Transcript of Status of EC-C assembly at Liverpool C Buttar EC PAR, Nikhef Nov 04.
Status of EC-C assembly at Liverpool
C Buttar
EC PAR, Nikhef Nov 04
Nikhef disk cylinder assembly tooling
TPPCs 4x32ch PCBs
Thermal plug
accesswindows
Cooling pipes
LMT trays
Service Handling
Disk insertion tooling
Progress with Diskcylinder tooling
• Shielding foil added to cylinder• Thermal feedthrough prepared and fitted• Cylinder and stub wings assembled onto tooling (July)• 4 disk alignment tools made by Manchester• Disk grabber-design by Nikhef-manufactured by
Sheffield/Lancaster• Disk fixations from Nikhef and Liverpool-delivered• alignment target holders designed (Nikhef) and
manufactured (Lancaster)• Disk insertion, alignment (X,Y), capture+removal
(August) alignment better than 100m• Wheels+jacks added and tooling+cylinder have been
moved in and out of the cold room (Sept)
• Alignment• disk capture DOF mechanism• Disk grabber
Cylinder inside the cold room
Moving intothe cold room
Status of tooling-Oct
• 2nd disk alignment, capture and removal has been performed with D7 populated with services– alignment checked with dummy masses– used interface to disk mini-cylinder– grounding: mini-cylinder and frame grounding– FSI spool+ ground foil handling – work with scaffolding around cylinder
• Work to be done– Thermal cycle of tooling+cylinder in the cold room– Removal and insertion of the beam to be
demonstrated– grabber needs to be improved-stronger springs
Mounting disk onto cylinderfrom mini-cylinderMounted relative to cylinder using pins
FSI spool sittingon mini-cylinder
move FSI spool back onto PPF0using PPF0 location screws
Remove FSI spool and place outsidepatch panel
Ground foils
Service status• LMTs
Testing of UK tapes at Glasgow, first 15 testedDelivery ~100/week, Taiwan to finish production 10/12
• TIsWill be tested as part of LMT-TI harness at Glasgow
• ‘String test’ LV/HVtest cableTPPCTILMTPPF0wiggly tapehybrid/module at Liverpool2 adjacent channels on pre-production TPPC testedFirst 16 TPPCs to be delivered to Liveerpool this week/next week for D9
• FibresLancaster has volunteered to take on reception testingFibres for disk testing (D1) at Liverpool, D9 delivered and tested ok, length issue
• DCS for D9 will be delivered by RB this week• Cooling pipes
Assume no cooling pipes initially and connect direct to disk as for disk testingRetro-fit cooling pipes at Liverpool/CERN when components ready and connect at STFT for testingCooling-replicate disk testing system and connect direct to the disk-or similarParts delivered and assembly underway at Liverpool
TPPC string test
String testTest cable TPPCTILMT
harnessPPF0wiggly tape hybrid
direct to hybrid String test
Cooling HEXsame design as for disktesting
Service handling
• Thermal plug delivered and fitted (Sheffield)
• PPF1 trays for LMTs ready (RAL)
• PPF1 tray holders (Sheffield) Delivered, being sent for anodising• Other parts for LMT handling in progress at (Nikhef+Lancaster)
• Temporary PPF1 for fibres Lancaster have volunteered to make this based on prototype being made at Nikhef At Liverpool we need to ensure we can connect in the cold room—looks good, measurement of fibre length indicated that fibres reach close to window in the thermal plug
Thermal plug and LMT trays+holders
Cooling connectioncaptive !Helicoflex not O-ring
LMT connection• checked connection with pcb by
measuring thermistor•use clip on light and dental mirror to check connections
• problem with some mis-alignments of guides•passed back to disk makers, they will check alignment with pcbs•can be fixed in-situ but to be avoided
Strain relief at aperture
bendy fibres?!
cable clamps (D3-D9 on cylinder)
fibre clamps (D3-D9 on cylinder)
Temporary patch panel (TPPC) and TI connections
Testing during assembly
• Ensure connections from PPF0 on disk to TPP on thermal plug are well made before moving into cold room—limited access!– LMT connections: check temperature through
LV, checks connection at PPF0– Check fibres and LMTs by sending trigger
burst using SCT DAQ(RODDAQ being used to test disk)Aim to do module by module in parallel with service laying
Schedule-ambitious!
• 10/11 Assemble service handling– awaiting final parts
• Week of 15/11+22/11 leak check and test cooling, move into cold room and test with D7– cooling being assembled – waiting for DCS cables (due this week)
• End November ready to install D9 and mount services
Issues
• Cooling and test of disk with services in cold room– cooling being set up for testing
• LMT delivery and making harnesses– delivery of D9 tapes by end this week ? – tape testing at harness preparation at Glasgow
• Problem with infininion connector at PPF0– cannot be fixed in the cylinder
• Experience !
Testing in cold room
• Based on experience with disks• Move into cold room and cable (1d)• Check cabling (1.5d)• Cooling down (1d)• Confirmation tests (5d)• Characterisation (5d)• Warm-up (with I-V) (1d)Total ~15d per disksCan we run cold overnight ?!