STRUCTURAL MODELLING OF CAUSE AND EFFECT FACTORS OF … · 2016. 8. 3. · 5.2 Process Diagram of...

53
STRUCTURAL MODELLING OF CAUSE AND EFFECT FACTORS OF CONSTRUCTION WASTE GENERATION IN MALAYSIAN CONSTRUCTION INDUSTRY SASITHARAN NAGAPAN A thesis submitted in fulfilment of the requirements for award of the Doctor of Philosophy Faculty of Civil and Environmental Engineering Universiti Tun Hussein Onn Malaysia DECEMBER 2014

Transcript of STRUCTURAL MODELLING OF CAUSE AND EFFECT FACTORS OF … · 2016. 8. 3. · 5.2 Process Diagram of...

  • STRUCTURAL MODELLING OF CAUSE AND EFFECT FACTORS OF

    CONSTRUCTION WASTE GENERATION IN MALAYSIAN

    CONSTRUCTION INDUSTRY

    SASITHARAN NAGAPAN

    A thesis submitted in

    fulfilment of the requirements for award of the

    Doctor of Philosophy

    Faculty of Civil and Environmental Engineering

    Universiti Tun Hussein Onn Malaysia

    DECEMBER 2014

  • v

    ABSTRACT

    Construction industry contributes significantly in improving socio-economic

    development of a country. However, this industry faces serious problems of

    construction waste generated worldwide including Malaysia. Construction waste is

    results from various factors which are necessary to identify for reducing the waste

    generated in construction project. Hence, this study focused on developing a

    structural model of construction waste generation and determining the most

    important group that contributes to construction waste generation. The questionnaire

    consisted of 77 causative factors which then clustered into 7 groups and 13 effects

    factors of construction waste which are clustered into 3 groups. These factors and

    assigned groups were validated by 30 construction personnel (contractors,

    consultants and clients) during the pilot study. The actual survey was conducted with

    a total of 302 questionnaires were received by respond rate of 60%. The data analysis

    is carried out using SmartPLS software. A structural model of construction waste

    generation was developed based on 7 groups of causative factors and 3 groups of

    effect factors using Partial Least Squared-Structural Equation Modelling (PLS-SEM)

    technique. It was found that the model is fit due to the R² value of 0.451 (R2

    ≥ 0.26 =

    substantial). The model identifies that all 10 groups are significant with t-value ≥

    2.58 from bootstrapping process of 5000 random samples. The model indicates that

    Handling of Materials and Equipment group has the highest impact on construction

    waste generation. Finally, this finding was validated by 22 construction practitioners

    who agreed that Handling of Material and Equipment group of factors contributes the

    highest amount of construction waste generation at site. This group of factors should

    be avoided during construction works to reduce the waste generation. The findings of

    this study are contributed to understand clearly the cause and effect factors of

    construction waste generation in Malaysia.

  • vi

    ABSTRAK

    Industri pembinaan adalah penyumbang yang ketara di dalam peningkatan

    pembangunan sosio-ekonomi sebuah negara. Walau bagaimanapun, industri ini

    menghadapi masalah yang serius bagi isu penjanaan sisa pembinaan di seluruh dunia

    termasuk Malaysia. Sisa pembinaan dihasilkan daripada pelbagai faktor yang perlu

    dikenalpasti untuk mengurangkan penjanaan sisa di projek pembinaan. Oleh itu,

    kajian ini telah fokus kepada membangunkan satu model struktur penjanaan sisa

    pembinaan dan menentukan kumpulan yang paling signifikan kepada penjanaan sisa

    pembinaan. Soal selidik terdiri daripada 77 faktor penyebab yang diklasterkan

    kepada 7 kumpulan dan 13 faktor kesan sisa pembinaan yang diklusterkan kepada 3

    kumpulan. Semua faktor dan kumpulan yang ditentukan ini telah disahkan oleh 30

    pekerja pembinaan (kontraktor, perunding dan pelanggan) semasa kajian rintis.

    Kajian sebenar telah dijalankan dengan 302 borang soal selidik yang telah diterima

    dengan kadar respon sebanyak 60%. Analisis data dilakukan dengan menggunakan

    perisian SmartPLS. Satu model struktur penjanaan sisa pembinaan telah dibangunkan

    berdasarkan 7 kumpulan faktor penyebab dan 3 kumpulan kesan dengan

    mengunakan teknik Partial Least Squared-Structural Equation Modelling (PLS-

    SEM). Ia mendapati bahawa model tersebut adalah baik kerana nilai R² adalah 0.451

    (R² ≥ 0.26 = substantial). Model tersebut telah kenalpasti bahawa semua 10

    kumpulan adalah signifikan dengan nilai-t ≥ 2.58 daripada proses bootstrapping

    bagi 5000 sampel rawak. Model tersebut telah menunjukkan bahawa kumpulan

    Pengendalian Bahan dan Peralatan mempunyai impak tinggi kepada penjanaan sisa

    pembinaan. Akhirnya, penemuan ini telah disahkan oleh 22 pengamal pembinaan

    yang bersetuju bahawa kumpulan Pengendalian Bahan dan Peralatan merupakan

    faktor penyumbang tertinggi bagi penjanaan sisa pembinaan di tapak. Faktor-faktor

    bagi kumpulan ini harus dielakkan semasa kerja pembinaan supaya penjanaan sisa

    pembinaan dapat dikurangkan. Penemuan kajian ini menyumbang kepada memahami

    dengan jelas faktor penyebab dan kesan penjanaan sisa pembinaan di Malaysia.

  • vii

    TABLE OF CONTENTS

    DECLARATION

    DEDICATION

    ACKNOWLEDGEMENT

    ABSTRACT

    ABSTRAK

    TABLE OF CONTENTS

    LIST OF TABLES

    LIST OF FIGURES

    LIST OF SYMBOLS AND ABBREVIATIONS

    LIST OF APPENDICES

    CHAPTER 1 INTRODUCTION

    1.1 Background

    1.2 Problem Statement

    1.3 Research Questions

    1.4 Aim and Objectives

    1.5 Scope of the Research

    1.6 Thesis Structure

    CHAPTER 2 CAUSE AND EFFECT FACTORS OF

    CONSTRUCTION WASTE

    2.1 Introduction

    2.2 Construction Industry

    2.3 Type of Construction Waste

    2.3.1 Physical Waste

    2.3.2 Non-Physical Waste

    2.4 Issues on Construction Waste

    2.5 Causative Factors of Construction Waste

    ii

    iii

    iv

    v

    vi

    vii

    xi

    xiii

    xv

    xvi

    1

    1

    2

    3

    3

    3

    4

    6

    6

    6

    7

    8

    10

    12

    13

  • viii

    2.5.1 Design Group of Factors (DESG)

    2.5.2 Handling Materials and Equipment Group

    of Factors (HAND)

    2.5.3 Workers Group of Factors (WORK)

    2.5.4 Management Group of Factors (MANA)

    2.5.5 Site Condition Group of Factors (SITE)

    2.5.6 Procurement Design Group of Factors

    (PROC)

    2.5.7 External Group of Factors (EXTE)

    2.6 Effect factors of Construction Waste

    2.6.1 Environment

    2.6.2 Economy

    2.6.3 Social

    2.7 Theoretical Model

    2.8 Summary

    CHAPTER 3 RESEARCH METHODOLOGY

    3.1 Introduction

    3.2 Research Plan

    3.3 Literature Review

    3.4 Quantitative Approach

    3.4.1 Questionnaire Design

    3.4.2 Pilot Study

    3.4.2.1 Reliability Test of Pilot Study

    3.4.2.2 Analysis of Pilot Study

    3.4.2.3 Summary of Pilot Study

    3.4.3 Questionnaire Survey

    3.5 Analysis Methods

    3.6 Model Development

    3.6.1 PLS-SEM

    3.7 Validation

    3.8 Summary

    CHAPTER 4 DATA COLLECTION AND ANALYSIS

    4.1 Introduction

    14

    15

    16

    17

    18

    19

    20

    21

    21

    22

    22

    23

    24

    26

    26

    26

    28

    28

    28

    30

    32

    33

    37

    38

    38

    39

    39

    43

    44

    45

    45

  • ix

    4.2 Actual Survey

    4.2.1 Sampling Statistics

    4.2.2 Organization

    4.2.3 Knowledge and Experience

    4.3 Univariate Analysis on Collected Data

    4.3.1 Waste Generated

    4.3.2 Data Reliability Test

    4.3.3 Ranking of Causative Factors

    4.3.3.1 Comparison with Other Countries

    4.3.4 Ranking of Effect Factors

    4.4 Summary

    CHAPTER 5 STRUCTURAL MODELLING OF CAUSE AND

    EFFECT FACTORS

    5.1 Introduction

    5.2 Development of Hypothetical Model

    5.3 Sample Size

    5.4 Model's Assessment Procedure

    5.4.1 Input Data

    5.4.2 Draw Hypothetical Model

    5.4.3 Assign Manifest to Latent Variable

    5.4.4 Execute Modelling Process

    5.5 Assessment of Measurement Model

    5.5.1 Individual Item Reliability

    5.5.2 Convergent Validity

    5.5.3 Discriminant Validity

    5.6 Assessment of Structural Model

    5.6.1 Hypothesis Testing

    5.7 Validation

    5.7.1 Statistical Validation

    5.7.2 Expert's Opinion Validation

    5.8 Summary

    CHAPTER 6 CONCLUSION AND RECOMMENDATION

    6.1 Introduction

    45

    46

    47

    48

    51

    52

    53

    54

    58

    59

    60

    61

    61

    61

    63

    63

    65

    65

    66

    70

    70

    70

    71

    72

    75

    77

    79

    79

    81

    84

    85

    85

  • x

    6.2 Conclusion of the Findings

    6.2.1 Objective 1: Identifying cause and effect

    factors of construction waste

    6.2.2 Objective 2: Determining hierarchically the

    cause and effect factors of construction

    waste

    6.2.3 Objective 3: Developing structural model of

    cause and effect factors of construction

    waste

    6.3 Limitation of the Study

    6.4 Contribution to Academic Knowledge

    6.5 Contribution to the Industry

    6.6 Recommendations for Future Research

    REFERENCES

    APPENDIX A: QUESTIONNAIRE FOR PILOT STUDY

    APPENDIX B: QUESTIONNAIRE FORM FOR DATA

    COLLECTION

    APPENDIX C: EXAMPLE OF CSV. FILE FORMAT USED IN

    PLS-SEM ANALYSIS

    APPENDIX D: PLS ASSESSMENT RESULTS

    APPENDIX E: QUESTIONNAIRE FORM FOR VALIDATION

    APPENDIX F: SIGNIFICANCE LETTER FROM INDUSTRY

    PUBLICATIONS AND ACHIEVEMENTS

    VITA

    85

    85

    87

    89

    90

    91

    91

    91

    93

    109

    114

    119

    120

    143

    147

    148

    154

  • xi

    LIST OF TABLES

    2.1 Construction Projects Registered under CIDB

    2.2 Physical Waste Generation

    2.3 Time and Cost Overrun Problems in Several

    Countries

    2.4 Various Groups of Factors

    2.5 Design Group of Factors

    2.6 Handling of Materials and Equipment group of

    Factors

    2.7 Worker Group of Factors

    2.8 Management Group of Factors

    2.9 Site Condition Group of Factors

    2.10 Procurement Group of Factors

    2.11 External Group of Factors

    2.12 Environment Group

    2.13 Economy Group

    2.14 Social Group

    3.1 Respondent’s Demographics in Pilot Study

    3.2 Cronbach's alpha for Pilot Study

    3.3 Cut-off Scale

    3.4 Analysis of Causative Factor from Pilot Study

    3.5 Analysis of Effect Factor from Pilot Study

    3.6 The Use of SEM Approach in Construction Research

    4.1 Survey Statistics

    4.2 Respondent’s Organization

    4.3 Type of Organization

    4.4 Types of Construction Waste Generated

    7

    10

    11

    13

    15

    16

    16

    17

    19

    19

    20

    21

    22

    23

    31

    33

    33

    34

    37

    43

    46

    47

    47

    52

  • xii

    4.5 Reliability Test Results

    4.6 Frequency and Ranking of Causative Factors

    4.7 Comparison with Factors of Construction Waste with

    other Countries

    4.8 Ranking of Overall Data for Effect Factors

    5.1 Sample Size Used by Researchers

    5.2 Convergent Validity

    5.3 Analysis of Cross-loading of Factors

    5.4 Latent Variable Correlations

    5.5 Results of Hypothesis Tests

    5.6 Q2 value for Predictive Relevancy

    5.7 Demographic of Respondents Who Involved in

    Validation Process

    5.8 Frequency Results for Expert's Opinion Validation

    6.1 Path Results of the Model

    54

    55

    58

    59

    63

    71

    72

    75

    79

    81

    82

    83

    89

  • xiii

    LIST OF FIGURES

    1.1 Construction Sector Growth Trend from 2004 to

    2012

    2.1 Wastage of Cement at Construction Site

    2.2 Packaging Waste at Construction Site

    2.3 Metal Waste at Construction Site

    2.4 Bricks Waste at Construction Site

    2.5 The Need for Rework

    2.6 Equipment Failure Leads to Stoppage of Work

    2.7 Construction Waste Illegally Dumped at Mangrove

    Swamp, Malacca in 2011

    2.8 Construction Waste at 17/1A Road, Petaling Jaya in

    2012

    2.9 Construction Waste Illegally Dumped at Taman

    Ruwiyah, Selayang in 2013

    2.10 Construction Waste Illegally Dumped at Kampung

    Melayu Subang in 2014

    2.11 Theoretical Model of Construction Waste

    3.1 The Flow Chart of this Research

    3.2 Experience of Respondents Involved in Pilot Study

    3.3 Example of E-tendering Model

    3.4 Example of Intentions to Share Knowledge Model

    3.5 Example of Cost Performance Model

    3.6 Example of Model Struktur Petunjuk Prestasi Utama

    4.1 Type of Projects Respondents handled

    4.2 Contract Amount of Projects Handled by

    1

    8

    9

    9

    9

    11

    11

    12

    12

    13

    13

    23

    27

    32

    41

    41

    42

    42

    48

  • xiv

    Respondents

    4.3 Academic Qualification of Respondents

    4.4 Respondent’s Experience

    4.5 Stages of Construction Waste Generation

    5.1 Hypothetical Model of Construction Waste

    5.2 Process Diagram of PLS-SEM Analysis

    5.3 Draw Hypothetical Model in SmartPLS

    5.4 Assign Manifest Screenshot of SmartPLS

    5.5 Complete Model of PLS-SEM

    5.6 Developed Structural Model

    5.7 t-value from Bootstrapping

    5.8 Generated Q2 Values of the Model

    6.1 Causative Factors of Construction Waste

    6.2 Effects factors of Construction Waste

    6.3 Top Five Significant Causative Factors

    6.4 Top Five Severity Effect Factors

    6.5 PLS-SEM of Cause and Effect Factors of

    Construction Waste

    49

    50

    51

    53

    62

    64

    66

    67

    67

    76

    78

    80

    86

    87

    88

    88

    89

  • xv

    LIST OF SYMBOLS AND ABBREVIATIONS

    CW - Construction Waste

    CIDB - Construction Industry Development Board

    PLS-SEM - Partial Least Square-Structural Equation Modelling

    SEM - Structural Equation Modelling

    KPKT - Urban Wellbeing, Housing and Local Government

    EPU - Economic Planning Unit

    PPSPPA - Solid Waste and Public Cleansing Management

    Corporation (Perbadanan Pengurusan Sisa Pepejal

    dan Pembersihan Awam)

    CIOB - The Chartered Institute of Building

    JKR - Public Works Department (Jabatan Kerja Raya)

    Ir. - Professional Engineer

    UTHM - Universiti Tun Hussein Onn Malaysia

    PSA - Politeknik Sultan Salahuddin Abdul Aziz Shah

    PMU - Politeknik Mukah Sarawak

    csv. - Comma Separated Value

    AVE - Average Variance Extracted

    CR - Composite Reliability

    GDP - Gross Domestic Product

    RM - Ringgit Malaysia

    BE - Bachelor of Engineering

    Q² - Predictive Relevancy

    CV Red - Cross Validated Redundancy

    CV Com - Cross Validated Communality

  • xvi

    LIST OF APPENDICES

    APPENDIX TITLE PAGE

    A Questionnaire for Pilot Study 109

    B Questionnaire Form for Data Collection 114

    C Example of csv. File Format Used in

    PLS-SEM Analysis 119

    D PLS Assessment Results (Iteration 1 until 8) 120

    E Questionnaire Form for Validation 143

    F Significance Letter from Industry 147

  • CHAPTER 1

    INTRODUCTION

    1.1 Background

    In Malaysia, construction development is growing rapidly since last few decades.

    Together with social development, construction sector has contributed significantly

    to Gross Domestic Product (GDP) of the country. The construction growth trend in

    GDP since 2004 is illustrated in Figure 1.1.

    Figure 1.1: Construction Sector Growth Trend from 2004 to 2012

    (Khan et al., 2014 & CIDB, 2013a)

    Figure 1.1 shows that, in year 2012, Malaysian construction sector registered

    an impressive GDP growth of 18.5% that is far surpassing the 4.6% in 2011. This

    growth is due to the huge amount invested for construction development projects

    1.8

    8.5

    4.4

    6.2 6.0

    4.6

    18.5

    -5

    0

    5

    10

    15

    20

    2004 2005 2006 2007 2008 2009 2010 2011 2012

    Co

    nst

    ruct

    ion

    Sec

    tor

    GD

    P (

    %)

  • 2

    under 10th Malaysia Plan (2011-2015) with the allocation of RM230 billion (EPU,

    2011).

    Even though the rapid development of construction provides facilities which

    are needed by people but it also contributes to negative impact to economy, social

    and environment (Noor et al., 2013; Azis et al., 2012; Llatas, 2011). The waste

    generated from construction activities has been increasing over the years and giving

    negative effect to environment. The waste generation has resulted in the increasing of

    illegal dumping activity (Katz & Baum, 2011) and shortage of landfill space (Ann et

    al., 2013). Thus, it is important to take actions for avoiding construction waste

    generation.

    1.2 Problem Statement

    Like other countries, Malaysia is also facing a serious problem of waste generation in

    the construction industry (Noor et al., 2013; Hassan et al., 2012; Aadal et al., 2013).

    This waste generation is due to the increasing demand for major infrastructure

    projects, commercial buildings and housing development (Begum et al., 2010;

    Mokhtar & Mahmood, 2008). It has resulted in creating a number of illegal dumping

    site nationwide (Wei, 2012; Sharifah & Zainal, 2014). The waste generation is

    caused by various factors which need to be identified for avoiding the waste.

    Unfortunately, Malaysia does not have accurate data of construction waste

    flows and factors causing the waste generation on-site or off-site (Begum et al.,

    2007). The same problem was also highlighted by foreign researchers (Yuan & Shen,

    2011; Lu & Yuan, 2011b; Azis et al., 2012). In order to overcome this issue,

    Construction Industry Development Board of Malaysia (CIDB) and National Solid

    Waste and Public Cleansing Corporation (PPSPPA) have encouraged researchers to

    conduct research works in construction wastes area (Hamid, 2011; Taha, 2012).

    Unfortunately only a few researchers have studied the issue of construction waste in

    Malaysia. However, most of these studies focused on quantifying the amount of

    construction waste generation and less attention is given on developing relationships

    model for cause and effect factors of construction waste generation.

  • 3

    Hence, this study focuses on identifying factors of construction waste

    generation and developing a structural model of cause and effect factors of

    construction waste generation for Malaysian construction industry.

    1.3 Research Questions

    Based on the problem statement of the study, the research questions are formulated

    to help researcher into achievable objectives. This research focuses on the following

    research questions:

    i. What are the cause and effect factors of construction waste?

    ii. What is the main factor of the cause and effect factors of construction waste?

    iii. How to develop a relationships model between the factors and construction

    waste generation?

    1.4 Aim and Objectives

    The aim of this study is to develop a relationship model of cause and effect factors of

    construction waste generation for Malaysian construction industry. In order to

    achieve this aim, the objectives of this study are:

    i. Identifying cause and effect factors of construction waste.

    ii. Determining hierarchically the cause and effect factors of construction waste.

    iii. Developing structural model of cause and effect factors of construction waste.

    1.5 Scope of the Research

    This study focuses on identifying the cause and effect factors of construction waste

    generation through factual perception of the construction practitioners. The target

    respondents are focuses to contractors, consultants and clients. These three categories

    of respondent are the major players in Malaysia construction industry (Yong &

  • 4

    Mustaffa, 2011). Contractors who involved in the study are registered with

    Construction Industry Development Board (CIDB) of Malaysia. There are seven

    categories of contractors from smallest contractor G1 (less than RM 200,000) until

    the largest contractor G7 (above than RM 10 million). Consultant who is working in

    Malaysia construction project is identified during direct visitation to their office/site.

    Client who has participated in the survey is from government body such as Public

    Work Department (JKR) and Solid Waste Management and Public Cleansing

    Corporation (PPSPPA). The gathering of data involves only quantitative method

    using structured questionnaire distributed throughout Malaysia. Since the research

    focuses for Malaysia construction industry, all the respondents involved are only

    from Malaysia.

    1.6 Thesis Structure

    This study focuses on developing a structural model of cause and effect factors of

    construction waste generation for Malaysian construction industry. The thesis of this

    study is divided into 6 chapters as stated below:

    Chapter 1: This chapter discusses the need of this study. It contains

    background, problem statement to summarize the main research questions and

    objectives of the study.

    Chapter 2: This chapter contains the review of published research works for

    the related study on construction waste factors and effects.

    Chapter 3: This chapter explains research plan and the methodology adopted

    for this research work. It presents details of analyzing approaches used for data

    analysis together with the data collection technique.

    Chapter 4: This chapter discusses the univariate analysis results including

    identifying and determining hierarchically the cause and effect factors of

    construction waste generation. It also highlights the most top factor of cause and

    effect of construction waste generation in Malaysia construction industry.

    Chapter 5: This chapter explains the multivariate approaches of structural

    equation modelling (SEM) analysis. It also includes the development of structural

  • 5

    model of cause and effect factors of construction waste generation using PLS-SEM

    approaches and as well as explains the course of validating the model’s output.

    Chapter 6: The final chapter discusses the conclusion of the results achieved

    from this study with direction for future works to benefit the construction industry

    for controlling the construction waste factors of a project.

  • CHAPTER 2

    CAUSE AND EFFECT FACTORS OF CONSTRUCTION WASTE

    2.1 Introduction

    This chapter provides an overview of the types, issues and factors of construction

    waste generation. Based on literature review the cause and effect factors are linked

    into a theoretical model. This model is addressing a gap in construction waste

    domain for Malaysia construction industry. This study explores the relationships of

    cause and effect of factors of construction waste generation.

    2.2 Construction Industry

    Construction industry plays a significant role in helping the development of a

    country to achieve developed nation status by the year 2020 (Islam & Ismail, 2010;

    Khan et al., 2014). Therefore to fulfil the development process, high number of

    construction projects are being planned and constructed in the 10th

    Malaysia Plan

    (2011-2015) (CIDB, 2013b). Table 2.1 shows the total number and amount of

    construction projects are being registered in Construction Industry Development

    Board, Ministry of Works, Malaysia.

  • 7

    Table: 2.1: Construction Projects Registered under CIDB

    Year

    Total

    Numbers of

    Projects

    Total Project Value

    (RM million) Source

    2009 7,039 74,913.65 CIDB, 2011

    2010 7,124 87,286.46 CIDB, 2011

    2011 7,359 97,034.17 CIDB, 2012

    2012 7,542 122,720.59 CIDB, 2013b

    From Table 2.1, it can be perceived that the trend of construction project

    numbers and its value are increasing from 2009 to 2012. Currently, numerous mega

    construction projects are ongoing in Malaysia such as Kuala Lumpur International

    Airport 2 (KLIA 2) project with RM 997,227,000.00 (Habibullah et al., 2012), and

    Electrified Double Track Project (EDTP), Ipoh - Padang Besar project with RM

    12.485 billion (Gamuda, 2014). Due to this rapid development in the construction

    sector, the construction industry faces the problem with construction waste

    generation. According to Nasaruddin & Ravana (2008) and Begum et al. (2010), the

    construction waste generation is increasing every year in Malaysia. This problem is a

    crucial challenge for the construction industry.

    According to Ofori (2000), construction industry in developing country needs

    to take challenges in reducing waste generation which was to land disposal and also

    need to find an environmental-friendly way of minimizing the waste. This is because

    the generated waste leads to negative impact on the environment (Papargyropoulou

    et al., 2011; Winkler, 2010). Hence, the construction waste such as time and cost

    overrun also reduces the overall projects performance in the construction industry

    (Alwi et al., 2002b).

    2.3 Type of Construction Waste

    Waste is considered as unwanted material (Ferguson et al., 1995) which is a by-

    product of human and industrial activity that has no residual value (Serpell &

    Alarcon, 1998). It is also considered as losses which are resulted from activities that

    consume direct or indirect costs but do not add value to the end product (Koskela,

    1992). For construction waste, it is generated due to construction activities which

  • 8

    include design works, planning, procurement, execution, renovation and also

    demolition. Currently, construction industry is facing severe problem due to

    construction waste generation that increase rapidly (Foo et al., 2013) worldwide such

    as in United States and Europe (Serpell et al., 1995), Singapore (Hwang & Yeo,

    2011), Sri Lanka (Senaratne & Wijesiri, 2008) and Malaysia (Azis et al., 2012).

    Construction waste has resulted in consumption of resources in excess than

    the necessary need to execute a service (Freitas, 1995 cited in Branco, 2007). It has a

    significant impact on environment and social aspects of life and also causing

    economic loss. Construction waste can be clustered into two types namely the

    physical and non-physical waste.

    2.3.1 Physical Waste

    Physical construction waste is defined as waste which arises from construction,

    renovation and demolition activities including land excavation or formation, civil and

    building construction, site clearance, demolition activities, roadwork, building

    renovation and repair of damaged buildings. Some researchers define physical waste

    as solid waste which comprises sand, bricks, blocks, steel, concrete debris, tiles

    bamboo, plastics, glass, wood, paper, vegetation and other organic materials (Katz &

    Baum, 2011; Hao et al., 2008; Bossink & Brouwers, 1996). These wasted materials

    are usually deposited at landfills. Figures 2.1-2.4 show the examples of physical

    waste at construction site.

    Figure 2.1: Wastage of Cement at Construction Site

  • 9

    Figure 2.2: Packaging Waste at Construction Site

    Figure 2.3: Metal Waste at Construction Site

    Figure 2.4: Bricks Waste at Construction Site

  • 10

    The generation of physical waste has been highlighted from various countries by

    researcher in term of percentage/weight/volume of waste generated as shown in

    Table 2.2.

    Table: 2.2: Physical Waste Generation

    References Material Waste Generation

    Jaillon et al. (2009) Hong Kong generates 21.5 million tonnes of

    construction waste in 2005.

    Kofoworola &

    Gheewala (2009)

    It is estimated that between 2002 and 2005, an average of 1.1 million tonnes of construction waste was

    generated per year in Thailand.

    Fatta et al. (2003) Construction and demolition waste in Greece is

    estimated to exceed 3.9 million tonnes from years 1999 to 2000.

    Nagapan et al. (2013) 422.9m3 construction waste generated within 2 months

    in three construction projects in Malaysia.

    McGrath & Anderson

    (2000) Construction waste is estimated around 70 million

    tonnes every year in United Kingdom.

    John et al. (2004) Generation of Construction and demolition waste in

    Brazil is estimated 68.5 million tonnes annually.

    2.3.2 Non-Physical Waste

    Non-physical waste is normally occurred during the construction process such as

    rework, waiting time, unnecessary transportation, delay in moving material and

    others. Non-physical waste can also be termed as non-value adding activities that are

    usually resulted to time and cost overrun for a construction project (Alwi et al.,

    2002a; Nazech et al., 2008). Figures 2.5 and 2.6 show the examples of activities that

    could result to non-physical waste at construction site.

  • 11

    Figure 2.5: The Need for Rework Figure 2.6: Equipment Failure Leads to

    Stoppage of Work

    Table 2.3 shows the time and cost overrun scenario in different countries.

    Table 2.3: Time and Cost Overrun Problems in Several Countries

    References Country

    Experiencing of the non

    physical waste problem

    Time Cost

    Senaratne & Wijesiri (2008) Sri Lanka √ √

    Hwang & Yeo (2011); Ekanayake & Ofori

    (2000); Zhao & Chua (2003) Singapore √

    Polat & Ballard (2004) Turkey √

    Alwi, Hampson, & Mohamed (2002a);

    Nazech et al., (2008) Indonesia √ √

    Formoso et al., (2002) Brazil √ √

    Serpell et al., (1995) Chile √

    Faniran & Caban (1998); Alwi et al., (2002) Australia √

    Koskela (1992) Finland √ √

    Table 2.3 indicates that are many countries experiencing the time and cost

    overrun. All these problems can be considered as non physical waste (Alwi et al.,

    2002b).

  • 12

    2.4 Issues on Construction Waste

    Construction wastes have become a pressing issue in many developing countries and

    have adverse effects on environment, economy and social aspects. The related issue

    of construction waste problem is illegal dumping of the waste. This problem become

    a frequent issue created from construction waste in many countries (Rahmat &

    Ibrahim, 2007, Yuan, 2012, Yu et al., 2013). Malaysia is facing serious illegal

    dumping problem throughout the country (Yahaya & Larsen, 2008). A study

    conducted by Mahayuddin, (2011), have identified 13 illegal dumpsites in Ipoh,

    Perak while Rahmat & Ibrahim, (2007) found 19 illegal dumping sites are located

    near to the road side corridor in Johor Bahru, Johor. Since 2011 until 2014, local

    newspapers highlighted illegal dumping issues in a few places in the country as

    shown in Figure 2.7-2.10 below.

    Figure 2.7: Construction Waste Illegally

    Dumped at Mangrove Swamp, Malacca

    in 2011 (Murali, 2011)

    Figure 2.8: Construction Waste at 17/1A

    Road, Petaling Jaya in 2012 (Wei, 2012)

  • 13

    Figure 2.9: Construction Waste Illegally

    Dumped at Taman Ruwiyah, Selayang

    in 2013 (Ghani, 2013)

    Figure 2.10: Construction Waste Illegally

    Dumped at Kampung Melayu Subang in

    2014 (Sharifah & Zainal, 2014)

    This construction waste problem is caused by many contributory factors of

    construction waste generation. Hence, to avoid/prevent the generation of construction

    waste, the practitioners need to identify the main factors of construction waste

    generation before engaging in construction works.

    2.5 Causative Factor of Construction Waste

    Construction waste is generated throughout the project from the inception stage until

    the completion stage. There are many factors contribute to construction waste

    generation. A total of 81 factors are identified from research articles worldwide

    (Nagapan et al., 2012). Most of the articles grouped their factors differently.

    However, majority of the articles introduced the groups of some similarities. Table

    2.4 shows various groups introduced by the previous researchers. It ranges between 4

    to 10 groups.

    Table 2.4: Various Groups of Factors

    Researchers Groups No of

    groups

    Senaratne & Wijesiri (2008) Management, Resources, Information, External 4

    Guerrero et al. (2012) Design, Construction process, Material management,

    Operation, Residues, Other 6

    Ekanayake & Ofori (2000) Design, Operational, Material Handling, Procurement 4

    Bossink and Brouwers

    (1996)

    Design, Procurement, Materials Handling, Operation,

    Residual, Other 6

  • 14

    Table 2.4 (continued)

    Table 2.4 shows the categorization of the group of factors by previous

    researchers varies between four to ten groups. In this study the factors are

    categorized into 7 groups. The groups are Design, Handling of Materials and

    Equipment, Workers, Management, Site Condition, Procurement and External group

    (Nagapan et al., 2013). Each group of factors is presented in the following sub-

    sections.

    2.5.1 Design Group of Factors (DESG)

    Design is an important stage before the construction activity is going to be started on

    site. Previous researchers identified many wasteful activities during the design stage.

    The majority of these wasteful activities consume time and effort without adding

    value for the construction project (Love, 1996). Besides that, in design group there

    are 12 factors contributing to waste generation. All the design factors are shown in

    Table 2.5.

    Researchers Groups No of

    groups

    Polat & Ballard (2004)

    Design, Procurement, Operation, Other

    4

    Graham & Smithers (1996) Design, Procurement, Materials Handling, Operation,

    Residual, Other 6

    Akhir et al. (2013)

    Information and communication, Equipments, Project and

    Contract Management, Material, Procurement, External,

    Manpower

    7

    Ilhaq (2010)

    Contractual, Design, Procurement, Transportation, Onsite

    management and Planning, Material storage, Material

    Handling, Site Operation, Others

    8

    Alwi et al. (2002a) People, Professional Management, Design and

    Documentation; Materials, Execution and External. 6

    Nazech et al. (2008)

    Manpower, Professional management, Design and

    Documentation, Materials, Work execution, External

    factors

    6

    Urio & Brent (2006) Design, Procurement, Materials Handling, Operation,

    Residual, Other 6

    Osmani et al. (2008)

    Contractual, Design, Procurement, Transportation, On-site

    Management and Planning, Material storage, Material

    handling, Site operation, Residual, Other.

    10

    Adnan (2012) Design, Procurement, Material, Operational, Others 5

  • 15

    Table 2.5: Design Group of Factors

    No Factors References

    1 Frequent design changes Adewuyi & Otali, (2013); Faniran & Caban (1998); Yunpeng

    (2011); Alwi et al. (2002b); Zhao & Chua (2003)

    2 Design errors Tam et al. (2007); Wan et al. (2009); Senaratne & Wijesiri

    (2008); Noor, (2013)

    3 Lack of design information Osmani et al. (2008); Urio & Brent (2006); Polat & Ballard

    (2004)

    4 Poor design quality Nazech et al. (2008); Formoso et al. (2002); Alwi et al.

    (2002a)

    5 Slow drawing distribution Nazech et al. (2008);

    Alwi et al. (2002a); Alwi et al. (2002b)

    6 Incomplete contract document Ekanayake & Ofori (2000); Poon et al. (2004)

    7 Complicated design Poon et al. (2004); Guerrero et al. (2012)

    8 Inexperience designer Ekanayake & Ofori (2000); Bossink & Browers (1996);

    Osmani et al. (2008)

    9 Error in contract

    documentation Urio & Brent (2006); Osmani et al. (2008)

    10 Interaction between various

    specialists Garas et al. (2001); Polat & Ballard (2004)

    11 Poor coordination of parties

    during design stage Poon et al. (2004); Urio & Brent (2006)

    12 Last minute client requirements Poon et al. (2004); Osmani et al. (2008)

    These 12 factors as indicates in Table 2.5 is identified from the past research

    works. The formation of ‘design group’ is in line with the research works carried out

    by Guerrero et al. (2012) where the group is one of the contributors to construction

    waste generation.

    2.5.2 Handling Materials and Equipment Group of Factors (HAND)

    Handling methods play a vital role to prevent damages in construction projects.

    Commonly, handling methods related to material handling and equipment handling

    by workers in any construction projects. Researchers from Malaysia concur with the

    problem and found most of the material was damaged due to handling works Ilhaq

    (2010). This waste generation group consisted of 9 factors are as shown in Table 2.6.

  • 16

    Table 2.6: Handling of Materials and Equipment Group of Factors

    No Factors References

    1 Wrong material storage Wahab & Lawal (2011); Lau et al. (2008); Mokhtar & Mahmood,

    (2008); Guerrero et al. (2012)

    2 Poor material handling Kofoworola & Gheewala (2009); Gavilan & Bernold (1994)

    3 Damage during

    transportation

    Ekanayake & Ofori (2000); Garas et al. (2001); Wahab & Lawal

    (2011); Guerrero et al. (2012)

    4 Poor quality of materials Lu et al. (2011); Nazech et al. (2008); Bossink & Browers (1996);

    Alwi et al. (2002a); Serpell et al. (1995)

    5 Equipment failure Tam et al. (2007); Gavilan & Bernold (1994); Zhao & Chua (2003)

    6 Delay during delivery Polat & Ballard (2004); Alwi et al. (2002a); Zhao & Chua (2003)

    7 Tools not suitable used Wang et al. (2008);Tam et al. (2007); Zhao & Chua (2003)

    8 Inefficient methods of

    unloading Osmani et al. (2008); Poon et al. (2004b); Lau et al. (2008)

    9 Materials supplied in

    loose form Ekanayake & Ofori (2000); Osmani et al. (2008)

    The group is supported from previous research work conducted by

    Ekanayake and Ofori (2000) from the National University of Singapore.

    2.5.3 Workers Group of Factors (WORK)

    Construction projects cannot be carried out without workers or labours. They are the

    major players during the construction activity. The workers will work together with

    other parties as a team to construct the project until its completion. In this study,

    'worker’s group' comprises of 14 factors of waste generation is as shown in Table 2.7.

    Table 2.7: Worker Group of Factors

    No Factors References

    1 Workers' mistakes during

    construction

    Gavilan & Bernold (1994); Llatas (2011);

    Polat & Ballard (2004)

    2 Incompetent worker Nazech et al. (2008); Lu et al. (2011); Formoso et al. (2002);

    Alwi et al. (2002a)

    3 Poor attitudes of workers Ekanayake & Ofori (2000); Serpell et al. (1995)

    4 Damage caused by workers Poon et al. (2004a); Urio & Brent (2006);

    Polat & Ballard (2004)

    5 Insufficient training for

    workers Garas et al. (2001); Wang et al. (2008); Formoso et al. (2002)

    6 Lack of experience Lu et al. (2011); Nazech et al. (2008);

    Alwi et al. (2002a)

    7 Shortage of skilled workers Alwi et al. (2002a); Polat & Ballard (2004); Noor (2013)

  • 17

    Table 2.7 (continued)

    No Factors References

    8 Inappropriate use of materials Urio & Brent (2006); Alwi et al. (2002a)

    9 Poor workmanship Faniran & Caban (1998); Tam et al. (2007)

    10 Worker’s no enthusiasm Yunpeng (2011); Zhao & Chua (2003)

    11 Inventory of materials not well

    documented

    Urio & Brent (2006); Mokhtar & Mahmood

    (2008)

    12 Abnormal wear of equipment Garas et al. (2001)

    13 Lack of awareness among the workers Mokhtar & Mahmood (2008)

    14 Too much overtime for workers Alwi et al. (2002a)

    Without workers factors as indicates in Table 2.7, construction could not take

    place and can cause project stoppage. This grouping of waste generation factors

    adapted from ‘people group’ (Alwi et al., 2002) which is later changed to more

    specific grouping as ‘workers group’.

    2.5.4 Management Group of Factors (MANA)

    From the beginning of construction projects, the management team is considered as a

    driver for the projects. They will plan, supervise and control the construction

    activities. In addition, Serpell (1995) point out that manager has to deal with many

    factors that may negatively affect the construction process. Hence, literature of past

    researchers leads to form a group namely 'management group' as illustrated in Table

    2.8. The similar group name has been applied by Garas et al. (2001) for a study

    conducted on Egyptian Construction Industry.

    Table 2.8: Management Group of Factors

    No Factors References

    1 Poor planning Ekanayake & Ofori (2000); Formoso et al. (2002); Senaratne &

    Wijesiri (2008); Zhao & Chua (2003)

    2 Poor controlling Garas et al. (2001); Kofoworola & Gheewala (2009);Senaratne &

    Wijesiri (2008)

    3 Poor site management Urio & Brent (2006); Lu et al. (2011); Formoso et al. (2002);

    Zhao & Chua (2003)

    4 Poor supervision Wang et al. (2008); Nazech et al. (2008); Alwi et al. (2002a);

    Zhao & Chua (2003)

    5 Inappropriate construction

    methods Wahab & Lawal (2011); Tam et al. (2007); Polat & Ballard (2004)

  • 18

    Table 2.8 (continued)

    No Factors References

    6 Lack of coordination among

    parties Yunpeng (2011); Garas et al. (2001); Alwi et al. (2002a)

    7 Poor information quality Wang et al. (2008); Senaratne & Wijesiri (2008); Serpell et al.

    (1995)

    8 Late information flow among

    parties

    Ekanayake & Ofori (2000); Osmani et al. (2008); Senaratne &

    Wijesiri (2008); Alwi et al. (2002b)

    9 Scarcity of equipment Formoso et al. (2002); Serpell et al. (1995); Polat & Ballard

    (2004)

    10 Lack of waste management

    plans

    Bossink & Browers (1996); Urio & Brent (2006); Polat &

    Ballard (2004); Akhir (2013)

    11 Resources problem Wahab & Lawal (2011); Senaratne & Wijesiri (2008)

    12 Rework Wan et al. (2009); Garas et al. (2001); Polat & Ballard (2004);

    Akhir (2013)

    13 Waiting periods Zhao & Chua (2003); Alwi et al. (2002b)

    14 Communication problems Gavilan & Bernold (1994); Yunpeng (2011)

    15 Outdated equipment Nazech et al. (2008); Alwi et al. (2002a)

    16 Non availability of

    equipment Zhao & Chua (2003); Serpell et al. (1995)

    17 Lack of knowledge about

    construction Kofoworola & Gheewala (2009); Urio & Brent (2006)

    18 Long project duration Poon et al. (2004b) ; Osmani et al. (2008)

    19 Lack of influence of

    contractors Urio & Brent (2006)

    20 Lack of environmental

    awareness Wang et al. (2008)

    Table 2.8 demonstrates that the management group is the biggest number of

    waste contributory factors involved with 20 factors contributing to the construction

    waste generation.

    2.5.5 Site Condition Group of Factors (SITE)

    Unfavourable site conditions such as soft soil/peat soil or hilly area for construction

    activities need more attention as compared to ordinary site. This is because the earth

    is geographically hilly and swampy. So, these conditions lead to construction waste

    generation. For this research, 'site condition group' contains 8 contributory factors as

    shown in Table 2.9.

  • 19

    Table 2.9: Site Condition Group of Factors

    No Factors References

    1 Leftover materials on site Lau et al. (2008); Faniran & Caban (1998); Poon et al.

    (2004a)

    2 Waste resulting from packaging Llatas (2011); Bossink & Browers (1996); Wang et al.

    (2008)

    3 Poor site condition Formoso (2002); Zhao & Chua (2003); Alwi et al. (2002)

    4 Waiting due to congestion at site Serpell et al. (1995); Zhao & Chua (2003)

    5 Waiting due to lighting problem Zhao & Chua (2003)

    6 Difficulties accessing construction

    sites Osmani et al. (2008)

    7 Unforeseen ground conditions Poon et al. (2004b)

    8 Interference of others crews at site Zhao & Chua (2003)

    In line with the group, there are few articles supported the grouping factors (Zhao &

    Chua, 2003; Alwi et al., 2002a).

    2.5.6 Procurement Group of Factors (PROC)

    Procurement is essential to deliver a project on time, on budget and to a high quality

    (CIOB, 2010). It is very close in dealing with supplier, contractor or client for

    purchasing and ordering the construction materials. During the construction process,

    many projects faced procurement problem (Lu & Yuan, 2011b; Tam et al., 2007). In

    this study 'procurement group' consists of 10 factors for construction waste

    generation as highlighted in Table 2.10.

    Table 2.10: Procurement Group of Factors

    No Factors References

    1 Ordering errors Mokhtar & Mahmood, (2008); Poon et al. (2004) ; Lu et al.

    (2011); Polat & Ballard (2004)

    2 Items not in compliance with

    specification

    Ekanayake & Ofori (2000); Formoso et al. (2002); Garas et

    al. (2001)

    3 Error in shipping Gavilan & Bernold (1994); Wang et al. (2008); Tam et al.

    (2007)

    4 Mistakes in quantity surveys Ekanayake & Ofori (2000); Tam et al. (2007); Polat &

    Ballard (2004)

    5 Supplier errors Urio & Brent (2006)

    6 Wrong material delivery

    procedures Urio & Brent (2006)

    7 Over allowances Osmani et al. (2008)

  • 20

    Table 2.10 (continued)

    No Factors References

    8 Frequent variation orders Ndihokubwayo & Haupt (2009)

    9 Different methods used for

    estimation Lau et al., (2008)

    10 Waiting for replacement Polat & Ballard (2004)

    2.5.7 External Group of factors (EXTE)

    External factors are uncontrollable factor which can generate construction waste

    (Alwi et al., 2002a). External factor group's is named in different way according to

    previous researchers. Some of the researchers name it as 'unpredicted situations'

    (Garas et al., 2001), 'others' (Urio & Brent, 2006) and 'external' (Alwi et al., 2002a) .

    For this study, the group consists of 8 uncontrollable factors contributing to waste

    generation as stated in Table 2.11.

    Table 2.11: External Group

    No Factors References

    1 Effect of weather Wahab & Lawal (2011); Senaratne & Wijesiri (2008); Akhir et

    al. (2013)

    2 Accidents Ekanayake & Ofori (2000); Bossink & Browers (1996); Polat &

    Ballard (2004)

    3 Pilferage Garas et al. (2001); Faniran & Caban (1998); Muhwezi et al.,

    (2012)

    4 Lack of legislative

    enforcement Esin & Cosgun (2007); Wang et al. (2008); Faridah et al. (2004)

    5 Vandalism Wahab & Lawal (2011); Garas et al. (2001)

    6 Damages caused by third

    parties Nazech et al. (2008); Alwi et al. (2002a)

    7 Festival celebration Serpell et al. (1995)

    8 Unpredictable local

    conditions Polat & Ballard (2004)

    This type of group as in Table 2.11 is supported by Nazech et al. (2008) who

    conducting study on construction waste generation for Indonesia construction

    industry.

  • 21

    2.6 Effect factors of Construction Waste

    Construction wastes give many negative effects to a country. In Malaysia,

    construction waste is getting worse with the illegal dumping issues as described in

    Chapter 2 Section 2.4. From the review of literature it has been identified that there

    are three main groups of effect factors for construction waste generation that are

    environment, economic and social (Begum et al., 2010; Begum et al., 2006; Mokhtar

    & Mahmood, 2008; Seow and Mohamad, 2007). The effect factor of construction

    waste is looking into these three elements.

    2.6.1 Environment

    Environment encompasses of all living and non living things on earth which interact

    with all of living species (Johnson et al., 2007). Therefore, these construction wastes

    (non living things) from the construction industry have high impact on the

    environment (Yunpeng, 2011). Table 2.12 is consisted of 4 effect factors.

    Table 2.12: Environment Group

    No Factors References

    1 Environmental

    pollutions

    Lu et al. (2011); Llatas (2011); Wang & Li (2011); Begum et al.

    (2010);Che Hasan et al. (2013); Liu & Huang ( 2013)

    2 Shortage of land Kofoworola & Gheewala (2009); Mokhtar & Mahmood (2008);

    Ortiz et al. (2010)

    3 Increasing of Illegal

    dumping

    Gavilan & Bernold (1994); Kofoworola & Gheewala (2009); Seow

    and Mohamad (2007); Seror et al. (2014)

    4 Ecological damage Yunpeng (2011); Lu & Yuan, 2010

    The group as presented in Table 2.12 is formed to reflect the effect of

    construction waste generation on the environment.

  • 22

    2.6.2 Economy

    A country growth is based on economic development in the country. The economy

    development system works when all professions, occupations, economic activities

    contribute to the economy development of the country (Esin & Cosgun, 2007). For

    this study, the effect factors related to cost overrun and time loss of a construction

    project (Formoso et al., 2002; Alwi et al., 2002). The economy group comprises of 5

    factors which give effect from construction waste is shown in Table 2.13.

    Table 2.13: Economy Group

    No Factors References

    1 Increase in transportation charge of

    construction waste have been raised

    Faridah et al., (2004); Faniran & Caban (1998);

    Ekanayake & Ofori (2000)

    2 Increase cost of projects Khairulzan & Halim (2006); Urio & Brent

    (2006); Ndihokubwayo & Haupt (2009)

    3 Increase landfill fee Gavilan & Bernold (1994); Wang et al. (2008)

    4 Increase in price of raw materials Faniran & Caban (1998); Khairulzan & Halim

    (2006)

    5 Delay of projects Khairulzan & Halim (2006); Ndihokubwayo &

    Haupt (2009);

    These 5 factors as shown in Table 2.13 are identified from literature review to

    reveal the construction waste effect from economic perspective.

    2.6.3 Social

    Social attributes occur whenever people interact under specific conditions,

    circumstances and actions (Merton, 1968). The social attribute is also related to

    human or population growth in a country (Katz & Baum, 2011). With more

    population in a country, more problems can arise from the construction waste

    generation. Furthermore, the impact of construction waste will lead people to create

    problems in term of health and negative relationships among them. The social factors

    are presented in Table 2.14.

  • 23

    Table 2.14: Social Group

    No Factors References

    1 Mental health effects Llatas (2011); Wang & Li (2011); Seow and Mohamad (2007); Tam et

    al. (2007)

    2 Physical health effects Wang et al. (2008); Yunpeng (2011); Noor (2013); Wu et al. (2014)

    3 Injury to public Khairulzan & Halim (2006); Mokhtar & Mahmood (2008); Ortiz et al.

    (2010)

    4 No aesthetic Khairulzan & Halim (2006); Seow & Mohamad (2007); Seror et al.

    (2014)

    Table 2.14 is reflected the effect of social group from construction waste generation.

    2.7 Theoretical Model

    Theoretical model or hypothetical model is developed from a review of past research

    works (Aibinu & Lawati, 2010). The theoretical model is basis for testing the

    relationships of independent and dependent variables (Fellows & Liu, 2008). Hence,

    based on a review of the literature, a structural model of cause and effect factors is

    developed as presented in Figure 2.11.

    Figure 2.11: Theoretical Model of Construction Waste

  • 24

    The theoretical model as in Figure 2.11 is concerned with relationships of cause and

    effect factors of construction waste. Furthermore, the linkages between causes

    (design, handling, workers, management, site condition, procurement and external

    factor) and effects (environment, economy and social) have been integrated into one

    relationship model. This addresses a gap in the literature by providing a complete

    model within the context of relationship in construction waste domain. In order to

    provide more complete understanding of the cause and effect factors of this model,

    several hypotheses is constructed from the model.

    The relationships between the cause and effect factors (independent variables)

    and construction waste generation (dependent variable) form the basis to formulate

    hypotheses as describe below:

    H1: DESG (design) has significant effect on construction waste

    H2: HAND (handling) has significant effect on construction waste

    H3: WORK (workers) has significant effect on construction waste

    H4: MANA (management) has significant effect on construction waste

    H5: SITE (site condition) has significant effect on construction waste

    H6: PROC (procurement) has significant effect on construction waste

    H7: EXTE (external factors) has significant effect on construction waste

    H8: Construction waste has significant effect on EN (environment)

    H9: Construction waste has significant effect on SO (social)

    H10: Construction waste has significant effect on EC (economy)

    2.8 Summary

    Construction industry is contributing significantly in economic and social

    development of the country. However, it is facing chronic problem of construction

    waste generation globally which needs serious attention and in depth study to resolve

    it. For this, the first and foremost important step is to understand the problem of

    construction waste, causes contributing to waste generation and the effects of waste.

    This chapter presents a comprehensive literature review carried out to understand the

    issue of construction waste and the cause and effect factors. This has resulted in

  • 93

    REFERENCES

    Aadal, H., Rad, K. G., Fard, A. B., Ghasemi, P., & Sabet, P. (2013). Implementing

    3R Concept in Construction Waste Management at Construction Site. Journal

    of Applied Environmental and Biological Sciences, 3(10), pp. 160–166.

    Adewuyi, T. O., & Otali, M. (2013). Evaluation of Causes of Construction Material

    Waste - Case of Rivers State, Nigeria. Ethiopian Journal of Environmental

    Studies and Management, 6, pp. 746–753.

    Adnan, N. F. (2012). A Study of Construction Waste Generation at Site Project in

    Batu Pahat, Johor. Universiti Tun Hussein Onn Malaysia: Thesis Master.

    Aibinu, A., & Al-lawati, A. (2010). Using PLS-SEM Technique to Model

    Construction Organizations Willingness to Participate in E-bidding.

    Automation in Construction, 19(6), pp. 714–724.

    doi:10.1016/j.autcon.2010.02.016.

    Akhir, N., Rahman, I. A., Memon, A. H., Nagapan, S. (2013). Factors of Waste

    Generation throughout Construction Life Cycle. Proceedings of the

    Malaysian Technical Universities Conference on Engineering and

    Technology (MUCET). Pahang, Malaysia.

    Akter, Ambra, & Ray. (2011a). Trustworthiness in mHealth Information Services :

    An Assessment of a Hierarchical Model with Mediating and Moderating

    Effects Using Partial Least Squares (PLS). Journal of the American Society

    for Information Science and Technology, 62(1), pp. 100–116. doi:10.1002/asi.

    Akter, S., Ambra, J. D., & Ray, P. (2011b). An evaluation of PLS based complex

    models: the roles of power analysis, predictive relevance and GoF index.

    Proceedings of the 17th Americas Conference on Information Systems.

    Detroit, Michigan. pp 1-7.

    Akintoye, A. (2000). Analysis of Factors Influencing Project Cost Estimating

    Practice. Construction Management and Economics,18(1), pp. 77-89.

  • 94

    Alwi, S., Hampson, K., & Mohamed, S. (2002a). Non Value-Adding Activities in

    Australian Construction Projects. Proceedings of the International

    Conference on Advancement in Design, Construction, Construction

    Management and Maintenance of Building Structure. Bali. pp. 270–278.

    Alwi, S., Hampson, K., & Mohamed, S. (2002b). Waste in the Indonesian

    Construction Projects. Proceedings of the 1st International Conference of

    CIB W107 - Creating a sustainable Construction Industry in Developing

    Countries. South Africa: Griffith University. pp. 305–315.

    Al-Najjar, J. M. (2008). Factors Influencing Time and Cost Overruns on

    Construction Projects in the Gaza Strip. Faculty of Engineering, The Islamic

    University Gaza: Master’s Thesis.

    Awang, M. (2014). Struktur Kompetensi Pengurusan Fasiliti dan Petunjuk Prestasi

    Utama Politeknik. Universiti Teknologi Malaysia: Ph.D. Thesis.

    Ann, Y., Poon, C. S., Wong, A., Yip, R., & Jaillon, L. (2013). Impact of

    Construction Waste Disposal Charging Scheme on Work Practices at

    Construction Sites in Hong Kong. Waste Management, 33(1), pp. 138–46.

    doi:10.1016/j.wasman.2012.09.023.

    Azis, A. A. A., Memon, A. H., Rahman, I. A., Nagapan, S., & Latif, Q. B. A. I.

    (2012). Challenges Faced by Construction Industry in Accomplishing

    Sustainability Goals. Proceedings of the IEEE Symposium on Business,

    Engineering and Industrial Applications. Bandung, Indonesia. pp. 630–634.

    Bagozzi, & Yi. (1988). On the Evaluation of Structural Equation Models. Journal of

    the Academy of Marketing Science, 16(1), pp.74–94.

    Banerjee, A., Chitnis, U. B., Jadhav, S. L., Bhawalkar, J. S., & Chaudhury, S. (2009).

    Hypothesis Testing, Type I and Type II Errors. Industrial Psychiatry Journal,

    18(2), pp. 127–131. doi:10.4103/0972-6748.62274.

    Bell, J. (1993). Doing your Research Project. Milton Keynes: Open University Press.

    Begum, R. A., Satari, S. K., & Pereira, J. J. (2010). Waste Generation and Recycling:

    Comparison of Conventional and Industrialized Building Systems. American

    Journal of Environmental Sciences, 6(4), pp. 383–388.

    doi:10.3844/ajessp.2010.383.388.

    Begum, R. A., Siwar, C., Pereira, J. J., & Jaafar, A. H. (2006). Factors and Values of

    Willingness to Pay for Improved Construction Waste Management: A

  • 95

    Perspective of Malaysian Contractors. Waste Management, 27(12), pp. 1902–

    1909. doi:10.1016/j.wasman.2006.08.013.

    Begum, R. A., & Pereira, J. J. (2008). Awareness , Attitude and Behavioural Status

    of Waste Management : A Profile of Malaysian Contractors. Asian Journal of

    Water, Environment and Pollution, 5(3), pp. 15–22.

    Bossink, B. A. G., & Brouwers, H. J. H. (1996). Construction Waste: Quantification

    and Source Evaluation. Journal of Construction Engineering and

    Management, 122(1), pp. 55–60. doi://dx.doi.org/10.1061/(ASCE)0733-

    9364(1996)122:1(55).

    Branco, C. R. C. (2007). An Effective Way to Reduce Residential Construction Waste:

    A Case Study in Texas. Texas A&M University: Master’s Thesis.

    Brown, J.D. (2001).Using Surveys in Language Programs. Cambridge: Cambridge

    University Press.

    Byrne, B.M (2010). Structural Equation Modeling with AMOS: Basic Concepts,

    Applications, and Programming. 2nd

    ed. New York: Taylor and Francis

    Group.

    Che Hasan, A. B., Yusof, Z. B., Mohd Ridzuan, A. R. B., Atan, I. B., Noordin, B. B.,

    & Abdul Ghani, A. H. B. (2013). Estimation Model of Construction Waste

    Materials in Malaysia: Steel. Proceedings of the IEEE Business Engineering

    and Industrial Applications Colloquium. Langkawi. pp. 709–713.

    Chin. (1998). The Partial Least Squares Approach to Structural Equation Modeling.

    Modern Methods for Business Research, 295(2), pp. 295–336.

    Chin, W. W. (2010). How to Write Up and Report PLS Analyses. In V. Esposito

    Vinzi et al. (eds.) (Ed.), Handbook of Partial Least Squares, Berlin: Springer.

    doi: 10.1007/978-3-540-32827-8 29.

    CIDB. (2011). Construction Statistics Quarterly Bulletin (Dec 2011). Construction

    Industry Development Board Malaysia. Retrieved from

    https://www.cidb.gov.my/cidbv2/images/pdf/buletin/2011/BahagianKeduaQ4

    2011.pdf.

    CIDB. (2012). Construction Statistics Quarterly Bulletin (Dec 2012). Construction

    Industry Development Board Malaysia. Retrieved from

    https://www.cidb.gov.my/cidbv2/images/pdf/buletin/2012/bahagian

    keduas42012.pdf.

  • 96

    CIDB. (2013a). Construction Sector Growth Trend from 1980 to 2012. International

    Construction Week 2013, Construction Industry Development Board

    Malaysia, Kuala Lumpur.

    CIDB. (2013b). Construction Statistics Quarterly Bulletin (Sept 2013). Construction

    Industry Development Board Malaysia. Retrieved from

    https://www.cidb.gov.my/cidbv2/images/pdf/buletin/2013/bahagian 2 q3-

    2013.pdf.

    CIOB. (2010). A Report Exploring Procurement in the Construction Industry, The

    Chartered Institute of Building. Berkshire, United Kingdom. pp 1-28.

    Chin, W. W. (1998). The Partial Least Squares Approach to Structural Equation

    Modeling. Modern Methods for Business Research, 295(2), pp. 295-336.

    Chin, W. W. (2010). How to Write up and Report PLS Analyses, in Handbook of

    Partial Least Squares: Concepts, Methods and Application. Esposito Vinzi,

    V.; Chin, W.W.; Henseler, J.; Wang, H. (Eds.), Springer, Germany. pp. 645-

    689.

    Cohen. (1988). Statistical Power Analysis for the Behavioral Sciences. 2nd

    ed. New

    Jersey: Lawrence Erlbaum Associates Publishers.

    Dainty, A. R. J., & Brooke, R. J. (2004). Towards Improved Construction Waste

    Minimisation : A Need for Improved Supply Chain Integration. Structural

    Survey Journal, 22(1), pp. 20–29. doi:10.1108/02630800410533285.

    Dulami, M.F., Ling, F.Y.Y., and Bajracharya, A. (2003). Organisational Motivation

    and Inter-organisational Interaction in Construction Innovation in Singapore.

    Construction Management and Economics, 21(3), pp. 307-318.

    Economic Planning Unit. (2011). 10th Malaysia Plan: Building on the Nation’s

    Strengths Prime Ministry Department. Retrieved from

    http://www.epu.gov.my/epu-theme/RMKE10/rmke10_english.html.

    Ekanayake, L. L., & Ofori, G. (2000). Construction Material Waste Source

    Evaluation. Proceedings of the Strategies for a Sustainable Built Environment,

    Pretoria. pp. 23-25.

    Enshassi, A., Al-Najjar, J., & Kumaraswamy, M. (2009). Delays and Cost Overruns

    in the Construction Projects in the Gaza Strip. Journal of Financial

    Management of Property and Construction, 14(2), pp. 126–151.

    doi:10.1108/13664380910977592.

  • 97

    Esin, T., & Cosgun, N. (2007). A Study Conducted to Reduce Construction Waste

    Generation in Turkey. Building and Environment, 42(4), pp. 1667–1674.

    doi:10.1016/j.buildenv.2006.02.008.

    Faridah, A., Halim, H. A., & Hasnain, M. (2004). A Study on Construction and

    Demolition Wastes from Buildings in Seberang Perai. Proceedings of the 3rd

    National Conference in Civil Engineering. Penang, Tanjung Bungah. pp. 1–5.

    Faniran, O. O., & Caban, G. (1998). Minimizing Waste on Construction Project Sites.

    Engineering Construction and Architectural Management Journal, 5(2), pp.

    182–188. doi:10.1108/eb021073.

    Fatta, D., Papadopoulos, A., Avramikos, E., Sgourou, E., Moustakas, K.,

    Kourmoussis, F., Loizidou, M. (2003). Generation and Management of

    Construction and Demolition Waste in Greece: An Existing Challenge.

    Resources, Conservation and Recycling, 40(1), pp. 81–91.

    doi:10.1016/S0921-3449(03)00035–1.

    Ferguson, J., Kermode, N., Nash, C. L., Sketch, W, A, J., & Huxford, R, P. (1995).

    Managing and Minimizing Construction Waste : A Practical Guide. London:

    Institute of Civil Engineers. pp. 3–14.

    Fellows, R and Liu, A.(2008). Research Methods for Construction. 3rd

    ed. Wiley-

    Blackwell: Utopia Press.

    Foo, L. C., Rahman, I. A., Asmi, A., Nagapan, S., & Khalid, K. I. (2013).

    Classification and Quantification of Construction Waste at Housing Project

    Site. International Journal of Zero Waste Generation, 1(1), pp. 1–4.

    Formoso, C. T., Soibelman, L., Cesare, C. De, & Isatto, E. L. (2002). Material Waste

    in Building Industry : Main Causes and Prevention. Journal of Construction

    Engineering and Management, 128(4), pp. 316–325.

    doi:http://dx.doi.org/10.1061/(ASCE)0733-9364(2002)128:4(316).

    Fornell, & Larcker. (1981). Structural Equation Models with Unobservable Variables

    and Measurement Error: Algebra and Statistics. Journal of Marketing

    Research, 18(3), pp. 328–388.

    Freitas, (1995). O Desperdício na Construção civil: Caminhos Para Sua Redução. In

    Branco, C. R. C. (2007). An Effective Way to Reduce Residential

    Construction Waste: A Case Study in Texas. Texas A&M University: Master

    Thesis.

  • 98

    Gamuda. (2014). Electrified Double Track Project (EDTP), Ipoh - Padang Besar.

    Gamuda Berhad. Retrieved from

    http://www.gamuda.com.my/mrt_railway_edtp.html.

    Garas, G. L., Anis, A. R., & Gammal, A. El. (2001). Material Waste in the Egyptian

    Construction Industry. Proceedings of the 9th Annual Conference of the

    International Group for Lean Construction, National University of Singapore,

    pp. 1–8.

    Gavilan, R. M., and Bernold, L. E. (1994). Source Evaluation of Solid Waste in

    Building Construction. Journal of Construction Engineering and

    Management, 120(3), pp. 536-552.

    Ghani. (2013). Sisa Binaan Dibuang Secara Haram bimbangkan Penduduk. Metro

    Newspaper. p. 5.

    Graham, P. and Smithers, G. (1996) Construction Waste Minimization for Australian

    Residential Development. Asia Pacific Building and Construction

    Management Journal, 2(1), pp. 14–19.

    Guerrero, L. A., Maas, G. J., Lambert, A. J. D., and Troyo, F. (2012). Construction

    Waste in Costa Rica. Proceedings of the ISWA World Solid Waste Congress,

    Florence. Italy.

    Habibullah, N., Zafirol, A., Halim, A., & Halim, A. A. (2012). Green Building

    Concept: Case Study: New LCC Terminal & KLIA 2 Sepang, Selangor,

    Malaysia. Journal of Design + Built, 5(1). Retrieved from

    http://www.ukm.my/jsb/jdb/.

    Hair, J. F., Ringle, C. M., & Sarstedt, M. (2011a). PLS-SEM: Indeed a Silver Bullet.

    The Journal of Marketing Theory and Practice, 19(2), pp.139–152.

    Hair, J. F., Sarstedt, M., Ringle, C. M., & Mena, J. (2011b). An Assessment of the

    Use of Partial Least Squares Structural Equation Modeling in Marketing

    Research. Journal of the Academy of Marketing Science, 40(3), pp. 414–433.

    Hair, J. F., Hult, G. T. M., Ringle, C. M., & Sarstedt, M. (2014). A Primer on Partial

    Least Squares Structural Equation Modeling (PLS-SEM).United State of

    America: SAGE Publications.

    Hamid, Z. A. (2011). Policy and Sustainable Development : Malaysian Construction

    Industry perspective. Proceedings of the One Day Seminar – Knowledge

    Sharing on Construction Management. Johor, Malaysia, pp. 1–82.

  • 99

    Hao, J. L., Hill, M. J., & Shen, L. Y. (2008). Managing Construction Waste on-site

    through System Dynamics Modelling : The Case of Hong Kong. Engineering,

    Construction and Architectural Management, 15(2), pp. 103–113.

    Hassan, S. H., Ahzahar, N., Fauzi, M. A., & Eman, J. (2012). Waste Management

    Issues in the Northern Region of Malaysia. Procedia - Social and Behavioral

    Sciences, 42, pp. 175–181.

    Harland, C. M., Lamming, R. C., Walker, H., Philips, W. E., Caldwell, N. D.,

    Johnson, T. E., (2006). Supply Management: Is it a Discipline? International

    Journal of Operations & Production Management, 26(7), pp. 730–753.

    Henseler, J. (2009). On the Convergence of the Partial Least Squares Path Modeling

    Algorithm. Computational Statistics, 25(1), pp. 107–120.

    Hulland. (1999). Use of Partial Least Squares (PLS) in Strategic Management

    Research: A Review of Four Recent Studies. Strategic Management Journal,

    20(2), pp. 195-204.

    Hwang, B., & Yeo, Z. B. (2011). Perception on Benefits of Construction Waste

    Management in the Singapore Construction Industry. Engineering

    Construction and Architectural Management Journal, 18(4), pp. 394–406.

    Idris, N. I. (2012). Construction Waste Management in Malaysia Landfills: A Case

    Study at Dengkil and Kuang Inert Waste Landfill. Universiti Tun Hussein

    Onn Malaysia: Master Thesis.

    Ilhaq, M. (2010). An Investigation with the Concepts of Construction Site Waste

    Minimisation. University of East London: Master Thesis.

    Islam, R., & Ismail, Y. (2010). Malaysia on Course to Become A Developed Country:

    Prioritizing Issues With The Analytic Hierarchy Process. International

    Journal of the Analytic Hierarchy Process, 2(2), pp.1–4.

    Islam, M.D.M. and Faniran, O.O. (2005), Structural Equation Model of Project

    Planning Effectiveness. Journal of Construction Management and Economics,

    23 (2), pp. 215–223.

    Ismail, I. B. (2014). Assessing The Risk of Factors on Time and Cost Overrun

    Throughout Lifecycle of Construction Project. Universiti Tun Hussein Onn

    Malaysia: Master’s Thesis.

  • 100

    Jaillon, L., Poon, C. S., & Chiang, Y. H. (2009). Quantifying the Waste Reduction

    Potential of using Prefabrication in Building Construction in Hong Kong.

    Waste Management, 29(1), pp. 309–320.

    Jayawardane, A.K.W. and Gunawardena, N.D. (1998). Construction Workers in

    Developing Countries: A Case Study of Sri Lanka. Journal of Construction

    Management and Economics, 16, pp. 521-530.

    Jin, X.H., Doloi, H., Gao, S.Y. (2007), Relationship-Based Determinants of Building

    Project Performance in China. Journal of Construction Management and

    Economics, 25, pp. 297–304.

    Jingkuang, L., & Yousong, W. (2011). Establishment and Application of

    Performance Assessment Model of Waste Management in Architectural

    Engineering Projects in China. Systems Engineering Procedia, 1, pp. 147–155.

    John, V. M., Angulo, S. C., Miranda, L. F., Agopyan, V., & Vasconcellos, F. (2004).

    Strategies for Innovation in Construction and Demolition Waste Management

    in Brazil. Proceedings of the CIB World Building Congress, National

    Research Council of Canada, Toronto.

    Johnson, D.L., Ambrose S.H., Bassett T.J., Bowen M.L., Crummey D.E., Isaacson

    J.S., Johnson D.N., Lamb P., Saul M., and Winter, N. A.E. (1997). Meanings

    of Environmental Terms. Journal of Environmental Quality, 26, pp. 581-589.

    Kasim, R., Alexander, K, & Hudson, J. (2006). A Choice of Research Strategy for

    Community-based Action Skills Requirements in the Process of Delivering

    Housing Market Renewal. Proceedings of the 6th

    International Postgraduates

    Research Conference in Built and Human Environment, Delft University,

    Netherland.

    Katz, A., & Baum, H. (2011). A Novel Methodology to Estimate the Evolution of

    Construction Waste in Construction Sites. Waste Management, 31(2), pp.

    353–358. doi:10.1016/j.wasman.2010.01.008.

    Khairulzan, Y. and Halim A. B. (2006). Eco-costing of Construction Waste. Journal

    of Management of Environmental Quality: An International Journal, 17(1),

    pp. 6-19.

    Khan, R. A., Liew, M. S., & Ghazali, Z. Bin. (2014). Malaysian Construction Sector

    and Malaysia Vision 2020: Developed Nation Status. Procedia - Social and

    Behavioral Sciences, 109, pp. 507–513.

  • 101

    Kitchenham, B., and Pfleeger, S. L. (2002). Principles of Survey Research: Part 5

    Populations and Samples. Software Engineering Notes, 27(5), pp. 17-20.

    Kofoworola, O. F., & Gheewala, S. H. (2009). Estimation of Construction Waste

    Generation and Management in Thailand. Waste Management, 29(2), pp.

    731–738. doi:10.1016/j.wasman.2008.07.004.

    Koskela, L. (1992). Application of the New Production Philosophy to Construction.

    Stanford: Center for Integrated Facility Engineering, Stanford University.

    Lam, P. T. I., Chan, E. H. W., Poon, C. S., Chau, C. K., & Chun, K. P. (2010).

    Factors Affecting the Implementation of Green Specifications in Construction.

    Journal of Environmental Management, 91(3), pp. 654–61.

    Lau, H. H., Whyte, A., & Law, P. (2008). Composition and Characteristics of

    Construction Waste Generated by Residential Housing Project. International

    Journal of Environmental Research, 2(3), pp. 261–268.

    Leung M.Y., Ng S.T., Skitmore M., Cheung S.O. (2005), Critical Stressors

    Influencing Construction Estimators in Hong Kong, Construction

    Management and Economics, 23 (1), pp. 33–43.

    Li, X. and Wang, R. (2007). Survey Research on Relationship among Service Failure:

    Service Recovery and Customer Satisfaction. Proceedings of the

    International conference on Management Science and Engineering, Harbin,

    China. pp. 1121-1123.

    Liu, W., & Huang, W. (2013). Research on Construction Waste Resourcelization

    Legislation. Proceedings of the Fifth International Conference on Measuring

    Technology and Mechatronics Automation. Hong Kong. pp. 893–897.

    Llatas, C. (2011). A Model for Quantifying Construction Waste in Projects

    According to the European Waste List. Waste Management, 31(6), pp. 1261–

    1276. doi:10.1016/j.wasman.2011.01.023.

    Lu, W., & Yuan, H. (2011). A Framework for Understanding Waste Management

    Studies in Construction. Waste Management 31(6), pp. 1252–1260.

    doi:10.1016/j.wasman.2011.01.018.

    Lu, W., Yuan, H., Li, J., Hao, J. J. L., Mi, X., & Ding, Z. (2011). An Empirical

    Investigation of Construction and Demolition Waste Generation Rates in

    Shenzhen city, South China. Waste Management, 31(4), pp. 680–687.

    doi:10.1016/j.wasman.2010.12.004.

  • 102

    Lohmoller, J.B., (1989), Latent Variable Path Modeling with Partial Least Squares,

    Heidelberg: Physica. In Aibinu, A., & Al-lawati, A. (2010). Using PLS-SEM

    Technique to Model Construction Organizations Willingness to Participate in

    E-bidding. Automation in Construction, 19(6), pp. 714–724.

    Love, P.E.D. (1996). Toward Concurrency and Integration in the Construction

    Industry. Proceeding of the 3rd ISPE International Conference on Current

    Engineering. Canada.

    Mahayuddin, S. A. (2011). Penjanaan, Komposisi dan Pengurusan Sisa Binaan:

    Kajian Kes Ipoh, Perak. Universiti Kebangsaan Malaysia: Ph.D. Thesis.

    McGrath, C. & Anderson, M. (2000). Waste Minimisation on a construction site:

    Digest 447, Building research Establishment, London.

    Memon, A. H. (2013). Structural Modelling of Factors Causing Cost Overrun in

    Construction Industry. Universiti Tun Hussein Onn Malaysia: Ph.D Thesis.

    Memon, A. H., & Rahman, I. A. (2014). SEM-PLS Analysis of Inhibiting Factors of

    Cost Performance for Large Construction Projects in Malaysia: Perspective of

    Clients and Consultants. The Scientific World Journal, 2014, pp. 1–9.

    Memon, A. H., Rahman, I., Razaki, M., Asmi, A., & Aziz, A. (2011). Time Overrun

    in Construction Projects from the Perspective of Project Management

    Consultant. Journal of Surveying, Construction & Property, 2(1), pp. 54–66.

    Merton, R.K. (1968). Social Theory and Social Structure. New York, Free Press.

    Mokhtar, S. N., & Mahmood, N. Z. (2008). Approach in Construction Industry : A

    study on Prefabrication Method as a Tool for Waste Minimization.

    Proceedings of the International Conference on Environmental Research and

    Technology. Penang. pp. 184–187.

    Molenaar, Washington, & Diekmann. (2000). Structural Equation Model of

    Construction Contract Dispute Potential. Journal of Construction

    Engineering and Management, 126(4), pp. 268–277.

    Muhwezi, L., Chamuriho, L. M., & Lema, N. M. (2012). An investigation into

    Materials Wastes on Building Construction Projects in Kampala-Uganda.

    Scholarly Journal of Engineering Research, 1(1), pp. 11–18.

    Murali, R. S. (2011). An Irresponsible Act: Tropical Mangrove Swamp has Become

    a Construction Dumpsite. The Star. p. 3.

  • 103

    Nasaruddin, F. H., & Ravana, S. D. (2008). E-Construction Waste Exchange in

    Malaysia: A Preliminary Study. Proceedings of the International Symposium

    on Information Technology. pp. 1–7.

    Nagapan, S., Rahman, I. A., Asmi, A., & Adnan, N. F. (2013). Study of Site's

    Construction Waste in Batu Pahat, Johor. Procedia Engineering, 53, pp. 99-

    103.

    Nagapan, S., Rahman, I. A., Asmi, A. (2012). Factors Contributing to Physical and

    Non-Physical Waste Generation in Construction Industry. International

    Journal of Advances in Applied Sciences, 1(1), pp. 1-10.

    Nazech, E. ., Zaldi, D., & Trigunarsyah, B. (2008). Identification of Construction

    Waste in Road and Highway Construction Projects. Proceedings of the

    Eleventh East Asia-Pacific Conference on Structural Engineering &

    Construction. Taipei. pp. 19–21. Retrieved from

    http://eprints.qut.edu.au/17765/.

    Ndihokubwayo, R., and Haupt, T. (2009). Variation Orders on Construction Projects:

    Value Adding or Waste. International Journal of Construction Project

    Management, 1(2), pp. 1- 17.

    Noor, R. N. H. R. M., Ridzuan, A. R. M., Endut, I. R., Noordin, B., Shehu, Z., &

    Ghani, A. H. A. (2013). The Quantification of Local Construction Waste for

    the Current Construction Waste Management Practices: A Case Study in

    Klang Valley. Proceedings of the Business Engineering and Industrial

    Applications Colloquium. pp. 183–188.

    Noor, M. M. (2013). Kajian Pengukuran Sisa Binaan di Tapak Bina Sekitar Batu

    Pahat, Johor. Universiti Tun Hussein Onn Malaysia: Master’s Thesis.

    Nunnally, J. C. (1978). Psychometric theory. 2nd

    ed. In Aibinu, A., & Al-lawati, A.

    (2010). Using PLS-SEM Technique to Model Construction Organizations

    Willingness to Participate in E-bidding. Automation in Construction, 19(6),

    pp. 714–724.

    Ofori, G. (2000). Challenges of Construction Industries in Developing Countries :

    Lessons from Various Countries. Proceedings of the 2nd International

    Conference on Construction in Developing Countries: Challenges Facing the

    Construction Industry in Developing Countries. pp. 15–17.

  • 104

    Osmani, M., Glass J., and Price, A.D.F. (2008). Architects’ Perspectives on

    Construction Waste Reduction by Design. Waste Management, (28), pp.

    1147–1158.

    Ortiz, O., Pasqualino, J.C. and Castells, F. (2010). Environmental Performance of

    Construction Waste: Comparing Three Scenarios from a Case Study in

    Catalonia, Spain. Waste Management, 30, pp. 646–654.

    Papargyropoulou, E., Preece, C., Padfield, R., & Abdullah, A. A. (2011). Sustainable

    Construction Waste Management in Malaysia: A Contractor’s Perspective.

    Proceedings of the Management and Innovation for a Sustainable Built

    Environment. Netherlands.

    Polat, G., & Ballard, G. (2004). Waste in Turkish Construction: Need for Lean

    Construction Techniques. Proceedings of the 12th Annual Conference of the

    International Group for Lean Construction. pp. 1–14.

    Poon, C. S., Yu, A. T. W., & Jaillon, L. (2004a). Reducing Building Waste at

    Construction Sites in Hong Kong. Construction Management and Economics,

    22(5), pp. 461–470.

    Poon C. S., Yu A. T. W., Wong S. W., and Cheung E. (2004b). Management of

    Construction Waste in Public Housing Projects in Hong Kong. Journal of

    Construction Management and Economics, 22(7), pp. 675-689.

    Rahman, I. A., Memon, A. H., Abdullah, N. H., & Azis, A. A. A. (2013).

    Application of PLS-SEM to Assess the Influence of Construction Resources

    on Cost Overrun. Applied Mechanics and Materials, 284, pp. 3649–3656.

    Rahmat, N. R., & Ibrahim, A. H. (2007). Illegal Dumping Site: Case Study in The

    District Of Johor Bahru Tengah, Johor. Proceedings of the 1st International

    Conference on Sustainable Materials. Park Royal Hotel, Penang. pp. 89–91.

    Ramayah, T., Lee, J. W. C., & In, J. B. C. (2011). Network Collaboration and

    Performance in the Tourism Sector. Service Business, 5(4), pp. 411–428.

    Reinartz, W.J., Haenlein, M. and Henseler, J. (2009). An Empirical Comparison of

    the Efficacy of Covariance-Based and Variance-Based SEM. International

    Journal of Market Research, 26 (4), pp. 332–344.

    Ringle, C. M., Sarstedt, M., & Straub, D. W. (2012). A Critical Look at the Use of

    PLS-SEM in MIS Quarterly. MIS Quarterly, 36(1), pp. 1–8.

  • 105

    Ringle, Wende, & Will. (2005). SmartPLS 2.0 (M3) Beta. Hamburg. Retrieved from

    http://www.smartpls.de/.

    Sambasivan, M., & Soon, Y. W. (2007). Causes and Effects of Delays in Malaysian

    Construction Industry. International Journal of project management, 25(5),

    pp. 517-526.

    Sekaran, U., & Bougie, R. (2010). Research Methods for Business: A Skill Building

    Approach. London: Wiley.

    Senaratne, S., & Wijesiri, D. (2008). Lean Construction as a Strategic Option :

    Testing its Suitability and Acceptability in Sri Lanka. Lean Construction

    Journal, 4(1), pp. 34–48.

    Seror, N., Hareli, S., & Portnov, B. (2014). Evaluating the Effect of Vehicle

    Impoundment Policy on Illegal Construction and Demolition Waste Dumping:

    Israel as a Case Study. Waste Management, 34(8), pp. 1436–45.

    Serpell, A., & Alarcon, L. (1998). Construction Process Improvement Methodology

    for Construction Projects. International Journal of Project Management,

    16(4), pp. 215–221.

    Serpell, A., Venturi, A., & Contreras, J. (1995). Characterization of Waste in

    Building Construction Projects. Third workshop on lean construction.

    Albuquerque. pp. 67–78.

    Seow, T. W and Mohamad, A. H (2007). Pengurusan Sisa Pembinaan di Tapak Bina.

    Proceedings of the Universiti Perguruan Sultan Idris, Tanjong Malim, Perak.

    Seuring, S., & Muller, M. (2008). From a Literature Review to a Conceptual

    Framework for Sustainable Supply Chain Management. Journal of Cleaner

    Production journal,16, pp. 1699–1710.

    Sharifah, & Zainal. (2014). Longgokan Sisa Bahan Binaan Makin Membukit. Sinar

    Harian. p. 20.

    Silva, N. De, & Vithana, S. B. K. H. (2008). Use of PC Elements for Waste

    Minimization in the Sri Lankan Construction Industry. Structural Survey,

    26(3), pp. 188–198.

    Sim, L.G. (2005). Mapping Approach for Examining Waste Management within

    Construction Sites. Universiti Teknologi Malaysia: Master’s Thesis.

  • 106

    Srivastava, S.K. (2007). Green Supply-Chain Management: A State-of the-Art

    Literature Review. International Journal of Management Reviews, 9(1), pp.

    53-80.

    Suangsuwan, J., Wiratchai, N., & Wongwanich, S. A. (2005). Development of

    Indicators, and the Cause and Effect Model of Collaboration of Primary

    School Teacher in Ayutthaya province, Thailand. Proceeding of the

    Australian Association for Research in Education Annual Conference,

    Thailand.

    Taha, M. P. M. (2012). Waste Minimization : Be Part of The Solution. Proceeding of

    the National Conference on Hydrology and Environment. Johor.

    Tam, V. W. Y., Shen, L. Y., Fung, I. W. H., & Wang, J. Y. (2007). Controlling

    Construction Waste by Implementing Governmental Ordinances in Hong

    Kong. Construction Innovation, 7(2), pp. 149–166.

    Tan, C. N. L., & Ramayah, T. (2014). The Role of Motivators in Improving

    Knowledge-Sharing Among Academics. Information Research, 19(1), pp. 1-

    19.

    Ullman, J. B. (2001). Structural Equation Modeling. In B. G. Tabachni