Status of the Large Hadron Collider Lyndon R. Evans Scientific Policy Committee
description
Transcript of Status of the Large Hadron Collider Lyndon R. Evans Scientific Policy Committee
Status of the Large Hadron ColliderLyndon R. Evans
Scientific Policy Committee
CERN, 15 March 2004
L.R. Evans – EDMS Document No. 451875
Scientific Policy Committee
2
Cable 1
L.R. Evans – EDMS Document No. 451875
Scientific Policy Committee
3
Cable 2
L.R. Evans – EDMS Document No. 451875
Scientific Policy Committee
4
Magnets
L.R. Evans – EDMS Document No. 451875
Scientific Policy Committee
5
Dipoles
L.R. Evans – EDMS Document No. 451875
Scientific Policy Committee
6
Dipoles
L.R. Evans – EDMS Document No. 451875
Scientific Policy Committee
7
Cryodipoles
L.R. Evans – EDMS Document No. 451875
Scientific Policy Committee
8
L.R. Evans – EDMS Document No. 451875
Scientific Policy Committee
9
Quadrupoles
L.R. Evans – EDMS Document No. 451875
Scientific Policy Committee
10
MSCB
L.R. Evans – EDMS Document No. 451875
Scientific Policy Committee
11
QRL Problems
• Conflicts between main contractor and installation subcontractor
have caused many delays and finally CERN was informed of a
change of subcontractor in January. Overall delay is now 8 months.
• The contractor has produced a new planning to recover the delays
but this compresses the time for installation and testing.
• A new installation planning is being optimised to recover the
delays. This is based on installation of 3 octants simultaneously.
L.R. Evans – EDMS Document No. 451875
Scientific Policy Committee
12
Planning
• The contract for tunnel installation has not yet been signed. We
will need approval from FC to increase the volume of this contract
by about 30% (3 MCHF). Since we must sign before June, we need
approval of FC chair, with a justification in June 2004 FC.
• We are now re-planning the commissioning on this very
compressed timescale and which requires experienced CERN staff.
We are evaluating the additional resources we need and the means
to procure them.
• We remain fully committed to providing the detectors with a first
run in 2007.