start and break slide
-
Upload
daphne-craig -
Category
Documents
-
view
24 -
download
0
description
Transcript of start and break slide
Kick-Off-MeetingApril 1st – 3rd 2009
Large Conference Hall of Hotel Riga
Riga/ Latvia
host:
Baltic Sea Region Programme 2007-2013 project
“Baltic Challenges and Chances for local and
regional development generated by Climate Change“
BalticClimate
April 2nd 2009 • Dennis Ehm, ARL 2
Kick-Off-Meeting, April 1st – 3rd 2009, Riga
„Progress Reports“
„Progress Reports“
On project level and
on Project Partner level
Dennis Ehm, ARL
April 2nd 2009 • Dennis Ehm, ARL 3
Kick-Off-Meeting, April 1st – 3rd 2009, Riga
„Progress reports“
What is a „Progress Report“?
A progress report documents e.g.
• the activities carried out, • milestones achieved, • outputs produced,• expenditures occurred,• expenditures controlled, and• budget used and remaining
in a pre-defined period of time passed by.
April 2nd 2009 • Dennis Ehm, ARL 4
Kick-Off-Meeting, April 1st – 3rd 2009, Riga
„Progress reports“
Who to whom?
A) on „project level“
LP JTS/ IB
B) on „partner level“
PP LP (or WP coordinator)
C) extra, informal: Subcontractor PP/LP
April 2nd 2009 • Dennis Ehm, ARL 5
Kick-Off-Meeting, April 1st – 3rd 2009, Riga
„Progress reports“
Why a Progress Report to the JTS/IB?
•To monitor the progress of planned project activities•Base for further activities
•As justification and base for the bi-annual payment of co-financing from ERDF to the project
April 2nd 2009 • Dennis Ehm, ARL 6
Kick-Off-Meeting, April 1st – 3rd 2009, Riga
„Progress reports“
Reporting periods and due date on project level
Reports are due 3 months after end of each reporting period.
Exactly defined in the Grant Contract:
April 2nd 2009 • Dennis Ehm, ARL 7
Kick-Off-Meeting, April 1st – 3rd 2009, Riga
„Progress reports“
Subjects of the progress reports
Every Progress Report:
• activities = Activity progress Report (AR)
• finances = Financial Report (FR)
remark: so far only a draft version of the progress report exists, thus amendments are still possible
April 2nd 2009 • Dennis Ehm, ARL 8
Kick-Off-Meeting, April 1st – 3rd 2009, Riga
„Progress reports“
Extra contents of the 1st progress report
• Partnership Agreement signed by all Project Partners
• Outputs defined, their indicators and their targets
• communication plan (due already July 31st 2009)
• preparation activities and expenditures
(remark: so far only a draft version of the progress report exists, thus amendments are still possible)
April 2nd 2009 • Dennis Ehm, ARL 9
Kick-Off-Meeting, April 1st – 3rd 2009, Riga
„Progress reports“
Extra content of the 4th progress report
Mid-term self evaluation
• Required but no formal structure set by EU
• Process, structure, indicators must be planned and defined by the project
• separate attachment to the 4th progress report
April 2nd 2009 • Dennis Ehm, ARL 10
Kick-Off-Meeting, April 1st – 3rd 2009, Riga
„Progress reports“
Content of the Activity Report (AR) to JTS/IB
probably (so far only a draft version of the progress report exists, thus
amendments are still possible):
• project summary (for official website)
• achievements
• overview of the work plan‘s progress
• progress per WP (activities and milestones)
• main outputs
• marketing information and material
April 2nd 2009 • Dennis Ehm, ARL 11
Kick-Off-Meeting, April 1st – 3rd 2009, Riga
„Progress reports“
Content of the Financial Report (FR) to JTS/IB
probably (so far only a draft version of the progress report exists, thus amendments are still possible):
• Eligible expenditures occurred per WP/ per BL
• specification of external services, equipment and investments
• total expenditures per Project Partner
• interests/ revenues (if applicable)
• complementary activities
• First Level Control (FLC) confirmation on project level
April 2nd 2009 • Dennis Ehm, ARL 12
Kick-Off-Meeting, April 1st – 3rd 2009, Riga
„Progress reports“
Progress reports on „partner level“
PP LP (or to WP coordinator)
• activities = Activity progress Report (AR)• in more detail than on project level
• selected topics for report on project level
• finances = Financial Report (FR)• expenditures basing on partner budget• First Level Control (FLC) on partner level
April 2nd 2009 • Dennis Ehm, ARL 13
Kick-Off-Meeting, April 1st – 3rd 2009, Riga
„Progress reports“
Timing/ Schedule
Allow one month for the LP
• to summarize single reports,
• to possibly ask for additional information and documents from single PPs and
• to get First Level Control Certification on project level.
April 2nd 2009 • Dennis Ehm, ARL 14
Kick-Off-Meeting, April 1st – 3rd 2009, Riga
„Progress reports“
Report due dates on partner level
Reports incl. First Level Control certification are due the latest 2 months after reporting period end (= 1 month priorprior to reports on project level!)
Period End date Deadline report on partner level
preparation 24.10.2008 30.09.2009
1 31.07.2009 30.09.2009
2 31.01.2010 30.03.2010
3 31.07.2010 30.09.2010
4 31.01.2011 30.03.2011
5 31.07.2011 30.09.2011
6 31.01.2012 30.03.2012
April 2nd 2009 • Dennis Ehm, ARL 15
Kick-Off-Meeting, April 1st – 3rd 2009, Riga
„Progress reports“
Reporting „system“
• reporting system is a puzzle of single reports (activity, financial)
• sum of each level is base for next higher level
April 2nd 2009 • Dennis Ehm, ARL 16
Kick-Off-Meeting, April 1st – 3rd 2009, Riga
„Progress reports“
Vertical reporting „system“
Level 1 (JTS/IB)
Level 2 (LP)
Level 3 (PPs)
(control/ check with application/contracts)
deliver
April 2nd 2009 • Dennis Ehm, ARL 17
Kick-Off-Meeting, April 1st – 3rd 2009, Riga
„Progress reports“
Horizontal reporting „system“
e.g.
output/activity WP1+WP2+WP3 = project outputs/activities
BL 2 of PP1 + PP2 + PP3-n = BL 2 of project
April 2nd 2009 • Dennis Ehm, ARL 18
Kick-Off-Meeting, April 1st – 3rd 2009, Riga
„Progress reports“
„System“
Every single reporting partner is part of the whole reporting system.
Only functions if everybody delivers its report(s).
April 2nd 2009 • Dennis Ehm, ARL 19
Kick-Off-Meeting, April 1st – 3rd 2009, Riga
„Progress reports“
Demand
Deliver
• in requested quality
• in requested volume
• in due time
April 2nd 2009 • Dennis Ehm, ARL 20
Kick-Off-Meeting, April 1st – 3rd 2009, Riga
„Progress reports“
Correct delivery
to ensure
next higher reporting level can sum up and
deliver requested quality and volume in due time!
April 2nd 2009 • Dennis Ehm, ARL 21
Kick-Off-Meeting, April 1st – 3rd 2009, Riga
„Progress reports“
Subsidy Payment base
Keep in mind:
Reports are the base for
payment of the subsidy!
April 2nd 2009 • Dennis Ehm, ARL 22
Kick-Off-Meeting, April 1st – 3rd 2009, Riga
„Progress reports“
Responsibility in the TEAM
Low-quality, late, or incomplete reports from
LP to IB/JTS:
late or no payment of subsidy to the whole project
later or no payment to all partners!
April 2nd 2009 • Dennis Ehm, ARL 23
Kick-Off-Meeting, April 1st – 3rd 2009, Riga
„Progress reports“
Consequences
E.g.
Financial report of one partner missing/ not accepted:
IB will not pay out any subsidy for the reporting period!
(even though all other partners delivered AR and FR in requested quality, volume and time!)
April 2nd 2009 • Dennis Ehm, ARL 24
Kick-Off-Meeting, April 1st – 3rd 2009, Riga
„Progress reports“
Awareness for work-flow
• Timing
• Every single report is base for higher level report
• Subsidy for whole project only if all single reports delivered in correct quality, volume and time
April 2nd 2009 • Dennis Ehm, ARL 25
Kick-Off-Meeting, April 1st – 3rd 2009, Riga
„Progress reports“
clue for success: TEAM-work
EVERYBODY must be aware of that!
WE are a project TEAM!
We rely on each others!
Let’s act this way!
Kick-Off-MeetingApril 1st – 3rd 2009
Large Conference Hall of Hotel Riga
Riga/ Latvia
host:
Baltic Sea Region Programme 2007-2013 project
“Baltic Challenges and Chances for local and
regional development generated by Climate Change“
BalticClimate