Study of Long-Term Options for Raspberry Falls and Selma Estates
Community Water Systems
January 30, 2015
Presentation Agenda
Project Background
Overview of Supply and Treatment Options
Supply and Treatment Option No. 1
Supply and Treatment Option No. 2
Triple Bottom Line Sustainability Analysis
Recommendation and Next Steps
Project Background
Treatment and pipeline supply options studied in 2011
Raspberry Falls-only treatment option selected
Monitoring results in May/June 2014 prompted renewed look
Preliminary screening of alternatives performed in September 2014
Loudoun Water requested Triple-Bottom-Line Sustainability Evaluation of the short-listed options
Financial
Environmental
Social
Overview of Supply and Treatment Options
Supply and Treatment Option No. 1
400 gpd/connection for potable use (196,400 gpd)
Combined facility located at Selma Estates
500 gpd/connection for irrigation supply
One irrigation supply system for Raspberry Falls (101,500 gpd)
One irrigation supply system for Selma Estates (138,500 gpd)
Supply and Treatment Option No. 2
900 gpd/connection for all water needs (441,900 gpd)
Combined facility would be located at Selma Estates
Supply and Treatment Option No. 1
Water supply
Existing Selma Estates wells used for potable supply
Existing Raspberry Falls wells used for irrigation supply
Two (2) new wells needed for Selma Estates irrigation supply
Treatment Techniques
Membrane filtration for pathogen/bacteria removal
Chlorine disinfection for virus/pathogen inactivation
Future GAC filtration allowance for SOC adsorption
Distribution System Improvements
New potable water booster pumps and irrigation booster pumps
New potable water storage tank and irrigation storage tanks
Irrigation distribution piping loops
Supply and Treatment Option No. 2
Water supply
Existing Selma Estates wells used for potable supply
Existing Raspberry Falls wells also used for potable supply
New raw water transmission main between Raspberry Falls and Selma Estates
Treatment Techniques
Membrane filtration for pathogen/bacteria removal
Chlorine disinfection for virus/pathogen inactivation
Future GAC filtration allowance for SOC adsorption
Distribution System Improvements
New potable water booster pumps
New potable water storage tank
Triple Bottom Line Sustainability Analysis
Criterion Type Criterion Criterion Scores
STO1 ‐ Combined Treatment with
Separate Irrigation
STO2 ‐ Combined Treatment for All
Uses
Economic Lowest Capital Cost 0 4
Environmental Lower Greenhouse Gas Emissions
2 0
Environmental Greater Aquifer Sustainability
2 0
Social Better Protection of Public Health
0 1
Social Better Quality of Life 0 1
Total Score (out of a possible 10 points) 4 6
Project Cost Estimates
Costs developed to Class 4 estimate level per the Association for the Advancement of Cost Engineering (AACE)
Accuracy level on the order of -15% to +30%
Supply and Treatment Option No. 1
Project cost estimate is $11.4 million
Range is $9.7 to $14.8 million
Supply and Treatment Option No. 2
Project cost estimate is $6.5 million
Range is $5.5 to $8.4 million