Status report as on 23.05.2013

6
STATUS REPORT OF MY HOME ABHRA Tower-”A” As On 23.05.13 1.First Floor Slab :Completed 2.Second Floor Slab: 1 & 2 Flats Shuttering Work Completed Bar Bending work In Progress

Transcript of Status report as on 23.05.2013

Page 1: Status report as on 23.05.2013

STATUS REPORT OF MY HOME ABHRA Tower-”A” As On 23.05.13

1.First Floor Slab :Completed2.Second Floor Slab: 1 & 2 Flats Shuttering Work Completed Bar Bending work In Progress

Page 2: Status report as on 23.05.2013

STATUS REPORT OF MY HOME ABHRA Tower-”B” As On 23.05.13

1.First Floor Slab : Completed2.Second Floor Slab :Flats No 1 & 2 Completed

Page 3: Status report as on 23.05.2013

STATUS REPORT OF MY HOME ABHRA Tower-”C” As On 23.05.13

1.Ground Floor Slab : Completed2.First Floor Slab : Flat No 01 Shuttering work In Progress

Page 4: Status report as on 23.05.2013

STATUS REPORT OF MY HOME ABHRA Tower-”D”As On 23.05.13

1.First Floor Slab: Completed2.Second Floor Slab : Flat No 1 & 2 flats Completed and 4th and 5th Flats shuttering

Completed,3rd flat Beam Bottom shuttering Work started

Page 5: Status report as on 23.05.2013

STATUS REPORT OF MY HOME ABHRA Tower-”E”As On 23.05.13

1.First Floor Slab :Completed2.Second Floor Slab : Flat no 1 & 2 Shuttering completed

Page 6: Status report as on 23.05.2013

STATUS REPORT OF MY HOME ABHRA “TOTAL SITE”As On 23.05.131.Total Site Ground Floor slab Completed

2.Total Site First Floor slab Except Tower :C Remain All Completed3.Total Site Second Floor Slab: Tower B & E 1 & 2 Flats Completed