STATEMENT OF REASONS - Blackburn with Darwen...the following works:- New entrance to Royal Blackburn...
Transcript of STATEMENT OF REASONS - Blackburn with Darwen...the following works:- New entrance to Royal Blackburn...
1
THE BOROUGH OF BLACKBURN WITH DARWEN (A6077 HASLINGDEN ROAD, BLACKBURN) SIDE ROADS ORDER 2019
THE HIGHWAYS ACT 1980
STATEMENT OF REASONS
1.0 Introduction
1.1 This is the Statement of Reasons of the Blackburn with Darwen Borough Council
(“the Council”) for making The Borough of Blackburn with Darwen (A6077 Haslingden
Road, Blackburn) Side Roads Order 2019 (the “SRO”) and referred to as the “Order”.
1.2 The SRO is being made to enable the Council to further progress with its ‘Growth Deal 3
“Pennine Gateways”’ project which will invest £13 million in transport infrastructure across
the borough between 2018 and 2021. The Pennine Gateways project will deliver key
transport infrastructure improvements at three of the main gateways into Blackburn with
Darwen off the M65 motorway at junctions 4, 5 and 6. Investment at these adjoining
gateways will extend the concept of the Hyndburn – Burnley – Pendle Growth Corridor to
the M65 Growth Corridor and will release the potential of a number of adjacent strategic
sites to attract and accelerate new development opportunities. Major transport
improvements will act as the catalyst for new housing and commercial development,
contributing to the delivery of the Council’s adopted Local Plan targets for new housing,
businesses and jobs.
1.3 This scheme is the final part of the Pennine gateways Growth Deal 3 project and will enable
the following works:-
New entrance to Royal Blackburn Hospital at Old Bank Lane / Haslingden Road –
creation of new highway
New access created on the Southern side of Haslingden Road, South West of Nursing
Home
Widening of highway on Haslingden Road between Shadsworth Road and Beehive
roundabout and proceeding towards Lions Dive
1.4 This statement sets out the following detail:
Location Order lands (section 3)
The powers to be used by the Council (section 4)
What the Council seeks to achieve (section 5)
Why the Council is making the Order (section 6)
2
The objectives and benefits (section 7)
Proposals for development (section 8)
The planning position (section 9)
Local Planning Policy, NPPF, LTP (sections 10,11,12)
Other regenerative benefits (section 13)
The Government’s position on funding (section 14)
Human Rights (section 15)
Acquisition of land (section 16)
Any obstacles relating to development (section 17)
Consultation and Responses (section 18)
Other organisations and groups (section 19)
Communications Strategy (section 20)
Related Orders (section 21)
Other information (section 22)
2 Background
2.1 The Pennine Gateways project has been named in the list within Appendix A to the 5th July
2016 Lancashire Enterprise Partnership Board report titled “Growth Deal Update” described
as follows:
“Project will deliver key transport infrastructure improvements at 3 main gateways into
Blackburn from the M65 at Junctions 4, 5 and 6 to unlock new housing and employment
growth. The proposal also supports the growth plans of Blackburn Hospital and its intention
to become a university teaching centre. The proposal complements Growth Deal
investment in Darwen and supports the LEP's strategic focus to establish the M65 as East
Lancashire's primary growth corridor. The scheme would also complement and support the
case for Highway England to upgrade M65 between JCTS 2-6.”
2.2 The wider Pennine Gateways project has been approved in principle by the Lancashire
Enterprise Partnership (LEP) for funding, and was given “Programme Entry” in Spring 2017
as part of Central Government’s Growth Deal 3 announcement. The Furthergate and North
Blackburn elements have been Fully Approved by the LEP. For more details visit the
following webpages: https://lancashirelep.co.uk/key-initiatives/transport/
2.3 It was reported that the Government has made available £1.8 billion of Growth Deal 3
funding to the 39 Local Enterprise Partnership's (LEPs) in England with most of the
available funding back loaded to 2020/21. The report presented contained a list of 24
scheme proposals which were categorised into priority 1, 2 and 3 schemes, the total value
3
of the schemes funding ask is £155.95M. The same matrix used previously to rank the
Growth Deal 1 and 2 schemes was used for the Growth Deal 3 bids to prioritise them, this
included ranking them on local strategic fit, strategic outcomes and deliverability including
within the required timescales for funding release.
2.4 The Council’s Executive Board of 8th March 2018 approved the progression of the Growth
Deal 3 Pennine Gateways project for delivery from April 2018 to March 2021. The project
consists of three infrastructure packages as follows:-
• Furthergate: Completion of the Burnley Road Link Road from Red Lion Roundabout
to Gorse Street and a new signalised Gorse Street junction. This project package is now
substantially complete and the Link Road named “Carl Fogarty Way” opened to the public
on 26th June 2019.
• North Blackburn: Brownhill Roundabout upgrade, Pleckgate Road / Ramsgreave
Drive junction improvements plus Whalley Old Road / Whitebirk Drive junction capacity
upgrade. This project package commenced on site in March 2019 with works at Brownhill
and Pleckgate now complete and Whalley Old Road at an advanced stage.
• South East Blackburn: Haslingden Road highway improvements including
widening and upgraded roundabouts at major access points (Haslingden Road, Blackburn)
plus a new link road to link Blackamoor Road with Roman Road. The Council is therefore
making two separate side roads orders and this statement deals with the SRO for
Haslingden Road. A separate side roads order is being made for the new Blackamoor Road
link road.
2.5 On 8th August 2019 the Council’s Executive Board approved the making of two side roads
orders for Blackburn South East.
3 Location of the land affected by the SRO
3.1 The land that is affected by the SRO is in the Audley and Queens Park, Blackburn Central
and Blackburn South East wards of the Borough of Blackburn with Darwen and is shown on
the SRO plan. The highway improvement works affect parts of Haslingden Road,
Blackburn and the land extends along a substantial part of Haslingden Road (at the junction
of Shadsworth Road ) in an eastern direction proceeding towards Lions Drive, Blackburn.
3.2 The land affected by the SRO is comprised of land owned by the Council, local businesses
and residents and existing highway land.
4
3.3 The SRO contains details of existing highways that adjoin the land and that are to be
improved. Other parts of the highway that will either become redundant when the
improvements are made or will disappear within the line of the new road are included in the
SRO as highways to be stopped up. No private means of access are to be stopped up
within this SRO, and hence no replacement means of access are being made.
4 What powers are being used?
4.1 The powers for making the SRO are contained within the Highways Act 1980 (“the Act”).
The SRO is made under section 14 of the Act. The Council is the ‘highways authority’ for
the purpose of the Act.
4.2 Section 14(1)(a) of the Highways Act 1980 provides for the highway authority to stop up,
divert, improve, raise, lower or otherwise alter a highway that crosses or enters the route of
the road or is or will be otherwise affected by the construction or improvement of the road,
and to construct a new highway for purposes concerned with any such alteration.
5 What the Council seeks to achieve
5.1 The A6077 Haslingden Road forms an important part of the highway network within the
Borough of Blackburn with Darwen, providing an arterial route linking Blackburn Town
Centre with the M65 motorway at Junction 5. The A6077 provides the main gateway to the
Royal Blackburn Hospital and the centralised Accident and Emergency department for the
East Lancashire NHS Trust.
5.2 The Haslingden Road corridor is the largest growth area within Blackburn with Darwen, with
a number of allocated sites for employment and housing. The Growth Deal 3 South East
Blackburn scheme is expected to:-
o Improve congestion on the Haslingden Road corridor between Royal
Blackburn Hospital and M65 Junction 5 by widening it to four lanes with
upgraded roundabouts at major access points on Haslingden Road including
Shadsworth Road and Royal Blackburn Hospital
o Enable further development of employment opportunities; and
o Support future housing growth in the Borough
5.3 One of the key objectives as set out within the Blackburn with Darwen Core Strategy is to
increase growth and new development in inner urban areas. The proposed scheme is
critical to unlocking economic and housing growth opportunities within South East
5
Blackburn. This closely aligns with all current national and local Government objectives and
was a key factor in identifying the schemes included in the Council’s submission to the
Local Growth Fund 3 call for potential projects in the Summer of 2016.
5.4 One of the key issues is that the A6077 Haslingden Road experiences severe congestion,
especially during peak hours and has not seen significant investment (other than between
the M65 Junction 5 and Lions Drive Roundabout) despite the significant growth in new
development along its length since the completion of the M65 in 1997. An extensive
analysis of traffic conditions along the A6077 Haslingden Road was reported in an Options
Assessment document prepared by Capita for the Council in September 2016.
5.5 The 2016 assessment indicates that the link sections of the A6077 Haslingden Road
corridor between the Lions Drive “Beehive” Roundabout and Royal Blackburn Hospital are
close to capacity with less than 15% in reserve. The study concludes that capacity
improvements to these route sections will need to be considered if the corridor is to
accommodate anticipated levels of traffic growth.
5.6 The modelling of existing junction layouts using recent traffic count data has indicated that
the following junctions are currently operating at, or above their theoretical capacities:
- A6077 Haslingden Road / Lions Drive
- Roman Road / Blackamoor Road; and
- A6077 Haslingden Road / Old Bank Lane
5.7 The assessment notes that the junctions already experience congestion during the peak
periods with high levels of delay and queues longer than those indicated by the modelling
results. These issues are likely to be amplified by blocking back from those junctions which
are over capacity or as a result of congestion building up from earlier time periods.
5.8 If the current highway capacity is maintained as overall travel demand increases with
natural background growth there will likely be an increase in road congestion and delay.
Alternatively, some of the new developments may not take place as investors look
elsewhere. Local businesses which are already affected by increased journey times might
be persuaded to relocate, and patients visiting Royal Blackburn Hospital could face
significant queues trying to access the facility. Local air quality will continue to worsen,
whilst residents on nearby roads will be adversely affected due to traffic taking
inappropriate alternative routes.
5.9 The scheme will directly support the development of 350 housing units, 3550 jobs and
38,535 square metres of commercial floorspace on the Haslingden Road corridor.
6
5.10 The improved highway network will be able to cope with the expected increase in traffic and
trip generation following the development of all Local Plan housing and employment site
allocations across Blackburn with Darwen.
5.11 Connectivity between the M65 and Blackburn Town Centre will be significantly enhanced.
5.12 The Council now wishes to progress with delivery of the Growth Deal 3 South East
Blackburn project package and will:
Widen the A6077 Haslingden Road between Shadsworth Road and Lions Drive
(Beehive Roundabout)
Upgrade roundabouts at major access points along Haslingden Road including
Shadsworth Road and outside the JJB Soccerdome
Build a new roundabout at Haslingden Road / Old Bank Lane which will improve the
current arrangements for general traffic and pedestrians, and act as a brand new
additional entrance to the Hospital.
5.13 There are significant benefits for the residents and businesses of Haslingden Road, in
terms of congestion, road safety and air quality. The Council has conducted a number of
information and discussion meetings in the early part of in order to inform the general public
and businesses.
5.14 Better journeys will also be achieved in terms of reliability, congestion, and time from M65
Junction 5 to Blackburn via the improved and widened main Haslingden Road.
6 Why is the Council making the Orders?
6.1 The main reason for making the SRO is to ensure that the Council can progress the Growth
Deal 3 “Pennine Gateways” project within the relevant timeframe. Works are scheduled to
commence in March 2020 in order to fulfil delivery timescales of Central Government’s
Local Growth Fund 3, which requires that the scheme be delivered by March 2021.
6.2 The Council is satisfied that:
a) It is necessary in relation to the classified roads to stop up, divert, improve, raise,
lower or otherwise alter a highway that crosses or enters the classified roads or will
be affected by the construction or improvement of the classified roads, and to
construct a new road
b) the proposed SRO will contribute to the achievement of the promotion or
improvement of the economic, social or environmental wellbeing of the area;
7
c) there are sufficient funds available to implement the SRO;
d) the SRO complies with the National Planning Policy Framework, Adopted Local
Plan Policies, the Council’s Core Strategy, the Local Transport Plan 3, and that the
SRO will help promote sustainable transport, and that planning permission for the
schemes have been approved (at the time of making the SRO);
e) there is a compelling case in the public interest as the interference with Human
Rights involved is proportionate in the interests of bringing about the improvements
that would follow from the carrying out of the highway works;
f) there is a reasonable prospect of implementation of the SRO should it be
confirmed
6.3 There are therefore no known impediments to the implementation of the scheme and the
Council considers it appropriate to make the SRO.
7 The Objectives and Benefits
7.1 As mentioned previously the main objectives of the works under the SRO are to reduce
congestion and improve journey time reliability on Haslingden Road and from the M65
Junction 5 to / from Blackburn Town Centre. The scheme aims to provide more capacity in
junctions to allow better traffic flow which aims to reduce journey times and improve
journeys for all highways users;
7.2 Provide access and opening up adjacent development sites for future employment
opportunities;
7.3 Improve accessibility for pedestrians and cyclists, and;
7.4 Improve traffic conditions on Haslingden Road with associated improvements for road
safety, congestion and air quality.
8 Proposals for the new highway development/improvement works
Design Standards
8.1 The new highway has been designed to Department of Transport standards. The
improvements to existing highways have been designed within the scope of Departmental
Standard TD 9/93 using the appropriate design speeds. In addition, structures have been
designed to the appropriate standards and advice notes.
General Layout
8
8.2 The SRO will facilitate the following changes (please refer to the SRO plan):
a) New A6077
This is the new section of A6077 creating a new roundabout at Haslingden Road
and Old Bank Lane, which will ease traffic flows.
b) Highways to be Stopped Up
Southern side of Haslingden Road (near Old Bank Lane)
c) Highways to be improved
Along parts of the length of Haslingden Road
d) Closures of private means of Access
None
e) New means of Access that is reasonably convenient
Southern side of Haslingden Road (near Old Bank Lane)
Southern side of Haslingden Road (at the roundabout adjacent to Shadswortth
Road)
Statutory Undertakers
8.3 Where Statutory Undertakers’ apparatus is affected by the scheme, arrangements will be
made to protect or divert the apparatus under the provisions of the New Roads and Street
Works Act 1991.
Pedestrian and Cyclist Facilities
8.4 Cycling infrastructure, including the use of advanced stop lines, will be implemented as part
of the scheme in accordance with Blackburn with Darwen Borough Council’s cycling
standards. Coloured surfacing will also be used in key areas to inform motorists of the
presence of cyclists. Alternative cycling facilities and routes have been provided by recent
infrastructure projects such as the Weavers Wheel, and will continue to be developed with
Royal Blackburn Hospital through the hospital site.
8.5 To encourage pedestrian use, footways will be provided on the entire length on both sides
of the improved Haslingden Road. The proposed new Royal Blackburn Hospital roundabout
and access significantly improves pedestrian movements between Old Bank Lane and
Royal Blackburn Hospital by the introduction of pedestrian refuges.
8.6 To ensure a high level of disabled access and other easy access to the site, a number of
design features will be incorporated. Dropped kerbs will be included in the design of all of
the footways and controlled crossing points will be highlighted by tactile paving.
9
Landscaping 8.7 Landscaping will be provided, as detailed within the detailed planning application (#10/19/0887)
and will be in keeping with landscaping delivered elsewhere in the Borough through major
transport schemes. Associated landscaping proposals are integral to the scheme and will both
tidy up and improve the appearance of the area and will further upgrade the area as a Major
Gateway into the Borough of Blackburn with Darwen.
Street Lighting
8.8 The street lighting design will be carried out to current standards. Lighting equipment will
incorporate latest LED technology to significantly reduce the energy demand for each unit.
Traffic Signals
8.9 There are no new traffic signal controlled junctions planned within the Haslingden Road
widening works.
Appearance
8.10 The surface course of the finished road carriageway and the footways will be completed in
a black bituminous material.
8.11 The edge of the carriageway will be completed in pre cast concrete kerbing units. There will
also be a need to complete certain lengths of kerbing in a combined kerb and drainage unit.
Back of footways will be completed in pre cast concrete edging units.
8.12 Tactile paving at pedestrian crossing facilities will be laid with coloured pre cast concrete
paving materials.
9 What is the current planning position?
9.1 Planning permission has been submitted on 16th September 2019 and is due to be
determined at the December 2019 Planning & Highways Committee (Reference number
10/19/0887) The application relates to highways improvements including road widening, a
new roundabout at junction of Old Bank Lane, new point of access into the housing
allocation site to South of Haslingden Road and demolition of associated buildings. The
proposed scheme accords with national, regional and local policies. The Development Plan
and the National Planning Policy Framework (NPPF) aim to promote increased levels of
development whilst protecting and enhancing the environment.
10
LOCAL PLANNING POLICY
10 Local Plan Part 2 (Adopted December 2015)
10.1 The Council recognises the need for future investment in transport infrastructure to
accommodate pressure from new development, and to unlock areas for development to
take place. Where this takes the form of new or improved road links, there is a need to
ensure that new development does not affect the proposed route of the road.
10.2 The scheme is aligned with new development plots identified (as shown on the Adopted
Policies Map), and aims to unlock the economic potential of the sites and encourage the
provision of new quality buildings and spaces.
10.3 There are a number of sites adjacent to the new highway improvements that have been
identified for development within the Council’s Adopted Local Plan.
Employment sites:
Site 13/6 Evolution Park, Shadsworth Road, Blackburn
Site 13/7 Plot C, Shadsworth Business Park, Blackburn
Site 13/8 Waterside Employment Site, Haslingden Road
Site 13/9 Premier Way, Walker Park, Blackburn
Housing sites:
Site 16/7 Haslingden Road Development Site (SE Blackburn)
Site 16/8 Blackamoor Road Development Site (SE Blackburn)
10.4 Details on the Local Plan can be accessed via the following weblink:
https://www.blackburn.gov.uk/planning/planningpolicies-strategies-and-guides/local-
plan-part2
Core Strategy
Blackburn with Darwen Core Strategy (2011)
10.5 The Council’s Core Strategy sets out the priorities for the future planning and development
of the Borough for the next 15 to 20 years: how much and what types of development there
should be, where it should be focused, when it is likely to take place, and how it will be
delivered.
11
10.6 The Core Strategy forms part of the statutory Local Development Plan. The Core Strategy
presents 11 Strategic Objectives. While the proposed Haslingden Road widening project
package will indirectly influence a number of these, the effects will be most pronounced
when considering the following objectives:
Improve the quality of the local environment and the Borough’s physical setting
Increase levels of demand both for existing housing stock and for new development
in inner urban area
10.7 The Core Strategy highlights that commuter traffic into and through Blackburn town centre
has historically presented a congestion problem for the Borough, particularly at major
junctions and along key corridors. It is envisaged that the proposed infrastructure
improvements would improve journey times, between Blackburn and Junction 5 of the M65
motorway.
10.8 Policy CS2 Typology of Employment Land states that the emphasis will be given to
providing the employment development in urban hub and gateway sites, with broad
locations included within the Haslingden Road and South East Blackburn area of
Blackburn. The Haslingden Road widening improvements would therefore directly
contribute to achievement of Policy CS2 by improving connections for the future gateway
sites.
10.9 Policy CS22 Accessibility Strategy states that new development should be located to
minimise the need for travel, and in that regard should be focused on either the borough’s
transport hubs or along the accessibility corridors, such as the A6077 Haslingden
Road. The dependent developments enabled through the implementation of the Haslingden
Road widening scheme will therefore be well located to take advantage of this accessibility
corridor and the potential for sustainable travel it offers.
11 National Planning Policy Framework (NPPF)
11.1 The NPPF (updated in February 2019) emphasises promoting sustainable transport in
section 9 (paras 102 to 111) of the policy. Some of the relevant paragraphs that apply to
this SRO are set out here.
11.2 Achieving sustainable development – Planning provides an economic role in ensuring that
the provision of appropriate infrastructure “will assist in building a strong, responsive and
competitive economy by ensuring that sufficient land of the right types is available in the
right places and by identifying and coordinating the provision of infrastructure” (para 8 of
the NPPF).
12
11.3 The NPPF at 108 provides that in assessing sites for development local authorities should
ensure that there are:
a) appropriate opportunities to promote sustainable transport modes can be – or
have been – taken up, given the type of development and its location;
b) safe and suitable access to the site can be achieved for all users; and
c) any significant impacts from the development on the transport network (in terms
of capacity and congestion), or on highway safety, can be cost effectively
mitigated to an acceptable degree.
11.4 Para. 110 of the NPPF provides that applications for development should:
a) give priority first to pedestrian and cycle movements, both within the scheme
and with neighbouring areas; and second – so far as possible – to facilitating
access to high quality public transport, with layouts that maximise the catchment
area for bus or other public transport services, and appropriate facilities that
encourage public transport use;
b) address the needs of people with disabilities and reduced mobility in relation to
all modes of transport;
c) create places that are safe, secure and attractive – which minimise the scope
for conflicts between pedestrians, cyclists and vehicles, avoid unnecessary
street clutter, and respond to local character and design standards;
d) allow for the efficient delivery of goods, and access by service and emergency
vehicles; and
e) be designed to enable charging of plug-in and other ultra-low emission vehicles
in safe, accessible and convenient locations.
11.5 The NPPF at paragraph 104 sets out that planning policies should:
a) support an appropriate mix of uses across an area, and within larger scale sites,
to minimise the number and length of journeys needed for employment,
shopping, leisure, education and other activities;
b) be prepared with the active involvement of local highways authorities, other
transport infrastructure providers and operators and neighbouring councils, so
that strategies and investments for supporting sustainable transport and
development patterns are aligned;
c) identify and protect, where there is robust evidence, sites and routes which
could be critical in developing infrastructure to widen transport choice and
realise opportunities for large scale development;
13
d) provide for high quality walking and cycling networks and supporting facilities
such as cycle parking (drawing on Local Cycling and Walking Infrastructure
Plans);
e) provide for any large scale transport facilities that need to be located in the
area, and the infrastructure and wider development required to support their
operation, expansion and contribution to the wider economy. In doing so they
should take into account whether such development is likely to be a nationally
significant infrastructure project and any relevant national policy statements;
and
f) recognise the importance of maintaining a national network of general aviation
airfields, and their need to adapt and change over time – taking into account
their economic value in serving business, leisure, training and emergency
service needs, and the Government’s General Aviation Strategy
12.0 Local Transport Plan
Blackburn with Darwen Local Transport Plan 3 (2011-2021)
12.1 Blackburn with Darwen Borough Council’s Third Local Transport Plan (“LTP3”) is a long
term strategic document covering the period 2011-2021, and is the key mechanism for
articulating and delivering transport policy at a local level. The plan highlights a number of
key issues within the borough to be addressed over the lifespan of the plan, including:
The borough’s young population and its relationship to the growth of car use and road
accidents;
Peak time congestion and traffic levels;
The impact on and the effects of the changing climate;
Chronic health issues;
Poor localised air quality and intrusive noise;
Car dependence;
The effects of long standing deprivation;
The ongoing requirement to generate jobs, improve wage and skill levels; and
The need to create sustainable communities through economic restructuring and
regeneration.
a) The proposed Haslingden Road widening will meet four goals described within the
LTP3, to:
14
Support the Economy;
Tackle Climate Change;
Promote Equality of Opportunity; and
Promote quality of life, health and the natural environment.
b) In ‘supporting the economy’, the scheme will achieve all the associated objectives:
reducing congestion and delay; improving the condition and attractiveness of the
transport infrastructure; ensuring good accessibility for the new developments; working
with partners to develop economic growth and bring forward new development, and
increasing accessibility to employment.
c) The LTP3 priority is to “Improve access to areas of regeneration and economic
growth”. Part of achieving this comes through the “greater coordination of transport
and land use planning”, ensuring that the transport infrastructure is capable of fully
supporting the expected growth in Blackburn with Darwen both in the current year and
the future.
d) The LTP3 Priority is to: “Reduce carbon emissions; reduced delay and fuel
consumption should improve emissions from vehicles, which should result in a
corresponding improvement in air quality. Improved air quality brings better health; an
improved environment and encourages physical activity by creating more walkable,
enjoyable public space.”
e) The project would improve journey times between Blackburn and a major transport
gateway Junction 5 of the M65, whilst opening land for new employment, leisure,
residential or mix-use development along the route of the new link road. In doing so,
the scheme is aligned with the LTP3 Priority to ‘Improve access to education and
employment’.
f) Through this analysis of key documents and policy, it is clear that there is a strong
evidence base for the implementation of the Haslingden Road widening project
package ; the proposed scheme is aligned with all the relevant local, regional and
national policy, and will further the strategic aims for the Borough, County and Country.
13 Other Regenerative benefits
13.1 The scheme will directly support the development of 350 housing units, 3550 jobs and
38,535 square metres of commercial floorspace on the Haslingden Road corridor.
15
14 Government position on funding
14.1 The Lancashire Enterprise Partnership, at its 31st January 2017 Board meeting, gave an
update on the Government’s Growth Deal funding bid, at £69.8 million being one of the
largest in the country. The Pennine Gateways project was named within the list within
Appendix A to the report, and as such the Council can demonstrate that the funding to
progress this scheme is in place, is available and has been confirmed.
14.2 A further financial breakdown was included within the Council’s 8th August 2019 Executive
Board report, extracted as follows:
2019/20 2020/21 2021/22 Total
Local Transport Plan £0.5m £1.01m £1m £2.51m
Lancashire Enterprise Partnership
£8.89m £8.89m
Total £0.5m £9.9m £1m £11.4m
15 Human Rights
15.1 Before deciding to make the SRO, the Council carefully considered the Human Rights Act
1998 and in particular Article 1 of the First Protocol.
15.2 Article 1 of the First Protocol provides that “ Every natural or legal person is entitled to the
peaceful enjoyment of his possessions. No one shall be deprived of his possessions except
in the public interest and subject to the conditions provided for by law and by the general
principles of international law.
It should be noted that the Council is in the process of acquiring all property interests,
commercial or residential, for the road scheme and therefore no person will be deprived of
his/her property.
15.3 The Council decided that there is a compelling case in the public interest for making the
SRO because the scheme provides numerous regenerative benefits as set out at section 4
of this Statement. The scheme proposes to address the Council’s wider planning and
transport requirements and makes a significant contribution to improving access across the
Borough.
15.4 The Council is aware that there will be some interference with rights, but is satisfied that
this is necessary to achieve the objectives and is also within proportion, especially as the
requirements under the Act are satisfied and there is a compelling case in favour of the
proposal for the benefit of the Borough as a whole.
16
16 Acquisition of land
16.1 As regards the land directly affected by the SRO, it is not all owned by the Council at the
time of writing this Statement, however the Council is seeking to acquire the parcels of land
required by mutual agreement or by agreeing heads of terms to purchase with respective
landowners. A compulsory purchase order is therefore not considered necessary for the
works to be carried out under the SRO.
17 What obstacles are there to the development?
17.1 The Council is satisfied that there are no known obstacles to development because of the
following:
17.2 Full planning application has been submitted for the delivery of the scheme (Planning
application reference 10/19/0887) which is scheduled to be determined at the Council’s
Planning and Highways Committee in December 2019
17.3 Full funding is available to carry out the works under the SRO, which effectively has
“Programme Entry” from the Lancashire Enterprise Partnership.
18 Consultation and responses
18.1 The Council’s website has hosted a dedicated information portal for the project at:
https://www.blackburn.gov.uk/transport-and-travel/transport-and-streets-policies-and-
strategies/transport-infrastructure-growth
18.2 The LEP has published information on the Growth Deal 3 project via:
https://lancashirelep.co.uk/key-initiatives/transport/
18.3 Two exhibition events have taken place in relation to the South East Blackburn project
package at the following times and locations:
Venue: Innovation Centre, Evolution Park, Haslingden Road, BB1 2FD on Tuesday 29th
January 2019 4pm to 7pm
Venue: St James’ Church Hall, Stopes Brow, Lower Darwen, Bb3 0QP on Thursday 7th
February 2019 4pm to 7pm
17
18.4 These events were drop-ins and were designed for residents and businesses to air views
on the project, provide comments, and to query points of detail on the proposed plans. The
events were well attended with approximately 300 people were present across the two
evenings.
18.5 The Council’s response to comments made by the general public at the two events have
been published via the following “you said, we did” style document at:
https://www.blackburn.gov.uk/sites/default/files/media/pdfs/TIGD-GD3-South-East-
Blackburn-public-consultation-responses-published.pdf
18.6 Further statutory consultations will follow on in relation to the applications for planning
permission.
19. Other Organisations and Groups
Letters of support have been received from Countryside Properties Limited, Chubb
Systems, The East Lancashire NHS Trust, Places for People and the Together Housing
Association Limted, all of which express strong support for the scheme. Further support for
the scheme is expected from the East Lancashire Chamber of Commerce and Haslingden
Road businesses. Local businesses recognise the importance of creating an environment
for business to grow leading to improved prospects for the borough and its residents.
20 Communications Strategy
A communications strategy has been prepared by the Council, which is targeted towards
general public, residents and businesses. The communications strategy states that the
internal and external stakeholders will be regularly updated through a quarterly online
newsletter which would provide updates on project delivery, disruption and timescales for
completion. An e-newsletter will also be prepared for circulation to local residents to
explain the main issues raised, the scope for these to be addressed and set out new stages
for delivery of the project. A notification letter would be dropped to adjacent properties of
works commencing. Ongoing information will be provided to MPs and Local Councillors.
All interested parties will be able to access the information on the project via the Council’s
website.
21 Related Orders
21.1 There are no related orders. In order to give effect to the proposal, it may, however, be
necessary for the Council to make Traffic Regulation Orders and these will be made
18
subsequent to the SRO confirmation, if required. There may also be a need for temporary
Traffic Regulation Orders to re-route traffic whilst works are being carried out, and these will
be made subsequent to the SRO confirmation.
21.2 As referred to in the statement, a separate unrelated side roads order is made relating to
the new link road at Blackamoor Road, Blackburn
22 Other Information
22.1 If a public inquiry is to be held in relation to the SRO, this statement is not intended to be
the Council's Statement of Case for the purposes of any of the Rules relating to inquiries.
22.2 The documentation in the attached list (which gives more detail) is available for inspection
at Blackburn Town Hall, King William Street, Blackburn during normal office hours. Those
documents may be added to or revised in due course if there is a public inquiry. A copy of
this Statement is available for inspection on the Council’s website and information portal at
https://www.blackburn.gov.uk/transport-and-travel/transport-and-streets-policies-and-
strategies/transport-infrastructure-growth
22.3 Persons requiring further information regarding the SRO should contact the following
officer, who will try to help you:
Mr. Mike Cliffe (Strategic Transport Manager) – 01254 585310
19
DOCUMENT LIST
1. Side Roads Order
2. Side Roads Order Map
3. Landscaping plans/General Arrangement Drawings
4. Report to Executive Board 8th August 2018
5. Report to Executive Board 8th August 2019