Sterling Blvd Water Main Phase 2 IFB# 2015-022-WTR.00016 Pre-Bid Conference May 12, 2015.
-
Upload
derick-short -
Category
Documents
-
view
213 -
download
0
Transcript of Sterling Blvd Water Main Phase 2 IFB# 2015-022-WTR.00016 Pre-Bid Conference May 12, 2015.
1. Location2. Summary of Work / Project Highlights3. Special Project Conditions4. Bid Phase – Procedural Highlights5. Procurement Schedule6. Q&A
Agenda
PHASE 2 LOCATION
PHASE 1 (EXISTING)
PHASE 1 (EXISTING)
PHASE 2 WATER MAIN
PHASE 2 WATER MAIN
NEW PHASE 2 PRV VAULT
NEW PHASE 2 PRV VAULT
NEW PHASE 2 PRV VAULT
NEW PHASE 2 PRV VAULT
W. HOLLY AVE
W. CHURCH RD
N. STE
RLIN
G BLV
D
S. STERLING
BLVD
GLEN
N DR
DAVIS
DR
EXISTING PHASE 2 PRV VAULT (TO BE DEMO’D)EXISTING PHASE 2 PRV VAULT (TO BE DEMO’D)
PROJECT HIGHLIGHTS: • 7,500 LF of 24” Water Main• 2 PRV Vaults• Multiple Road, Trail, & Entrance Crossings (4 Trenchless)• 400 Day Contract Time to Substantial Completion (30 Days to Final Completion)• Phase 1 complete 2007
PHASE 2 WATER MAIN
PHASE 2 WATER MAIN
PHASE 1PHASE 1
GLENN
DR
SHEPARD DR
S. STERLING
BLVD
W. M
APLE
AVE
JACK & BORE LOCATION
JACK & BORE LOCATION
NEW 12” PRV VAULTNEW 12”
PRV VAULT
JACK & BORE LOCATIONS
JACK & BORE LOCATIONS
DAVIS
DR
W & OD TRAIL
W. GREENTHORN AVEJACK & BORE
LOCATIONJACK & BORE
LOCATION
EXISTING PRV VAULT (TO BE DEMO’D)
EXISTING PRV VAULT (TO BE DEMO’D)
STERLING MIDDLE SCHOOL
GOLF & SWIM CLUB
GOLF & SWIM CLUB
LOUDOUN FOOTBALL
CHASE HERITAGE PROP.
W & OD TRAIL
STERLING ONE INDUSTRIAL
SPECIAL PROJECT CONDITIONS
PHASE 1PHASE 1
GLENN
DR
DAVIS DR
SHEPARD DR
S. STERLING
BLVD
W. M
APLE
AVE
W. GREENTHORN AVE
LOUDOUN LITTLE LEAGUE
PHASE 2 WATER MAIN
PHASE 2 WATER MAIN
Sterling Middle School (LCSB)
• Work shall be completed between June 15, 2016 – August 30, 2016
• Temporary sidewalks and signs• Electronic sign relocation• Employee certifications
Sterling Golf & Swim Club
• Demo sign footers & salvage signs• Install new foundations & reinstall upon completion• Maintain 24/7 Access
Lower Loudoun Little League
• Work shall be completed between November 1, 2015 – February 28, 2016 and/or July 15, 2016 – August 30, 2016
• Restoration shall include sod• Potential staging area
Lower Loudoun Football League
• Work shall be completed between November 15, 2015 – August 30, 2016• Replace existing bench• Potential staging area
Chase Heritage Property
• Maintain one entrance at all times• All work shall be complete at single entrance before relocating to second entrance
Washington & Old Dominion Trail
• Coordination with Dominion Virginia Power (DVP) & VA Regional Park Authority
• Test pit buried electric utility locations within 60 days of NTP and notify DVP
• Road lane closures on Sterling Blvd
Sterling One Industrial Property
• Jobsite hours 3:00 PM – 11:00 PM• Access restrictions• Site open to public during non-working hours• Temporary parking lot for tenants• Dumpster pad construction• Maintain tractor trailer access
Bid Phase – Procedural Highlights
00200 Instructions to Bidders• Article 3 – Qualifications• Article 4 – Bidder Site Inspections (Paragraph 4.05)• Article 7 – Interpretations and Addenda (7 days prior to bid opening)• Article 8 – Bid Security (>$100,000 » 5%)• Article 13 – Basis of Bid; Comparison of Bids (Lump Sum)• Article 14 – Submittal of Bid (Procedures)
Procurement Schedule
Date Milestone
May 1, 2015 Bid Advertisement
May 12, 2015 Pre-Bid Conference
June 4, 2015 Bid Opening at 2:00 PM – LW ASF Building
June 24, 2015 Loudoun Water CIP Committee Meeting
July 9, 2015 Loudoun Water Board Meeting