Sub-Contractor's perspective
HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS
![Page 3: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/3.jpg)
◦ Introduction◦ How did we get there◦ Company History, Growth & Development◦ Key Points
Outline
![Page 4: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/4.jpg)
NTC Contracting has been very successful at gaining works on the Wheatstone Project.
Major Contracts include:◦ “Early Works Civil” for Bechtel◦ “Non Permanent Works” for Bechtel◦ “QMC Bridge Earthworks and Road Works” for McConnell Dowell◦ “ISBL & OSBL Civil Works” for Laing O’Rouke◦ “Aggregate Cartage” for Thiess◦ “WWTP Irrigation Field Installation” for Monadelphous◦ “Site Civil Works” for Energy Power Systems◦ “Concrete Disposal” for Veolia◦ “Underground Civil Works” for CB&I
Introduction
![Page 5: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/5.jpg)
Minor Hire Works include:◦ KEJV◦ John Holland◦ Zinfra◦ Mammoet◦ ATCO◦ Spinafex◦ Outback Trees◦ RockJV◦ BestJV◦ Keller
Peak Workforce was 120 staff on the project and we have completed over 250,000hrs on the project LTI free to date.
Introduction
![Page 6: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/6.jpg)
All of these works were not handed to us, we had to work for them.
Key Aspects:◦ Prior to Wheatstone we were of medium size with 30-40 staff◦ Had worked in mining environments but only as a minor subcontractor◦ We spent time and money developing the company systems including
◦ Quality◦ Safety◦ Environmental◦ Human Resources◦ Financial
◦ We called, we researched, we networked, we tendered
How did we get there?
![Page 7: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/7.jpg)
NTC Contracting started as Northern Transport during the 1950s in Onslow. The company was established by the McAullay family (a local family living in Onslow) and provided the small township of Onslow transportation and general civil services.
The company was purchased by Chris and Richard Evans in May 1998 and later commenced a regular freight run from Perth to Onslow.
Northern Transport Company grew through haulage and small civil contracts in the Pilbara often for mining clients
NTC Contracting Pty Ltd (NTC) was officially formed in 2008 as a Civil Contracting branch of Northern Transport Company.
Who We Are
![Page 8: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/8.jpg)
NTC started evolving in the late 1990’s from running a regular freight service and working on local contracting jobs within Onslow into larger projects including mine site civil construction.
The Growth of NTC
![Page 9: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/9.jpg)
Late 1990
Loading for a trip to Perth
![Page 10: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/10.jpg)
Late 1990
Prior to leaving for freight run to Perth
![Page 11: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/11.jpg)
◦ In early 2000 Onslow Salt started production in Onslow.
◦ NTC tendered for and won the cartage contract ◦ The contract involved carting salt from the
crystallisers to the wash plant◦ Was a 7 day a week 24 hour operation.
Early 2000 – Onslow Salt
![Page 12: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/12.jpg)
Early 2000 – Onslow Salt
Some of the first loads of salt
![Page 13: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/13.jpg)
Early 2000 – Onslow Salt
Taking samples from the salt Stockpile
![Page 14: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/14.jpg)
◦ In March 2006 Cyclone Glenda hit Onslow as a Category 3 cyclone. ◦ A lot of damage was caused to the Onslow Salt levee walls ◦ NTC tendered for and was awarded the head contract for the repairs◦ NTC undertook HSE under the guidance of Onslow Salt.
Cyclone Track
Mid 2000 – Cyclone Glenda
![Page 15: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/15.jpg)
Mid 2000 – Cyclone Glenda
Excavating for Wall Repairs
![Page 16: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/16.jpg)
Mid 2000 – Cyclone Glenda
Sorting Armour Rock
![Page 17: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/17.jpg)
◦ In June 2008 NTC commenced work on the Sino Iron project under VDM Group building the 1700 man camp 123.
◦ This evolved into a Site wide Services contract under MCC for Civil Construction services around the entire Sino Iron site
◦ NTC undertook their own HS&E, Quality Assurance and Human Resources Management
AG Mill Construction
2008 – Sino Iron Project
![Page 18: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/18.jpg)
2008 – Sino Iron Project
Terex MT4400
![Page 19: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/19.jpg)
2008 – Sino Iron Project
Causeway Construction
![Page 20: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/20.jpg)
2008 – Sino Iron Project
Health and Safety◦ NTC managed HSE in line with site
requirements ◦ Used client supplied paperworkHuman Resources◦ Developed site greenfields agreement to
meet site Industrial Relations requirementsEnvironmental◦ Started using a waste management system
![Page 21: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/21.jpg)
◦ In June 2011 NTC tendered for and was awarded subcontract under OTOC for earthworks 350 man camp.
◦ First Oil and Gas Contract◦ On completion tendered Road Maintenance Contract under Technip EPCM◦ Awarded Contract brought a great opportunity for NTC to upskill their management systems
Macedon Project
2011 – Macedon Project
![Page 22: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/22.jpg)
2011 – Macedon Project
NTC Commenced the Camp Construction under OTOC
![Page 23: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/23.jpg)
2011 – Macedon Project
All of NTC’s equipment had to meet the BHP Requirements for the site
![Page 24: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/24.jpg)
2011 – Macedon Project
NTC introduced regular stretching into our prestart meetings
![Page 25: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/25.jpg)
Q1-Q2 2011Wheatstone ProjectFebruary 2011NTC initiated communication with Bechtel and was able to undertake the project prequalification
April 2011A large investment of time was required to update systems to reach the standard required. NTC completed the prequalification and was approved as a First Tier Contractor
![Page 26: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/26.jpg)
Q2, Q3 & Q4 2011 Wheatstone ProjectMay 2011NTC was invited to tender for “Early Works Civil” package
August 2011NTC was awarded “Early Works Civil” package
November 2011NTC Commenced work on the Wheatstone Project
![Page 27: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/27.jpg)
Q1 2012Wheatstone Project18 Jan 2012 Ground was Broken on the CV Site creating access along Camp Road 1 into the site
![Page 28: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/28.jpg)
Q2/Q3 2012Wheatstone Project
June 2012NTC reached 50,000 hours on site without a lost time injury
![Page 29: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/29.jpg)
Q3 2012Wheatstone Project
Sept 2012 NTC poured the very first permanent concrete for the project in the Communications Tower base
![Page 30: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/30.jpg)
NTC DevelopmentFebruary 2013NTC achieved accreditations in Quality and Safety Management SystemsISO9001 – Quality AssuranceAS4801 – Occupational Health and Safety
![Page 31: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/31.jpg)
July 2013
NTC was awarded our second major contract on Wheatstone titled “Non-Permanent Works” consisting of
◦ Road construction and sealing, ◦ Drain construction ◦ Various civil maintenance works
Q3 2013Wheatstone Project
![Page 32: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/32.jpg)
NTC Now
NTC works closely with environmental personnel such as Fauna Handlers to ensure appropriate
management of the environment
![Page 33: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/33.jpg)
NTC Now
NTC has systems in place to ensure correct barricading is always used
![Page 34: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/34.jpg)
NTC Now
NTC promotes a family culture when it comes to completing JHA’s, prestart meetings and Take 5’s
![Page 35: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/35.jpg)
NTC Now
NTC takes inspections of plant seriously; undertaking checks before any plant is started each morning
![Page 36: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/36.jpg)
NTC Now
Heavy machinery has a lot of moving parts - NTC has systems and procedures to manage and clean-up
spills
![Page 37: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/37.jpg)
NTC Now
As per the NTC Fitness for work procedure, prestart meetings and breathalyser checks are mandatory for all staff every day and toolbox meetings held
every week
![Page 38: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/38.jpg)
NTC is currently undertaking our Environmental Management System Accreditation audit to achieve ISO14001
We hope to be able to display the below logo in our documentation soon
NTC Now
![Page 39: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/39.jpg)
◦ Don’t expect contracts to fall into your lap because of your location or expertise.
◦ Do your research about who is awarded what contract, start cold calling.
◦ Be prepared to invest in Plant and Equipment if required but don’t to this too early in case a lead falls through
Key Points
![Page 40: Sub-Contractor's perspective HOW A LOCAL CONTRACTOR HAS MANAGED TO WIN CONTRACTS WITH THE LARGER CONTRACTORS.](https://reader034.fdocuments.us/reader034/viewer/2022051516/56649d945503460f94a7b8f2/html5/thumbnails/40.jpg)
Start working on your company systems◦ Health and Safety◦ Environmental◦ Quality Assurance◦ Human resources
Ask to become a prequalified supplier to some major contractors. This process will help guide you through what is needed to become compliant.
Key Points