State of the Art of Project Management in 2010
Russell D. ArchibaldFellow PMI and APM/IPMA, PhD (Hon), MSc, PMP
PMI Milwaukee/Southeast Wisconsin ChapterProfessional Development DayMilwaukee, WI October 19, 2005
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
2
Where I’m Coming From 1959: in charge of PERT on POLARIS
solid rocket, Aerojet General PMI Member No. 6, APM (UK) No. 3 Clients in 14 countries on 4
continents; books in 6 languages Global perspective across a number
of PM application areas/industries
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
3
Objective of My Presentation
To convey a comprehensive picture of the worldwide state of the art
in project management 5 years from now
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
4
The World of Project Management: Six Players
1. Buyers (owners of projects)2. Sellers (contractors or developers of
projects)3. Consultants/trainers in PM 4. PM software developers and
vendors5. Universities6. Professional associations
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
5
Six Areas of Prediction: 2010
1. Strategic Project Management2. Specialization by Project Category3. Total Project Life-Cycle
Management4. PM Systems, Tools and Practices 5. PM Discipline and Individuals6. The “Profession” of PM
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
6
1. Strategic Project Management
2010: Best organizations will integrate
strategic management, project management, and operations management through project portfolio management
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
7
Project Portfolio Management Portfolios link corporate strategy
with project management ‘Portfolio steering group’ holds
responsibility Must implement an integrated
project portfolio management process
Various types of project portfolios
StrategicObjective
1
OperationalStrategy 1.3
OperationalStrategy 1.2
OperationalStrategy 1.1
Project 1.1.3
Project 1.1.2
Project 1.1.1
Project 1.2.2
Project 1.2.1
Project 1.3.3
Project 1.3.2
Project 1.3.1
Program 1.1
Project Portfolio for Strategic Objective 1
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
9
2. Specialization by Project Category
2010: Widespread use of systematic approach
to project categorization and classification
Improvements in Strategic PM Operational PM PM software PM consulting, education, and training
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
10
Systematic Approach Analyze purposes and uses
of project categorization
Systematize and prioritize them
Relate them to project characteristics, attributes, and criteria: Categories
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
11
The Purposes/Methods Matrix for Project Categorization/PC
One axis: Purposes and Uses of PC Second axis: Methods of
categorizing and classifying projects within the categories
Enter codes to indicate which methods serve which purpose
Methods >Purposes v
Market Share & Strat. Intent
Project End Result
Development or
Deployment
Other
1. Strategic
2. Operational
3. PM Education
4. PM People Development
Indicate usefulness with codesIndicate usefulness with codes
Project Categorization Purposes/Methods Matrix
Source: Archibald 2005, Lille, France
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
13
Categories Based on End Results
1. Aerospace/Defense
2. Business & Organizational Change
3. Communication Systems
4. Events5. Facilities
6. Information Systems7. International
Development8. Media &
Entertainment9. Product/Service
Development10. Research & Dev.
Source: Archibald 2003, p 35-36
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
14
Hierarchical and Multi-Dimensional
Category level1 2 3 4Major category
Sub-category 2Sub-category 3
Sub-category 4
Similar to P/WBS approach
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
15
Example:Category 5. Facilities Projects
1. Facility decommissioning
2. Facility demolition
3. Facility maintenance & modification
4. Facility design/procure/construct1.Civil 2.Energy 3.Environmental 4.Industrial 5.Commercial 6.Residential 7.Ships 8.Other:
5. Other: ?
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
16
Classifying Within Sub-Categories: Many possible Criteria Project size Major & minor projects Project complexity External or internal customer Degree of customer involvement Levels of risk, who takes responsibility Stand-alone versus create supporting
infrastructure Standard versus transitional Mega projects: not categorizable Other: ? (See Crawford, Hobbs and Turner, 2002
and 2004)
Simple Example: Category/Class Matrix
Classifying Projectswithin
Project Categories & Sub-Categories
Project Size: $M
Major Project: Yes
or No
Complex-ity:
1 to 10
Customer:
Internal or
External
Customer
Involvement: Hi or Low
Risk Level: 1 to 10
Category Level 2 Level 3
5. Physical Facilities
5.1 Decommissioning
5.2 Demolition
5.3 Maintenance & Modification
5.4 Design/proc/const
5.4.1 Civil
5.4.2 Energy
5.4.3 Environmental
5.4.4 Industrial
5.4.5 Commercial
5.4.6 Residential
5.4.7 Ships
5.4.8 Other
5.5 Other
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
18
Project Categorization Enables Improvements in:
How project buyers and sellers: Strategically select and prioritize projects Operationally plan and execute their projects:
Individually Within programs, and Within project portfolios
Determine their true maturity in PM Educate and train their PM people Develop and manage PM career paths
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
19
Organizational Capabilities & Maturity in PM Many PM Maturity Models
PMI’s OPM3 (For a critical review see http://www.pmforum.org/pmwt04/viewpoints04-910more.htm )
PRINCE2 in UK (http://www.prince2.org.uk/ ) Many others
Purposes of these models: Assess current capabilities Educate Improve
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
20
UK Office of Gov’t Commerce-OGC: Prince2 plus others Visit www.ogc.gov.uk “Successful Delivery Toolkit” CD and
other valuable documents available free “OGC works with government to
improve procurement and project/programme management. We also work with suppliers to make the government marketplace more efficient and attractive to business.”
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
21
Japanese Approach Japan’s P2M (Project & Program
Management)
http://www.pmcc.or.jp/english/p2m.html
Integrated program management Jointly developed by industry and
government To date no related maturity model
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
22
Maturity of Project Management Within a Category
Different perspective from total organizational PM maturity
Maturity must be viewed by project class or category
The most mature categories are: Aerospace/Defense Facilities
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
23
PM Maturity by Project Categories
Research in Brazil: http://www.maturityresearch.com/
Applying the Prado/MMGP maturity model to project categories shown previously.
Brazil: 180 million people, strong high-technology industries, 17 PMI chapters
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
24
PM Maturity Models2010
At least 2 major models in wide use: PMI’s OPM3, OGC/UK’s PMM
3rd major model will appear: Japan’s P2M
Translations of these will appear in 8 or 10 languages
Adaptations will emerge within specific areas of PM application and project categories
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
25
Project Categorization Enables Improvements in:(Cont’d)
PM software applications
Consulting and training in PM services
University offerings in PM
PM Professional associations’ services
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
26
3. Total Project Life-Cycle Management
2010: Best PM practitioners (project
buyers/owners) will include concept phase plus achievement of project benefits as part of the project manager responsibilities
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
27
Total Project Life-Cycle Management Early years: Focus on planning &
executing phases 2010: Total life cycle management:
Including early conceptual & ‘after’ phases
Portfolio PM links corporate strategy with conceptual life-cycle phase
Include realization of project benefits as part of PM discipline
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
28
Realizing Project Benefits Organizational change often required to
achieve full benefits from completing a specific project
“Business Change Manager” is sometimes appointed in 2005
Achieving project benefits will often be included in project life-cycle in 2010
Emphasizes importance of Project Sponsor role
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
29
Example: Total Life-Cycle Management
New book coming out by Paul Dinsmore and Terry Cooke-Davies
"Right Projects Done Right" “Takes a broad holistic view of
projects -- from the project idea all the way through to generation of the benefits proposed by the project”
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
30
Project Life-Cycle Models Predictive
Adaptive, repetitive: Agile PM
Different models for different project categories
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
31
Project Life-Cycle Models Many life-cycle models are in use They portray a project as an overall
process or system Their purposes include:
To enable all to understand overall process To capture best experience, enable
improvement To relate roles, responsibilities, systems and
tools to all elements of the project
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
32
Improving the PLCMS
1. Document the integrated project life-cycle model
2. Document & describe the PLCMS3. Re-engineer the integrated process
Apply systems thinking: TOC
4. Implement the improvements5. Repeat these steps as required
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
33
Applying Systems Thinking to Project Management
2010 Catalogs will exist of life-cycle
models for each major project category
Wider application of systems thinking and TOC to project life-cycle models will produce continual improvements
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
34
4. PM Systems, Tools and Practices
2010 Systems fully integrated with corporate
IS PM software more specialized to fit
project categories or types Web-enabled PM used by all; virtual
teams commonplace Wireless everywhere PM software vendors will begin
consolidation phase of a mature industry
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
35
Project Management Software
2010 Little change in overall picture (see
next slide) Probably (?) some consolidation PM software a mature industry?
Software CategoryPMI PM Software Survey 1999
PMBOK® Guide Knowledge Areas
Suites (36) All
Process/Scope Management (19)
Integration Management
Schedule Management (43)
Time Management
Cost Management (27) Cost Management
Resource Management (27)
Human Resources Management
Risk Management and Assessment (15)
Risk Management
Communications Mgt (17) Subcategories: Graphics Add-ons (21) Timesheets (25) Web Publ/Organ’rs (15)
Communications Management
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
37
One or More Corporate PM Systems?
2010 Best Practice: One integrated
corporate system Able to link different systems when
customer or partner demands other systems
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
38
PM and Operations Management
2010 Best practice: Project and
Operations management will be integrated through corporate-wide Project/Operations Planning and Control System
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
39
Integrated Operations Planning and Control
Source: Archibald 2003, p 197
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
40
Critical Chain vs Critical Path Resource buffers quantified in CC Range estimates of duration in CC Some claim great benefits from CC Others say CPM can be used in
same way2010
Critical chain still not widely applied
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
41
Russian Resource Critical Path/RPC Considers all constraints Calculates resource constrained
activity float (similar to CC buffers) Uses range estimates for duration
and resources Produces success probabilities for
risk management(Liberzon/Archibald 2003)
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
42
5. PM Discipline and Individuals
2010 Certification will be
Based more on proven capabilities Sharply focused on specific areas of application
and/or project types Awarded at 3 or 4 levels
Demonstrated PM capabilities (not necessarily certification) will be a prerequisite for senior management positions
Governmental licensing in PM will not exist
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
43
PM Certification Programs PMI: 2 levels: PMP & CAPM 119,978 PMPs on June 30, 2005 Heavily based on knowledge of PMBOK Critics say it is:
Not based enough on capability Not sufficiently application oriented Not certification of project managers per
se Only oriented to managing one project
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
44
PMI Certification PMBOK now available in 8
languages Moving toward
Multi-project program and portfolio management
Application specific certification PMI College of Scheduling now
working on a potential Scheduling Certification Program
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
45
IPMA Certification: 4 Levels A: Certificated Programme
Director/CPD B: Certificated Project Manager/CPM C: Registered Project Management
Professional/RPMP D: Project Management
Fachman/Fachfrau/PMF
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
46
APM (UK) Certification Currently 3 levels:
Certified Project Manager (IPMA level B) Practitioner Qualification (IPMA level C) APMP (IPMA level D)
APM Group accredits trainers for OGChttp://www.apmgroup.co.uk/
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
47
Other Certification Programs Australian Institute of PM/IAPM:
3 levels Based on National Competency Standards for
PM American Society for Advancement of
PM/asapm (http://www.asapm.org/ ): Developing 4 level IPMA certification program
NASA: 4 level internal certification http://www.appl.nasa.gov/businessunits/career/pmdp/index.html
Others:
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
48
6. The ‘Profession’ of Project Management
2010 PM will merge into general
management, become required competency for top executives, similar to financial management competency
Many will still say it is a profession but no governmental licensing will exist
PM will be widely known and used by managers at all levels
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
49
Chief Projects Officer/CPO
2010 Perhaps 20% of companies will have
a CPO Does for PM what the CFO does for
financial management Directs the Project Management
Office/PMO At corporate or operating division levels
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
50
Licensing of People in PM True profession requires official
licensing No country, state or province
presently licenses project managers or specialists
PM is a management discipline, not a true profession
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
51
The ‘Profession’ of PM Discussions continue around the
world: Management discipline or ‘profession’?
Experienced practitioners: “PM is a core competency for every
executive and professional” “PM is a sub set of general management;
little probability that it will become a ‘legally based profession’
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
52
ReferencesArchibald, Russell D., “State of the Art of Project
Management: 2005,” PMI Milwaukee/Southeast Wisconsin Chapter Professional Development Day, Milwaukee, WI October 29, 2005 (download at http://www.pmi-milwaukee.org/ )
Ibid, “Purposed and Methods of Practical Project Categorization,” 5th International PM Workshop, Institut Supérieur de Gestion Industrielle, Groupe ESC Lille, France, 22-26 August 2005.
Ibid, “A Global System for Categorizing Projects,” 2nd Latin American Forum—PM in Government, Brasilia, Brazil, 21-22 September, 2004
Ibid, “Managing High-Technology Programs and Projects,” 2003. NY: Wiley
Liberzon, Vladimir, & Russell D. Archibald, “From Russia with Love”, PMI Congress, The Hague, 2003
October 19, 2005 PMI Milwakee/SE Wisconsin Chapter
53
Thank you for listening!
Questions? Rebuttals? Arguments?
[email protected] references atwww.russarchibald.com
Go to ‘Author>recent papers’