State Route 309 (Elida Rd.) Safety Improvement Project

25
State Route 309 (Elida Rd.) Safety Improvement Project

Transcript of State Route 309 (Elida Rd.) Safety Improvement Project

Page 1: State Route 309 (Elida Rd.) Safety Improvement Project

State Route 309 (Elida Rd.) Safety Improvement Project

Page 2: State Route 309 (Elida Rd.) Safety Improvement Project

Why is ODOT proposing improvements to SR309?

� In 2002 ODOT began prioritizing problematic corridors statewide that either had safety and/or congestion concerns

� In Allen County, the priorities were:– Elida Rd. (SR309 west)– Bellefontaine Ave. (SR117/SR309 east)– Allentown Rd. (SR81 west)

Page 3: State Route 309 (Elida Rd.) Safety Improvement Project

Why is ODOT proposing improvements to SR309?

� ODOT is dedicated to improving the safety and efficiency of the state highway system for the benefit of the motoring public

� ODOT is sponsoring this project since a majority of the corridor is located outside of the City of Lima Corporation limits

Page 4: State Route 309 (Elida Rd.) Safety Improvement Project

Project Development Process (PDP)

Page 5: State Route 309 (Elida Rd.) Safety Improvement Project

Study Area

� Study limits for project are from Eastown Rd. to Robb Ave.

� Limits were established based upon concentration of accidents as well as logical beginning and ending points

Page 6: State Route 309 (Elida Rd.) Safety Improvement Project

Facts about the corridor

� Numerous accidents (typically rear end and angle types) are occurring throughout the corridor

� Corridor crash rate of 7.63 Accidents per Million vehicle miles traveled (MVM) compares to a statewide rate of 3.18 (MVM)

� Existing traffic volumes are approx. 21,570 Average Daily Traffic (ADT)

� Design year traffic (2026) is approx. 27,230 ADT� Nearly 100% of adjacent land is currently zoned

commercial

Page 7: State Route 309 (Elida Rd.) Safety Improvement Project

Purpose of Improvements

� Provide a safer and more efficient corridor that balances the needs of local access with the through movements.

Page 8: State Route 309 (Elida Rd.) Safety Improvement Project

Need for Improvements

� Ranked in the top 200 statewide in high accident locations as identified through ODOT’s Highway Safety Program (HSP)– This corridor, which is currently ranked 145th has

ranked as high as 2nd in the state

� Rear end and angle accidents are frequent throughout the corridor, specifically at high volume driveways

Page 9: State Route 309 (Elida Rd.) Safety Improvement Project

Need for Improvements (Cont.)

� Angle type accidents associated with driveways are numerous due to the excessive number of existing driveways accessing SR309

– There are currently over 110 driveways accessing SR309 between Robb Ave. and Eastown Rd.

– There are approximately 64 driveways per mile; ideal number is less than 32 driveways per mile

� Some driveways are currently located too close to existing signalized intersections

Page 10: State Route 309 (Elida Rd.) Safety Improvement Project

Observations

� Access management techniques must be employed

� Left turn movements must be reduced or eliminated due to the high number of potential conflicts throughout the corridor

� Existing two way left turn lane is losing it’s functionality

Page 11: State Route 309 (Elida Rd.) Safety Improvement Project

What is Access Management?

� … a more efficient way of dealing with problems associated with traffic congestion and safety caused by motorists turning at driveways and intersections

� Examples:– Elimination of driveways– Relocation of existing driveways– Prohibiting left turn movements to and from

driveways

Page 12: State Route 309 (Elida Rd.) Safety Improvement Project

Why Access Management?

� Managing access points helps in maintaining the efficiency of the through route

� Less conflict points create a safer overall corridor

Page 13: State Route 309 (Elida Rd.) Safety Improvement Project

General Recommendations

� Construct a six-inch raised curb median to prohibit left turning movements in and out of driveways along SR 309 from Eastown Rd. to Robb Ave.

Page 14: State Route 309 (Elida Rd.) Safety Improvement Project

Example of Raised Curb Median

Page 15: State Route 309 (Elida Rd.) Safety Improvement Project

General Recommendations

� Construct service roads where appropriate– Extend Arthur Ave. to American Ave.– Extend American Ave. to the east from Cable Rd.– Construct new service Rd. next to former Bobick’s

Golf Headquarters

Page 16: State Route 309 (Elida Rd.) Safety Improvement Project

General Recommendations

� Upgrade or install new traffic signals at the following locations:– Eastown Rd.– American Ave.– Hartzler Rd.– New service Rd. next to former Bobick’s Golf

headquarters– Cable Rd.– Arthur Ave.– Robb Ave.

Page 17: State Route 309 (Elida Rd.) Safety Improvement Project

General Recommendations

� Create the opportunity to perform U-turns at appropriately spaced locations throughout the corridor in order to accommodate both east and west SR309 access into businesses

Page 18: State Route 309 (Elida Rd.) Safety Improvement Project

General Recommendations

� U-turn locations are proposed at:– Aldi’s/IHOP (unsignalized) (west to east only)– American Ave.– Hartzler Rd.– New service Rd. near former Bobick’s Golf Headquarters– Arthur Ave.– Robb Ave.

� No U-turns will be allowed at the following intersections:

– Eastown Rd.– Cable Rd.

Page 19: State Route 309 (Elida Rd.) Safety Improvement Project

General Recommendations

� Add Right turn lanes along SR309 at Cable Rd.

� Widen Hartzler Rd. to 3 lanes– North approach into Lima Mall will be realigned

across from Hartzler Rd.

Page 20: State Route 309 (Elida Rd.) Safety Improvement Project

General Recommendations

� Driveways near intersections or U-turns will be relocated

� Eliminate/reduce the number of driveways for individual properties

Page 21: State Route 309 (Elida Rd.) Safety Improvement Project

General Recommendations

� Improve aesthetics of corridor� Concepts under consideration

– Decorative pattern in raised curb median– Decorative mast arms for signals– Decorative lighting

Page 22: State Route 309 (Elida Rd.) Safety Improvement Project

Major Steps in Property Major Steps in Property Acquisition ProcessAcquisition Process

Valuation(Appraisal)

Acquisition Discussions(Negotiations)

Transfer of Title(Closing)

Page 23: State Route 309 (Elida Rd.) Safety Improvement Project

Maintaining Traffic During Construction

� Through traffic will be maintained at all times during construction

� Local access to adjacent properties will be maintained at all times

Page 24: State Route 309 (Elida Rd.) Safety Improvement Project

Funding

� Project estimates– Right of Way $3.5 million– Construction $6.5 million

� Project will be funded utilizing both state and federal funds

� A portion of the federal funds being used will come from a $5 million earmark from Sen. DeWine

� Remaining funding comes from ODOT Safety program funds designated towards projects to reduce accidents

Page 25: State Route 309 (Elida Rd.) Safety Improvement Project

TimeframesTimeframes

�� TonightTonight –– Recommending Recommending preferred alternative and preferred alternative and receiving comments for next 2 receiving comments for next 2 weeksweeks

�� Nov, 2006Nov, 2006 –– Begin Incorporating Begin Incorporating comments into design and right comments into design and right of way plansof way plans

�� Fall 2007Fall 2007 –– Begin property Begin property acquisitionacquisition

�� Spring 2010Spring 2010––Begin ConstructionBegin Construction�� Fall 2010Fall 2010 –– End ConstructionEnd Construction