Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice...

30
Stormwater Retrofits at Nolensville High School PRESENTED BY STEVE CASEY, P.E., CPESC RESILIENT WATERSHEDS SHORT COURSE NASHVILLE, TN OCTOBER 11, 2018

Transcript of Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice...

Page 1: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Stormwater Retrofits at Nolensville

High School

PRESENTED BY STEVE CASEY, P.E., CPESC

RESILIENT WATERSHEDS SHORT COURSE

NASHVILLE, TN

OCTOBER 11, 2018

Page 2: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Nolensville High School

2

Source: https://www.bing.com/maps/

Page 3: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Introduction

►High school site selection

►Specific practice site selection

►Goals for project

►Details of project including some lessons learned

3

Page 4: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

High School Site Selection

▪ CRC approached CEC with site

▪ Mill Creek watershed

o Increase baseflow

o Divert from detention basin

▪ Rapidly developing

o Residential development around school

▪ Education opportunity

o Residential development around school connected via greenways

4

Detention Basin at Nolensville High School

Page 5: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Plan Development

► Kevin Fortney with Williamson County Schools – great partner

▪ CEC was provided school designer’s plans in .dwg format

▪ No field survey performed

► Vena Jones with Tennessee Department of Environment and

Conservation (TDEC) reviewed plans

▪ She knew history of site

▪ Riparian mitigation area – RSC in particular viewed as benefit

► Project was viewed as maintenance

▪ Relatively small footprint retrofit project

► Project would lessen burden on existing stormwater

management infrastructure

▪ Less focus on “design storm” and more on “maximizing benefit”

5

Page 6: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Stormwater Retrofit Practice Layout

6

Bioretention Area 1

Bioretention Area 2

RSC

Page 7: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Bioretention Areas

7

Bioretention Area 1

Bioretention Area 2

Page 8: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Regenerative Stormwater Conveyance

8

RSC

Page 9: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Specific Practice site selection

▪ Maximize diversion

from detention basin

▪ Good accessibility for

construction

▪ Visibility for education

▪ Intercept impervious

surface runoff (triple

catch basin is a good

sign )

9

Page 10: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Specific Practice Site Selection

RIPARIAN MITIGATION

AREA

10

TRIPLE CATCH BASIN

MILL CREEK BEYOND

RIPARIAN MITIGATION AREA

Page 11: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Specific Practice Site Selection

REGENERATIVE

STORMWATER

CONVEYANCE (RSC)

11

RIPARIAN MITIGATION

AREA

FLUME TO ALLOW FLOW

THROUGH SIDEWALK ADJACENT

TO TRIPLE CATCH BASIN

Page 12: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Regenerative Stormwater Conveyance

► Four cell RSC was constructed rather than just two cells

based upon field conditions being different than what was

represented in the original school design plans –

importance of field survey

► Geotextile was not placed under the infiltration areas

► Flow limited to what could pass through flume. Excess

would flow into triple catch basin.

12

Page 13: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Specific Practice Site Selection – Bioretention 1

13

BEFORE

AFTER

Page 14: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Specific Practice Site Selection – Bioretention 2

14

Page 15: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Bioretention Areas

► Placed where grass had been but with questionable perviousness

15

Page 16: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Bioretention Areas

17

Page 17: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Timeline

18

2/13 Proposal

2/14 Notice to Proceed

3/8 – Concept Plan

4/6 – Meeting with Kevin Fortney, WCS

4/16 – 65% Plans

5/30 –Meeting to discuss 65% Plans

6/14 – Voted on by WCS Board

7/23 – Sent bids to Cumberland River Compact (CRC)

8/1 – Start Construction

8/10 – School Starts – goal was to be finished before school started

8/21 – Observed RSC Blowout

8/29 – Repaired Blowout

9/19 – 2 Additional Cells were added to RSC

10/9 – Planting Plan Delivered to CRC

Page 18: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Stormwater Practice Pontifications

► Stormwater retrofit projects are usually bound by more constraints than new projects

► Existing stormwater management infrastructure deemed sufficient due to recent design/construction of school (within last 4-5 years)

▪ However, these retrofits effectively increased the ability of the existing infrastructure to accommodate larger and more intense storms

► Opportunity to maximize available footprints in practice locations to promote infiltration and diversion of water from existing detention basin that had been partly excavated out of rock

► Engineering budget was shifted to spend more on field time than office time compared to original scope

19

Page 19: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

More stormwater practice thoughts…

► Using principles of bioretention and RSC design, rather than strict adherence to design criteria

▪ Checking 100 year, 24-hour design storm flow through RSC, in particular

▪ Redundancy: Bioretention Area 1 in watershed of RSC thereby reducing burden on RSC (and triple catch basin)

▪ Use same engineered media (sand, compost, fine soil) in bioretention areas as in RSC for simplicity but add hardwood mulch around RSC plantings before placing river gravel mulch

▪ Geotextile only on sides of excavations

▪ Allowing approximately 6” of pooling within bioretention areas

▪ Pooling as deep as 18” in RSC based on field conditions

20

Page 20: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Now for some Math!

► Next few slides provide some hydrology & hydraulics

information that was calculated in support of the design

► Watershed delineations were based upon the original

school design plans and observations in the field

21

Page 21: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Bioretention in Parking Island

22

► Drainage Area = 1.49 acres

► CN = 95

► Tc = 6 minutes

Storm

Event

Peak

Flow (cfs)

Volume

(ac-ft)

2-yr 7.1 0.353

10-yr 10.1 0.513

100-yr 14.9 0.772

Page 22: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Bioretention near Tennis Courts

23

► Drainage Area = 1.47 acres

► CN = 87

► Tc = 6 minutes

Storm

Event

Peak

Flow (cfs)

Volume

(ac-ft)

2-yr 5.6 0.259

10-yr 8.7 0.409

100-yr 13.6 0.662

Page 23: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Regenerative Stormwater Conveyance (RSC)

24

► Drainage Area = 1.70 acres

► CN = 95

► Tc = 6 minutes

Storm

Event

Peak

Flow (cfs)

Volume

(ac-ft)

2-yr 8.1 0.403

10-yr 11.5 0.585

100-yr 17.0 0.880

Page 24: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Flume Through Sidewalk

25

► Max Flow = 2.9 cfs

Page 25: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Flow over rock weir

26

► Max Flow = 14 cfs

Page 26: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Planting Plan

►Clumping plants

►Drought tolerance

►Withstand flowing

water energy in RSC

►No plantings in

middle of final RSC

cell due to depth, but

on edges

27

Coreopsis sp.

Hydrangea sp.

Echinacea sp.

Page 27: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Planting Plan

28

Page 28: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Cost Information

► Construction cost not including planting

▪ Total construction cost ~$75,000

▪ Material costs:

o Raingarden Soil Mix: $36.50/CY ($65/load delivery fee)

o Class A & B Rip Rap: $23.50 per ton

o Dump Truck fee to haul away excavated material:

$100.00/hour plus $75.00 dump fee per load

This equated to about $275.00 per truck load

29

Page 29: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Key points to keep in mind for retrofit projects

30

► Field survey is recommended

► Look for triple catch basins!

► Try to include redundancy in your design:

Bioretention Area 1 in watershed of RSC and triple catch

basin conveys flow that does not pass through flume

► Create hydraulic jump (drop) at entrances to practices if

possible; otherwise, sediment will likely accumulate

upstream

► Plan for maintenance

► Safety: a railing is planned for sidewalk adjacent to the RSC

► Similar practices could save cost of traditional

infrastructure on new projects

Page 30: Stormwater Retrofits at Nolensville High School · 2018-11-02  · Stormwater Practice Pontifications Stormwater retrofit projects are usually bound by more constraints than new projects

Closing Remarks

► Special thanks to the Cumberland River Compact with

whom I have had the pleasure of working on cool projects!

► Kevin Fortney, Williamson County Schools Facilities and

Construction Director

► Vena Jones, TDEC

► Contractor: Viking Products, Mt. Juliet, TN

► Justin Bryan, P.E., CEC Project Manager for this project

► Jay Cameli, RLA, CEC Landscape Architect

Civil & Environmental Consultants, Inc.

325 Seaboard Lane, Suite 170

Franklin, TN 37067

615-333-7797

[email protected]