START: Advanced Cooling Design Studies and … Library/Events/2017/utsr/track2/Thole... · START:...
Transcript of START: Advanced Cooling Design Studies and … Library/Events/2017/utsr/track2/Thole... · START:...
START: Advanced Cooling Design Studiesand Turbine Rim Seal Results
Brian Knisely, Ivan Monge‐Concepcion, Shawn SirokaMike Barringer, Reid Berdanier, Jeremiah Bunch, David Johnson, Jeremy Neal, and Karen Thole
November 2017
Atul Kohliand many others
Patcharin BurkeRichard Dennisand many others
2
The overall goal of the DOE project is to advance cooling of turbine components with the aim of improving efficiencies and lowering costs
Specific goals include:1) demonstrate increased turbine efficiency by reducing cooling flow to the turbine through the systematic studies of Reynolds number, cooling flowrates, and airfoil cooling designs;
2) determine the appropriate scaling parameters for different testing environments including Virginia Tech, U Pitt, and DOE‐NETL.
Siw, Chyu, and Alvin, 2015
Ramesh, Ramirez, Ekkad, Alvin, 2016
3
DOE Project StatusTask 2 – Facility UpgradeTask 3 – Cooled Blade DesignTask 4 – InstrumentationTask 6 – Advanced Manufacturing
Progress to Date
Turbine Sealing Test ResultsFull Span vs Partial Span
4
Task 1.0 –Project Management, Planning and Reporting
Task 2.0 – Facility Upgrade Planning and Execution Second compressor and heater integration
Task 3.0 – Cooled Blade Design and Manufacturing ‐‐A cooled blade airfoil design will be completed by Pratt & Whitney‐‐ Rainbow blade ring to include baseline and five configurations
Task 4.0 – Instrumentation Upgrades and Validation ‐‐Unsteady pressures; rotating data acquisition; long wave infrared radiation detection
Task 5.0 Cooled Blade Testing‐‐ Testing will be done on the full blade ring containing five different cooling configurations different cooling flow rates, Reynolds numbers, Mach numbers and other relevant parameters for each of the five configurations.
Task 6.0 Evaluation of Advanced Manufacturing Methods
There are six specific tasks for: Improving Turbine Efficiencies through Heat Transfer and Aerodynamics Research in START
Several important flow conditions in the turbine main gas path and secondary air system are at engine relevant scaling parameters
Parameter at Blade Inlet AeroEngine
START (I)Single Compressor
(2014‐2015)
START (II)Two Compressors
(2016)
Coolant‐to‐Mainstream Density Ratio / 2.0 1.0 ‐ 1.3 1.0 ‐ 2.0
Stage Pressure Ratio , / , 2 1.5 ‐ 2.5 1.5 – 2.5
Rotational Reynolds Number 2.0 x 107 + 1 x 107 2 x 107
Rotational Speed rpm 15000+ 11000 11000
Mass flow rate lbm/s 25+ 12.5 25
Pressure PSIA 100’s 60‐80 60‐80
Axial Reynolds Number 3 x 105 3 x 105 3 x 105
Vane Exit Mach Number Ma 0.7 0.7 0.7
Airfoil Geometry (True Engine Scale) Span Full Half Full
Turbine Inlet Temp Secondary Coolant Temp F ~ 2500
~ 100025040
75040
5
The facility upgrades were completed and benchmarked in spring 2017
6
The delivery system for the turbine cooling air includes a heat exchanger, moisture separator, filter, and manifold system
Turbine Cooling AirP = 60‐80 psiaT = 40 Fm = 2 lbm/s (1600 SCFM)
Shell‐and‐Tube Heat Exchanger
MoistureSeparator
Filter Manifold
Manifold1st Vanes
ManifoldTOBI
Turbine Flow Meters
(Low P Loss)
Flow Control Valves
(Electronically Actuated)
Air From CompressorP = 60‐80 psiaT = 250 Fm = 2 lbm/s (1600 SCFM)
* * * *
Glycol/Water
Manifold2nd Vanes ROBI
Manifold2nd Vanes AWS
.
.
10 Hoses
7
8
Full‐span vanes and blades were installed by increasing the main gas path area
The Phase 1 turbine was a 1.5 stage design while the Phase 2 is a 1.0 stage design including the following features
Parameter Phase 1 Phase 2
Turbine Stage 1.5 1.0
Blade Tip Clearance (/S [%]) 3.8 3.3, 5.8
Vane ‐ Rim Seal Design Double Overlap Double Overlap
Vane ‐ Rim Cavity Purge Holes 150 150
Vane
Disk
GEOMETRY FEATURE
VANES BLADES
Phase 1 Phase 2 Phase 1 Phase 2
Span Half Full Half Full
Manufacturing Additive Cast/Machined Cast/Machined Cast/Machined
Mate Face Gaps Sealed Sealed Dampers Dampers
Film Cooling Holes None Airfoil/Platform = SealedTrailing Edge = Open
None All Open
9
0
2
4
6
8
10
12
14
0 5 10 15 20 25 30
Burner Firing
Rate (M
Btu/hr)
Main Gas Path Flowrate (lbm/sec)
START Rig Burner Chart
750 F
600 F
Main Gas Path Temperature (F)
500 F
400 F
300 F
Twin Burner
Single Burner
The new combustion heater is currently configured for DOE testing using a single burner
Single Burner
Chamber Sight Port
Phase 2
10
The new combustion heater was successfully commissioned for both long‐duration steady thermal tests and transient ramp tests
Long Duration Steady Tests
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
0 30 60 90 120Time (minutes)
Turbine inlet temperature, T0,in/Tamb
Turbine mass flow rate, ṁ/ṁavg
Vane pressure ratio, Pex/P0,in
Tests have been run as long as 12 hours
250
270
290
310
330
350
370
390
410
430
0 500 1,000 1,500 2,000
Tempe
rature (°F)
Time (Seconds)
11
0
0.0005
0.001
0.0015
0.002
0.0025
0.003
0.0035
1 1.2 1.4 1.6 1.8 2
Mass F
low Param
eter per hole
[lbm*R
^.5/(s*p
sia)/#ho
les]
Pressure Ratio, P0/PS
150 open, 7/1/1490 open, 7/1/1460 open, 7/1/1430 open, 7/1/1415 open, 7/21/145 open, 7/23/142017‐06‐15 Test #1
After installation of new capabilities, numerous experiments were conducted to ensure accurate measurements
P0 PS
Phase 1 = 150Phase 1 = 90Phase 1 = 60
Phase 1 = 5Phase 2 = 150
Phase 1 = 30Phase 1 = 15
# of Purge Holes
FP / N = Mass Flow Parameter Per Hole =lbmR0.5
s psia #holes
FP P ,
, .
12
Shakedown testing included measuring the aerodynamic loading on the 1st Vane airfoil surfaces and good agreement was found to CFD
13
0.4
0.5
0.6
0.7
0.8
0.9
1
0 0.2 0.4 0.6 0.8 1
P/Pt,in
S/Smax
Phase 1
CFDVane AVane B
0.4
0.5
0.6
0.7
0.8
0.9
1.0
0 0.2 0.4 0.6 0.8 1
P/Pt,in
S/Smax
Phase 2
CFDVane AVane B
Nor
mal
ized
Pre
ssur
eV
aria
tion,
P
P0 [p
sig]
Nor
mal
ized
Tem
pera
ture
Var
iatio
n,
T P0 [d
egF]
The turbine inlet pressure and thermal fields were also surveyed using multiple circumferential Kiel probes and thermocouples
Temperature VariationRelative to Average
(F)
Pressure VariationRelative to Average
(PSIG)
14
15
Three RadialTraverses
One Radial‐CircumferentialTraverse
The turbine inlet pressure and thermal fields were surveyed using multiple radial traverses with Kiel probes and thermocouples
15
Courtesy of D. Straub, DOE‐NETL 16
1
NETL Baseline 2
NETL ‘Trailing Edge’
3 NETL
‘Antivortex’
4 NETL ‘Double
Wall’
5 NETL ‘TrEAD’
Leading Edge
Internal Impingement cooling
Impingement cooling
Impingement cooling
Impingement cooling
Impingement cooling
External Showerhead Showerhead Showerhead Showerhead Showerhead
Pressure Surface
Internal Serpentine with ‘V’ Discrete Trip Strips
Serpentine with ‘V’ Discrete Trip Strips
Serpentine with Discrete ‘V’ Trip Strips
Partially Bridged Pedestal Double Wall
Partially Bridged Pedestal Double Wall
External 7‐7‐7 Shaped Hole
7‐7‐7 Shaped Hole
Shaped Antivortex Tripod Hole
7‐7‐7 Shaped Hole
Shaped Antivortex Tripod Hole
Suction Surface
Internal Serpentine with ‘V’ Discrete Trip Strips
Serpentine with ‘V’ Discrete Trip Strips
Serpentine with ‘V’ Discrete Trip Strips
Partially Bridged Pedestal Double Wall
Partially Bridged Pedestal Double Wall
External 7‐7‐7 Shaped Hole
7‐7‐7 Shaped Hole
Shaped Antivortex Tripod Hole
7‐7‐7 Shaped Hole
Shaped Antivortex Tripod Hole
Trailing Edge
Internal
Triple Chamber, Double Impingement, Trip Strips, and Pedestals
High Solidity Diamond Pedestal Array
Triple Chamber, Double Impingement, Trip Strips, and Pedestals
Triple Chamber, Double Impingement, Trip Strips, and Pedestals
High Solidity Diamond Pedestal Array
External
Diffused Partitioned Pressure Side Cut
Diffused Partitioned Pressure Side Cut
Diffused Partitioned Pressure Side Cut
Diffused Partitioned Pressure Side Cut
Diffused Partitioned Pressure Side Cut
Task 3.0 – Cooled Blade Design and Manufacturing
1NETL Baseline
2NETL ‘Trailing
Edge’
3NETL
‘Antivortex’
4NETL ‘Double
Wall’
4NETL ‘TrEAD’
PW subcontract status: internal core design for all blades complete, thermal and structural assessments in progress
Double Impingement
vs.Diamond Pedestals
Shapedvs.
Tripod Holes
Serpentinevs.
Double Wall
Baselinevs.
Advanced
Approved for public release
Task 4.0 – Instrumentation Upgrades and Validation
18 18
Blade tip clearance probes were installed and calibrated
19
Heat transfer into the blades will also be measured using thin film heat flux gauges both purchased and manufactured in‐house at PSU
Anthony et al. 2011
Courtesy of PrOXisense
Digital telemetry hardware will allow HFG operation
Gages will be procured from Oxford University (PrOXisense) and manufactured at PSU
21
1000
μm
1300 μm
25 μm
1200 μm
200 μm
252 μm
254 μm
700 μm
700 μm
100 μm
Oxford 2015 Design
AFRL 2016 Design
Oldfield 1986 Design
Penn State Design
HFG sensing elements are being made smaller with increased sensitivity using modern fabrication technology
Single Grain of Salt
22
Penn State’s Nano Fabrication Lab will provide the equipment to make the complex heat flux gauges
Polyimide FilmRelease tape
Silicon Wafer
1. Adhere Polyimide to Silicon wafer and prepare surface
2. Spin coat a chemical resist to
the surface
Polyimide FilmRelease tape
Silicon Wafer
Resist
3. Develop resist
Polyimide FilmRelease tape
Silicon Wafer
Resist
Radiation Source
Mask
Polyimide FilmRelease tape
Silicon Wafer
ResistResist
4. Prepare to deposit metal
Polyimide FilmRelease tape
Silicon Wafer
ResistResist
5. Sputter metal of sensor material
Metal
Polyimide FilmRelease tape
Silicon Wafer
6. Strip resist, leaving the final metal
Metal
23
70 80 90 100 110 120 130 140 150 160 170
78
80
82
84
86
88
90
Temperature [C]
Res
ista
nce
[Ohm
]
mim13
R = 6.63e+01*(1+2.26e-03*T+-4.11e-07*T^{2}); R^2 = 1.0000Raw data
The CVD eqn constants are alpha = 2.22e-03 delta = 1.85e+00
Temperature C
Typical Calibration Curve
Resistance Ω
Fluke Calibration Oil Bath
254 μm
0.05CAccuracy
The HFG sensing elements are each calibrated to within 0.05C
Single Sided Heat Flux Gauge Probe
24
Courtesy of Limmat Scientific
The new high frequency response aero‐probe and data acquisition system arrive soon and allow time resolved spatial maps of pressure
Porreca et al. [2007]
Regina et al. [2014]
25
Task 6.0: Evaluation of Advanced Manufacturing Methods Public film cooling configurations are being tested in a engine scale test rig with metal AM coupons
25
Co‐flow and counter‐flow coolant inlets
ZnSe window for IR measurements
7‐7‐7 public shaped hole from Schroeder & Thole (2014)
Bi and hc/h∞matched to engine
Film cooling coupons were manufacture using laser powder bed fusion in two different build orientations
Material: Hastelloy® X Machine: EOS M280 DMLS machine
27
SEM micrographs show high levels of roughness in the diffuser and metering section of AM film holes
(black regions on surfaces are paint)
1x Vertical(D=0.015”)
1x EDM(D=0.015”)
2x Angled(D=0.030”)
28
The build direction affects the type of roughness in the hole, which affects film performance
M = 1.2 M = 3.02x Ang
2x Vert
Hole Scale
Build Dir
Chan Height
MfgMethod Ra/D*
2x Ang 1.7D AM 0.022x Vert 1.7D AM 0.01
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
φCoolant
Mainstream
Co‐flow
29
0.4
0.45
0.5
0.55
0.6
0.65
0.5 1 1.5 2 2.5 3 3.5 4M
In‐hole convection dominates overall effectiveness near the exit of the hole
φh
Hole Scale
Build Dir
ChanHeight
MfgMethod Ra/D*
1x Ang 1.7D AM 0.041x Vert 1.7D AM 0.022x Ang 1.7D AM 0.022x Vert 1.7D AM 0.01
φh
Coolant
Mainstream
Co‐flow
31
Vane Vane
150 purge holes
The first test campaign after the facility upgrades were completed was to compare full and partial span turbine sealing results
33
31
CO2 concentration measurements are made through static pressure taps using a gas analyzer, sampling system, and mass flow controllers
Concentration Effectiveness
CO2
Mass Flow Controller
Secondary Air Supply
Sampling System
Mass Flow Controller
c∞~0
cs=1%
Gas Analyzer, c
Plenum
Siemens Ultramat 6
Alicat
Sealing effectiveness does not scale with purge‐to‐main gas path flow ratios
43
Sealing effectiveness levels at low purge flows scale better with pressure ratio across the purge holes (similar to momentum flux ratio)
37
Inflection point in the data was detected in sealing effectiveness, which occurred when rim seal and rim cavity pressures agreed
35
38
The normalizing parameter proposed by Owen et al. [2012] showed good scaling of the data but does not agree with theoretical model
∗
/ //
∗
= where = 0
Key Findings to Date
40
The START facility has been upgraded to integrate the second compressor and combustor; benchmarking of the facility with the full span airfoils are complete; significant instrumentation upgrades have been completed and are continuing
Design for the turbine airfoils integrating the baseline and advanced cooling configurations are progressing
Comparison of sealing effectiveness levels for full‐span and partial‐span airfoils have been made; purge flow‐to‐main gas path flow ratios do not scale the effectiveness
Questions?