STEINER HALL RENOVATION MAY 2009-AUGUST 2009 The Steiner Hall Renovation is proudly brought to you by: UWSP Residential Living Staff & Students, UWSP Facilities Services, University of Wisconsin System, Wisconsin Department of Administration, Wisconsin Department of State Facilities, Somerville Architects Engineers & Construction Services, and Ellis Stone Construction! This project supports Residential Living’s environmentally friendly efforts and complies with DSF Sustainability Standards, Act 141 and Executive Order 145. Steiner Hall Comprises a total of 53,917 GSF (Gross Square Feet) and 270 total beds A Sustainable Renovation!

description

Steiner Hall Renovation May 2009-August 2009. A Sustainable Renovation!. Steiner Hall Comprises a total of 53,917 GSF (Gross Square Feet) and 270 total beds. The Steiner Hall Renovation is proudly brought to you by: UWSP Residential Living Staff & Students, UWSP Facilities Services, - PowerPoint PPT Presentation

Transcript of Steiner Hall Renovation May 2009-August 2009

Page 1: Steiner Hall Renovation May 2009-August 2009

STEINER HALL RENOVATIONMAY 2009-AUGUST 2009

The Steiner Hall Renovation is proudly brought to you by: UWSP Residential Living Staff & Students, UWSP Facilities Services,

University of Wisconsin System, Wisconsin Department of Administration, Wisconsin Department of State Facilities, Somerville Architects Engineers & Construction Services,

and Ellis Stone Construction!

This project supports Residential Living’s environmentally friendly efforts and complies with DSF Sustainability Standards, Act 141 and Executive Order 145.

Steiner HallComprises a total of 53,917 GSF (Gross Square Feet)

and 270 total beds

A Sustainable Renovation!

Page 2: Steiner Hall Renovation May 2009-August 2009

PROJECT SCOPE

Patio & Ramp Reconstruction Elevator Installation Accessibility Upgrades

Accessible Bathrooms each floor Door & Hardware throughout Accessible Resident Rooms

ADA Compliant Hall Director Apartment & Patio Lighting Upgrades Window Replacement Individual Resident Room Temperature Control Heating, Ventilation & Air Conditioning Casework Fire Sprinkler System throughout Plastering of Masonry Blocks Furniture & Flooring Upgrades Lobby Reconfiguration Generator Installation

Page 3: Steiner Hall Renovation May 2009-August 2009

PATIO & RAMP RECONSTRUCTIONThe exterior ramp and patio were demolished and rebuilt according to the ADA (Americans with Disabilities Act) requirements making them accessible to all. Along with the ADA improvements the new design of the patio and ramp also enhanced exterior programming and lounging capabilities for residents and provided additional protected bike storage next to the building.

The stone used on the construction of the new patio is a sustainable & regional material. Short distance transits are environmentally friendly as fewer gas emissions are produced during shorter travels.

Page 4: Steiner Hall Renovation May 2009-August 2009

ELEVATORThe component of making Steiner hall accessible to all was primarily achieved through the addition of a 5-stop

elevator. The elevator was installed in the previous location of the mailboxes. All will enjoy the ease of move-in and move-out day with the use of the new 4500 lb, 28 person capacity elevator!

Elevator install in progress…

Operational as of Friday, August 20, 2009!

Page 5: Steiner Hall Renovation May 2009-August 2009

ACCESSIBILTY UPGRADESIn addition to the elevator and exterior ramp, the accessibility component of the project was further enhanced by the remodel of the bathrooms. The bathtubs in the private baths were removed and the entire private bath was reconfigured to accommodate a new roll-in shower with accessible grab bars making the bathrooms fully ADA compliant. The removal of the male and female gender private restrooms in the lower level were reconstructed into one Unisex restroom. All bathrooms now accommodate wheelchair accessibility!

Due to maintenance concerns, the resident room doors and others throughout the building were replaced with new. New lever style hardware was installed making the operation of the door more accessible and user friendly to those with limited mobility.

Accessible Bathrooms located on every floor. New Doors & Accessible Hardware

installed throughout the building.

Page 6: Steiner Hall Renovation May 2009-August 2009

Did you know…EVERY UWSP resident room is environmentally friendly from its floor to ceiling! Paint: The ceilings and walls are painted with a water based (latex), Low VOC (Volatile Organic Chemical) paint, which means they emit minimal to no airborne contaminants as according to the environmental standards.

Floorcovering: The carpet tile in each room contains a 100% recycled content backing. The product is certified as Platinum/EPP (SCAS Standard) and California Platinum (California Gold Standard) by SCS.

Furniture: Dressers and desks are manufactured from sustainable forests with Low VOC stains and finishes and GreenGuard Indoor Air Quality certified

laminate tops.

Chairs: Desk chairs

are manufactured in Green Bay Wisconsin, allowing for a short freight distances and fewer gas emissions. The chairs also contain recycled content and are 100% recyclable including the fabric!

Mattresses: Are manufactured in Watertown Wisconsin and are also100% recyclable! Once recycled these mattresses are made into secondary products such as carpet padding.

ACCESSIBILTY UPGRADESMaking Steiner hall accessible to all included the addition of 11 double occupancy ADA (Americans with Disabilities Act) compliant resident rooms. Clear-open floor space of each lounge room was increased to allow for a full 5’-0” turning radius of a wheelchair along with other accessible considerations such as dual-height peep holes in the door, availability of dual height hang bars upon request and outlets that can accommodate bed-shakers as needed.

Page 7: Steiner Hall Renovation May 2009-August 2009

HALL DIRECTOR APARTMENT & PATIO

As with the front patio and ramp, the stone used on the construction of the new patio is a sustainable & regional material. All wall, floor and laminate finishes utilized in the apartment are environmentally friendly!

Each residence hall contains an apartment for the Residence Hall Director. The Steiner Hall Director apartment was reconfigured and reconstructed to fully comply with the Americans with Disabilities Act. This is the second apartment on campus that can fully accommodate a wheel-chair bound Director and/or his or her family member. A secondary patio entrance was also added to the apartment to provide privacy and help aid in the

necessary lifestyle balance of work & personal life.

Page 8: Steiner Hall Renovation May 2009-August 2009

LIGHTING UPGRADESThe need for lighting upgrades were prompted by resident requests which proved lighting was inadequate within the resident rooms along with ongoing and more frequent and costly maintenance concerns of the various aging fixtures throughout the building. Each resident room received new wall mount fixtures over mirrors and a third fixture was added on the ceiling for optimum lighting versatility and illumination.

WINDOW REPLACEMENTThe previous single paned windows throughout the building were installed in 1967 during the original building construction. Due to their lack of energy efficiency and added maintenance issues over the years the window replacement process became a necessary element of the renovation.

All fixtures utilize energy star efficient fluorescent lamps! Resident room ceiling fixtures have dual switching and the common area fixtures are on occupancy sensors. The mechanics of these fixtures assist in maximum energy efficiency by only being on when needed in the common areas and allowing residents to determine the amount of illumination within their resident room as necessary.

The new windows are double pane with low emissivity providing a more energy efficient window! Did you know…all resident room draperies were replaced with a new recyclable room darkening fabric and fabricated by our own UWSP Residential Living Upholstery staff!

Page 9: Steiner Hall Renovation May 2009-August 2009

INDIVIDUAL TEMPERATURE CONTROL A repeated concern by residents in the annual resident room satisfaction surveys is the lack of individual room temperature control. Therefore, the replacement of the current steam radiant heat with new individual room thermostat control, four pipe heating/cooling system that incorporates hot water and future air conditioning was necessary to include in the renovation.

CASEWORKMaintenance accessible custom laminate casework with a solid surface acrylic sill was added to cover the HVAC pipes in each of the resident rooms and various locations throughout the building. The custom casework is not only a necessary protective covering, but it also supports Residential Living’s efforts to provide a more residential atmosphere throughout the building.

The Wilsonart laminate used on the casework has been specifically selected for its functionality, durability, aesthetics and environmental certification. The laminate is GREENGUARD Indoor Air Quality certified which means it is recognized as a healthy indoor air quality product. Because we spend at least 90% on average of our daily lives indoors the specification and use of products that promote and support a healthy living environment is vital to our well being. Did you know…your desks and dresser tops are also GreenGuard Indoor Air Quality certified!

Room temperature was previously controlled by a single “thermostat” room which regulated the room temperature for an entire tower of rooms. As residents in non-thermostat rooms opened their windows, the thermostat room would generate more and more heat to balance the temperature throughout the tower…causing a cyclical waste of steam energy and heat. Independent control will eliminate this waste of energy!

Page 10: Steiner Hall Renovation May 2009-August 2009

FIRE SPRINKLER SYSTEMFor resident safety, a fire sprinkler system was installed in each resident room and throughout the building.

PLASTERING OFMASONRY WALLS

In support of Residential Living’s desire to provide a more residential appeal to the resident rooms and resident corridors, all masonry block walls received thin coat plaster with a skip trowel texture and new paint.

All paint is Low to No- VOC (Volatile Organic Chemical) formula which makes for a more air-friendly room and reduces our impact on carbon foot printing!

Before

After

Page 11: Steiner Hall Renovation May 2009-August 2009

LOBBY RECONFIGURATIONWith the installation of the elevator, the lobby, front desk and mailboxes experienced relocation, reconfiguration and new construction. The front desk was reconstructed with a new wood paneled contoured front and ADA accessible height countertop. A wall was also removed to add spaciousness and day lighting throughout the front entry and lobby seating area. The lobby received all new finishes and furnishings to welcome and compliment the new design of the hall!

From the carpet, vinyl wallcovering and furnishings all elements of the lobby are environmentally friendly! All products are GreenGuard Indoor Air Quality certified with recycled content.

Page 12: Steiner Hall Renovation May 2009-August 2009

FURNITURE & FLOOR COVERING UPGRADESFrom the 4th floor resident rooms to the lower level T-Center, all floorcoverings were replaced throughout the building. New and refurbished furnishings were installed and re-installed throughout the common areas of Steiner Hall in support of our environmental Reduce, Reuse, Recycle efforts!

All floorcoverings contain recycled content, low VOC adhesives and are environmentally friendly. Did you know…UWSP Residential Living has recycled OVER 230,000 lbs of carpet since 2004!

Page 13: Steiner Hall Renovation May 2009-August 2009

GENERATORA Diesel Engine 100kw, 400 amp main breaker; 120/208 Voltage generator was installed that will power all emergency needs for the South DeBot quad with a “single elevator select” option.

A diesel powered generator typically lasts longer than their gasoline counterparts and are more fuel efficient…and quieter!

.

Page 14: Steiner Hall Renovation May 2009-August 2009

Wood........................................................8,348 lbsConcrete...............................................371,064 lbsMetal & Steel.........................................51,910 lbsWindow Frames…………………………………….8,000 lbsWindow Glass……………………………………….8,712 lbsAcoustical Ceiling Tile……………………………5,150 lbsCarpet…………………………………………………23,725 lbsDrapery……………………………………………………567 lbsToilets & Sinks………………………………………….500 lbsCardboard…………………………………………….7,200 lbs

DID YOU KNOW…WE RECYCLED AND/OR REUSED

OVER 85% OF STEINER HALL MATERIALS!!!

Total Recycled Reused Materials over 240 Tons!

In our dedicated efforts to minimize our impact on the environment,we recycled and/or reused over 85% of the materials that were removed from

Steiner hall during the renovation process!

Page 15: Steiner Hall Renovation May 2009-August 2009

WHAT IT TAKES TOGET THE JOB DONE…

Page 16: Steiner Hall Renovation May 2009-August 2009

CIRCLE DRIVE PREPARED FOR STEINER HALL DEMOLITION

Page 17: Steiner Hall Renovation May 2009-August 2009

CIRCLE DRIVE 6-17-09

Page 18: Steiner Hall Renovation May 2009-August 2009

FRONT PATIO AND RAMP DEMOLITION

Page 19: Steiner Hall Renovation May 2009-August 2009

RESIDENT ROOM DURING DEMOLITION

Page 20: Steiner Hall Renovation May 2009-August 2009

VESTIBULE DEMOLITION

Page 21: Steiner Hall Renovation May 2009-August 2009

HVAC & FIRE SUPPRESSION INSTALLATION IN RESIDENT ROOMS

Page 22: Steiner Hall Renovation May 2009-August 2009

LOBBY DEMOLITION

Page 23: Steiner Hall Renovation May 2009-August 2009

ELEVATOR CUT IN AND FRONT DESK DEMOLITION

Page 24: Steiner Hall Renovation May 2009-August 2009

FRONT DESK DEMOLITION

Page 25: Steiner Hall Renovation May 2009-August 2009

STUDY LOUNGE DEMOLITION & ELEVATOR WALL CONSTRUCTION

Page 26: Steiner Hall Renovation May 2009-August 2009

STUDY LOUNGE DEMOLITION

Page 27: Steiner Hall Renovation May 2009-August 2009

LOBBY – TEMPORARY STAGING FOR NEW WINDOWS

Page 28: Steiner Hall Renovation May 2009-August 2009

LOWER LEVEL STUDY LOUNGE 6-17-09

Page 29: Steiner Hall Renovation May 2009-August 2009

LOWER LEVEL ACTIVITY AREA 6-17-09

Page 30: Steiner Hall Renovation May 2009-August 2009

LOWER LEVEL ACTIVITY AREA 6-8-09

Page 31: Steiner Hall Renovation May 2009-August 2009

LOBBY DEMOLITION

Page 32: Steiner Hall Renovation May 2009-August 2009

STUDY LOUNGE ELEVATOR TRENCH

Page 33: Steiner Hall Renovation May 2009-August 2009

RESIDENT FLOOR BATHROOM DEMOLITION

Page 34: Steiner Hall Renovation May 2009-August 2009

HALL DIRECTOR APARTMENT DEMOLITION

Page 35: Steiner Hall Renovation May 2009-August 2009

FRONT DESK DEMOLITION

Page 36: Steiner Hall Renovation May 2009-August 2009

LOBBY CARPET INSTALL

Page 37: Steiner Hall Renovation May 2009-August 2009

CORRIDOR CARPET INSTALL 8-17-09

Page 38: Steiner Hall Renovation May 2009-August 2009

RESIDENT ROOM CASEWORK INSTALL

Page 39: Steiner Hall Renovation May 2009-August 2009

RESIDENT ROOM HEATING UNIT INSTALLATION

Page 40: Steiner Hall Renovation May 2009-August 2009

ROOM CARPET INSTALLATION 7-13-09

Page 41: Steiner Hall Renovation May 2009-August 2009

FRONT DESK INSTALLATION DETAILS

Page 42: Steiner Hall Renovation May 2009-August 2009

UWSP STUDENT GROUNDS CREW INSTALL PLANTINGS AT PATIO

Page 43: Steiner Hall Renovation May 2009-August 2009

ACTIVITY AREA CARPET INSTALL

Page 44: Steiner Hall Renovation May 2009-August 2009

RESIDENTIAL LIVING’S TRADES STAFF REINSTALL LAUNDRY ROOM APPLIANCES

Page 45: Steiner Hall Renovation May 2009-August 2009

RESIDENTIAL LIVING’S STUDENT PROJECT CREW RESET FURNITURE THROUGHOUT HALL

Page 46: Steiner Hall Renovation May 2009-August 2009

COMPLETED STANDARD RESIDENT ROOM

Page 47: Steiner Hall Renovation May 2009-August 2009

Many thanks to all who participated in the project!If you have any questions or concerns regarding the project,

please contact Residential Living Building Services at 715-346-2397.

Please continue to join and support UWSP Residential Living’s efforts of living an

environmentally friendly lifestyle!

Reduce, Reuse, Recycle!

Presentation By:Cindy Von Gnechten, Residential Living Facilities Designer