Starter Strip Starter Strip comes in lengths of 10’ Starter strip is installed around the exterior...

8
Estimate Starter Strip for Vinyl Siding

Transcript of Starter Strip Starter Strip comes in lengths of 10’ Starter strip is installed around the exterior...

Page 1: Starter Strip Starter Strip comes in lengths of 10’ Starter strip is installed around the exterior perimeter of the building The starter strip is nailed.

Estimate Starter Strip for Vinyl Siding

Page 2: Starter Strip Starter Strip comes in lengths of 10’ Starter strip is installed around the exterior perimeter of the building The starter strip is nailed.

Starter Strip• Starter Strip comes in lengths of 10’• Starter strip is installed around the exterior perimeter of

the building• The starter strip is nailed every 12” to 16” apart with

roofing nails • Perimeter is the linear measure of the boundaries of a

figure of structure• The perimeter of a square is the total length of its four

sides P = 4s• To find perimeter of a rectangle use the formula P= 2(w +l)

Page 3: Starter Strip Starter Strip comes in lengths of 10’ Starter strip is installed around the exterior perimeter of the building The starter strip is nailed.
Page 4: Starter Strip Starter Strip comes in lengths of 10’ Starter strip is installed around the exterior perimeter of the building The starter strip is nailed.

Estimating perimeter

Page 5: Starter Strip Starter Strip comes in lengths of 10’ Starter strip is installed around the exterior perimeter of the building The starter strip is nailed.

Estimating PerimeterProblem #1

40’

20’

10’

8’

30’

Page 6: Starter Strip Starter Strip comes in lengths of 10’ Starter strip is installed around the exterior perimeter of the building The starter strip is nailed.

Estimating PerimeterProblem #2

40’

20’

12’

8’

18’

3’

7’

7’

Page 7: Starter Strip Starter Strip comes in lengths of 10’ Starter strip is installed around the exterior perimeter of the building The starter strip is nailed.

WORKSHEET FORESTIMATING STARTER STRIP FOR VINYL SIDING

Practice problem #1 Side #1Side #2 Side #3Side #4Side #5 Side #6 _________________TOTAL LFTOTAL LF/10 = pieces of starter strip needed (round up

to whole number)# of starter strip =

Page 8: Starter Strip Starter Strip comes in lengths of 10’ Starter strip is installed around the exterior perimeter of the building The starter strip is nailed.

Practice problem #2

Side #1 Side #7Side #2 Side #8Side #3 Side #9Side #4 Side #10Side #5 Side #11Side #6 Side #12