Status - Indian Electrical Industry April to March...
Transcript of Status - Indian Electrical Industry April to March...
Status - Indian Electrical Industry
April to March
2016-2017
Source: CEA & MNRE
112% achievement with Thermal power achieving 127% addition on planned Generation
60% achievement with power achieving 104% addition on planned Generation
13th Plan Capacity Addition ‘NIL’ addition of Thermal Power as 50,025 MW
projects are already under construction Gas–4340MW; Hydro-15300MW, Nuclear-2800MW
Solar – 81,237 MW
Wind –29034 MW
Other RES
5,055 MW
Source: CEA
Transmission Addition in ‘CKM’ during 12th Plan Up to March 2017
Sub-station Addition in MVA/ MW during 12th Plan Up to March 2017
400 KV Transmission & Sub-Station completion is over achieved in 12th Plan; 765kV also achieved >95%.
HVDC & 765 KV will be the key focus area in the 13th plan period up to 2019
64%
31%
Draft 13th plan published; however, to be finalized after adding Intra-state additions Source: CEA, MNRE
Growth Index for Electrical Equipment industry for the period
Marginal growth in motors, declining trend for HT motors due to core sector industry capex not taking off
Decline in Dist. Trf. – REC range & Meters due to delay in DDUGJY & IPDs implementation Growth for Power TRF, LV and MV_HV SWGR Cable, TLT register moderate growth; decline in Conductors Exports playing major role in overall growth
64%
31%
Overall Growth Index
Sector wise break up of weightages
64%
Sector wise break-up of Growth Index
Sector wise break-up of % Quarterly Growth Index
Cum growth Till Mar 17
In Q4 HV Swgr shown high growth, MV Swgr
shown moderate growth
1. Conductors declining consistently in all Qtrs
2. TLT declined in Q4 due to low off-take
3. Insulator sales picked up in Q4
22.3 (-) 0.7 11.8
4.7 (-) 5.1 3.5
Sector wise break-up of % Quarterly Growth Index
Cum growth Till Mar 17
Meters & Capacitors declining due to less
domestic & export orders; RM maintain sustain growth
Decline in DTs in all Qs due to delay in order finalizations
thru various schemes; Pick-up in Power Trf. & Cables
3.8 15.5 (-) 11.1
1.0 (-) 4.0 (-) 13.9
64%
31%
Source: DGCI&S, MoC, GOI Trend of Imports & Exports
High Imports (Main Country) HV Custom Built products (Korea), Insulator (China), Power Cap (USA), Power Trf.–HVDC(UK), AC motors > 75 KW (China), AC Generators > 750 KVA (China)
ITC codes Product Groups
Apr-Feb. 2016-17 % Growth over
2015-2016 Domestic Industry Size for 2015-16 Rs. Crs
Domestic Growth
%
Import Export Import Export
Value in Rs. Crores
8501 excl. 850110 & 20 Motors & AC Generators 1660 1392 (-) 9.7 (-) 7.8 6360 1.0
850423 Power TRF 315 1303 59.0 20.0 5000 15.4
850421-22, 850433-34 Distribution TRF 115 960 (-) 40 (-) 17.6 7000 (-) 11.7
853210 Capacitors 104 206 85.0 0.0 568 (-) 4.0
8535, 853720 HV SWGR incl. Panels 2037 1808 70.0 5.3 5040 11.8
8536, 853710 LT Switchgears incl Panels 7733 5500 18.0 4.7 12260 22.3
854442/49/60 Cables - LV & HV 576 1955 (-) 1.1 14.5 39200 3.4
854610, 20, 90 Insulators 722 465 25.0 1.2 2050 3.5
902830 Energy Meters 20 643 25.0 44.0 3000 (-) 14
73082011 Tr. Line Towers 137 1188 430.0 (-) 47.6 7150 4.7
7604 & 7614 Conductors 342 1396 5.5 (-) 28.7 8125 (-) 5.1
Raw Material Price Trend for past 3 years 2014-15 to 2016-17
Consistent growth in AL & CU price in last 6 months of about 20% CRGO prices now stabilized & showing rising trend in Q4 Growth in Steel prices due to MIP support
Raw Material Price Trend for past 3 years 2014-15 to 2016-17
USD Exchange rate declined in Q4; however remained above 67 levels during the year
Decline in Labour Index in last 9 months indicate inflation under check
Growth in ‘Fuel & Power’ WPI by 12% in FY16-17 due to increase in prices of petroleum products & Coking Coal
Important discussion points in IEEMA Divisions
Dist Trf – Poor visibility of demand beyond 2019 due to introduction of solar pumps in rural electrification
RM – Serious concern due to increase in Imports; Recommending mandatory IS:12615
Cable – Impractical & Unacceptable tender conditions in some utilities
MV_HV Swgr – Need for workshop with Utilities, DHI & MoP for model terms & conditions & promoting Make in India and CEA Advisory on domestically funded projects; exploring use of technology evolutions and engaging with R&D institutions for the same;
LV Switchgear - voltage for DC applications in Rural areas was agreed for 48V DC for DC applications in remotely located rural areas. Standard approved by ETD50 under printing
Capacitor -explore the genesis of penalty imposed on harmonics at TNEB and MSEDCL
Power Trf – Vendor development for world class quality and explore medium term status of demand drivers
EIM – EU exports declining; Defense sector demand picking up
Renewables- 90% of Solar Capacity installed is thru Imports of equipment’s from China.
Power Generation- Thermal business are going down drastically with no point of returning normal anytime soon.
Common Point – Review of Test gaps with CPRI and ERDA + high testing charges particularly at CPRI
Thank you!