Status and Highlights of the Pulsed Magnet Program as of summer 2010, mid-point in current award...

3
Status and Highlights of the Pulsed Magnet Program as of summer 2010, mid-point in current award period Delivered 350 th science pulse > 70T in 75T magnets assembly. (March 2008) Completed rebuild & rework of 100T outsert coils 1-4, (November 2008) Completed assembly of 100T Outsert, (January 2009) Science Program delivers 100 th 85T pulse (Insert #1) (May 2009) 1 st insert fault , non destructive as predicted. (June 2009) Completed conceptual design of Duplex user magnet upgrade. (October 2009) Magnet Group awarded R&D 100 Award (MRI for Carry-on Liquids) (October 2009) Science Program delivers 150 th 85T pulse (Insert #2) (December 2009) Completed conceptual design of 95T – 100T insert upgrade (May 2010) WR WR WR WR

Transcript of Status and Highlights of the Pulsed Magnet Program as of summer 2010, mid-point in current award...

Page 1: Status and Highlights of the Pulsed Magnet Program as of summer 2010, mid-point in current award period Delivered 350 th science pulse > 70T in 75T magnets.

Status and Highlights of the Pulsed Magnet Program

as of summer 2010, mid-point in current award period

• Delivered 350th science pulse > 70T in 75T magnets assembly. (March 2008)• Completed rebuild & rework of 100T outsert coils 1-4, (November 2008)• Completed assembly of 100T Outsert, (January 2009) • Science Program delivers 100th 85T pulse (Insert #1) (May 2009) • 1st insert fault , non destructive as predicted. (June 2009)• Completed conceptual design of Duplex user magnet upgrade. (October 2009)• Magnet Group awarded R&D 100 Award (MRI for Carry-on Liquids) (October 2009) • Science Program delivers 150th 85T pulse (Insert #2) (December 2009)• Completed conceptual design of 95T – 100T insert upgrade (May 2010)• Commissioned 4 MJ Capacitor bank for User Program (June 2010) • Insert #3 fabricated and delivered as a spare (June 2010)• Science Program delivers 177th 85T pulse (Insert #2) (July 2010) • Released Outsert Conductor Procurement Package (spare outsert work) (July 2010) • Complete 10mm CAD Package for 95T-100T Upgrade (August 2010)

WR

WR

WR

WR

Page 2: Status and Highlights of the Pulsed Magnet Program as of summer 2010, mid-point in current award period Delivered 350 th science pulse > 70T in 75T magnets.

Vision for the Pulsed Magnet Program (2012)

as of summer 2010, mid-point in current award period

• Deliver 2nd generation insert magnet upgrade (95T–100T ) (Jan 2011)• 95T attainable, 100T operations at proof of principal level

• Deliver duplex magnet technology (> 70T ops for user program) (June 2011)

• Complete fabrication of outsert coil replacements coils 3,4,5,6 (Oct 2011)

• Large cross section Cu-Nb conductor developed & delivered (July 2011)• Development in progress 2010 at Bochvar, #1 priority

• Production of outsert coils #1 & #2 using Cu-Nb conductor• Enable increase in field from Outsert circuit #1

TBD?

TBD?

Page 3: Status and Highlights of the Pulsed Magnet Program as of summer 2010, mid-point in current award period Delivered 350 th science pulse > 70T in 75T magnets.

Vision for the Pulsed Magnet Program (2017)

as of summer 2010, mid-point in current award period

• Delivering sustained 100 T science pulses using 2nd generation coil upgrades.

• Operating 10-50 MJ capacitor bank or new Lithium-ion battery bank.

• User facility operating at 80T–85T using duplex magnet technology optimized for new power technology. • coils use enhanced composite and conductor technologies.

• Implementing 3rd generation coil technology for generator magnets.• 3rd generation upgrades implement fault tolerant coil technology and enhanced

materials.