7 1,559.2 1,528.0 1,559.2 1,559.2
84.1 322.7 322.7 322.7 322.7
93.4 85.1 85.1
125.6 125.6
947.1 1,067.6 2,028.3 2,135.1 2,135.1
323.9 594.0 625.2 625.2
235.1 614.7 647.1 647.1
![Page 30: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/30.jpg)
![Page 31: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/31.jpg)
1201-5 1201-6 1201-7 1201-8 1201-9 1201-10
![Page 32: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/32.jpg)
2,024.6
98.6
260.6
85.2
1,424.1
56.8
![Page 33: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/33.jpg)
327.3
85.2
1,575.00 1,575.00
1,163.7
1,102.0
2.0 2.0 2.0
809.6
320.0
85.60
![Page 34: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/34.jpg)
27.00
1,358.7
![Page 35: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/35.jpg)
19.2
243.2
![Page 36: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/36.jpg)
411.5
![Page 37: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/37.jpg)
1201-11 1201-12 1201-13 1201-14 1201-15 1201-16
2.22 2.22
39.44 39.44
37.98 37.98
![Page 38: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/38.jpg)
354.48 113.03
128.95 20.96
219.51 87.12
10.09 10.09
312.61
82.56 18.82
11.12
2,203.0 734.3
548.6 182.9
1,593.2 531.1
![Page 39: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/39.jpg)
326.8 108.9
2.0
2.0
0.00 0.00
477.63 159.21
![Page 40: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/40.jpg)
258.50 86.17
4,561.00 1,368.30
22.0
473.3 157.8
1,729.7 576.6
296.7 98.9
![Page 41: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/41.jpg)
4,344.8 1,448.3
161.4
-
![Page 42: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/42.jpg)
![Page 43: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/43.jpg)
1201-17 1201-18 1201-19 1201-20 1201-21 1201-22
![Page 44: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/44.jpg)
![Page 45: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/45.jpg)
2.0 2.0 2.0
2.0 2.0 2.0 2.0
![Page 46: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/46.jpg)
![Page 47: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/47.jpg)
![Page 48: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/48.jpg)
![Page 49: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/49.jpg)
1201-23 1201-24 1202 1204-1 1204-2 1204-3
![Page 50: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/50.jpg)
![Page 51: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/51.jpg)
1.0 1.0 1.0
2.0 2.0
![Page 52: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/52.jpg)
![Page 53: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/53.jpg)
33.2
![Page 54: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/54.jpg)
![Page 55: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/55.jpg)
1204-4 1301 1302 1400 1500 1601-1
87.60 142.14 144.71 145.41
82.80 135.90 87.73
86.42 103.63 193.90 195.29
159.34 309.44
62.58 110.02 228.42 206.28
7.87 10.66 29.59 18.42
59.49 137.77
291.29 555.22 570.51 473.56
2,906.47 4,697.51 4,228.68 2,914.77
2,392.98 3,864.57 3,492.22 2,604.85
![Page 56: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/56.jpg)
259.18 482.69 220.92 197.08
7.24
399.28 452.05 173.83 498.71
113.48
11.51
354.00 550.70 480.00 480.70
169.30 273.41 179.92 251.31
343.1 2,710.2 3,094.0 2,893.9
264.8 1,073.1 394.3 1,529.7
541.4 1,738.9 360.9 742.1
![Page 57: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/57.jpg)
46.6 456.1
58.3
4,160.6 4,019.7 6,807.2
645.0
1.0
4,036.6 5,384.9 2,901.4
1,750.0
2,328.6 2,117.9 695.0
900.0
291.29 555.22 570.51 473.56
236.55 593.10 322.30 668.00
74.19 415.60
81.00 62.00
![Page 58: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/58.jpg)
203.85 308.90
128.90 235.73 188.80 105.57
658.00 1,709.00 1,758.00 605.00
2,167.00 4,058.00
713.5
343.1 2,710.2 3,094.0 2,893.9
181.2 498.8
![Page 59: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/59.jpg)
1,149.2 5,522.2 3,849.2 5,165.7
667.6
530.5 1,622.5
68.6 183.9 56.6 87.6
544.0 28.0 4.3
2,328.6 2,117.9 695.0
550.7 480.0 480.7
419.6 407.0 282.7
![Page 60: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/60.jpg)
![Page 61: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/61.jpg)
1601-2 1601-3 1601-4 1601-5 1601-6 1602
![Page 62: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/62.jpg)
480.00
3.65
2,572.6
883.5
65.5 101.0
![Page 63: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/63.jpg)
5,627.5 4,341.5
8,940.0
7,056.0 3,598.0
1,163.7 905.1
3,050.0
3,040.0 1,855.0
809.6 629.7
744.9
756.0 456.0
518.70
![Page 64: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/64.jpg)
364.48
364.48
204.40
620.6
![Page 65: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/65.jpg)
634.4
810.0 607.5
54.19 42.15
243.2 189.16
![Page 66: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/66.jpg)
411.5 338.9
7.20 5.60
1,558.0 1,339.9
![Page 67: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/67.jpg)
1603 1701 1702 1900 2001 2002
133.88 97.84
68.09
245.26 161.38
256.62 154.23
29.61 14.22
473.02 324.76
2,670.84 3,034.46
3,448.06 2,237.00
![Page 68: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/68.jpg)
269.81 204.30
395.71 265.77
31.60 56.12
552.00 403.60
4.74 4.33
235.04 161.72
3,142.4 2,387.1
1,121.2 632.9
936.4 628.0
![Page 69: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/69.jpg)
3,402.8 3,615.2
3,597.9 2,618.9
1,499.0 1,062.9
473.02 324.76
339.25 317.70
![Page 70: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/70.jpg)
119.60 89.56
1,071.00 628.00
533.9
3,142.4 2,387.1
![Page 71: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/71.jpg)
5,199.9 3,648.0
1,577.1
104.1 67.4
17.4 26.1
1,499.0 1,062.9
552.0 403.6
523.9 386.5
![Page 72: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/72.jpg)
![Page 73: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/73.jpg)
2003 2004 2005 (1~3) 2006 2007-1 2007-2
![Page 74: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/74.jpg)
2.01 8.19 8.19
158.10 97.60 97.60
1.87 2.91 2.91
778.5 52.0 52.0
42.8
7.4 37.2 37.2
![Page 75: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/75.jpg)
1,028.6 496.8 400.5
114.0 114.0
0.5 0.5
681.4 393.3 393.3
545.9 241.0 241.0
62.73 54.72 54.72
![Page 76: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/76.jpg)
53.23
53.23
19.26 43.20 43.20
![Page 77: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/77.jpg)
87.7 310.9 310.9
138.6
41.0 66.2 66.2
84.2 63.5 63.5
![Page 78: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/78.jpg)
141.3 88.6 88.6
99.3 158.8 127.4
![Page 79: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/79.jpg)
2007-3 2007-4 2008-1 2008-2 2100 2201
71.62
1.67
57.25
11.47
134.48
38.69
113.38
44.03
8.73
3.15
230.51
41.03
2,324.82
241.69
1,690.42
691.45
![Page 80: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/80.jpg)
154.89
8.19 8.19 7.35 7.35 12.02
250.27
47.51
21.17
201.26
97.60 97.60 97.60 97.60
140.87
2.91 2.91 2.76 2.76 29.80
52.0 52.0 47.5 47.5
2,009.8
119.6
37.2 37.2
84.4
![Page 81: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/81.jpg)
496.8 496.8 524.2 555.7
3,413.4
114.0 114.0 580.0
1.0 0.5
393.3 393.3 393.3 393.3
2,389.1
660.0
241.0 241.0 305.0 305.0
659.7
430.0
230.51
347.60
54.72 54.72 26.82 26.82
![Page 82: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/82.jpg)
75.50
168.92
512.00
421.00
399.27 399.27
399.27 399.27
43.20 43.20 14.40 14.40
2,009.8
![Page 83: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/83.jpg)
310.9 310.9 354.2 354.2
2,213.8
644.1
67.5
243.4
66.2 66.2 62.5 66.2
37.6
659.7
201.3
63.5 63.5 63.5 63.5
370.4
![Page 84: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/84.jpg)
88.6 88.6 88.4 88.4
158.8 158.8 56.4 56.4
![Page 85: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/85.jpg)
2202 2301 2302 2400 2501-1 2501-2
83.11
59.98
145.51
116.68
12.73
247.42
2,583.56
1,768.38
![Page 86: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/86.jpg)
134.67
35.95
219.49
12.09
51.68
395.00
122.63
1,771.7
97.7
58.4
![Page 87: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/87.jpg)
2,840.4
2,450.0
1,240.0
247.42
279.90
![Page 88: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/88.jpg)
97.53
499.00
1,771.7
![Page 89: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/89.jpg)
1,927.7
546.0
49.1
96.9
1,240.0
395.0
236.8
![Page 90: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/90.jpg)
1.00 1.00
![Page 91: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/91.jpg)
2501-3 2501-4 2501-5 2501-6 2501-7 2501-8
![Page 92: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/92.jpg)
![Page 93: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/93.jpg)
![Page 94: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/94.jpg)
![Page 95: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/95.jpg)
![Page 96: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/96.jpg)
0.85 1.00 1.00 1.00
![Page 97: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/97.jpg)
2501-9 2502 2602-1 2602-2 2602-3 2602-4
![Page 98: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/98.jpg)
![Page 99: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/99.jpg)
![Page 100: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/100.jpg)
![Page 101: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/101.jpg)
![Page 102: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/102.jpg)
1.00
1.00 1.00
![Page 103: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/103.jpg)
2602-5 2602-6 2602-7 2602-8 2602-9 2602-10
![Page 104: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/104.jpg)
![Page 105: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/105.jpg)
![Page 106: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/106.jpg)
![Page 107: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/107.jpg)
![Page 108: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/108.jpg)
1.00
![Page 109: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/109.jpg)
2602-11 2602-12 2602-13 2602-14 2700 2800
![Page 110: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/110.jpg)
![Page 111: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/111.jpg)
![Page 112: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/112.jpg)
![Page 113: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/113.jpg)
![Page 114: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/114.jpg)
1.00
![Page 115: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/115.jpg)
2900 3000 3100 3201 3202A-1 3202A-2
5.65 5.65
15.52 15.52
2.65 2.65
40.05 40.05
5.35 5.59
1.20 1.30
12.68 13.70
26.31 26.31
322.00 322.00
276.75 283.82
![Page 116: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/116.jpg)
14.35 14.35
29.64 29.64
52.60 52.60
23.70 23.76
247.7 247.7
![Page 117: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/117.jpg)
351.8 351.8
383.0
1.0 2.5
284.0 284.0
650.0
1.0
120.6 120.6
540.0
26.31 26.31
18.00 18.00
![Page 118: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/118.jpg)
35.33 35.33
182.00 194.00
133.79
133.79
247.7 247.7
![Page 119: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/119.jpg)
247.7 247.7
143.0 143.0
120.6 120.6
52.6 52.6
![Page 120: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/120.jpg)
![Page 121: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/121.jpg)
3202A-3 3202A-4 3202A-5 3202A-6 3202A-7 3202A-8
5.65 5.65
15.52 15.52
2.65 2.65
40.05 40.05
8.72 8.24
2.54 2.35
26.88 24.86
26.31 26.31
322.00 322.00
375.64 361.52
![Page 122: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/122.jpg)
14.35 14.35
0.40 0.40
29.64 29.64
52.60 52.60
0.00 51.80
47.70 47.70 47.70
24.93 24.82
0.23 0.23
104.1 104.1
247.7 247.7
![Page 123: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/123.jpg)
84.9 84.9
337.2 337.2
351.8 351.8
201.3 201.3
284.0 284.0
120.6 120.6
120.6 120.6
26.31 26.31
18.00 18.00
19.71 19.71
![Page 124: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/124.jpg)
35.33 35.33
348.00 325.00
133.79
133.79
5.75 5.75
247.7 247.7
19.2 19.2
![Page 125: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/125.jpg)
135.8 135.8
247.7 247.7
143.0 143.0
21.4 21.4
120.6 120.6
52.6 52.6
10.7 10.7
![Page 126: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/126.jpg)
52.6 52.6
44.5 44.5
![Page 127: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/127.jpg)
3202A-9 3202A-10 3202A-11 3202A-12 3202A-13 3202B-1
5.22
21.66
9.63
1.06
29.00
2.65
3.40
22.09
32.83
5.43
15.41
0.97
3.92
24.05
20.64
249.62
174.13
189.47
439.30
![Page 128: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/128.jpg)
8.86
26.09
19.61
19.73
42.80
51.80
13.43
20.10
104.1
![Page 129: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/129.jpg)
84.9
270.4
330.0
346.0
257.4
320.0 320.0
320.0
100.8
120.0 120.0
132.0
24.05
0.00
19.71
![Page 130: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/130.jpg)
9.32
129.00
416.00
133.79 91.74
133.79 91.74
5.75
19.2
![Page 131: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/131.jpg)
135.8
-
100.8
42.8
![Page 132: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/132.jpg)
![Page 133: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/133.jpg)
3202B-2 3202B-3 3202B-4 3202B-5 3202B-6 3202B-7
![Page 134: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/134.jpg)
38.70
70.3
![Page 135: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/135.jpg)
53.3
280.6 280.6 280.6
260.0 67.6 260.0 260.0
108.6 108.6 108.6
![Page 136: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/136.jpg)
91.74 91.74 91.74
91.74 91.74 91.74
17.0
![Page 137: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/137.jpg)
116.6
![Page 138: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/138.jpg)
![Page 139: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/139.jpg)
3202B-8 3202B-9 3203 3204 3205 3206
1.46
1.71
3.14
4.98
0.43
4.57
59.32
57.13
![Page 140: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/140.jpg)
4.49
4.20
22.40
38.70
3.16
54.9
![Page 141: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/141.jpg)
59.2
280.6
108.1
260.0
62.4
108.6
4.57
2.80
![Page 142: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/142.jpg)
5.90
45.00
91.74 28.48
91.74 28.48
54.9
![Page 143: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/143.jpg)
54.9
62.4
22.4
![Page 144: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/144.jpg)
![Page 145: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/145.jpg)
3207 3208 3209 3210 L.S. 1 L.S. 2
![Page 146: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/146.jpg)
21.00
50.2
![Page 147: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/147.jpg)
![Page 148: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/148.jpg)
50.2
![Page 149: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/149.jpg)
50.2
![Page 150: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/150.jpg)
![Page 151: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/151.jpg)
L.S. 3 L.S. 4 L.S. 5 L.S. 6 L.S. 7 L.S. 8
4.71 7.80
14.66 29.23
54.62 54.62
156.03 156.03
![Page 152: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/152.jpg)
54.37 84.98
8.96
8.01 16.21
160.8 230.5
![Page 153: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/153.jpg)
![Page 154: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/154.jpg)
49.30 45.20
![Page 155: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/155.jpg)
![Page 156: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/156.jpg)
![Page 157: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/157.jpg)
L.S. 9 L.S. 10 L.S. 11 L.S. 12 L.S. 13 L.S. 14
![Page 158: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/158.jpg)
![Page 159: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/159.jpg)
![Page 160: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/160.jpg)
![Page 161: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/161.jpg)
![Page 162: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/162.jpg)
![Page 163: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/163.jpg)
L.S. 15 L.S. 16 Gas tank Fence ADB .
.
.
2.13 2.16 .
.
.
.
4.23 4.36 16.72 .
.
.
.
.
21.60 .
.
.
.
10.13 11.07 39.99 .
.
.
.
.
.
.
.
.
.
.
.
26.31 26.26 24.92 .
.
.
.
.
48.98 49.80 93.00 .
.
.
.
.
.
.
.
.
![Page 164: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/164.jpg)
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
7.85 7.94 5.96 .
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
![Page 165: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/165.jpg)
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
![Page 166: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/166.jpg)
.
.
.
.
51.05 52.75 42.90 .
.
.
.
.
.
147.35 148.65 .
182.00 .
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
![Page 167: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/167.jpg)
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
![Page 168: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/168.jpg)
.
.
.
.
.
.
.
.
.
169.33 .
.
.
.
.
0.50
![Page 169: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/169.jpg)
SAUDI BINLADEN GROUP - ABCDPAYMENT CERTIFICATE DEPARTMENT
Project CORRECTIONAL FACILITIES P-1182, DammamSubject AS-BUILT QUANTITIESPeriod As of 18 Feb 2016
NO DESCRIPTION Unit TotalROOF WATERPROOFINGSupply & apply complete roofing waterproofing system using APP Bituminuos Waterproofing Membrane
1 Light weight foam concrete (excl cement)1 160 Hazem m2 3,667.18 1 m2 17,202.09
2 Light weight foam concrete (incl) cement2 m2 59,725.53 2 m2 21,860.71
1 m2 -
3 Sand cement mortar cant strip 800x800mm3 123 Ameel Lm 17,688.20 9 160 Hazem Lm 1,343.60 3 322 Cretec Lm 7,998.88 9 510 Kabbani Lm 6,730.27
4 Solvent base primer ASTM D414 123 Ameel m2 45,825.38 2 160 Hazem m2 3,775.30 4 322 Cretec m2 21,223.12 2 510 Kabbani m2 18,771.39
5 4mm Single layer bituminous membrane5 123 Ameel m2 46,902.85 3 160 Hazem m2 3,675.30 4 322 Cretec m2 21,223.12 3 510 Kabbani m2 17,765.14
6 250 micron Separation layer polyethylene6 123 Ameel m2 48,735.27 4 160 Hazem m2 991.78 6 322 Cretec m2 22,010.45 4 510 Kabbani m2 17,769.94
7 Thermal insulation7 123 Ameel m2 48,155.27 5 160 Hazem m2 1,566.78 7 322 Cretec m2 22,010.45 5 510 Kabbani m2 17,769.94
8 Protection layer of non-woven geotextile Alyaf 180gr/m28 123 Ameel m2 47,735.27 6 160 Hazem m2 1,994.73 8 322 Cretec m2 22,010.45 6 510 Kabbani m2 17,769.94
9 50mm thick Crushed gravel screened at 20-30mm size9 123 Ameel m2 302.51
510 Kabbani
123 Ameel322 Cretec510 Kabbani
![Page 170: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/170.jpg)
10 400x400x40mm Cement tiles 10 123 Ameel m2 46,777.19 8 160 Hazem m2 -
10 322 Cretec m2 24,595.48 8 510 Kabbani m2 17,769.94
11 APP bituminuos membrane skirting to roof parapet11 123 Ameel Lm 17,688.20 10 160 Hazem Lm 1,336.60 11 322 Cretec Lm 7,998.88 10 510 Kabbani Lm 6,760.87
12 Upper end of membrane w/ alumininum flashing & sealant12 123 Ameel Lm 18,118.64 11 160 Hazem Lm 410.30 12 322 Cretec Lm 7,998.88 11 510 Kabbani Lm 6,730.27
13 Treatment of drains & pipes13 123 Ameel pcs 3,356.19 12 160 Hazem pcs 73.00 13 322 Cretec pcs 1,358.28 12 510 Kabbani pcs 2,156.50
1 WET AREAS1.1 Liquid membrane Dura shield
1.1 m2 6,222.33 1.1 160 Hazem m2 517.07 2 m2 557.29
1.2 Ditto, to wall & upstands1.2 160 Hazem Lm 548.74 3 510 Kabbani Lm 909.44
1.3 Treatment of drains & pipes1.3 123 Ameel pcs 1,217.95 1.3 160 Hazem pcs 122.00 4 510 Kabbani pcs 238.00
2 TANK WATERPROOFING WORK (Basement)2.1 One coat primer & 2 layer 4+3mm thick (hor & vert)
2.1 123 Ameel m2 11,045.87 2 510 Kabbani m2 7,070.53
2.2 Supply & protection of layer of Non-woven geotextile2.2 123 Ameel m2 5,374.31 3 510 Kabbani m2 5,230.00
2.3 Ditto, to wall & upstands
2.4 Treatment of drains & pipes2.4 123 Ameel pcs 132.00
Protection board 4mm Armorproof (for external wall)6 510 Kabbani m2 1,793.29
123 Ameel
510 Kabbani
![Page 171: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/171.jpg)
Upper end of membrane w/ alumininum flashing & sealant8 510 Kabbani Lm 305.50
3 EXTERNAL FLOOR WATER PROOFING (Electrical rooms boxes/ftg for tanks & foundation basement)3.1 Double layer modified bituminuos membrane
3.2 Protection boards 9mm around basement Lm -
3.3 MS40 protection board around wall3.3 m2 5,631.20
4 INTERNAL WATER TANK (Pitch Tar Epoxy Coating)4.1 Apply 2 consecutive coats of 500micron
4.1 123 Ameel m2 3,787.46
5 UNDERGROUND INTERNAL TANK (Epoxy Coat)5.1 Apply 2 consecutive coats of 600micron
5.1 123 Ameel m2 2,580.78
3 Epoxy Coating (Masterseal 180 or Noticoat EP 405)3.5 Application of epoxy coats on floors, walls & ceiling
3.5 123 Ameel m2 16,460.53
123 Ameel
![Page 172: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/172.jpg)
100 201 202 400 500 601
Supply & apply complete roofing waterproofing system using APP Bituminuos Waterproofing Membrane
2,273.70 515.74 2,895.15 1,718.79 1,378.34 910.25
605.02 146.78 930.78
566.18 354.50 345.84
2,273.70 515.74 2,895.15
1,718.79 1,378.34 910.25
2,273.70 515.74 2,895.15
1,718.79 1,378.34 910.25
2,273.70 515.74 2,895.15
1,718.79 1,378.34 910.25
2,273.70 515.74 2,895.15
1,718.79 1,378.34 910.25
2,273.70 515.74 2,895.15
1,718.79 1,378.34 910.25
302.51
![Page 173: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/173.jpg)
2,273.70 515.74 2,895.15
1,718.79 1,378.34 910.25
605.02 146.78 930.78
566.18 354.50 345.84
605.02 146.78 930.78
566.18 354.50 345.84
182.00 81.00 182.00
157.00 150.00 28.00
295.69 122.93 85.32
96.00 44.00
![Page 174: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/174.jpg)
EXTERNAL FLOOR WATER PROOFING (Electrical rooms boxes/ftg for tanks & foundation basement)
![Page 175: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/175.jpg)
602 700 800 901-1 901-2 901-3
450.20 450.20
582.63 566.50 473.81 473.95
271.20 169.69 151.20 151.20
184.82 126.60
582.63 473.81 450.20 450.20
473.95 563.05
582.63 473.81 450.20 450.20
473.95 563.05
582.63 473.81 473.81 473.81
473.95 563.05
582.63 473.81 473.81 473.81
473.95 563.05
582.63 473.81 473.81 473.81
473.95 563.05
![Page 176: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/176.jpg)
582.63 473.81 473.81 473.81
473.95 563.05
271.20 169.69 151.20 151.20
184.82 126.60
271.20 169.69 178.62 178.62
184.82 126.60
79.00 29.00 12.00 12.00
23.00 57.00
95.98 66.79 41.90 29.32 29.32
62.20 52.55 52.55
22.00 10.00 10.00 10.00
![Page 177: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/177.jpg)
![Page 178: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/178.jpg)
901-4 901-5 902 903-1 903-2 1001
450.06
473.81 473.81 473.81 473.81 2,767.20
178.62 178.62 189.60 189.60
152.06
473.81 473.81 473.81 473.81
450.06
473.81 473.81 473.81 473.81
450.06
473.81 473.81 473.81 473.81
450.06
473.81 473.81 473.81 473.81
450.06
473.81 473.81 473.81 473.81
450.06
![Page 179: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/179.jpg)
473.81 473.81 473.81 473.81
450.06
178.62 178.62 189.60 189.60
152.06
178.62 178.62 189.60 189.60
152.06
29.00 29.00 66.00 66.00
52.00
66.79 66.79 66.87 142.00
53.22
81.04
22.00 22.00
168.00
![Page 180: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/180.jpg)
![Page 181: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/181.jpg)
1002 1100 1201-1 1201-2 1201-3 1201-4
1,060.05
1,143.05 1,491.03 1,491.03 1,491.03
459.80 643.72
444.36 493.48
1,143.05 1,491.03
1,491.03 1,060.05
1,143.05 1,491.03
1,491.03 1,060.05
1,143.05 1,491.03
1,491.03 1,060.05
1,143.05 1,491.03
1,491.03 1,060.05
1,143.05 1,491.03
1,491.03 1,060.05
![Page 182: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/182.jpg)
1,143.05 1,491.03
1,491.03 1,060.05
459.80 643.72
444.36 493.48
459.80 643.72
444.36 493.48
83.00 84.60
120.00 158.00
110.84
66.00
![Page 183: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/183.jpg)
![Page 184: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/184.jpg)
1201-5 1201-6 1201-7 1201-8 1201-9 1201-10
1,467.64 1,467.64 965.00 2,446.06
1,491.03 3,444.51 987.63 1,491.03
643.72 643.72
444.36 523.48 523.48 409.09 932.48
1,491.03 1,491.03
1,491.03 1,467.64 1,467.64 965.00 2,446.06
1,491.03 1,491.03
1,491.03 1,467.64 1,467.64 965.00 2,446.06
1,491.03 1,491.03
1,491.03 1,467.64 1,467.64 965.00 2,446.06
1,491.03 1,491.03
1,491.03 1,467.64 1,467.64 965.00 2,446.06
1,491.03 1,491.03
1,491.03 1,467.64 1,467.64 965.00 2,446.06
![Page 185: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/185.jpg)
1,491.03 1,491.03
1,491.03 1,467.64 1,467.64 965.00 2,446.06
643.72 643.72
444.36 538.78 538.78 409.09 932.48
643.72 643.72
444.36 523.48 523.48 409.09 932.48
125.49 125.49
120.00 168.00 168.00 175.00 328.00
184.30
280.28
463.30
44.55
70.00
![Page 186: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/186.jpg)
![Page 187: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/187.jpg)
1201-11 1201-12 1201-13 1201-14 1201-15 1201-16
1,436.60 2,446.06
1,491.03 1,491.03
643.72 550.60
444.36 932.48
1,491.03 1,436.60
1,491.03 2,446.06
100.00 1,491.03 1,336.60
1,491.03 2,446.06
1,000.00 1,491.03 436.60
1,491.03 2,446.06
420.00 1,491.03 1,016.60
1,491.03 2,446.06
1,491.03 1,436.60
1,491.03 2,446.06
![Page 188: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/188.jpg)
1,491.03 1,491.03
1,491.03 2,446.06
643.72 550.60
444.36 932.48
643.72 275.30
444.36 932.48
84.60 26.00
120.00 328.00
243.33 223.79
84.64 365.10
67.00
![Page 189: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/189.jpg)
![Page 190: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/190.jpg)
1201-17 1201-18 1201-19 1201-20 1201-21 1201-22
2,446.06 2,441.02
1,118.27 2,485.05
500.81 1,170.40
932.48 935.61
1,160.02 2,485.05
2,446.06 2,441.02
1,160.02 2,485.05
2,446.06 2,441.02
1,160.02 1,686.11
787.33 2,446.06 2,421.60
1,160.02 1,686.11
787.33 2,446.06 2,421.60
1,160.02 1,686.11
787.33 2,446.06 2,421.60
![Page 191: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/191.jpg)
1,160.02 1,686.11
787.33 2,446.06 2,421.60
500.81 1,170.40
932.48 935.61
500.81 1,170.40
932.48 935.61
77.00 141.00
328.00 244.00
92.15 614.34 399.32
21.60 5.40 135.00
![Page 192: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/192.jpg)
![Page 193: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/193.jpg)
1201-23 1201-24 1202 1204-1 1204-2 1204-3
2,485.05 3,048.77 1,799.13 1,799.13
1,170.40 1,170.40 816.67 154.19
2,485.05 2,485.05 1,799.13 619.08
2,485.05 2,485.05 1,799.13 619.08
2,485.05 2,485.05 1,799.13 619.08
2,485.05 2,485.05 1,799.13 619.08
2,485.05 2,485.05 1,799.13 619.08
![Page 194: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/194.jpg)
2,485.05 2,485.05 1,799.13 619.08
1,170.40 1,170.40 816.67 154.19
1,170.40 1,170.40 816.67 154.19
141.00 141.00 262.00 4.01
614.34 534.48 434.54
135.00 5.40 64.00
![Page 195: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/195.jpg)
![Page 196: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/196.jpg)
1204-4 1301 1302 1400 1500 1601-1
1,799.13 2,394.76 2,070.15 1,184.29
816.67 744.83
491.92
1,799.13 1,035.08
1,184.29 1,006.25
1,799.13 2,070.15
1,184.29
1,799.13 2,070.15
1,184.29
1,799.13 2,070.15
1,184.29
1,799.13 2,070.15
1,184.29
![Page 197: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/197.jpg)
1,799.13 2,070.15
1,184.29
816.67 744.83
491.92
816.67 744.83
491.92
262.00 125.00
58.96
434.54 221.36
64.00 88.00
![Page 198: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/198.jpg)
![Page 199: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/199.jpg)
1601-2 1601-3 1601-4 1601-5 1601-6 1602
2,012.50
2,070.15 2,070.15 1,180.57 2,094.42 2,131.21
744.83 756.26 271.13
649.65 661.06 744.83
2,070.15 2,070.15 1,180.57
2,094.42 2,131.21 2,012.50
2,070.15 2,070.15 1,180.57
2,094.42 2,131.21 2,012.50
2,070.15 2,070.15 1,180.57
2,094.42 2,131.21 2,012.50
2,070.15 2,070.15 1,180.57
2,094.42 2,131.21 2,012.50
2,070.15 2,070.15 1,180.57
2,094.42 2,131.21 2,012.50
![Page 200: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/200.jpg)
2,070.15 2,070.15 1,180.57
2,094.42 2,131.21 2,012.50
744.83 756.26 271.13
649.65 661.06 744.83
744.83 756.26 271.13
649.65 661.06 744.83
125.00 130.00 117.00
84.02 85.50 149.00
221.36
88.00
![Page 201: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/201.jpg)
![Page 202: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/202.jpg)
1603 1701 1702 1900 2001 2002
1,254.52 155.32 2,368.80 1,624.67 1,233.06
618.98
67.92 1,126.73 610.09 586.18
1,254.52
155.32 1,942.42 1,413.46 1,233.06
1,254.52
155.32 1,942.42 1,413.46 1,233.06
1,254.52
155.32 1,942.42 1,413.46 1,233.06
1,254.52
155.32 1,942.42 1,413.46 1,233.06
1,254.52
155.32 1,942.42 1,413.46 1,233.06
![Page 203: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/203.jpg)
1,254.52
155.32 1,942.42 1,413.46 1,233.06
618.98
67.92 1,126.73 610.09 586.18
618.98
67.92 1,126.73 610.09 586.18
42.00
5.00 35.26 180.00 52.00
![Page 204: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/204.jpg)
![Page 205: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/205.jpg)
2003 2004 2005 (1~3) 2006 2007-1 2007-2
336.00 439.00
1,251.20 1,611.84
589.04 315.14 150.00 135.00
1,251.20 551.78 336.00 439.00
1,251.20 551.78 336.00 439.00
1,251.20 883.85 451.67
1,251.20 883.85 451.67
1,251.20 883.85 451.67
![Page 206: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/206.jpg)
1,251.20 883.85 451.67
589.04 315.14 150.00 135.00
589.04 315.14 135.00
28.00 20.00 5.00 8.00
199.07 178.59 173.20
296.80
46.00 53.00 25.00
![Page 207: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/207.jpg)
![Page 208: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/208.jpg)
2007-3 2007-4 2008-1 2008-2 2100 2201
216.85 1,221.49
101.40 648.88
216.85 1,221.49
216.85 1,221.49
216.85 1,221.49
216.85 1,221.49
216.85 1,221.49
![Page 209: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/209.jpg)
216.85 1,221.49
101.40 648.88
101.40 648.88
31.00 79.54
80.00
25.00
55.00
![Page 210: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/210.jpg)
4.00
![Page 211: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/211.jpg)
2202 2301 2302 2400 2501 2502
1,512.10 133.48
609.02 55.60 7.00
8.00
1,512.10 133.48 108.12
1,512.10 133.48 108.12
1,512.10 133.48
7.82
1,512.10 133.48
7.82
1,512.10 133.48 2.95
7.82
![Page 212: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/212.jpg)
1,512.10 133.48
7.82
609.02 55.60
8.00
609.02 55.60
8.00
120.00 19.00
0.50
172.84 39.20
16.82
![Page 213: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/213.jpg)
84.04 39.20
![Page 214: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/214.jpg)
2602-1 2602-2 2602-3 2602-4 2602-5 2602-6
![Page 215: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/215.jpg)
![Page 216: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/216.jpg)
![Page 217: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/217.jpg)
2602-7 2602-8 2602-9 2602-10 2602-11 2602-12
![Page 218: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/218.jpg)
![Page 219: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/219.jpg)
![Page 220: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/220.jpg)
2602-13 2602-14 2700 2800 2900 3000
243.18 2,638.62
88.20 469.44
243.18 2,638.62
243.18 2,638.62
243.18 2,638.62
243.18 2,638.62
243.18 2,638.62
![Page 221: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/221.jpg)
243.18
2,585.03
88.20 469.44
88.20 469.44
20.00 145.00
64.44 21.45 145.34 556.59
19.00 10.00 71.00 38.00
183.43
![Page 222: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/222.jpg)
183.43
![Page 223: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/223.jpg)
3100 3201 3202A-1 3202A-2 3202A-3 3202A-4
1,903.90 161.35 161.35
265.60 51.60
51.80 16.20
1,903.90 161.35
161.35
1,903.90 161.35
161.35
1,903.90 161.35
161.35 16.40
1,903.90 161.35
161.35 16.40
1,903.90 161.35
161.35 16.40
![Page 224: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/224.jpg)
1,903.90 161.35
161.35 16.40
265.60 51.60
51.80 16.20
265.60 51.60
51.80 16.20
168.00 2.00
1.00 1.00
173.88
55.00
46.80
![Page 225: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/225.jpg)
![Page 226: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/226.jpg)
3202A-5 3202A-6 3202A-7 3202A-8 3202A-9 3202A-10
157.00 157.00
161.35 161.35
51.60 51.60 51.00 51.00
161.35 161.35 157.00 157.00
161.35 161.35 157.00 157.00
161.35 161.35 157.00 157.00
161.35 161.35 157.00 157.00
161.35 161.35 157.00 157.00
![Page 227: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/227.jpg)
161.35 161.35 161.35
51.60 51.60 51.00 51.00
51.60 51.60 51.60
2.00 5.00 2.00 2.00
![Page 228: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/228.jpg)
![Page 229: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/229.jpg)
3202A-11 3202A-12 3202A-13 3202B-1 3202B-2 3202B-3
161.35 161.35 108.07
51.60 51.60
41.60
161.35 161.35
108.07
161.35 161.35
108.07
161.35 161.35
108.07
161.35 161.35
108.07
161.35 161.35
108.07
![Page 230: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/230.jpg)
161.35 161.35
108.07
51.60 51.60
41.60
51.60 51.60
41.60
2.00 2.00
1.00
![Page 231: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/231.jpg)
![Page 232: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/232.jpg)
3202B-4 3202B-5 3202B-6 3202B-7 3202B-8 3202B-9
108.07 108.07 108.07 108.07 108.07
41.60 41.60 41.60 41.60 41.60
108.07 108.07 108.07 108.07 108.07
108.07 108.07 108.07 108.07 108.07
108.07 108.07 108.07 108.07 108.07
108.07 108.07 108.07 108.07 108.07
108.07 108.07 108.07 108.07 108.07
![Page 233: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/233.jpg)
108.07 108.07 108.07 108.07 108.07
41.60 41.60 41.60 41.60 41.60
41.60 41.60 41.60 41.60 41.60
2.00 2.00 2.00 2.00 2.00
![Page 234: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/234.jpg)
![Page 235: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/235.jpg)
3203 3204 3205 3206 3207 3208
215.18 26.00
406.76
75.80 20.80 177.23
57.60 215.18 26.00
406.76
215.18 26.00 406.76
215.18 26.00 406.76
215.18 21.00 406.76
215.18 26.00 406.76
![Page 236: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/236.jpg)
28.16
406.76
75.80 20.80 177.23
21.60
177.23
4.00 2.00 27.00
12.24
3.00
120.59 2,671.33 2,201.44
120.59 1,997.35 1,532.25
![Page 237: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/237.jpg)
737.99 669.19
3,787.46
266.00 4,285.77
![Page 238: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/238.jpg)
3209 3210 Water Tank MH's LPG Tank 1 LPG Tank 2
![Page 239: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/239.jpg)
300.00 266.00 1,644.95 93.34 5,252.24
300.00 5,205.00
1,644.95 93.34
![Page 240: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/240.jpg)
301.50
266.00
11,908.76
![Page 241: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/241.jpg)
LPG Tank 3 L.S. 1 L.S. 2 L.S. 3 L.S. 4 L.S. 5
![Page 242: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/242.jpg)
100.00 199.97 275.70 270.70 455.20 335.75
100.00 57.38 61.16 67.96 136.68 70.71
10.00 10.00 10.00 10.00 10.00
![Page 243: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/243.jpg)
163.49 214.54 183.76 279.92 292.13
100.50 121.78 135.47 296.10 126.38
![Page 244: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/244.jpg)
L.S. 6 L.S. 7 L.S. 8 L.S. 9 L.S. 10 L.S. 11
![Page 245: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/245.jpg)
248.84 413.89 227.44 272.72 315.49 272.20
67.96 136.68 71.73 65.28 87.98 72.48
8.00 10.00 8.00 8.00 10.00 10.00
![Page 246: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/246.jpg)
161.90 313.46 160.18 207.44 233.16 199.72
116.53 296.86 119.59 112.67 191.83 136.33
![Page 247: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/247.jpg)
L.S. 12 L.S. 13 L.S. 14 L.S. 15 L.S. 16 Gas tank
![Page 248: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/248.jpg)
433.66 209.64 507.36 269.03 236.65
94.83 65.94 120.66 68.71 61.16
10.00 8.00 10.00
![Page 249: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/249.jpg)
340.95 143.70 381.18 200.33 175.49
176.51 130.18 279.63 127.90 112.52
![Page 250: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/250.jpg)
Fence curbstone ..........
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
![Page 251: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/251.jpg)
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
![Page 252: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/252.jpg)
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
![Page 253: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/253.jpg)
SAUDI BINLADEN GROUP - ABCDPAYMENT CERTIFICATE DEPARTMENT
Project CORRECTIONAL FACILITIES P-1182, DammamSubject AS-BUILT QUANTITIESPeriod As of 18 Feb 2016
NO DESCRIPTION Unit Total 1 PAINTING WORKS
INTERNALFLOOR
Epoxy coating system16-2 m2 1,261.9
WALLEmulsion (acrylic)
17-1214 Marim Jalani m2 17,126.5 214 Marim Jalani (elect rms) m2 877.6
4.4 m2 -
10.1 m2 4,483.0
1 m2 1,512.1
Epoxy coating system16-1 214 Marim Jalani m2 9,680.2
Vetonit repair4.7 295 Dar Anan m2 -
Extra over for wall ht >4.5m16-5 214 Marim Jalani m2 300.1
CEILINGAnti-bacterial Paint
Emulsion
18-2214 Marim Jalani m2 7,989.8 214 Marim Jalani - HCS m2 1,377.6 214 Marim Jalani (elect rms) m2 65.1
5.1 295 Dar Anan m2 27.4 2 560 Nahedh Al Monshri m2 666.1
Extra over for wall ht >4.5m
16-6214 Marim Jalani m2 2,673.0 214 Marim Jalani - HCS m2 246.0
METAL DOORS & WINDOWSBar Grill Door (BGD)
15-1 214 Marim Jalani m2 4,281.0
Access Door (AD)15-2 214 Marim Jalani m2 257.9
Hollow Metal Door (HMD)15-3 214 Marim Jalani m2 4,116.8
Full Putty Works
214 Marim Jalani
295 Dar Anan453 Benayat560 Nahedh Al Monshri
![Page 254: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/254.jpg)
15-4 214 Marim Jalani m2 4,921.0
Bar Grill Window17-3 214 Marim Jalani pcs 1,204.4
Louver Window17-4 214 Marim Jalani pcs 32.2
ADDITIONAL WORKSElectrical rooms (exterior)
18-1 214 Marim Jalani pcs 6.3
Low current rooms (interior)18-2 214 Marim Jalani pcs 7.9
Building electrical rooms (interior)18-3 214 Marim Jalani pcs 15.3
EXTERNALWALL
Texturedm2 93,444.0
16-4 m2 3,158.4
3.2 m2 1,126.1
Maytas m2 12,699.0
Repair works
m2 148,083.4
Scaffolding for textured painting works above 4.5m Ht3.3 295 Dar Anan Lm 137.7
Textured on Parapet coping3.5 295 Dar Anan Lm 251.1
2 TILING WORKSINTERNAL
FLOORCeramic tile 100x100 (install only)
1.40 m2 43.4
Ceramic tile 200x200 (install only)1.50 295 Dar Anan m2 80.0
Ceramic tile 300x300 (install only)1.60 295 Dar Anan m2 648.3
Terrazzo tile 400x400x40 (supply/install only)1.12 295 Dar Anan m2 807.7
1 m2 985.7
Terrazzo tile 400x400x40, pattern (supply/install only)1.13 295 Dar Anan m2 186.6
197 Al Tawakl214 Marim Jalani295 Dar Anan
197 Al Tawakl
295 Dar Anan
553 Al Otaibi (install only)
![Page 255: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/255.jpg)
Terrazzo border W=100 (supply/install only)1.15 295 Dar Anan Lm 261.9
Terrazzo border W=200 (supply/install only)1.16 295 Dar Anan Lm 77.5
Terrazzo tread 40mmx300, riser 20mmx1501.17 295 Dar Anan Lm 3.3
BASECeramic tile 100x400 (install only)
3 553 Al Otaibi Lm 735.3 Ceramic cove base (install only)
2.1 295 Dar Anan Lm 253.2 Terrazzo skirting 100x200mm (supply/install)
2.2 295 Dar Anan Lm 833.5
WALLCeramic tile 100x100 (install only)
3.8 295 Dar Anan m2 164.7
Ceramic tile 200x200 (install only)3.9 295 Dar Anan m2 1,132.7 2 553 Al Otaibi m2 118.8
Ceramic corner cove 200x200 (install only)3.11 295 Dar Anan Lm 831.0
553 Al Otaibi Lm -
![Page 256: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/256.jpg)
100 201 202 400 500 601
3,246.2 4,017.9 406.1 92.8 105.9 22.3
4,483.0
75.0
140.0
350.0 353.7
7.7 15.8 1.6
134.4 216.4 71.4 21.6 21.0
![Page 257: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/257.jpg)
1.4
2,371.7 2,921.0 2,122.2 1,881.0 738.6 1,716.0
3,162.2 3,894.6 2,829.6 2,508.0 984.8 2,745.6
554.1 257.5
![Page 258: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/258.jpg)
494.5 109.9
118.8
![Page 259: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/259.jpg)
602 700 800 901-1 901-2 901-3
80.4 343.0 343.0 24.6 44.1 44.1
210.0 226.1
382.5 135.1 189.1
2.5 9.0 9.0
37.2 42.6 38.4 38.4 38.4
![Page 260: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/260.jpg)
465.0 457.8 502.8 502.8
586.6
417.3
620.0 712.8 610.4 670.4 670.4
28.8
32.0
224.2
123.6
![Page 261: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/261.jpg)
148.2
3.3
309.2
99.3
104.5
177.3
![Page 262: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/262.jpg)
901-4 901-5 902 903-1 903-2 1001
343.0 259.6 308.0 44.1 45.6
226.1 23.0 50.0
189.1 112.5 136.1
9.0 10.5
15.1
38.4 38.4 39.6 37.8 37.8
![Page 263: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/263.jpg)
149.5
2.1 23.1
0.7
83.8 384.0
441.8 543.7 598.5
234.6 512.0
13.3
2.9
70.9 174.1
![Page 264: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/264.jpg)
130.9
34.4
50.4
60.2
11.1
60.0
![Page 265: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/265.jpg)
1002 1100 1201-1 1201-2 1201-3 1201-4
4.8 16.0 16.0 16.0
95.0 106.9 106.9
![Page 266: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/266.jpg)
61.5
9.1 42.0 42.0 42.0
0.7
1,076.4 1,470.0 2,663.5 3,196.2 3,196.2 3,196.2
1,435.2 1,960.0 4,261.6 4,261.6 4,261.6 4,261.6
![Page 267: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/267.jpg)
![Page 268: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/268.jpg)
1201-5 1201-6 1201-7 1201-8 1201-9 1201-10
608.1 608.1 68.1 106.0
1,950.0
706.7 1,099.3 344.4 344.4
564.2 564.2 246.0
300.0 300.0 300.0
16.0 16.0 11.8 11.8
118.8
![Page 269: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/269.jpg)
250.0 250.0 250.0 250.0
42.0 42.0 47.4 47.4
0.7 0.7 0.7 0.7
0.7 0.7 0.7
1.4 1.4 1.4 1.4
266.4 3,196.2 3,196.2 799.1 3,196.2 3,196.2
4,261.6 4,261.6 4,261.6 4,261.6 4,261.6 4,261.6
![Page 270: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/270.jpg)
![Page 271: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/271.jpg)
1201-11 1201-12 1201-13 1201-14 1201-15 1201-16
390.9 608.1 68.1 106.0
1,275.0 2,100.0
35.3 76.0
706.7 1,099.3 344.4
362.7 564.2
180.0 300.0 300.0
11.8 11.8 15.1 15.1
71.3 118.8 118.8
![Page 272: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/272.jpg)
250.0 125.0 125.0 250.0
47.4 47.4 47.4 60.0
3,196.2 3,196.2 3,196.2 3,196.2
4,261.6 4,261.6 4,261.6 4,261.6
![Page 273: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/273.jpg)
![Page 274: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/274.jpg)
1201-17 1201-18 1201-19 1201-20 1201-21 1201-22
564.6 106.0
2,025.0
48.8
1,099.3 344.4
564.2
249.0 300.0 300.0
16.8 16.8
118.8 59.4 118.8 118.8
![Page 275: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/275.jpg)
250.0 250.0 250.0 250.0 250.0 250.0
47.4 47.4 42.0 42.0 42.0 42.0
0.7 0.7 0.7 0.7
0.7 0.7 0.7 0.7
266.4 1,065.4 1,598.1
2,495.2 2,079.3
2,130.8 2,258.6 2,599.6
![Page 276: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/276.jpg)
![Page 277: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/277.jpg)
1201-23 1201-24 1202 1204-1 1204-2 1204-3
152.0 152.0
300.0 300.0 288.0 288.0 288.0
16.8 16.8 5.7
118.8 118.8 90.7 70.6
![Page 278: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/278.jpg)
250.0 250.0 240.0 240.0 240.0
42.0 42.0 49.0 49.0 49.0
0.7
0.7 0.7 0.5 0.7
0.7 0.5 0.7
2,054.4 327.8 1,966.8
1,663.5 3,326.9 980.3
4,108.8 1,835.7 2,622.4
![Page 279: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/279.jpg)
![Page 280: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/280.jpg)
1204-4 1301 1302 1400 1500 1601-1
1,615.0
1,415.0
500.0
53.5
288.0
4.6
90.7 240.0
![Page 281: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/281.jpg)
240.0
49.0 13.9 35.0 11.2
0.5
0.7
655.6 1,684.2 2,326.2 2,907.8
2,221.8
2,622.4 2,245.6 3,101.6 3,877.1
![Page 282: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/282.jpg)
![Page 283: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/283.jpg)
1601-2 1601-3 1601-4 1601-5 1601-6 1602
452.2
3.4
240.0 168.0 240.0 162.0
![Page 284: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/284.jpg)
11.2 12.6 12.6 11.2
0.7 0.7 0.7 0.7 0.7
1,904.4 1,904.4 1,904.4 1,904.4
2,539.2 2,539.2 2,539.2 2,539.2
343.8
63.0
![Page 285: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/285.jpg)
113.6
77.5
274.0
![Page 286: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/286.jpg)
1603 1701 1702 1900 2001 2002
![Page 287: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/287.jpg)
7.7 3.5
1.3 0.9
1,863.6 1,482.0
2,484.8 1,976.0 3,146.0
![Page 288: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/288.jpg)
![Page 289: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/289.jpg)
2003 2004 2005 (1~3) 2006 2007-1 2007-2
70.2 38.4 0.6 1.2
![Page 290: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/290.jpg)
1.4
39.8
98.9
![Page 291: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/291.jpg)
92.6
5.2
125.6
141.4
![Page 292: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/292.jpg)
2007-3 2007-4 2008-1 2008-2 2100 2201
343.0
101.5
1.2 1.2 9.0 9.0
![Page 293: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/293.jpg)
501.6 1,438.8
262.2 262.2 262.2
668.8 1,918.4
42.4 42.4 42.4
59.0 58.9 58.9
![Page 294: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/294.jpg)
![Page 295: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/295.jpg)
2202 2301 2302 2400 2501-1 2501-2
15.1 1.8 1.8
![Page 296: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/296.jpg)
1,368.0 1,156.2 191.0 48.6 48.6
1,824.0 1,541.6 254.6 81.0 81.0
![Page 297: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/297.jpg)
![Page 298: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/298.jpg)
2501-3 2501-4 2501-5 2501-6 2501-7 2501-8
1.8 1.8 1.8 1.8 1.8 1.8
![Page 299: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/299.jpg)
48.6 48.6 48.6 48.6 48.6 48.6
81.0 81.0 81.0 81.0 81.0 81.0
![Page 300: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/300.jpg)
![Page 301: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/301.jpg)
2501-9 2502 2602-1 2602-2 2602-3 2602-4
15.4
9.8
1.2 1.2 1.2 1.2
![Page 302: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/302.jpg)
133.2 133.2 133.2 133.2
222.0 222.0 222.0 222.0
![Page 303: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/303.jpg)
![Page 304: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/304.jpg)
2602-5 2602-6 2602-7 2602-8 2602-9 2602-1
14.0
14.0
1.2 1.2 1.2 1.2 1.2 1.2
![Page 305: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/305.jpg)
133.2 133.2 133.2 133.2 133.2 133.2
222.0 222.0 222.0 222.0 222.0 222.0
2.5 2.8
17.4 19.4
![Page 306: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/306.jpg)
40.2 44.7
13.7 15.2
![Page 307: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/307.jpg)
2602-11 2602-12 2602-13 2602-14 2700 2800
1.2 1.2 1.2
![Page 308: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/308.jpg)
133.2 133.2 133.2 270.2
222.0 222.0 222.0 1,080.8
![Page 309: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/309.jpg)
![Page 310: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/310.jpg)
2900 3000 3100 3201 3202A-1 3202A-2
450.0
152.6
71.6
51.6 39.6 14.4 14.4
![Page 311: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/311.jpg)
2.1 2.1
371.2 854.0 346.8 163.2 163.2
1,484.8 1,366.4 462.4 272.0 272.0
648.3
33.1
![Page 312: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/312.jpg)
218.8
22.4
862.5
452.3
![Page 313: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/313.jpg)
3202A-3 3202A-4 3202A-5 3202A-6 3202A-7 3202A-8
238.0 238.0 238.0 238.0
-
152.6 152.6
-
110.6 110.6 110.6 110.6
- 71.6 71.6
14.4 14.4 14.4 14.4 14.4 14.4
![Page 314: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/314.jpg)
2.1 2.1 2.1 2.1 2.1
163.2 163.2 163.2
175.0
201.3
272.0 272.0 272.0
10.7
52.6
![Page 315: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/315.jpg)
![Page 316: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/316.jpg)
3202A-9 3202A-10 3202A-11 3202A-12 3202A-13 3202B-1
238.0 189.0
152.6 152.6 152.6
110.6 73.5
71.6 71.6 71.6
14.4 14.4 14.4 14.4 14.4 10.8
![Page 317: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/317.jpg)
2.1 2.1 2.1 2.1 2.1 0.7
163.2 163.2 145.5
175.0
152.4
272.0 272.0 242.6
![Page 318: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/318.jpg)
![Page 319: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/319.jpg)
3202B-2 3202B-3 3202B-4 3202B-5 3202B-6 3202B-7
189.0
119.3 119.3 119.3 119.3
73.5
47.3 47.3 47.3 47.3
10.8 10.8 10.8 10.8 10.8 10.8
![Page 320: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/320.jpg)
0.7 0.7 0.7 0.7
145.8 145.8 145.5 145.5 145.5
243.0 243.0 242.6 242.6 242.6
![Page 321: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/321.jpg)
![Page 322: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/322.jpg)
3202B-8 3202B-9 3203 3204 3205 3206
101.5 238.5
238.0
119.3
105.0
27.4 47.3
10.8 10.8 16.2
![Page 323: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/323.jpg)
0.7 0.7
145.5 145.5 269.0 61.2
138.1
242.6 242.6 358.7 81.6
21.6
![Page 324: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/324.jpg)
![Page 325: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/325.jpg)
3207 3208 3209 3210 L.S. 1 L.S. 2
445.0 298.0 178.9
105.0
5.4
![Page 326: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/326.jpg)
2.1
339.2 453.0
678.4 604.0
![Page 327: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/327.jpg)
![Page 328: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/328.jpg)
L.S. 3 L.S. 4 L.S. 5 L.S. 6 L.S. 7 L.S. 8
![Page 329: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/329.jpg)
![Page 330: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/330.jpg)
![Page 331: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/331.jpg)
L.S. 9 L.S. 10 L.S. 11 L.S. 12 L.S. 13 L.S. 14
![Page 332: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/332.jpg)
![Page 333: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/333.jpg)
![Page 334: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/334.jpg)
L.S. 15 L.S. 16 Gas tank Fence curbstone
![Page 335: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/335.jpg)
![Page 336: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/336.jpg)
![Page 337: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/337.jpg)
SAUDI BINLADEN GROUP - ABCDPAYMENT CERTIFICATE DEPARTMENT
Project CORRECTIONAL FACILITIES P-1182, DammamSubject AS-BUILT QUANTITIESPeriod As of 18 Feb 2016
NO DESCRIPTION Unit Total JOINERY
1 AluminumWindows
m2 1,044.52
Curtain walls130 United Arab Aluminum m2 86.65
Shutter130 United Arab Aluminum m2 1.86
Door130 United Arab Aluminum m2 0.87
2 MetalWindows
5.1 pcs 430.00
130 United Arab Aluminum
453 Benayat
![Page 338: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/338.jpg)
100 201 202 400 500 601
143.09 225.73 175.73 37.79 13.10 13.23
31.54 4.23 26.88 17.28
0.17
2.00
![Page 339: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/339.jpg)
602 700 800 901-1 901-2 901-3
20.93 28.85 24.98 1.38 9.18 9.18
![Page 340: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/340.jpg)
901-4 901-5 902 903-1 903-2 1001
9.18 9.82 11.23 9.82 10.98 1.94
3.00
![Page 341: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/341.jpg)
1002 1100 1201-1 1201-2 1201-3 1201-4
0.53 0.38
13.00 60.00 60.00 60.00 60.00
![Page 342: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/342.jpg)
1201-5 1201-6 1201-7 1201-8 1201-9 1201-10
![Page 343: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/343.jpg)
1201-11 1201-12 1201-13 1201-14 1201-15 1201-16
36.00 24.00
![Page 344: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/344.jpg)
1201-17 1201-18 1201-19 1201-20 1201-21 1201-22
![Page 345: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/345.jpg)
1201-23 1201-24 1202 1204-1 1204-2 1204-3
![Page 346: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/346.jpg)
1204-4 1301 1302 1400 1500 1601-1
1.60 15.84
0.48 0.48
34.00 50.00 12.00
![Page 347: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/347.jpg)
1601-2 1601-3 1601-4 1601-5 1601-6 1602
1.76 15.84 1.76 15.84 1.76 1.06
![Page 348: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/348.jpg)
1603 1701 1702 1900 2001 2002
0.64 2.56 12.96 12.96
4.61 1.15
0.76 0.34
11.00 5.00
![Page 349: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/349.jpg)
2003 2004 2005 (1~3) 2006 2007-1 2007-2
13.20 12.96 1.78
![Page 350: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/350.jpg)
2007-3 2007-4 2008-1 2008-2 2100 2201
2.37 4.03
0.15
![Page 351: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/351.jpg)
2202 2301 2302 2400 2501-1 2501-2
2.64 3.62 0.54 1.42 0.93 0.93
0.87
![Page 352: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/352.jpg)
2501-3 2501-4 2501-5 2501-6 2501-7 2501-8
0.93 0.93 0.93 0.93 0.93 0.93
![Page 353: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/353.jpg)
2501-9 2502 2602-1 2602-2 2602-3 2602-4
0.93 2.08 2.08 2.08 2.08
![Page 354: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/354.jpg)
2602-5 2602-6 2602-7 2602-8 2602-9 2602-10
2.08 2.08 2.08 2.08 2.08 2.08
![Page 355: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/355.jpg)
2602-11 2602-12 2602-13 2602-14 2700 2800
2.08 2.08 2.08 2.08 9.46 20.40
0.14 0.30
![Page 356: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/356.jpg)
2900 3000 3100 3201 3202A-1 3202A-2
29.52 24.82 38.64
![Page 357: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/357.jpg)
3202A-3 3202A-4 3202A-5 3202A-6 3202A-7 3202A-8
![Page 358: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/358.jpg)
3202A-9 3202A-10 3202A-11 3202A-12 3202A-13 3202B-1
![Page 359: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/359.jpg)
3202B-2 3202B-3 3202B-4 3202B-5 3202B-6 3202B-7
![Page 360: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/360.jpg)
3202B-8 3202B-9 3203 3204 3205 3206
![Page 361: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/361.jpg)
3207 3208 3209 3210 L.S. 1 L.S. 2
![Page 362: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/362.jpg)
L.S. 3 L.S. 4 L.S. 5 L.S. 6 L.S. 7 L.S. 8
![Page 363: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/363.jpg)
L.S. 9 L.S. 10 L.S. 11 L.S. 12 L.S. 13 L.S. 14
![Page 364: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/364.jpg)
L.S. 15 L.S. 16 Gas tank Fence curbstone ................
![Page 365: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/365.jpg)
SAUDI BINLADEN GROUP - ABCDPAYMENT CERTIFICATE DEPARTMENT
Project CORRECTIONAL FACILITIES P-1182, DammamSubject AS-BUILT QUANTITIESPeriod As of 18 Feb 2016
NO DESCRIPTION Unit Total GREENHOUSE BUILDING
1 Design, Supply & Installation of Green HouseFooting
1 lot 3.00
Greenhouse structure2 148 USMS pcs 2.91
Cooling system3 148 USMS pcs 1.80
148 USMS
![Page 366: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/366.jpg)
2005-1 2005-2 2005-3
1.00 1.00 1.00
0.97 0.97 0.97
0.60 0.60 0.60
![Page 367: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/367.jpg)
SAUDI BINLADEN GROUP - ABCDPAYMENT CERTIFICATE DEPARTMENT
Project CORRECTIONAL FACILITIES P-1182, DammamSubject AS-BUILT QUANTITIESPeriod As of 18 Feb 2016
NO DESCRIPTION Unit Total EXTERIOR WORKS
1 Plants
2 Miscellaneous WorksDrainage gravel
Palms m2 227.30 Trees m2 1,037.00 grass, shrubs, GC m2 889.00
m2 2,153.30 Filter Membrane
363 USMSPalms m2 757.50 Trees m2 3,629.40 grass m2 664.00 shrubs, GC m2 1,114.00
Soil Mix363 USMSPalms m3 340.90 Trees m3 1,037.00 grass m3 33.20 shrubs, GC m3 55.70
Excavation & Hauling363 USMSPalms m3 386.30 Trees m3 1,244.40
Gravel Mulching363 USMSPalms m2 - Trees m2 -
3 Irrigation WorksSub-main pipeline incl necessary fittings
363 USMS75mm Lm 477.00 63mm Lm 1,939.50 50mm Lm - 32mm Lm 129.00
Lateral pipeline incl necessary fittings363 USMS40mm Lm 349.50 32mm Lm 1,739.50 25mm Lm 796.50 20mm Lm 1,407.50
363 USMS
![Page 368: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/368.jpg)
Conduits pipeline incl necessary fittings363 USMS110mm Lm 663.00 90mm Lm 154.00 75mm Lm 55.00 63mm Lm 361.00 50mm Lm 1,140.00
Irrigation wire363 USMSAWG-14 Lm 5,326.00
![Page 369: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/369.jpg)
PC 05
227.30 1,037.00 889.00
757.50 3,629.40 664.00 1,114.00
340.90 1,037.00 33.20 55.70
386.30 1,244.40
477.00 1,939.50
129.00
349.50 1,739.50 796.50 1,407.50
![Page 370: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/370.jpg)
663.00 154.00 55.00 361.00 1,140.00
5,326.00
![Page 371: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/371.jpg)
SAUDI BINLADEN GROUP - ABCDPAYMENT CERTIFICATE DEPARTMENT
Project CORRECTIONAL FACILITIES P-1182, DammamSubject AS-BUILT QUANTITIESPeriod As of 18 Feb 2016
NO DESCRIPTION Unit Total 1 EXTERIOR WORKS
Precast curbstone364 USMS (straight & curved) Lm 20,520 295 Dar anan (straight) Lm - 295 Dar anan (curved) Lm -
Broom finish B2364 USMS m2 2,948
Broom finish B5364 USMS m2 1,374
Interlock tiles, sandy color 6cm thick364 USMS m2 460
Interlock triple hexagonal tiles 8cm thick364 USMS m2 1,890
Concrete edger 20x10x8364 USMS Lm 155
Precast tiles 40x40x4 cm (cement tiles)364 USMS m2 1,921
![Page 372: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/372.jpg)
20,520.00
2,948.00
1,374.00
460.00
1,890.00
155.00
1,921.00
![Page 373: Subcontractors Progress Qtys To Date](https://reader033.fdocuments.us/reader033/viewer/2022042618/577c83b11a28abe054b5d6b6/html5/thumbnails/373.jpg)
Page 373 of 373
SAUDI BINLADIN GROUPProject CORRECTIONAL FACILITIES P1182, Dammam Subject SUBCONTRACTOR TO DATE PAYMENT Date As of 23 Feb 2016
Subcontractor PC Amount Remarks
123 Al Ameel PC09 10,328,033.40 130 United Arab Alum PC03 1,466,350.60 148 USMS PC03 841,861.77 160 Al Hazem PC04 290,997.89 191 Al Manhal PC01 61,880.00 214 Marim Jalani PC05 2,759,385.31 295 Dar Anan PC03 4,099,835.15 322 Cretec PC07 3,575,286.41 Final363 USMS PC05 855,488.91 364 USMS PC05 2,499,665.00 453 Benayat PC23 78,120,069.42 510 Kabbani PC11 2,629,417.25 526 Dar Anan PC03 1,990,555.39 550 Tawakl Modern PC04 1,580,987.18 553 Otaibi PC01 98,293.29 560 Al Monsrhri PC04 1,306,096.75 562 Awan Al Award PC05 777,539.39
Contract No.