Impact of increased penetration of wind and PV solar resources on ...
Study of Wind Energy Penetration in the Iberian Peninsula RED ELÉCTRICA DE ESPAÑA 1 WIND POWER...
-
Upload
bertina-clark -
Category
Documents
-
view
223 -
download
5
Transcript of Study of Wind Energy Penetration in the Iberian Peninsula RED ELÉCTRICA DE ESPAÑA 1 WIND POWER...
Study of Wind Energy Penetration in the Iberian Peninsula1
RED ELÉCTRICA DE ESPAÑA
WIND POWER GENERATION
Study of Wind Energy Penetration in the Iberian Peninsula.
DE ESPAÑ AR ED ELÉC TRIC A
1st March 2006
Study of Wind Energy Penetration in the Iberian Peninsula2
RED ELÉCTRICA DE ESPAÑA
Introduction: Evolution of installed wind power in Spain.
35 34 43 87 164405
760
1443
2051
3200
4530
6202
8046
9926
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
Study of Wind Energy Penetration in the Iberian Peninsula3
RED ELÉCTRICA DE ESPAÑA
8.046 MW ins. Wind power235 GWh annual demand
37,5 MW “peak” 41 Minhab.
16.629 MW ins. Wind power(x2,1) 513 GWh annual demand (x2,2)
74 MW “peak” (x2)83 Minhab (x2)
Import CapacityA: 1.400 - 1.400 MW CZ: 1.700 - 2.300 MWCH: 3.000 - 4.000 MWDK: 1.750 - 1.750 MWF: 2.100 - 2.550 MWNL: 3.000 - 2.900 MWPL: 1.100 - 1.100 MWS: 460 - 460 MW
Import CapacityF: 1.200 - 1.400 MWP: 550 - 700 MWMO: 400 - 400 MW
Introduction: • Energy Data 2004 (UCTE) (“Peak”: 3ºX-Dec)• Interchange Cap. Data 2004-5 (ETSO)
Study of Wind Energy Penetration in the Iberian Peninsula4
RED ELÉCTRICA DE ESPAÑA
Study Objectives:
Identify technical limits for wind power production: reference for installation plans.
Establish technical requirements for wind farms: fault ride-through capability.
Ministry Plan H2011 (October 2002):
Background:
Load SituationAdmissible Wind Power Production (frtc≥500 ms)
Peak 10.000 MW
Off-peak 3.000 ÷ 5.000 MW
13.000 MWinst
Study of Wind Energy Penetration in the Iberian Peninsula5
RED ELÉCTRICA DE ESPAÑA
Transient stability study.
System reserves impact.
Daily load coverage.
Participation of the wind farms in system restoration.
What does the study deal with?
What does the study NOT deal with?
Study of Wind Energy Penetration in the Iberian Peninsula6
RED ELÉCTRICA DE ESPAÑA
Follow-through group
Analysis group
REE REN
AEE (ABB) CNE
Network Planning Group (Spain) & REN:
REE, CNE, Wind Associations (AEE y APPA), Spanish electricity companies and REN
Study organization : Working groups.
Study of Wind Energy Penetration in the Iberian Peninsula7
RED ELÉCTRICA DE ESPAÑA
Power system model
Study Methodology:
-1771,1
PSS/E
Are the criteria met?
Operational Point
(load flow)
Models and data of the involved dynamics (“Dynamic data”)
ResultsYes No
Study of Wind Energy Penetration in the Iberian Peninsula8
RED ELÉCTRICA DE ESPAÑA
Power System Scenarios: Initial Case Horizon 2011.
1.500 MW
600 MW
900 MW
Future installed wind power*
9.800 MW
3.200 MW
800 MW
2.950 MW
13.000 MW3.750 MW
Initial installed wind power
Iberian load 65.400 MW
Spanish load
53.400 MW
Portuguese load
12.000 MW
(*) Future wind power are distributed at buses where wind power evacuation is forecasted.
700 MW
600 MW
0 MW
Initial wind power production
5.000 MW
1.450 MW
13.000 MW
3.750 MW
Initial installed wind power
Iberian load 26.000 MW
Spanish load
21.500 MW
Portuguese load
4.500 MW
Peak load: Off-peak:
Existing wind power 05/05/31 (forecast)
Study of Wind Energy Penetration in the Iberian Peninsula9
RED ELÉCTRICA DE ESPAÑA
Study Criteria:
Iberian Scope
Criteria (highest production capacity) : Fault cleared in breaker failure times. Each TSO will apply their steady state
security criteria. Transient Stability Criteria:
Out of step is not acceptable except if this problem is reduced to an individual generator.
Generating trips greater than 3000 MW (maximum instantaneous deflection between generation and load, UCTE Operational Handbook) are not acceptable.
Tripping of any France-Spain International interconnections by out of step relays is not acceptable.
Load shedding is not acceptable (except load trip by protection selectivity).
Hypothesis: Production: 80% of the installed wind power.
Increasing steps of wind power penetration. Future wind power is technically adapted.
50% of technical adaptation level in the wind power Portuguese penetrationSensitivity analysis of adaptation levels for the Spanish Peninsular wind power:
Without technical adaptation.
50% of the present one.
75% of the present one.
100% of the present one.
Study of Wind Energy Penetration in the Iberian Peninsula10
RED ELÉCTRICA DE ESPAÑA
Study Preliminary Results: dependence on the technical adaptation level*.
Case of demand
% of wind power technically adapted respect to the present
one (10GW)
Permissible wind power production (MW)
Peak
50% < 10.000 MW*
75% 14.000 MW*
100% >16.000 MW*
Off-peak0% 5.000 MW*
75% > 10.000 MW*
16-20.000 MWinst
(*) The preliminary results presented correspond to Spain only and these are, however, subject to possible
changes due to the pending Portuguese study
Study of Wind Energy Penetration in the Iberian Peninsula11
RED ELÉCTRICA DE ESPAÑA
Study Results: Technical Requirements for Wind Power.
Remain connected to the system in case of faults in the network (3/2/1 phase short-circuits), allowing the protection system to clear de default (fault ride-through capability):
Limits in power consumption (P,Q) during the fault and recovery:
exception periods - ≈150 ms- and lower restriction for unbalance faults
Voltage–time at the connection point to be supported (P.O.12.3)
Requirements:
Design:
Generators and equipment must be able to carry currents during the fault
Operation
Appropriate protection adjustment
Voltage (pu)
1
0,2
0,5 1 Time (sec)
start of disturbance
0,80,95 pu
0 15
Clearance of the faultFault length
Situations where generators must remain connected
0,6isolate 2 ph faults
Study of Wind Energy Penetration in the Iberian Peninsula12
RED ELÉCTRICA DE ESPAÑA
The decreasing of the short circuit currents, during a fault, due to the highest wind power penetration case analysed are between 10 to 20%
Other aspects to consider, once the full “ride through capability“ has been reached : Impact in the necessities of reserves of regulation with high wind power
penetrations that assure the system adequacy In case of “blackout”: to analyze the possibility of participation of the wind
farms in the system restoration.
Stage 2: Other conclusions.
Study of Wind Energy Penetration in the Iberian Peninsula13
RED ELÉCTRICA DE ESPAÑA
Conclusions:
The technical adaptation of the existing wind farms allows: The correct operation, guaranteeing a selective1 and coordinated1
behaviour in relation to the rest of the system The recovering of the local and zonal production capacities (highest
production capacity criterion) , reduced by the massive disconnections due to the non adapted existing wind farm.
To maximize the wind power production, allowing itself greater penetrations
The future D/C with France increases the wind power integration and eliminates the possible limitations in the use of the interconnections
(1) Essential properties that the protections of the equipment connected to the power
system must satisfy