    POLAND - the largest road construction site

    Listopad 2009

    Expressway S7 Biaobrzegi - Jedlisk

  • 8/14/2019 Strategic Highway Expansion - Poland

    2/10

    2

    The largest road construction program in Europe:

    over1000 km of motorways

    over1500 km of expressways

    to be built by 2015.

    A1 Construction of Sonica Bek section

    S8 K construction of Konotopa Powzkowska section

  • 8/14/2019 Strategic Highway Expansion - Poland

    3/10

    3

    VISION

    To build a system of high

    capacity roads providing

    the fastest and safest

    connection of all centers ofeconomic activity in Poland

    and links with the European

    transport system.

    In total over 2000 km of motorways

    and 2500 km of expressways

  • 8/14/2019 Strategic Highway Expansion - Poland

    4/10

    4

    CURRENT STATUS

    Completed1319 km

    of high capacity

    roads,

    of which 817 km of

    motorwaysand482 km of

    expressways.

    Completed

    Construction ongoing

    Completed by 2009 end

    Tender ongoing

    PPP commecrcial;y closed

    Tender to be anounced in 2009

    Preparatory works

  • 8/14/2019 Strategic Highway Expansion - Poland

    5/10

    5

    BUDGET (USD billion, without concessions)

    FINANCING MECHANISMS

    Debt financing through the National Road Fund

    Selected toll motorway projects proposed

    for DBFO concession:

    A1 north works ongoingA1 central commercially closed

    A2 west works ongoing

    A2 east new proposed project

    Droga ekspresowa S69 Laliki - Zwardo

    Obwodnica Puaw w cigu drogi ekspresowej S12

    2009 2010 2011 2012 total

    7,8 10,2 14,5 8,7 41,2

  • 8/14/2019 Strategic Highway Expansion - Poland

    6/10

    6

    National Road Fund

    Special account administered by the Bank of National Economy (BGK)

    Annual plan of expenditures and debt agreed with the Government

    BGK takes credits from international financial institutions (chiefly European

    Investment Bank)

    BGK issues tradeable bonds on national market

    BGK debt is covered by the state budget guarantees

    A1/A4 Budowa wza Sonica Budowa drogi ekspresowej S69 Szare - Laliki

  • 8/14/2019 Strategic Highway Expansion - Poland

    7/10

    7

    INFRASTRUCTURE BONDS ISSUED BY BGK

    In 2009 BGK will issue 2.8 USD billion in unfrastructure bonds (2 USD

    billion already issued, next issue planned for first decade of December)

    Tenure - 3, 5 and 9 year bonds

    Yield state treasure bonds + margin

    Maximum security state treasury

    guarantees backed by revenues

    of the National Road Fund

    In 2010 BGK is expected to issue

    another 2.9 USD billion in

    infrastructure bonds

    Autostrada A1 Rusocin Nowe Marzy

  • 8/14/2019 Strategic Highway Expansion - Poland

    8/10

    8

    CASE A2 WARSAW - EASTERN BORDERFIRST SEGMENT WARSAW LUKOWISKO (88 KM)

    DBFO CONCESSION FOR

    CONSTRUCTION AND OPERATION OF TOLL MOTORWAY

    A2 motorway in Polish territory is a part of

    E30 corridor linking Ireland with Russia.

    It is commonly referred to as the most

    important European road corridor

    running through Ireland, UK,

    The Netherlands, Germany, Poland

    Belarus and Russia.

    The total length is 5800 km.

  • 8/14/2019 Strategic Highway Expansion - Poland

    9/10

    9

    A2 TOLL MOTORWAY (WEST TO EAST)

    SWIECKO (WESTERN BORDER)

    NOWY TOMYSL:

    under construction, availability based concession

    NOWY TOMYSL KONIN:

    under operation, real toll concession

    KONIN LODZ:

    under operation, construction financed

    by the National Road Fund/EU grants

    LODZ WARSZAWA: DBFO concession failed, under constructionconstruction financed by the National Road Fund

    WARSZAWA EASTERN BORDERFirst subsegment (Minsk Mazowiecki Bypass 21 km) under construction

    Proposed DBFO concession for Warsaw Lukowisko (construction and

    operation including Minsk Mazowiecki bypass operation only)

    http://pl.wikipedia.org/w/index.php?title=Plik:NowaMapaA2.svg&filetimestamp=20090904203012
  • 8/14/2019 Strategic Highway Expansion - Poland

    10/10

    10

    A2 Warszawa ukowisko

    total length for construction 88 km

    total length for operation 108 km

    completely new alignment, full length dual carriagewa two-lane motorway

    toll plazas, service areas, interchanges

    real toll closed system for light vehicles, electronic toll for heavy vehicles

    concession tenure: 35 years (2050)

    cost estimate: 2.5 USD billion

    invitation to tender: mid 2010