Structures Vinod KJS

download Structures Vinod KJS

of 15

Transcript of Structures Vinod KJS

  • 7/27/2019 Structures Vinod KJS

    1/15

    AGENCY:CHANDESWAR CONSTRUCTION

    Name of the structureName of the structure

    Location As per Drg As per Bill

    1 0838-M311-BC4-101 Discharge Chute Coal Mill BC 864.220 864.220 0.000 6500 5617.43

    2 0838-M311-BC5-101 Discharge Chute Coal Mill BC Tail End 1920.690 1920.690 0.000 6500 1 2484.485

    3 0838-M311-BC5-102 Discharge Chute Coal Mill BC HeadEnd

    1948.280 1948.280 0.000 6500 12663.82

    4 0838-M311-BC3-101 Discharge ChuteCoal Mill Belt

    Conveyor2095.920 2095.920 0.000 On Hold

    5 A1-08148-BC-102 TR 6 Column 4662.578 4662.578 0.000 6000 27975.468

    6 A1-08148-BC-102 TR 6 Column brasings 1220.883 1220.883 0.000 6000 7325.298

    7 A1-08148-BC-01Conveyor Gallery

    Structure10822.219 11327.271 505.052

    Brasings wt

    is more6000 64933.314

    8 A1-08148-BC-03Conveyor Gallery

    Structure3922.344 3922.344 0.000 6000 23534.064

    9 A1-08148-BC-102 TR 1 Column 333.162 333.162 0.000 6000 1998.972

    10 A1-08148-BC-103 TR 2 Column 569.584 569.584 0.000 6000 3417.504

    11 A1-08148-L1-1-13 Truck Tripler Structure Coal Handling Shed 24000.440 24000.440 0.000 6000 144002.64

    12 A1-08148-L1-1-14 Truck Tripler Structure Coal Handling Shed 9079.755 9079.755 0.000 6000 54478.53

    13 POC 111300 BC1 Transfer Tower

    walkwayCoal Mill 825.038 1380.934 555.896

    Gratings wt

    added6000 4950.228

    Total 62265.113 63326.061 1060.948 363381.75

    FABRICATION BILL

    9/5/2011DESCRIPTION

    Coal Mill Belt

    Conveyor Gallery

    Remarks Total Value

    BILL No:RA 02

    S.No. Drg.No.

    Total wt in KgS Diffrence

    Wt in KgsRate per

    MT

  • 7/27/2019 Structures Vinod KJS

    2/15

    4662.578 864.220

    1220.883 1920.690

    10822.219 1948.280

    3922.344

    333.162

    569.584

    24000.440

    9079.755

    825.038

    55436.003 4733.190 60169.193

    55436.000 4733.19

    6000.000 6500.000

    332616.00 30765.74 363381.74

  • 7/27/2019 Structures Vinod KJS

    3/15

    5617.43

    12484.485

    12663.82

    27975.468

    7325.298

    67963.626

    23534.064

    1998.972

    3417.504

    144002.64

    54478.53

    8285.604

    369747.441 6365.69

  • 7/27/2019 Structures Vinod KJS

    4/15

    AGENCY:CHANDESWAR CONSTRUCTION

    As per Bill As per Drg

    Excess

    Qty

    1 0838-M361 BC2-101 Discharge Chute 0.785 0.785 0.000 6500.00 5099.00 5099.77

    2 0838-M361 BC1-101 Discharge Chute 0.641 0.641 0.000 6500.00 4166.00 4166.24

    3 0838-M361 BC4-101 Discharge Chute 0.637 0.637 0.000 6500.00 4143.00 4143.49

    4 0838-M361 BC3-101 Discharge Chute 0.722 0.722 0.000 6500.00 4691.00 4691.44

    5 0 838-M311 BC1-105 Discharge Chute 2.096 2.096 0.000 6500.00 13623.00 13623.48

    6 0 8148-BC1-1-02 Conveyor Column TR6 4.929 4.929 0.000 6000.00 29573.00 29573.74

    7 08148-BC1-15 GTU Support Column 10.835 10.835 0.000 6000.00 65011.00 65011.23

    8 46016307Gantry 1 for Coal Reclaimer

    Yard3.067 3.067

    0.000 6000.00 18403.00 18403.20

    9 46016307Gantry 2 for Coal Reclaimer

    Yard2.874 2.874

    0.000 6000.00 17242.00 17242.56

    10 KSSPL Standard gallery 500BW 1.689 1.6890.000 6000.00 10133.71 10133.71

    11A1-08148-BC1-01 Conveyor Gallery for

    Supporting Girder8.033 8.033

    0.000 6000.00 48198.00 48198.83

    12 A1-08148-BC1-101Walkway for Conveyor

    Gallery1.095 1.095 0.000 6000.00 6572.00 6572.53

    13 A1-08148-BC1-01a way or onveyor

    1.225 1.225 0.000 6000.00 7351.00 7351.02

    Total 234205.71 234211.24

    FABRICATION BILL

    BILL No:RA 03

    .No. Drg.No. DESCRIPTION

    Rate per

    unit in

    Rs/-

    Billed Amount in

    Rs/-

    Payable

    Amount in Rs/-

    Material Wt in MT

    Payable Amount is Rs/- 234211.00

  • 7/27/2019 Structures Vinod KJS

    5/15

    10/13/2011

    Remarks

  • 7/27/2019 Structures Vinod KJS

    6/15

    AGENCY:CHANDESWAR CONSTRUCTION

    As per Bill As per DrgExcess

    Qty

    abrication1 311 BC4(RMH) Discharge Chute 0.527 0.527 0.000 6500.00 3423.68 3423.68 0.00

    2 0838-M-331-BC3-101 Discharge Chute 2.194 2.194 0.000 6500.00 14263.99 14263.99 0.00

    3 0838-M361 BC5-101 Discharge Chute 0.772 0.772 0.000 6500.00 5014.82 5014.82 0.00

    Total 3.493 3.493 0.000 22702.49 22702.49 0.00

    abrication5 A-08148-BC1-1-03 Conveyor Gallery 4.445 4.445 0.000 6000.00 26670.85 26670.85 0.00

    6 A1-08148-BC1-1-01 Conveyor Gallery 4.063 4.063 0.000 6000.00 24376.02 24376.02 0.00

    7 A1-08148-BC1-1-01 Conveyor Gallery 6.803 6.803 0.000 6000.00 40818.96 40818.96 0.00

    8 A1-08148-BC1-1-01 Conveyor Gallery 6.863 6.863 0.000 6000.00 41178.36 41178.36 0.00

    9 A-08148-BC1-1-03 Conveyor Gallery 8.567 8.567 0.000 6000.00 51404.37 51404.37 0.00

    10 A-08148-BC1-1-02 TR6(ii) Loose Brasings 1.605 1.605 0.000 6000.00 9630.04 9630.04 0.00

    11 A2-08148-BC1-15 GTU support Loose Brasings 3.408 3.408 0.000 6000.00 20445.31 20445.31 0.00

    12 A-08148-BC1-1-02 TR6(iii) Loose Brasings 1.654 1.654 0.000 6000.00 9923.22 9923.22 0.00

    13 A-08148-BC1-1-03 Stools for Conveyor Gallery 2.328 2.328 0.000 6000.00 13966.56 13966.56 0.00

    Total 39.736 39.736 0.000 238413.69 238413.69 0.00

    rection

    14A1-08148-BC1-1-01

    Conveyor Gallery 37.680 33.912 3.768 5500.00207238.19

    186514.3720723.82

    15 A-08148-BC1-1-03 Conveyor Gallery 18.160 16.344 1.816 5500.00 99880.28 89892.25 9988.03

    16 A-08148-BC1-1-02 Tresiles 22.093 19.884 2.209 5500.00 121510.63 109359.56 12151.06

    17 A2-08148-BC1-15 GTU support 14.243 12.818 1.424 5500.00 78335.16 70501.64 7833.52

    18 A-08148-BC1-1-03 Stools for Conveyor Gallery 2.328 2.095 0.233 5500.00 12802.68 11522.41 1280.27

    Total 94.503 85.053 9.450 519766.93 467790.24 51976.69

    137.73 128.28 9.45 780883.10 728906.41G.Total

    As per Mech.Depot.Recommended Bill Amount in Rs/- 780883.10

    As per Trusst Engineers Recommended Amount Rs/- 728906.41

    Billed Amount

    in Rs/-

    Payable

    Amount in Rs/-

    BILL No:RA 04

    .No. Drg.No. DESCRIPTION

    Material Wt in MT Rate per

    unit in

    Rs/-

    Excess / Hold

    usst Engineers

  • 7/27/2019 Structures Vinod KJS

    7/15

    29-Nov-11

    Hold 10% due to

    Erection Alignment

    is not completed

    Remarks

    usst Engineers

  • 7/27/2019 Structures Vinod KJS

    8/15

    AGENCY:CHANDESWAR CONSTRUCTION

    As per Bill As per DrgExcess

    Qty

    Fabrication

    1 46016311 Fab. of Reclaimer Gantry to TT4 3.620 3.620 0.000 6000.00 21718.35 15202.85 6515.51

    2 A1-08148-BC1-47 Fab.of L 11BC1 GT4 Suppt. Column 4.467 4.467 0.000 6000.00 26804.51 26804.51 0.00

    3 A1-08148-BC1-47 Fab.of Conv.Gallery of L11 BC1 11.935 11.355 0.580 6000.00 71611.98 68131.38 3480.60

    4 A1-08148-BC1-47 Stool Fabrication of L11 BC1 1.017 1.017 0.000 6000.00 6101.94 6101.94 0.005 46016095 Walkway Fab.for TT2 of L11 BC1 0.245 0.245 0.000 6000.00 1467.72 1467.72 0.00

    6 Water treatment p Staircase Fabrication 0.459 0.459 0.000 6000.00 2753.22 2753.22 0.00

    21.743 21.163 0.580 130457.72 120461.61 9996.11

    Erection

    7 46016311 Erection of Reclaimer Gantry to TT4 9.664 9.664 0.000 5500.00 53149.99 37204.99 15945.00

    8 A1-08148-BC1-47 Fab.of L 11 BC1 GT4 Suppt. Conveyor 4.467 4.467 0.000 5500.00 24570.80 24570.80 0.00

    9 A1-08148-BC1-47 Erec.of Conv.Gallery of L11 BC1 11.935 11.355 0.580 5500.00 65644.32 62453.77 3190.55

    10 A1-08148-BC1-47 Stool Erection of L11 BC1 1.017 1.017 0.000 5500.00 5593.45 5593.45 0.00

    11 46016095 Gratings Erection for TT2 0.826 0.826 0.000 3200.00 2644.14 2644.14 0.00

    12 46016095 Handrailing Erection 79 Mtrs 79 Mtrs 0.000 140.00 11061.00 11061.00 0.00

    13 46016095 Walkway Fab.for TT2 of L11 BC1 0.245 0.245 0.000 5500.00 0.00 1345.41 -1345.41

    14 46016095 Erectrion 1.070 0.000 1.070 5500.00 5883.12 0.00 5883.1215 Water treatment plant Staircase Erection 0.459 0.459 0.000 5500.00 2523.79 2523.79 0.00

    16 Water treatment plant Gratings Erection 0.179 0.179 0.000 3200.00 571.58 571.58 0.00

    17 Water treatment plant Handrailing Erection 24.8 Mtrs 24.8 Mtrs 0.000 140.00 3472.00 3472.00 0.00

    18 Packing Plant Weigh Bridge 45.000 22.500 22.500 7000.00 315000.00 157500.00 157500.00

    45.000 22.500 22.500 490114.18 308940.92 181173.26

    66.743 43.663 23.080 620571.90 429402.53 191169.36

    As per Trusst Engineers Recommended Amount Rs/- 429402.53

    Billed Amount

    in Rs/-

    Payable

    Amount in Rs/-

    G.Total

    As per Mech.Dept.Recommended Bill Amount in Rs/- 620571.90

    Rate per

    unit in

    Rs/-

    Excess/Hold

    Amount

    Total

    Total

    BILL No:RA 05

    .No. Drg.No. DESCRIPTION

    Material Wt in MT

    russt Engineers

  • 7/27/2019 Structures Vinod KJS

    9/15

    russt Engineers

  • 7/27/2019 Structures Vinod KJS

    10/15

    5-Jan-12

    30% hold due to

    Gantrys rectification

    work.

    Excess Wt

    30% hold due to

    Gantrys rectification

    work.

    Excess Wt

    Excess Wt

    50% Hold of 45MT as

    ts Wt is not confirmed

    o far.

    Remarks

    Trusst Engineers

  • 7/27/2019 Structures Vinod KJS

    11/15

    russt Engineers

  • 7/27/2019 Structures Vinod KJS

    12/15

    AGENCY:CHANDESWAR CONSTRUCTION

    As per Bill As per DrgExcess

    Qty

    Fabrication1 Satna Project KSSPL Gallery Fabrication 3.448 3.448 0.000 6000.00 20685.59 20685.59 0.00

    2 PHS-080-55-WBExtra Support Structure Erection for

    Truck Trippler0.507 0.507 0.000 6000.00 3039.17 3039.17 0.00

    3 46016309 Gantry III Fabrication 0.964 0.964 0.000 6000.00 5781.29 5781.29 0.00

    4 46016309 Gantry I,II,III Walkway Fabrication 5.025 5.025 0.000 6000.00 30147.96 30147.96 0.005 61D00 430/01

    .0.265 0.265 0.000 6000.00 1592.34 1592.34 0.00

    6 No Drg. No.Support Stru. For Cable Gallery at

    Water Treatment Plant1.066 1.066 0.000 6000.00 6395.82 6395.82 0.00

    67642.17 67642.17 0.00

    Erection

    1 PHS-080-55-WBExtra Support Structure Erection for

    Truck Trippler0.507 0.507 0.000 5500.00 2785.90 2785.90 0.00

    2 46016309 Gantry III Erection 0.964 0.964 0.000 5500.00 5299.51 5299.51 0.00

    3 46016309 Gantry I,II,III Walkway Erection 5.025 5.025 0.000 5500.00 27635.63 27635.63 0.00

    4 61D00 430/01Support Stru. For Un Burnt Silo Bulk

    Loading Hopper0.265 0.265 0.000 5500.00 1459.64 1459.65 0.00

    No Drg. No.Support Stru. For Cable Gallery at

    Water Treatment Plant1.066 1.066 0.000 5500.00 5862.83 5862.83 0.00

    5 PHS-080-55-WB Truck Tripler Hydraulic System 16.000 16.000 0.000 7000.00 112000.00 112000.00 0.00

    6 A1-08148-L1-02-01 Feeder Erection 11.500 11.500 0.000 7000.00 80500.00 80500.00 0.007 A1-08148-BC1-47 Gratings Erection 3.549 3.549 0.000 3200.00 11356.80 11356.80 0.00

    8 A1-08148-BC1-48 Gratings Erection 10.824 10.824 0.000 3200.00 34638.24 34638.24 0.00

    9 46016309 Gratings Erection 3.510 3.510 0.000 3200.00 11232.00 11232.00 0.00

    10 A1-08148-BC1-47 Hand Railing 170Mtrs 170Mtrs 0.000 140.00 23800.00 23800.00 0.00

    11 46016309 Hand Railing 164Mtrs 164Mtrs 0.000 140.00 22960.00 22960.00 0.00

    12 A1-08148-BC1-48 Hand Railing 502.980 502.980 0.000 140.00 70417.00 70417.00 0.00409947.55 409947.56 0.00

    477589.00 477589.00 0.00

    Total

    BILL No:RA 06

    S.No. Drg.No. DESCRIPTION

    Material Wt in MT Billed

    Amount in

    Rs/-

    Payable

    Amount in Rs/-

    Excess/

    Hold

    Amount

    Total

    Rate per

    unit in

    Rs/-

    G.Total

    As per Mech.Dept.Recommended Bill Amount in Rs/- 477589.00

    As per Trusst Engineers Recommended Amount Rs/- 477589.00

    RUSST ENGINEERS

  • 7/27/2019 Structures Vinod KJS

    13/15

    20-Jan-12

    emarks

    RUSST ENGINEERS

  • 7/27/2019 Structures Vinod KJS

    14/15

    As per Bill As per Drg Excess Qty

    14 A1-08148-BC1-1-01 Conveyor Gallery 37.680 33.912 3.76815 A-08148-BC1-1-03 Conveyor Gallery 18.160 16.344 1.816

    16 A-08148-BC1-1-02 Tresiles 22.093 19.884 2.209

    17 A2-08148-BC1-15 GTU support 14.243 12.818 1.424

    18A-08148-BC1-1-03

    Stools for Conveyor

    Gallery2.328 2.095 0.233

    Total 94.503 85.053 9.450

    S.No. Drg.No. DESCRIPTIONMaterial Wt in MT

    KJS CEMENT LIMITED

    FOR-6000 TPD GREENFIED CEMENT PR

  • 7/27/2019 Structures Vinod KJS

    15/15

    5500.00 207238.19 186514.37 20723.825500.00 99880.28 89892.25 9988.03

    5500.00 121510.63 109359.56 12151.06

    5500.00 78335.16 70501.64 7833.52

    5500.0012802.68

    11522.411280.27

    519766.93 467790.24 51976.69

    Hold 10% due to

    Erection

    Alignment is not

    completed

    Rate per unit

    in Rs/-

    Billed Amount

    in Rs/-

    Payable

    Amount inExcess / Hold Remarks

    JECT