Sub Station BLDG 1
-
Upload
yash-singh -
Category
Documents
-
view
225 -
download
0
description
Transcript of Sub Station BLDG 1
SUB STATION BLDG 1
1 Footing No. LF1
Excavation 4 1.4
conc.work 4 1.3
F2Excavation 5 1.6Conc. Work 5 1.5
Total Excavation Total Conc. Work
2 Footing reinforcement No. of Bars
Bars parallel to length 1.3/0.15= 9+ 1 BAR= 10 4 10Length=1.3-0.15-0.15= 1.0Bars parallel to breadth1.3/0.15= 9+ 1 BAR= 10 4 10Length=1.3-0.15-0.15= 1.0
Bars parallel to length1.5/0.15= 10 + 1 Bar = 11 5 11Length= 1.5-0.15-0.15 = 1.2Bars parallel to breadth1.5/0.15= 10 + 1 Bar = 11 5 11Length= 1.5-0.15-0.15 = 1.2
3 Surface dressing 9.774.5
4 Lean Conc In footing F1 4 1.3F 2 5 1.5
For plinth beam H 24.48V 21.69
No. of column in footing
F1 10 tor 150 c/c
F2 12 tor 150 c/c
5 Column above plinth level L
C1of Height 4.0 m 9 0.3
6 Reinforcement detail
C 1 of Height 4 m 9Length of Lateral Ties 2*(0.41)+4*(0.26) 1.86Spacing 12 Dia 75c/cHeight of column/754/0.075 = 53 Bar + 1= 54
HOOKS= 8*Dia 8*0.012 0.096
Total rmft in stirup of 12 Dia 54 1.956
Longitudinal bar length 4+.045+1.5+48*0.012(DIA) 4 6.1214+.045+1.5+48*0.016(DIA) 4 6.313
7 Plinth beams LPB 1 Excavation H PB 1 2 10.72V PB 1 2 8.86
Conc. Work HPB 1 2 16.32V PB 1 2 14.46
Reinf. Of 16 Dia 6
PB 2 Excavation HPB 2 1 5.16VPB 2 1 4.23
Conc Work HPB 2 1 8.16VPB 2 1 7.23
Reinf. Of 12 Dia 6
8 Roof Beam LRB 1
HRB 1 2 16.32
Reinf. Of 12 Dia 6
RB 2 HRB 2 1 8.16VRB 2 3 21.69
Reinf. Of 16 Dia 6
LB 1 HLB1 3 24.48VLB1 3 21.69
Reinf. Of 12 Dia 6
9 Shuttering
Ar of roof
Column C 1 of Height 4 m 9 0.3
Plinth Beam PB 1 HPB 1 16.32VPB 2 14.46PB 2 HPB 2 8.16VPB 2 7.23
Column in footing F1 4 1.3F2 5 1.5
10 Wall 42.65steps 3 1.96
11 Plaster of Height 4 m 2 42.65
12 Roof Slab RS 1 1 3.43RS 2 1 4.73
13 Reinf in roof slab
RS 1 1Reinf. Of 8 Dia 150 c/c Spacing of bars Length /0.150 = 3.43/0.153.43/0.15= 23 Bar + 1 = 24 24 7.23Breadth /0.15= 7.23/0.157.23/0.15= 48 Bar + 1 = 49 49 3.43
RS 2 1Reinf. Of 10 Dia 150 c/c Spacing of bars Length /0.150 = 4.73/0.154.73/0.15= 32 Bar + 1 = 33 33 7.23Breadth /0.15= 7.23/0.157.23/0.15= 48 Bar + 1 = 49 49 4.73
14 Flooring sub station 8.16Platform 1
15 window 7.8Rolling shutter 3
16 Ramp conc work 2.2
B H Quantity Unit
1.4 1.6 12.544 cum
1.3 1.5 10.14
1.6 1.6 20.481.5 1.5 16.875
33.024 cum 27.015 cum
L
101 40 m 80
12132
1 40 m
1.2 66 m
1.2 66 m
9.37 91.54494.2 18.9
Total 110.4449 sqm
1.3 0.15 1.014 cum 1.5 0.15 1.6875 cum
0.23 0.15 0.84456 cum0.23 0.15 0.748305 cum
.1m added extra
B H
0.45 4 4.86 cum
121638.252
16591.048
950.616 m
220.356 m227.268 m
B H
0.23 0.6 1.479360.23 0.6 1.22268
2.70204 cum
0.23 0.6 2.252160.23 0.6 1.99548
4.24764 cum
184.68 m
0.23 0.45 0.53406 cum 0.23 0.45 0.437805 cum
0.23 0.45 0.84456 cum0.23 0.45 0.748305 cum
Total Excavation
Total Conc work
92.34 m
B H
0.23 0.45 1.68912 cum
97.92 m
0.23 0.45 0.84456 cum0.23 0.45 2.244915 cum
179.1 m
0.23 0.45 2.53368 cum 0.23 0.45 2.244915 cum
277.02 m
62.4968 sqm
0.45 4 54 2*(lh+bh)
0.23 0.6 19.86 sqm 0.23 0.6 17.628 sqm 2(lh+bh)
0.23 0.45 7.551 sqm0.23 0.45 6.714 sqm
Total 51.753 sqm
1.3 1.5 31.21.5 1.5 45
Total 76.2 sqm
0.23 4 39.238 cum0.3 0.15 0.2646 cum
4 341.2 sqm 2 SIDES
7.23 0.13 3.223857 cum 7.23 0.15 5.129685 cum
8683.18
10940.72
173.52
168.07
683.18 m
238.59
231.77940.72 m
7.23 58.9968 sqm3.5 3.5 sqm
1.2 9.36 sqm2.4 7.2 sqm
3.5 0.6 2.31 cum
2* becoz of bottom and top
PRICING OF SUB STATION BLDG 1 AT TUGHALAKABAD
S. No. Description of item Qty1 Surface dressing not exceeding 15 cm deep in soft/loose soil 110.4449
2 36.697905
3 3.8424
4 203.148
5 69.255
6 62.4968
7 110.4449
8 Cement concrete in foundation filling and mass concrete type D2 1:4:8 4.294365
9 3392.549
10 181.953
11 49.582695
12 62.4968
13 8.353542
14 39.5026
15 170.6
16 Rendering 10mm thick in CM 1:6 finished even and smooth internal plaster 153.6
17 62.4968
18
19
20 Roof treatment21 Dry distemper 22 Three coats of white wash on ceiling 23 Three coats of lime wash on internal walls
Excavation in trenches n. exc. 1.5 m wide and n. exc. 1.5 m in depth for foundation n.exc. 10 sqm on plan and n. exc. 1.5 m depth and getting out in soft/loose soil.
Returning, filling, in including spreading, levelling, watering and well ramming in layers not exc. 25 cm in soft/loose soil.
M/L Treating the bottom and sides of excavation at the rate of 5 litres per sqm of surface area
Treating the back fill in contact with foundation at the rate of 7.5 litre of emulsion per sqm of vertical surface
Treating the top surface of filled earth at the rate of 5 litres of emulsion per sqm of surface.
Treating the soil along with external perimeter of building at the rate of 2.25 litre of emulsion per meter of perimeter of wall.
TMT bars 10 mm dia and over cut to length bent to shape required including cranking bending spirally for hooping for cloumns hooking ends and binding with mild steel wire not less than 0.9-0 mm dia
Formwork to sides of concrete in foundation footings bases of columns and plinth beams
Reinforced cement concrete (design mix) in foundation including footings foundation beams plinth beams bases of columns etc in M25
Formwork to soffits of suspended slabs such as roof slabs floor slabs landings and similar works
Reinforced cement concrete (design mix) in slabs simply supported on walls beams and columns in floor roof landings and balconies etc in M25
Modular bricks in cement mortar 1:6 with fly ash bricks straight or curved on plan not exc 6 m mean radius
Rendering 10mm thick in CM 1:4 second layer of 5 mm in CM 1:4 with water proofing compund sand finished external plaster
Rendering 5mm thick in CM 1:3 to RCC soffits bottom of beams lintal RCC chajjas slabs etc
20-25 mm thick kota stone flooring 600x600 over 20 mm screed in CM1:6 over 100 mm thick PCC Type D2 over 150 mm thick hard core
7-8 mm thick non skid ceramic tiles 300x300 mm laid over cement screed in CM 1:4 over 100 mm thick PCC 1:2:4
24 9.36
25 shutter 7.2
Grand total
Supply and fix steel windows with side hung shutters including projecting type hinges with steel handle and steel peg stays with glazing bars
Add 3% for unforeseen
items
Plinth area of building
Plinth area rate per Sqm
shutter?
Unit Rate Amount SSRSqm 7.9 872.51471 3011
Cum 115.2 4227.5987 3006
Cum 41.7 160.22808 3009 8 10
Sqm 80.6 16373.729 3047 0.39 0.61
Sqm 126.8 8781.534 3048
Sqm 80.6 5037.2421 3049 683.18 80
Sqm 38.6 4263.1731 3051 940.72
Cum 2303.3 9891.2109 4025
kg 48.6 164877.88 10034
Sqm 134.2 24418.093 7004
Cum 3482.2 172656.86 4053
Sqm 211.5 13218.073 7006
Cum 3770 31492.853 4055
Cum 255.3 10085.014 5019
Sqm 134.8 22996.8814001 & 14004 683.18 1020.72
Sqm 77.3 11873.28 14001
Sqm 76.3 4768.505814001 & 14004 266.4402 622.6392
Sqm 805.69 0 13013 & others
Sqm 520.4 0 13074
Sqm 300 0 AssessedSqm 31.1 0 15010Sqm 11.8 0 15006Sqm 11.8 0 15006
Sqm 1689.4 15812.784 10071
Sqm 0Total 521807.46
15654.224
537461.68
Sqm
#DIV/0!
12 16 20 25
0.89 1.57 2.46 3.85
132 591.048
1638.252
1770.252 591.048 0 0
1575.5243 927.94536 0 0
3392.549