STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, … › wp-content › uploads › sites › ... ·...

22
STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, PRESSURE WASHING AND PAINTING OF THE INTERIOR WALLS OF MULTLEVEL PARKING GARAGE AT UNITED STATES EMBASSY, ABUJA. 1.0 General Information 1.1 This statement of work is to be accomplished at United States Embassy Compound located at Plot 1075, Diplomatic Drive, Central Area District, Abuja. The Contractor shall carry out ALL needful repair and restoration on ALL manner of defects and/or cracks to include but not limited to leaky reinforced suspended concrete parking floors seal, painting and masonry deterioration rework and aesthetic restoration on the structural concrete walls, suspended concrete slab floor, concrete slab soffit, failed concrete construction joints, failed concrete Isolation joints, failed concrete contraction joints and failed concrete expansion joints. 1.2 The contractor shall in addition carryout the pressure washing if applicable and repainting of the interior walls, beams, rails, doors, columns, slab soffits, bicycle rack, guard booths sally ports and other interior concrete surfaces of the Multilevel Parking Garage Building (PKG) to include the loading bay, storage rooms, visitors parking, in the compound and exterior concrete walls, slab soffit, beams, columns, parapet, elevator entrance aluminum vestibule, bollards, corner guards and of 4 th Parking level of the PKG. 1.3 This project requires an experienced contractor to execute the job as per the contract requirements and most stringent of local and international Industry standards. 2.0 General Requirements 2.1 The cost proposal for this contract shall include all labor, material not furnished by USG, tools, equipment, workers/equipment mobilization, description work to be completed, a quote for completion of all work, a schedule for completion of all work and demobilization, engineering and supervision required to finish, install and complete the work in accordance with the Contract Documents. 2.2 The Contractor shall carry out the work as per material (primer and paint specifications) the contractor shall verify all dimensions (square meters) before bidding during or after the actual onsite inspection and measurements. The contractor must compliances follow all local and with most stringent of local and International codes whichever is more stringent for architectural, civil and structural works required for this project, including the American Society for Testing and Materials (ASTM) & relevant codes and instructions issued by the United States Government (USG) representative designated as Contracting Officer’s Representative (COR). 2.3 The Contractor shall schedule all work under this project during normal Embassy business hours which are defined as 7:30am to 4:30pm Mondays to Thursdays and 7.30am to 1.30 pm on Fridays, excluding local and bank USG holidays, unless approved in advance by the Contracting Officer

Transcript of STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, … › wp-content › uploads › sites › ... ·...

Page 1: STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, … › wp-content › uploads › sites › ... · Contracting Officer’s Representative (COR). 2.3 The Contractor shall schedule

STATEMENT OF WORK

FOR LEAKY FLOOR SLAB REPAIR, PRESSURE WASHING AND PAINTING OF THE

INTERIOR WALLS OF MULTLEVEL PARKING GARAGE

AT

UNITED STATES EMBASSY, ABUJA.

1.0 General Information

1.1 This statement of work is to be accomplished at United States Embassy Compound located at Plot

1075, Diplomatic Drive, Central Area District, Abuja. The Contractor shall carry out ALL needful repair

and restoration on ALL manner of defects and/or cracks to include but not limited to leaky reinforced

suspended concrete parking floors seal, painting and masonry deterioration rework and aesthetic

restoration on the structural concrete walls, suspended concrete slab floor, concrete slab soffit, failed

concrete construction joints, failed concrete Isolation joints, failed concrete contraction joints and failed

concrete expansion joints.

1.2 The contractor shall in addition carryout the pressure washing if applicable and repainting of the

interior walls, beams, rails, doors, columns, slab soffits, bicycle rack, guard booths sally ports and other

interior concrete surfaces of the Multilevel Parking Garage Building (PKG) to include the loading bay,

storage rooms, visitors parking, in the compound and exterior concrete walls, slab soffit, beams, columns,

parapet, elevator entrance aluminum vestibule, bollards, corner guards and of 4th Parking level of the

PKG.

1.3 This project requires an experienced contractor to execute the job as per the contract requirements

and most stringent of local and international Industry standards.

2.0 General Requirements

2.1 The cost proposal for this contract shall include all labor, material not furnished by USG, tools,

equipment, workers/equipment mobilization, description work to be completed, a quote for completion

of all work, a schedule for completion of all work and demobilization, engineering and supervision

required to finish, install and complete the work in accordance with the Contract Documents.

2.2 The Contractor shall carry out the work as per material (primer and paint specifications) the

contractor shall verify all dimensions (square meters) before bidding during or after the actual onsite

inspection and measurements. The contractor must compliances follow all local and with most stringent

of local and International codes whichever is more stringent for architectural, civil and structural works

required for this project, including the American Society for Testing and Materials (ASTM) & relevant

codes and instructions issued by the United States Government (USG) representative designated as

Contracting Officer’s Representative (COR).

2.3 The Contractor shall schedule all work under this project during normal Embassy business hours

which are defined as 7:30am to 4:30pm Mondays to Thursdays and 7.30am to 1.30 pm on Fridays,

excluding local and bank USG holidays, unless approved in advance by the Contracting Officer

Page 2: STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, … › wp-content › uploads › sites › ... · Contracting Officer’s Representative (COR). 2.3 The Contractor shall schedule

Representative (COR). A minimum of 48hours prior notice will be required from the contractor for the

extra work hours/days

2.4 The contractor is responsible for verifying all dimensions, material quantities and existing

conditions prior to submitting a quote and during the project. All potential change to the contract must

be reported to COR for evaluation and consideration for contract modification. Contractor shall not

perform any work other than stated in the scope herewith unless received a written approval from the

contracting officer (CO) through the COR.

2.5 Workmanship shall be of high quality as characterized by pleasing appearance, proper dimensions,

proper shape, proper grade, and even surface. All manufactured items shall be new and installed in

accordance with the manufacturer’s instructions.

2.6 The contractor shall coordinate the work schedule and access to the work areas with the COR. Work

areas shall be cleaned up and debris disposed of properly on a daily basis. Contractor shall furnish bins

or other disposal means for the disposal of wastes generated from this project. No equipment or material

shall be stored on the work site without specific permission from the COR.

2.7 Contractor shall ensure that the Embassy furnished materials and equipment are prudently managed

and that the equipment are used correctly per the manufacturer’s manual. Where approved Codes of

Practice are applicable, the workmanship and procedures described by the relevant Codes shall be

regarded as the minimum standard acceptable.

2.8 The contractor shall not perform any work other than that specifically stated herein without

approval by COR. Any proposed changes or additional requirements of potential impact to the contract

cost/time discovered during the course of the work shall be reported in writing to the Contracting Officer

through the designated COR.

2.9 The contractor must ensure that all materials to be used are in conformance to the product/materials

samples presented in the approved submittals and bill of quantities reported in writing to the COR. The

contractor must submit all material samples of materials and with their product data (PD) sheets must be

submittals of samples and Product Data (PD) for all materials input in advance for to the project

execution must be pre-approval by the COR unless otherwise noted before project execution. The

contractor must provide in advance a floor by floor schedule to aid in notification of parking garage users

to remove their cars/vehicles from that floor during painting. NOTE: The contract is liable for overspray

on vehicles during painting.

2.10 The contractor shall provide along with his schedule drawings showing the work area and weekly

progress reports to the COR.

3.0 Responsibilities and Project Management.

3.1 COR. A Contracting Officers Representative (COR) will be assigned to ensure quality assurance

goals are met. The Contractor shall provide the COR or any Embassy representative access to the site at

all times.

Page 3: STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, … › wp-content › uploads › sites › ... · Contracting Officer’s Representative (COR). 2.3 The Contractor shall schedule

3.2 Point of Contact. The COR shall be the main point of contact for this Project. The Contractor

shall report to the COR on (a) status of the Project, (b) changes in schedule, (c) accidents and safety

issues, (d) disruptions to utility services; and all other important information pertaining to the Project

3.3 Preparation and protection of work area. Painting shall not disturb or damage any fixed

property (including light fixtures, floors, window metal grille, metal guard rails, camera, surface conduit

pipes, metal anchors and other surfaces that are not to be painted. The Contractor shall move, protect

and return such property to its original position at the Contractor's expense upon completion of work in

that area if there is paint stain or spill on any the properties excluded on this contract.

3.4 English Speaking Representative. The Contractor shall provide an English-speaking

representative on-site during all working hours with the authority to make all decisions on behalf of the

Contractor and subcontractors.

3.5 Embassy provided materials. Embassy will provide the following Government owned

equipment and materials: Commercial airless paint sprayer, height reaching equipment (Scissors lift),

Hydra Stop 300 Epoxy Crack Injection for leak repair (or similar compound), Sherwin Williams

manufactured Exterior Semi-Gloss Acrylic Enamel Creamy (Color Code: SW-7012), CHEMPROBE

CONFORMAL STAIN SERIES 607 (Color Code: TNEMEC 31 GR SLATE GREY PAINT) and

Sherwin Williams manufactured Waterborne Interior Acrylic Semi – Gloss Nuance Paint (Color Code:

SW7049). The Embassy will provide operators for the furnished motorized equipment.

3.6 Contractor provided materials. The Contractor shall supply everything necessary for the

execution and completion of the work unless otherwise noted as items to be furnished by US Embassy

including but not limited to paints, brushes, rollers, drop sheets, drop clothes, sandpaper, fillers, sealants,

scrapers, thinners, tints, color charts, painters tape (not masking tape), ladders, scaffolding and other tools

and equipment per best industry practice. Site preparation and installation performance shall be in

accordance with building codes and standards.

No products containing lead shall be used on this project. Primers, sealers, undercoats - Ensure that

primers, sealers and undercoats are suitable for the substrate and compatible with the finish coat and each

other.

3.7 Quality assurance. Before paint’s application, the US Embassy designated Contracting Officer’s

Representative (COR) will inspect all preparatory work required such as crack’s repair, cleaning surfaces,

surface preparatory work prior to painting and approve to proceed into the next work level. The contractor

shall review the compliances of the work performed at agreed upon milestone with the COR to evaluate

the progress of work and deliverable acceptance.

3.8 Pre-Paint Schedule and coordination. Schedule of work must be preapproved the Embassy.

Embassy reserved the right to revise and/or change the agreed schedule of work to convenient

Embassy operation with or without an advance notices. The awarded contractor must present the COR

with a preapproved painting schedule that provides planning details concerning the areas to be painted,

Page 4: STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, … › wp-content › uploads › sites › ... · Contracting Officer’s Representative (COR). 2.3 The Contractor shall schedule

approximate number of staff and access hours needed for that section. The Embassy COR will work out

an agreed upon timetable for access and order of painting based on the contractor’s submitted schedule.

3.9 Management Personnel. The Contractor shall staff the site, full-time, with a competent senior

manager who shall perform project management. Remote project management is not an option. This

individual shall keep a detailed written history of the project and shall update the Government weekly.

The staff can double act as English Speaking Representative for the contractor.

3.10 Site Preparation and Cleaning Up: The Contractor shall at all times keep the work area,

including storage areas, free from accumulations of waste materials. Before completing the work, the

Contractor shall remove the work and premises any rubbish, tools, scaffolding, equipment, and materials

that are not the property of the Government. Unsightly materials and debris including excess materials,

garbage, and equipment should be removed as required; while materials should be scheduled for delivery

only as required for immediate use.

3.11 Hours of Work: The work will have to be scheduled for normal working hours on Monday –

Thursday 07.30 – 16.30 & Friday 07.30 – 13.30. Some work may be scheduled for after hours or weekend

on a need to basis upon 48 hours minimum preapproved advance request from the contractor.

3.12 Utilities: The contractor will have access to water and electricity on site.

3.13 Site Security. The Contractor is responsible for on-site security as necessary to ensure no

unauthorized access to their work sites. The Contractor is 100% responsible for securing their working

materials and equipment. Any damage to facilities or infrastructure, which happens due to a lack of

security, will be the responsibility of the Contractor to correct.

a. Security requirements: Upon award of contract, the contractor must furnish details of all staff

that will be onsite. The details will be inclusive of:

1. Full Name

2. Position

3. Means of Identification

b. The US Embassy reserves the right to refuse entry to any or all contractor personnel. Each

contractor personnel must have a valid identity card. Access to the US premises shall only be by

prior, approved schedule and escort by the assigned US Government Escort.

3.14 Health and Safety: Safety is the highest priority on this and all US Embassy contracts. The

Contractor shall be solely responsible for risk assessments, managing health, and safety issues associated

with this project, as well as those established by ANSI and OSHA. The US Embassy reserves the right

to stop and/or remove from site contractor personnel who fail to comply with relevant OHS/OHSA

requirements.

Page 5: STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, … › wp-content › uploads › sites › ... · Contracting Officer’s Representative (COR). 2.3 The Contractor shall schedule

a. Based on hazard assessments, Contractor shall provide or afford each affected employee personal

protective equipment (PPE) that will protect the employee from hazards. At a minimum PPE shall consist

of eye protection, hard hats, closed toe shoes and respiratory protection with filters. If the workers arrive

on-site with sandals or athletic shoes, the Contractor is expected to provide rubber boots to them or send

them home. All construction workers and management personnel must wear hard hats at all times on the

construction sites. Other PPE such as gloves, dust masks, air respirators and boots are also

recommended. These items must be provided at the Contractor’s expense. Workers may use discretion if

they feel unsafe in using the equipment in a hostile environment. Any worker at an elevated location

above 4 meters, with the exception of a portable ladder, must be provided and utilize a safety harness.

b. The contractor must document in the bid for work how the hazard controls will be implemented

and maintained during the project. The Contractor shall prepare and implement an Activity Hazard

Analysis (AHA) prior to the start of work. The Contactor must have a competent person on-site for

inspection of equipment, training workers in the safe use of equipment and the recognition of hazards

related to their use, supervision, and identifying and correcting unsafe work practices for high hazard

work.

3.15 Potential Hazards: The potential job hazards analysis for this project are listed below with the

control method requirements:

• Use of scaffolding at elevated heights for painting

Job steps Potential hazards Safe action or procedure

1- Setting Up

Scaffolding

Struck by falling

scaffolding

A scaffold competent person shall supervise the

erection, alteration, moving, or dismantling of

scaffolding.

Get help with getting heavy/bulky items to elevated

levels.

Keep tools, equipment extension cords, ropes, out of

walk ways.

Improper set-up Scaffolding shall be constructed in conformance with

the requirements of manufacturer.

Before scaffolding is designed or erected, the work

area shall be analyzed to identify existing hazards

(overhead lines, elevated temperatures, structural

stability, soil condition, etc.) that could affect personnel

as they erect, alter, move, or dismantle, or work on

scaffolding.

Install scaffolding with at least 2 people.

Install scaffolding per manufacturers’ requirements.

2. Climbing Up the

scaffolding

Struck by falling

scaffolding

Each employee who performs work while on a scaffold

(scaffold user) shall be trained by a scaffold competent

Page 6: STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, … › wp-content › uploads › sites › ... · Contracting Officer’s Representative (COR). 2.3 The Contractor shall schedule

person qualified to recognize the hazards associated

with the type of scaffold being used.

Inspect scaffolding on a regular basis.

Fall Injury self Only use scaffolding for its intended purpose.

Fall injury others

Provide a safe means of access.

Properly plank /deck working surfaces.

Do not climb scaffold frame. Do not remove rails or

bracing. Do not move scaffolding. Always close the

hatch when entering a new level.

Fall protection is required if working above 6 feet.

Maintain three points of contact while on climbing.

Do not allow others to be standing around the

scaffolding when not needed.

3. Working while on

the scaffolding

Fall Injury self

Fall Injury Others

Dropped objects can

injure or kill persons

below

A scaffold competent person shall inspect scaffolding

before each work shift, when the scaffold is to be used,

and before work resumes after the scaffold has been

altered or moved. The inspection shall be documented

on a Scaffold Inspection Tag that is attached to the

scaffolding.

Fall protection is required if working above 6 feet.

Look before you walk.

Maintain three points of contact while on climbing.

Do not allow others to be standing around the

scaffolding when not needed.

Keep 2 feet on the working surface at all times. Keep

body center of gravity inside. Do not rely on end rails

or diagonals for support.

No more than 2 persons per tower occupancy.

The workers located above shall be careful. Rope off

area below as NO ACCESS when working above.

Personal Protective Equipment (PPE) Requirements:

Fall Protection

Scaffolds shall be equipped with a standard guardrail or other fall protection systems.

For workers erecting and dismantling scaffolds, an evaluation shall be conducted by a

Competent Person for fall protection to determine the feasibility and safety of providing fall

protection. If fall protection is not feasible, an Activity Hazard Analyses detailing rationale for

infeasibility of use of fall protection shall be submitted and accepted by the POSHO.

• Use of primers and paints

Job steps Potential hazards Safe action or procedure

Page 7: STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, … › wp-content › uploads › sites › ... · Contracting Officer’s Representative (COR). 2.3 The Contractor shall schedule

Open paint can Puncture or cuts from

screwdriver or can

opener

Wear gloves; work with pointed/sharp tool

edges pointed away from yourself.

Stir/mix/pour paint Paint splashes in

eyes/on skin

Exposure to paint

fumes

Wear eye protection, gloves; work on level

surfaces.

Work in well ventilated areas, consider

wearing dust mask.

Painting Splashes in eyes / on

skin

Exposure to paint

fumes

Skin irritation

Skin irritation to hands

Contamination of

clothing

Eye irritation

Muscle strain from

repetitive motion,

reaching awkward

positions

Cuts from sharp tools

(hand axe, paint

scraper)

Fire

Wear eye protection, gloves; paint slowly to

reduce splash.

Work in well ventilated areas, consider

wearing dust mask.

Wear a respirator and other PPE as

recommended on the MSDS.

Wear long-sleeved, loose fitting clothing that

covers all exposed skin.

Wash exposed areas thoroughly with soap and

water after handling.

Do not wash skin or hands with paint thinner

or lacquer thinner, use hand cleaner.

Wear gloves that are impervious to paint and

thinner

Wash work clothes separately from other

clothing; rinse washer after thoroughly after

use.

Wear goggles that seal eyes from paint

Take rest breaks as needed; position body

minimize awkward movements

Wear gloves, keep blaze preparation toll

under control at all times, cut away from

yourself

Properly store paints that may be combustible

Properly dispose of dirty rags into airtight

containers

No smoking allowed in or around painting

area or paint storage area

Promptly clean up spills and leaks

Keep combustibles away from ignition

sources

Keep fire extinguisher near painting

operations

Page 8: STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, … › wp-content › uploads › sites › ... · Contracting Officer’s Representative (COR). 2.3 The Contractor shall schedule

Personal Protective Equipment (PPE) Requirements:

Respirator

Hand protection

Eye protection

Coveralls long-sleeved

The Contractor must have on hand primers and paints MSDS during application.

• Use of pressure washer

Job steps Potential hazards Safe action or procedure

Obtain permission

from supervisor

Serious physical

injury

Ensure that properly trained individuals have

been authorized to use a high pressure cleaner

Inspecting and

wearing proper PPE

Falling

Particles in eye

Ensure slip resistant closed toed, even sole,

clean and sturdy shoes are worn.

Ensure that employees are wearing safety

glasses.

Ensure that employees are wearing PPE

including full length trousers, safety shoes,

safety gloves and hearing protection

Pre-start checks Burns, inhaling

fumes, electrocution,

injury

Check diesel level and top up if necessary.

Do not refuel in a confined area due to danger

of inhaling fumes.

When refueling, ensure area is free from any

source of flame or sparks.

Inspect pressure cleaner for oil, fuel and/or

water leaks and report immediately.

Check all connections on hoses and machine

for cracks, etc. – especially those for high

pressure hose and report immediately.

If high pressure nozzle comes off during

cleaning operation, it could cause serious

injury.

Connect hoses Connect water hose to high pressure cleaner

with care.

Connection for pressure hose should not be

over-tightened. Only tighten by hand and do

not use spanners.

Fueling the pressure

cleaner

Fire, burns Do not smoke while filling the fuel tank.

Do not fill the fuel tank indoors.

Page 9: STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, … › wp-content › uploads › sites › ... · Contracting Officer’s Representative (COR). 2.3 The Contractor shall schedule

Do not fill the tank while the engine is hot or

running.

Wipe up any spilled fuel before starting or

restarting the engine

Commence cleaning

operation by turning

the equipment on

Burns, eye/face

injury, bodily injury,

slips & trips

Never point or aim the gun/wand at yourself or

anyone else.

Never put your hand, fingers or body directly in

front of the spray nozzle.

Devote your individual attention to the work

being performed.

Do not overreach. Keep proper footing and

balance at all times.

If the pressure washer is not working properly

shut off the power and notify your supervisor.

Do not operate the pressure washer when under

the influence of medications or other mind-

altering substances.

Avoid distractions such as ear phones.

Do not spray directly at glass or fragile objects.

Do Not run power washer in an enclosed area.

Exhaust fumes contain poisonous carbon

monoxide gas. Breathing exhaust gases can

cause serious illness or death.

Do Not touch or come in contact with hot

mufflers, cylinders, cooling fins or hot exhaust

gases as this may result in severe burns.

Never tamper with governor spring, governor

links or other components which may increase

the speed (RPM) of the engine.

Do Not make adjustments to your equipment

without first removing the spark plug.

When transporting pressure washer, the fuel

shut-off valves must be in the closed position, to

prevent fuel from spilling out.

Operate unit on level surface only. Otherwise

fuel may spill on engine and/or pump.

Lubrication may be insufficient if unit is not

level.

Do Not run the unit for longer than 3 minutes

with spray gun in the closed position

Never squeeze the spray gun trigger unless you

are securely braced.

Page 10: STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, … › wp-content › uploads › sites › ... · Contracting Officer’s Representative (COR). 2.3 The Contractor shall schedule

The force of water through the nozzle is

powerful enough to cause you to lose your

balance and fall.

Never leave the pressurized unit unattended.

Always shut off the unit and relieve trapped

pressure before leaving.

NEVER attempt to use power washers on or

near any electrical outlets, fuse boxes,

transformers, high voltage wires, etc.

NEVER start pressure washer without adequate

water supply.

Turn the pressure

cleaner off

Always turn the power off and wait until the

trapped water pressure is relieved.

Clean work area

Injury, falls

Clean up spilled soap, fuel or oil immediately to

avoid falls.

Keep clutter out of work area to avoid falls

Personal Protective Equipment (PPE) Requirements:

Safety glasses, full length trousers, safety gloves (when appropriate), hearing protection

(recommended), and safety shoes.

• Use of step ladders

Job steps Potential hazards Safe action or procedure

Inspecting and

wearing proper PPE

Falling

Particles in eye

Ensure slip resistant closed toed, even sole,

clean and sturdy shoes are worn.

Ensure that employees are wearing safety

glasses.

Ensure that employees are wearing PPE

including full length trousers, safety shoes,

safety gloves and hearing protection.

Visually/Manually

Select a Ladder

Falling, injury Visually review the ladders for style, size, duty

rating and materials. Portable step ladders are

usually recommended when you need a reach of

two to eight feet.

Select ladder that is the right size or length. A

ladder that is generally long enough when it

provides access to work area without

necessitating standing on the top two steps of a

step ladder.

Page 11: STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, … › wp-content › uploads › sites › ... · Contracting Officer’s Representative (COR). 2.3 The Contractor shall schedule

Ladders selected must be sufficient for the

weight of the employee plus the weight of any

tools and materials.

Review the duty rating on the side of the ladder.

Fiberglass has become the best choice material

for ladders.

Do not use a metal ladder when working on or

near electrical equipment.

Wood ladders are not authorized.

Transporting a ladder

by lifting and carrying

Muscle strain

injuries to self and

others from losing

control of ladder

Property damage

Use proper lifting technique.

Ask for help if the ladder is too heavy or over 6

feet in length.

Bend at the knees and lift ladder with your leg

muscles instead of your back muscles.

Limit turning and twisting motions while

carrying the ladder. This may cause a back

injury.

Maintain control of ladder by firmly gripping

the ladder.

Devote constant attention to the area traveled to

avoid striking property or other people.

Always carry step ladders in the closed position.

Transporting a ladder

by vehicle

Injuries to self and

others from losing

control of ladder

Property damage

Maintain control of ladder by firmly gripping

the ladder.

Devote constant attention to the area traveled to

avoid striking property or other people.

Always carry step ladders in the closed position.

Ensure that step ladder is properly secured on

rack with cords while being transported on a

vehicle.

Visually / Manually

Inspect Ladder before

use

Lacerations, muscle

strain

Check the stability of the ladder.

Check joints between step and side rails in

insure they are tight.

Insure that rungs are clean and free of grease

and oil.

Check for loose, bent hinge or broken rungs.

Immediately remove damaged ladders from

service, label them as “Out-of-Service” and

notify the appropriate supervisor.

Page 12: STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, … › wp-content › uploads › sites › ... · Contracting Officer’s Representative (COR). 2.3 The Contractor shall schedule

Setting up the ladder Injuries to self and

others

Barricades and warning signs should be posted

when ladders are placed near doors or other

locations where they could be struck.

Never place ladders on boxes, barrels, or other

unstable bases for additional height.

Ladders must be placed on level surfaces.

Make sure that ladders are not blocking

doorways and emergency routes.

Never use a step ladder on slippery surfaces.

Ensure the ladder is opened fully and ladder

locks, spreaders or braces are engaged before

climbing.

Never use a step ladder over 20 feet in length.

Potential

electrocution

Metal ladders are not used near electrical lines.

Climbing up ladder Falling, Injury Maintain three points of contact while on the

ladder.

Do not over-reach, jump or slide a ladder while

on it.

Always face the ladder and use both hands

while ascending and/or descending.

Tools or materials should be raised by means of

a rope after the climber has reached the working

position. Carrying heavy loads up or down

ladders is prohibited.

Ladders should not be used by more than one

person at a time.

Do not lean sideways out of the ladder’s width.

Always wear proper footwear; closed-toe,

sturdy, and clean.

Perform job task

Falling Devote your individual attention to the work

being performed.

Climbing down the

ladder

Falling, Injury Maintain three points of contact while on the

ladder.

Do not over-reach, jump or slide a ladder while

on it.

Always face the ladder and use both hands

while ascending and/or descending.

Do not lean sideways out of ladder’s width.

Always wear proper footwear; closed-toe,

sturdy, and clean.

Page 13: STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, … › wp-content › uploads › sites › ... · Contracting Officer’s Representative (COR). 2.3 The Contractor shall schedule

Removing ladder,

barricades and other

equipment

Injuries to self and

others from losing

control of ladder

Maintain control of the ladder by firmly

gripping the ladder.

Devote constant attention to the area traveled to

avoid striking property or other people.

Never leave tools or materials on the top of a

step ladder.

Storing ladder Injuries to self and

others by ladder

falling

Ladders should be stored in a designated storage

area

Personal Protective Equipment (PPE) Requirements:

Slip resistant even sole, closed-toe, sturdy and clean proper footwear

Recommended – Safety glasses/goggles/hard hat based on job task

• Use of extension ladders

Job steps Potential hazards Safe action or procedure

Inspecting and

wearing proper PPE

Falling

Particles in eye

Ensure slip resistant closed toed, even sole,

clean and sturdy shoes are worn.

Ensure that employees are wearing safety

glasses.

Ensure that employees are wearing PPE

including full length trousers, safety shoes,

safety gloves and hearing protection.

Visually/Manually

Select a Ladder

Falling, injury Visually review the ladders for style, size, duty

rating and materials.

Select ladder that is the right size or length. A

ladder that is generally long enough when it

provides access to work area without

necessitating standing on the top two steps of a

ladder.

Ladders selected must be sufficient for the

weight of the employee plus the weight of any

tools and materials.

Review the duty rating on the side of the ladder.

Fiberglass has become the best choice material

for ladders.

Do not use a metal ladder when working on or

near electrical equipment.

Wood ladders are not authorized.

Page 14: STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, … › wp-content › uploads › sites › ... · Contracting Officer’s Representative (COR). 2.3 The Contractor shall schedule

Transporting a ladder

by lifting and carrying

Muscle strain

injuries to self and

others from losing

control of ladder

Property damage

Use proper lifting technique.

Lifting and moving a 20foot extension ladder is

a two person job.

Bend at the knees and lift ladder with your leg

muscles instead of your back muscles.

Limit turning and twisting motions while

carrying the ladder. This may cause a back

injury.

Maintain control of ladder by firmly gripping

the ladder.

Devote constant attention to the area traveled to

avoid striking property or other people.

Always carry step ladders in the closed position.

Carry extension ladders parallel to the ground

and hold the side rail in the middle.

Visually / Manually

Inspect Ladder before

use

Lacerations, muscle

strain

Check the stability of the ladder.

Check joints between step and side rails in

insure they are tight.

Insure that rungs are clean and free of grease

and oil.

Check for loose, bent hinge or broken rungs.

Immediately remove damaged ladders from

service, label them as “Out-of-Service” and

notify the appropriate supervisor.

Setting up the ladder Injuries to self and

others

Barricades and warning signs should be posted

when ladders are placed near doors or other

locations where they could be struck.

Never place ladders on boxes, barrels, or other

unstable bases for additional height.

Ladders must be placed on level surfaces.

Make sure that ladders are not blocking

doorways and emergency routes.

Never use an extension ladder on slippery

surfaces.

Ensure the ladder is opened fully and ladder

locks, spreaders or braces are engaged before

climbing.

Extension ladders should be tied off at the top,

blocked, secured or held by a second worker

when in use.

Page 15: STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, … › wp-content › uploads › sites › ... · Contracting Officer’s Representative (COR). 2.3 The Contractor shall schedule

Ensure that sections of the ladder overlap

enough to retain the strength of the ladder as

follows:

−Ladders up to 36’ – 3 feet overlap

−Ladders over 36’ to 48’ – 4 feet overlap

− Ladders over 48’-60’ – 5 feet overlap

Never splice or tie two ladders together.

Always inspect the area to make sure that it is

free of electrical lines.

Observe the proper placement angle for your

extension ladder.

The base of the ladder should be one-foot (1’)

out from the wall for every 4 feet of height.

When using a ladder to access to a landing, it

must extend 3 rungs or 3 feet above the landing.

Elevate and extend extension ladders only from

the ground.

Metal ladders are not used near electrical lines

Potential

electrocution

Metal ladders are not used near electrical lines.

Climbing up ladder Falling, Injury Maintain three points of contact while on the

ladder.

Do not over-reach, jump or slide a ladder while

on it.

If possible, have someone steady the ladder as

you climb it.

Always face the ladder and use both hands

while ascending and/or descending.

Tools or materials should be raised by means of

a rope after the climber has reached the working

position. Carrying heavy loads up or down

ladders is prohibited.

Ladders should not be used by more than one

person at a time.

Do not lean sideways out of the ladder’s width.

Always wear proper footwear; closed-toe,

sturdy, and clean.

Perform job task

Falling Devote your individual attention to the work

being performed.

Climbing down the

ladder

Falling, Injury Maintain three points of contact while on the

ladder.

Page 16: STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, … › wp-content › uploads › sites › ... · Contracting Officer’s Representative (COR). 2.3 The Contractor shall schedule

Do not over-reach, jump or slide a ladder while

on it.

Always face the ladder and use both hands

while ascending and/or descending.

Do not lean sideways out of ladder’s width.

Always wear proper footwear; closed-toe,

sturdy, and clean.

Removing ladder,

barricades and other

equipment

Injuries to self and

others from losing

control of ladder

Maintain control of the ladder by firmly

gripping the ladder.

Devote constant attention to the area traveled to

avoid striking property or other people.

Never leave tools or materials on the top of a

ladder.

Storing ladder Injuries to self and

others by ladder

falling

Ladders should be stored in a designated storage

area

Personal Protective Equipment (PPE) Requirements:

Slip resistant even sole, closed-toe, sturdy and clean proper footwear

Recommended – Safety glasses/goggles/hard hat based on job task

4.0 Technical Evaluation Submittals.

a Qualifications for installation firm and installation supervisor.

b The Contractor shall certify in writing and with supporting diagrams from previous work

that Contractor has potential for performing such work and has the required materials. The

trained applicator shall submit to the Embassy a list of five projects that he has completed

within the last five years, exhibiting the applicator’s skills. The list shall include project

name, location, photos and description of work and completion date.

c Painting applicator certificate (if available). Products shall be installed by a trained

applicator with a minimum of five years experience and meet the requirements of the

contract.

d Safety and Hazard control measures plan.

e Construction schedule.

f The Contractor shall provide product data (PD) and material safety data sheet (MSDS) for

each type of manufactured material as per ASTM standards.

5.0 Project Requirements

5.1 The Contractor is to provide and set up scaffold in line with all required safety measures to carry

out the work. All elevations will require scaffold access and or man lift to access. USG properties support

to the project are the paint spraying machine and man lift with operator to only area accessible and

Page 17: STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, … › wp-content › uploads › sites › ... · Contracting Officer’s Representative (COR). 2.3 The Contractor shall schedule

admissible to the motorized man lift usage. Contractor shall be responsible for the provision of powered

pressure washer with a size of spray power pressure ranging from 1200 – 2000 PSI and scaffoldings to

access areas where the USG furnished man lift cannot be used. Power to the pressure washer if electrical

will be provided by the USG with contractor providing the extension cords needed for connection.

Contractor will be responsible for the fueling of gasoline powered pressure washers. Contractor shall

comply with daily cleaning of USG furnished equipment and tools at end of the work. All contractor

responsible equipment refueling shall be done outside the USG compound. Contractor is responsible to

provide extension power cord to extend the limit of power cable of the USG furnished equipment and

tools to the power connection point.

5.2 Contractor shall carry out adequate pretreatment and preparation not limited to washing, screeding,

priming, de-moisturized, etc. of the surface to be painted prior painting. The contractor shall carry out

repair of cracks and other concrete defects omitted or not captured by the concrete repairs that were

recently carried out on the buildings. In the occurrence of needful to carry out any nonstructural repairs

not limited to cracks, shrinkage, flaking, and discoloration the defect must be jointly assessed and the

remedial procedure must be discussed onsite and approved by the COR.

5.3 The buildings surface area to be pressure washed and painted are estimated and listed below. The

estimations provided herewith are furnished for the USG independent Bill of Estimate Measurement and

Evaluation (BEME) guidance only, Contractor is responsible to verify the measurements as necessary

prior the quote submission.

STRUCTURE TYPE PAINTING ESTIMATED AREA

Slabs soffit (Decking ) and Beams 17,074.00 Sq. m

Walls 4,590.00 Sq. m

Columns 528.00 Sq. m

Storage rooms 1991.00 Sq. m

Metal surfaces (Corner guards, window

grilles, guard rails,

256.00 Sq. m

Doors and frames 72.7 Sq. m

Parking floor signs and parking delineation

lines

Lump

Page 18: STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, … › wp-content › uploads › sites › ... · Contracting Officer’s Representative (COR). 2.3 The Contractor shall schedule

5.4 Contractor is sole responsible to clean the environment where work is performed daily, cart away

all debris accruing from the work and dispose appropriately to restore the environment to as met

condition.

5.5 Contractor is to remove ladders, equipment, materials from Embassy staff access areas at the end

of each work day. Work is not to disrupt the functioning of the embassy or impact security procedures

(at the CACs’ and Guard booths).

6.0 Repair Procedures.

6.1 Repair of Leaky Concrete Joints and Cracks on Suspended Slabs

a. Epoxy Crack Injection for Leaky slab repair: Comply with manufacturer’s written

instructions and the following.

b. Clean areas to receive capping adhesive of oil, dirt, and other substances that would

interfere with bond, and clean cracks with oil-free compressed air or low-pressure water

to remove loose particles.

c. Place injection ports as recommended by epoxy manufacturer, spacing no farther apart

than thickness of member being injected. Seal injection ports in place with capping

adhesive.

d. Seal cracks at exposed surfaces with a ribbon of capping adhesive at least 6 mm thick

by 25 mm wider than crack.

e. Inject cracks wider than 0.075 mm to a depth of 200 mm or to a width of less than 0.075

mm, whichever is less.

f. Inject epoxy adhesive, beginning at widest part of crack and working toward narrower

parts. Inject adhesive into ports to refusal, capping adjacent ports when they extrude

epoxy. Cap injection ports and inject through adjacent ports until crack is filled.

g. After epoxy adhesive has set, remove injection ports and grind surfaces smooth.

6.2 Emulsion Painting Of Walls, Slab Soffits, Columns, Beams and Masonry Surfaces.

a. Preparation: Practice standard recommendations in regard to preparation of surfaces to

receive paint and application of paint itself. Procedures shall include, but not necessarily

be limited to, the following:

b. Cleaning - Pressure wash all external masonry surface to remove all loose or peeled paint,

deposits, stains, and mildews growth. Clean down and remove oil, grease and loose

foreign matter, including, mold mildew, dirt and corrosion products, in a manner which

Driveway and parking floors Lump

Page 19: STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, … › wp-content › uploads › sites › ... · Contracting Officer’s Representative (COR). 2.3 The Contractor shall schedule

causes neither undue damage to the substrate nor damage to, or contamination of, the

surroundings or the paint system to be applied;

c. Glossy Surfaces - Adequately scuff and/or solvent or chemically etch as appropriate to

provide satisfactory adhesion for subsequent paint coats. Apply the appropriate sealers,

primers, and base coats on all bare substrates if required.

d. Filling - Fill cracks and holes with fillers, sealers or grouting cements as appropriate for

the finishing system and substrate, and sand smooth, to ensure all coats finish smooth.

e. Drying - Unless otherwise specified, ensure that surfaces are cured before applying

additional coats of paint.

f. Tape non-painted surfaces adjacent to areas of painting to ensure that no brush or roller

marks appear on doors, wood frames, or concrete floor. Place painting canvas and tarps

to prevent drip marks or spills onto floors.

g. Wet Paint Warning - Place notices and do not remove until paint is dry.

h. Initial coat; using 3/8” nap rollers approved for smooth surfaces apply paint and related

material with over any patched or repaired drywall surface and let dry prior to applying

final coats. The Contractor shall apply materials at the manufacturer’s recommended

spreading rate. The Contractor shall provide a total dry film thickness of the system as

recommended by the manufacturer. Final paint shall be applied in two coats and according

to the instructions of selected finish color paint. Allow each coat to harden for the drying

time (or time between coats) recommended by the manufacturer.

i. Finish - Ensure each coat of paint is uniform in color, gloss, thickness and texture and free

of runs, sags, blisters, visible roller marks, or other discontinuities. Upon completion of

painting, the Contractor shall clean the glass and paint-spattered surfaces. The Contractor

shall remove spattered paint by washing, scraping or other proper methods, and using care

not to scratch or damage adjacent finished surfaces. The Contractor shall remove

temporary protective wrappings after completion of painting operations in each space or

area, and shall reinstall items removed when final coat is thoroughly dry

j. Ensuring that the substrate is clean and dry, apply two coats of USG Furnished Sherwin

Williams manufactured Exterior Semi-Gloss Acrylic Enamel Creamy (Color Code: SW-

7012) or CHEMPROBE CONFORMAL STAIN SERIES 607 (Color Code: TNEMEC 31

GR SLATE GREY PAINT) with electric paint sprayer and/or contractor furnished brush

or roller as applicable. On some areas, additional coat of paint may be required to ensure

adequate paint coverage for a good and even color throughout. Light sand away runs or

rough surfaces noted between coats.

k. Patching Mortar: Use a preapproved locally available patching mortar to be furnished by

the contractor. Mix dry-pack mortar as directed by the manufacturer using only enough

water as required for handling and placing.

l. Repair materials and installation not specified above may be used, subject to acceptance

of the COR.

m. All floors are to be pressure-wash cleaned and NOT to be painted, unless specified

otherwise.

Page 20: STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, … › wp-content › uploads › sites › ... · Contracting Officer’s Representative (COR). 2.3 The Contractor shall schedule

6.3 Repainting Of Doors, Windows Grilles, Guard Rails, Hand Rails, Door Frames, And Other

Metal Surfaces.

a. Clean up the exterior part of all the painted surface with a cleaning solvent or by other means

acceptable to the industry best practice.

b. Glossy Surfaces - Adequately scuff and/or solvent or chemically etch as appropriate to provide

satisfactory adhesion for subsequent paint coats. Apply the appropriate sealers, primers, and base coats

on all bare substrates if required.

c. Repair all cracks by filling or sealing with suitable fillers. Scrape off all existing loose paint with a

metal scraper. Patch up uneven surfaces with the appropriate fillers. Allow for adequate drying time,

and sand down the uneven surface for a smooth finish.

d. Apply the appropriate sealers, primers, and base coats on all bare substrates.

e. Ensuring that the substrate is clean and dry, apply two coats of USG Furnished Sherwin Williams

manufactured Waterborne Interior Acrylic Semi – Gloss Nuance Paint (Color Code: SW7049) by brush

and/or Roller. On some areas, additional coats may be required to ensure adequate paint coverage for a

good and even color throughout.

f. Drying - Unless otherwise specified, ensure that surfaces are cured before applying additional coats

of paint or dry enough to remove the protection not to spill over the painting to the adjacent property.

6.4 Mockups.

a. Prior to the commencement of the work plan, Contractor shall perform mockups to comply with

the contract requirements using materials indicated for the completed Work to comply with the following.

b. Build mockups in the location and of the size or area indicated or as directed by COR.

c. In presence of COR, perform the repair and painting procedure to demonstrate materials and

techniques proposed for repair of cracks, defects, leakages, painting and others as directed by the COR.

d. Review mockups procedures and sample onsite with the COR as a representational sample of

the targeted deliverables to achieve by the contractor at completion of the project.

e. The mockup sample can be accepted if meet the expectations of the contract or rework by the

contractor until minimum level of expectations is achieved.

f. Approved mockups may become part of the completed Work if undisturbed and/or damaged at time

of project completion.

7.0 Project Completion

7.1 The Contractor shall commence work under this contract promptly, execute the work diligently,

and achieve final completion and acceptance including final cleanup of the premises within the period

specified. USG reserved the right to adjust the schedule and/or phasing plan of the contractor as

convenient to its operation.

a Milestones:

Page 21: STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, … › wp-content › uploads › sites › ... · Contracting Officer’s Representative (COR). 2.3 The Contractor shall schedule

b Contractor Pre-Proposal Site Visit [To be informed]

c Award of Contract & Notice to Proceed (NTP) [To be informed]

d Construction Begins Within 10 days of NTP

e Project Estimated Duration 60 calendar days

7.2 Preliminary And Final Acceptance:

a After completing the execution of a unit or portion thereof, the Contractor shall give a notice in

writing stating that the job is complete in all respects and ready for preliminary acceptance.

b The job shall be jointly inspected visually by representatives of Contractor and USG

representatives. All observed defects and omissions as per SOW, workmanships and specifications

shall be noted down.

c The Contractor shall make good all defects, deficiencies and omissions noted down during

preliminary acceptance and shall inform in advance the USG representatives for conducting

inspection for final acceptance.

d Final acceptance shall be communicated in writing through the contract COR to the contractor.

7.3 WARRANTY:

The contractor shall provide 6-month warranty to start upon date of invoice that covers all painted wall

finishes that the contractor must correct at no additional cost any discrepancies of workmanship, or color

fading caused by product or application.

NOTE

This is an USG Property; the materials used should be of an international standard for a

property of this standing. Requirements in this SOW serve as a direction to the Contractor for

the repainting of the interior of the Embassy Multi-Levels Parking Garage (PKG). The

Contractor shall perform all services in accordance with international professional standards of

skill, care and diligence adhered to by reputable firms and shall conform to accepted

professional practices.

END OF STATEMENT OF WORK

Page 22: STATEMENT OF WORK FOR LEAKY FLOOR SLAB REPAIR, … › wp-content › uploads › sites › ... · Contracting Officer’s Representative (COR). 2.3 The Contractor shall schedule