Standard Costing Final

download Standard Costing Final

of 34

Transcript of Standard Costing Final

  • 7/29/2019 Standard Costing Final

    1/34

    1

    STANDARD COSTING & VARIANCE ANALYSIS

    USES OF ACCOUNTING INFORMATIONAccounting information is quite useful to the Management in terms of arriving at a

    decision and also in planning, control and performance evaluation. Accounting

    information can be used for:

    1. Projecting the profit level.

    2. Analysing the impact of cost if sales volume drop by 10 %.

    3. Measuring the efficiency of production.4. Measuring the performance of each segment.

    5. Designing performance measurement systems to encourage employees to

    participate for the betterment of the Organization

    The answers to the above issues lie in the installation of a good accounting

    system encompassing an effective Budgetary control and STANDARD COSTING

    SYSTEM.Establishing a Standard costing system will be quite useful to the

    Management in both planning and control. In the planning stage, it can assist the

    Management with necessary data; at the control stage, it can be used to find the

    deviations between the actual vis-a-vis the standards. The measurement of such

    deviations is carried out through the technique ofVARIANCE ANALYSIS.

    What is Costing ?

    Costing (or cost-benefit analysis) is the process of analyzing the costs and benefits of

    different options to determine

    what approach should be taken to a particular conflict. what solution or resolution should be chosen once various options are being

    considered.

  • 7/29/2019 Standard Costing Final

    2/34

    2

    Meaning of Standard

    When you want to measure some thing, you must take some parameter or yardstick

    for measuring. We can call this as standard. What are your daily expenses? An

    average of $50! If you have been spending this much for so many days, then this is

    your daily standard expense.

    The word standard means a benchmark or yardstick. The standard cost is a

    predetermined cost which determines in advance what each product or service should

    cost under given circumstances.

    In the words of Backer and Jacobsen, Standard cost is the amount the firm thinks a

    product or the operation of the process for a period of time should cost, based upon

    certain assumed conditions of efficiency, economic conditions and other factors.

    STANDARD COSTING

    MEANING AND DEFINATION OF STANDARD COSTING TECHNIQUE

    A Standard Cost is a planned cost for a unit of product or service rendered.

    C.I.M.A (London) has defined standard cost as a pre-determined cost which is

    calculated from managements standard of efficient operations and the relevant

    necessary expenditure. It may be used as a basis for determination of prices and cost

    control through variance analysis

    According to C.I.M.A (London), standard costing is defined as The preparation

    and use of standard costs, their comparison with actual costs and the analysis of

    variances to their causes and point of incidence.

    Wheldon hasdefined it in the following words: Standard Costing is a method of

    ascertaining costs whereby statistics are prepared to show (a) The standard cost; (b)

    the actual cost; and (c) the difference between these costs, which is teremed as

    variance.

  • 7/29/2019 Standard Costing Final

    3/34

    3

    Classification of Standards

    The two principal considerations for classification of standards are :

    Attainability of standards. Frequency with which the standards are revised.

    Ideal standard

    Ideal standard is fixed on the assumption of those conditions which may rarely exist.

    This standard is notpracticable and may not be achieved.

    This is the standard which represents a high level of efficiency. Ideal standard is fixed

    on the assumption that favourable conditions will prevail and management will be at

    its best. The price paid for materials will be lowest and wastes etc. will be minimum

    possible. The labour time for making the production will be minimum and rates of

    wages will also be low. The overhead expenses are also set with maximum efficiency

    in mind. All the conditions, both internal and external, should be favourable and only

    then ideal standard will be achieved.

    Theoretic Normal

    BasicCurrently

    Attainable

  • 7/29/2019 Standard Costing Final

    4/34

    4

    Basic

    The changes in manufacturing costs can be measured by taking basic standard, as a

    base standard cannotserve as a tool for cost control purpose because the standard isnot revised for a long time.

    Basic standard is established for a long period and is not adjusted to the preset

    conations. The same standard remains in force for a long period. These standards are

    revised only on the changes in specification of material and technology productions. It

    is indeed just like a number against which subsequent process changes can be

    measured. Basic standard enables the measurement of changes in costs.

    NormalThe normal standard concept is theoretical and cannot be used for cost control

    purpose. Normal standard can be properly applied for absorption of overhead cost

    over a long period of time.

    Normal standard has been defined as a standard which, it is anticipated, can be

    attained over a future period of time, preferably long enough to cover one trade cycle.

    The standard attempts to cover variance in the production from one time to another

    time. An average is taken from the periods of recession and depression.

    Current

    It is presumed that conditions of production will remain unchanged. In case there is

    any change in price or manufacturing condition, the standards are also revised.

    Current standard may be ideal standard and expected standard.

    A current standard is a standard which is established for use over a short period of

    time and is related to current condition. It reflects the performance that should be

    attained during the current period. The period for current standard is normally one

    year.

    Revision of standards

    We need to revise the standards which follow for better control. Even standards are

    also subjected to change like the production method, environment, raw material, and

    technology.

  • 7/29/2019 Standard Costing Final

    5/34

    5

    Standards may need to be changed to accommodate changes in the organization or its

    environment. When there is a sudden change in economic circumstances, technology

    or production methods, the standard cost will no longer be accurate.

    STEPS IN STANDARD COSTING

    Standard costing involves:

    The setting of standards

    Ascertaining actual results

    Comparing standards and actual costs to determine the variances

    Investigating the variances and taking appropriate action where necessary.

    PRELIMINARIES IN ESTABLISHING A SYSTEM OF

    STANDARD COSTS

    1. The establishment of cost centers with clearly defined areas ofresponsibility.

    2. The classification of accounts, with provision for standard and actual costs with

    variances.

    3. The type of standard to be operated.

    4. The setting of standard costs for each element of cost.

  • 7/29/2019 Standard Costing Final

    6/34

    6

    Objectives of Standard Costing

    To Establish Control. To Set Standard for various Elements of cost. To Fix Responsibility. To Make Budgetary Control more Effective.

    The Need for Standards

    Standards Are common in business Are often imposed by government agencies (and called regulations) Standard costs Are predetermined unit costs Used as measures of performance

    Distinguishing Between Standards and Budgets

    Standards and budgets are both Pre-determined costs Part of management planning and control A standard is a unit amount whereas a budget is a total amount Standard costs may be incorporated into a cost accounting system

  • 7/29/2019 Standard Costing Final

    7/34

    7

    Standard v/s Historical Costing

    Standard Costing

    It is a predetermined cost. It is an ideal cost. It is a future cost, it can be used for cost control. It is used for the measurement of operational efficiency of the enterprises.

    Historical costing

    It is recorded after production. It is an actual or incurred cost. It is related to past, cannot be used for cost control. It is used to ascertain the profit or loss incurred during a particular period.

    Standard Cost v/s Estimated Cost

    Standard Cost

    It is scientifically used & it is a regular system based upon estimation &survey.

    Its object is to ascertain, what the cost should be? It is used for effective cost control & to take proper action to maximize. It is continuous process of costing & take into account all the manufacturing

    process.

    It is used where standard costing is in operation. It is more accurate than estimated cost.

  • 7/29/2019 Standard Costing Final

    8/34

    8

    Estimated Cost

    It is used as statistical data and it is based on lot of guess work. Its object is to ascertain what the cost will be? Its purpose is planning and ascertainment of cost for fixing sale price. It is used for a specific use i.e. fixing sale price. It is used where standard costing is not in operation. It is not accurate as it is based on past experience.

  • 7/29/2019 Standard Costing Final

    9/34

    9

    Advantages of Standard Costing Technique

    Increase in Efficiency. Detection of Efficient or Idle Centers. Ease in Managerial Decisions. Facilities Quality Control. Best use of Material. Facilities Budget Formation. Helps in Stock Valution. Knowledge of Workers Efficiency. Increase in Profits. Best use of Production capacity.

    Standard costing is a management control technique for every activity. It is not only

    useful for cost control purposes but is also helpful in production planning and policy

    formulation. It allows management by exception. In the light of various objectives of

    this system, some of the advantages of this tool are given below:

    1. Efficiency measurement-- The comparison of actual costs with standard costsenables the management to evaluate performance of various cost centers. In

    the absence of standard costing system, actual costs of different period may be

    compared to measure efficiency. It is not proper to compare costs of different

    period because circumstance of both the periods may be different. Still, a

    decision about base period can be made with which actual performance can be

    compared.

    2. Finding of variance-- The performance variances are determined bycomparing actual costs with standard costs. Management is able to spot out the

    place of inefficiencies. It can fix responsibility for deviation in performance. It

  • 7/29/2019 Standard Costing Final

    10/34

    10

    is possible to take corrective measures at the earliest. A regular check on

    various expenditures is also ensured by standard cost system.

    3. Management by exception-- The targets of different individuals are fixed ifthe performance is according to predetermined standards. In this case, there is

    nothing to worry. The attention of the management is drawn only when actual

    performance is less than the budgeted performance. Management by exception

    means that everybody is given a target to be achieved and management need

    not supervise each and everything. The responsibilities are fixed and every

    body tries to achieve his/her targets.

    4. Cost control-- Every costing system aims at cost control and cost reduction.The standards are being constantly analyzed and an effort is made to improve

    efficiency. Whenever a variance occurs, the reasons are studied and immediate

    corrective measures are undertaken. The action taken in spotting weak points

    enables cost control system.

    5. Right decisions-- It enables and provides useful information to themanagement in taking important decisions. For example, the problem created

    by inflating, rising prices. It can also be used to provide incentive plans for

    employees etc.

    6. Eliminating inefficiencies-- The setting of standards for different elements ofcost requires a detailed study of different aspects. The standards are set

    differently for manufacturing, administrative and selling expenses. Improved

    methods are used for setting these standards. The determination of

    manufacturing expenses will require time and motion study for labor and

    effective material control devices for materials. Similar studies will be needed

    for finding other expenses. All these studies will make it possible to eliminate

    inefficiencies at different steps.

  • 7/29/2019 Standard Costing Final

    11/34

    11

    Limitation of Standard Costing

    Determination by the Experts. Determination of Standard Cost is difficult in this age of inflation. Unsuitable in some Industries. Morale of Employees Lowered. Necessity of Budgetary Control. It cannot be used in those organizations where non-standard products are

    produced. If the production is undertaken according to the customer

    specifications, then each job will involve different amount of expenditures.

    The process of setting standard is a difficult task, as it requires technical skills.The time and motion study is required to be undertaken for this purpose. These

    studies require a lot of time and money.

    There are no inset circumstances to be considered for fixing standards. Theconditions under which standards are fixed do not remain static. With the

    change in circumstances, if the standards are not revised the same become

    impracticable.

    The fixing of responsibility is not an easy task. The variances are to beclassified into controllable and uncontrollable variances. Standard costing is

    applicable only for controllable variances.

    For instance, if the industry changed the technology then the system will not be

    suitable. In that case, we will have to change or revise the standards. A frequentrevision of standards will become costly.

  • 7/29/2019 Standard Costing Final

    12/34

    12

    Setting Standards

    Normally, setting up standards is based on the past experience. The total standard cost

    includes direct materials, direct labor and overheads. Normally, all these are fixed to

    some extent. The standards should be set up in a systematic way so that they are used

    as a tool for cost control.

    Various Elements which Influence the Setting of Standards

    Setting Standards for Direct Materials

    There are several basic principles which ought to be appreciated in setting standards

    for direct materials. Generally, when you want to purchase some material what are the

    factors you consider. If material is used for a product, it is known as direct material.

    On the other hand, if the material cost cannot be assigned to the manufacturing of the

    product, it will be called indirect material. Therefore, it involves two things:

    Quality of material Price of the material

    When you want to purchase material, the quality and size should be determined. The

    standard quality to be maintained should be decided. The quantity is determined by

    the production department. This department makes use of historical records, and an

    allowance for changing conditions will also be given for setting standards. A number

    of test runs may be undertaken on different days and under different situations, and an

    average of these results should be used for setting material quantity standards.

    The second step in determining direct material cost will be a decision about the

    standard price. Materials cost will be decided in consultation with the purchase

    department. The cost of purchasing and store keeping of materials should also be

    taken into consideration. The procedure for purchase of materials, minimum and

    maximum levels for various materials, discount policy and means of transport are the

    other factors which have bearing on the materials cost price. It includes the following:

  • 7/29/2019 Standard Costing Final

    13/34

    13

    Cost of materials Ordering cost Carrying cost

    The purpose should be to increase efficiency in procuring and store keeping of

    materials. The type of standard used-- ideal standard or expected standard-- also

    affects the choice of standard price.

    Setting Direct Labor Cost

    If you want to engage a labor force for manufacturing a product or a service for which

    you need to pay some amount, this is called wages. If the labor is engaged directly to

    produce the product, this is known as direct labor. The second largest amount of cost

    is of labor. The benefit derived from the workers can be assigned to a particular

    product or a process. If the wages paid to workers cannot be directly assigned to a

    particular product, these will be known as indirect wages. The time required for

    producing a product would be ascertained and labor should be properly graded.

    Different grades of workers will be paid different rates of wages. The times spent by

    different grades of workers for manufacturing a product should also be studied for

    deciding upon direct labor cost. The setting of standard for direct labor will be done

    basically on the following:

    Standard labor time for producing Labor rate per hour

    Standard labor time indicates the time taken by different categories of labor force

    which are as under:

    Skilled labor Semi-skilled labor Unskilled labor

    For setting a standard time for labor force, we normally take in to account previous

    experience, past performance records, test run result, work-study etc. The labor rate

  • 7/29/2019 Standard Costing Final

    14/34

    14

    standard refers to the expected wage rates to be paid for different categories of

    workers. Past wage rates and demand and supply principle may not be a safe guide for

    determining standard labor rates. The anticipation of expected changes in labor rates

    will be an essential factor. In case there is an agreement with workers for payment of

    wages in the coming period, these rates should be used. If a premium or bonus

    scheme is in operation, then anticipated extra payments should also be included.

    Where a piece rate system is used, standard cost will be fixed per piece. The object of

    fixed standard labor time and labor rate is to device maximum efficiency in the use of

    labor.

    Setting Standards of Overheads

    The next important element comes under overheads. The very purpose of setting

    standard for overheads is to minimize the total cost. Standard overhead rates are

    computed by dividing overhead expenses by direct labor hours or units produced. The

    standard overhead cost is obtained by multiplying standard overhead rate by the labor

    hours spent or number of units produced. The determination of overhead rate involves

    three things:

    Determination of overheads Determination of labor hours or units manufactured Calculating overheads rate by dividing A by B

    The overheads are classified into fixed overheads, variable overheads and semi-

    variable overheads. The fixed overheads remain the same irrespective of level of

    production, while variable overheads change in the proportion of production. The

    expenses increase or decrease with the increase or decrease in output. Semi-variable

    overheads are neither fixed nor variable. These overheads increase with the increase

    in production but the rate of increase will be less than the rate of increase in

    production. The division of overheads into fixed, variable and semi-variable

    categories will help in determining overheads.

  • 7/29/2019 Standard Costing Final

    15/34

    15

    Determination of Standard Costs

    How should the ideal standards for better controlling be determined?

    1. Determination of Cost Center

    According to J. Betty, A cost center is a department or part of a department or an

    item of equipment or machinery or a person or a group of persons in respect of which

    costs are accumulated, and one where control can be exercised. Cost centers are

    necessary for determining the costs. If the whole factory is engaged in manufacturing

    a product, the factory will be a cost center. In fact, a cost center describes the productwhile cost is accumulated. Cost centers enable the determination of costs and fixation

    of responsibility. A cost center relating to a person is called personnel cost center, and

    a cost center relating to products and equipments is called impersonal cost center.

    2. Current Standards

    A current standard is a standard which is established for use over a short period of

    time and is related to current condition. It reflects the performance that should be

    attained during the current period. The period for current standard is normally one

    year. It is presumed that conditions of production will remain unchanged. In case

    there is any change in price or manufacturing condition, the standards are also

    revised. Current standard may be ideal standard and expected standard.

    3. Ideal Standard

    This is the standard which represents a high level of efficiency. Ideal standard is fixed

    on the assumption that favorable conditions will prevail and management will be at its

    best. The price paid for materials will be lowest and wastes etc. will be minimum

    possible. The labor time for making the production will be minimum and rates of

    wages will also be low. The overheads expenses are also set with maximum efficiency

    in mind. All the conditions, both internal and external, should be favorable and only

    then ideal standard will be achieved.

  • 7/29/2019 Standard Costing Final

    16/34

    16

    Ideal standard is fixed on the assumption of those conditions which may rarely exist.

    This standard is not practicable and may not be achieved. Though this standard may

    not be achieved, even then an effort is made. The deviation between targets and actual

    performance is ignorable. In practice, ideal standard has an adverse effect on the

    employees. They do not try to reach the standard because the standards are not

    considered realistic.

    4. Basic Standards

    A basic standard may be defined as a standard which is established for use for an

    indefinite period which may a long period. Basic standard is established for a longperiod and is not adjusted to the preset conations. The same standard remains in force

    for a long period. These standards are revised only on the changes in specification of

    material and technology productions. It is indeed just like a number against which

    subsequent process changes can be measured. Basic standard enables the

    measurement of changes in costs. For example, if the basic cost for material is Rs. 20

    per unit and the current price is Rs. 25 per unit, it will show an increase of 25% in the

    cost of materials. The changes in manufacturing costs can be measured by taking

    basic standard, as a base standard cannot serve as a tool for cost control purpose

    because the standard is not revised for a long time. The deviation between standard

    cost and actual cost cannot be used as a yardstick for measuring efficiency.

    5. Normal Standards

    As per terminology, normal standard has been defined as a standard which, it is

    anticipated, can be attained over a future period of time, preferably long enough to

    cover one trade cycle. This standard is based on the conditions which will cover a

    future period of five years, concerning one trade cycle. If a normal cycle of ups and

    downs in sales and production is 10 years, then standard will be set on average sales

    and production which will cover all the years. The standard attempts to cover variance

    in the production from one time to another time. An average is taken from the periods

    of recession and depression. The normal standard concept is theoretical and cannot be

  • 7/29/2019 Standard Costing Final

    17/34

    17

    used for cost control purpose. Normal standard can be properly applied for absorption

    of overhead cost over a long period of time.

    6. Organization for Standard Costing

    The success of standard costing system will depend upon the setting up of proper

    standards. For the purpose of setting standards, a person or a committee should be

    given this job. In a big concern, a standard costing committee is formed for this

    purpose. The committee includes production manager, purchase manager, sales

    manager, personnel manager, chief engineer and cost accountant. The cost accountant

    acts as a co-coordinator of this committee.

    7. Accounting System

    Classification of accounts is necessary to meet the required purpose, i.e. function,

    asset or revenue item. Codes can be used to have a speedy collection of accounts. A

    standard is a pre-determined measure of material, labor and overheads. It may be

    expressed in quality and its monetary measurements in standard costs.

  • 7/29/2019 Standard Costing Final

    18/34

    18

    What is variances??

    If actual costs are greater than standard costs the variance is unfavourable. If actual costs are less than standard costs the variance is favourable. The difference between the actual costs and the standard costs are known as

    variances.

    Standard costing and the related variances is a valuable management tool. If avariance arises, management becomes aware that manufacturing costs have

    differed from the standard (planned, expected) costs.

    Variance analysis involves two phases :

    Computation of individual variances. Determination of the cause of each variance.

    Classification of Variances

    variances

    Direct Material

    Variances

    Direct Labour

    Variances

  • 7/29/2019 Standard Costing Final

    19/34

    19

    Direct Material Variance

    Direct Labour Variance

    Direct Cost Variance (MCV)

    Material Price

    Variance (MPV)

    Material Usage

    Variance (MUV)

    Material Mix

    Variance (MMV)

    Material Yield

    Variance (MYV)

    Direct Cost Variance

    Rate Variance

    Efficiency

    Variance

    Mix Variance Yield Variance

    Idle Time

    Variance

  • 7/29/2019 Standard Costing Final

    20/34

    20

    ABBREVATIVES used in Direct Material Variance

    SP = Standard Price per unit of material.

    SQ = Standard Quantity of material to be used for actual output.

    AP = Actual Price per unit of material.

    AQ = Actual Quantity of material used.

    SQM = Standard Quantity Mix.

    AQM = Actual Quantity Mix.

    AY = Actual Yield.

    SY = Standard Yield from actual input.

    SR = Standard Rate per unit of material.

    TSC = Total Standard Cost for Actual Output

    TAC = Total Actual Cost.

    RSQ = Revised Standard Quantity.

  • 7/29/2019 Standard Costing Final

    21/34

    21

    Direct Material Variance

    The standard direct materials cost per unit is calculated as follows

    Material Cost Variance - According to C.I.M.A., London Material costvariance is the difference between the standard cost of direct materials

    specified for the output achieved and the actual cost of direct material used.

    MCV = ( SP * SQ )( AP * AQ ) or ( TSCTAC )

    TSC = Actual Output * SR

    Material Price Variance - According to C.I.M.A., London Material pricevariance is that portion of the material cost variance which is due to the

    difference between the standard price specified and the actual price paid.

    MPV = ( SPAP ) * AQ

    Material Usage Variance - According to C.I.M.A., London Material usagevariance is that portion of the material cost variance which is due to the

    difference between the standard quantity specified and the actual quantityused.

    MUV = ( SQAQ ) * SP

    Varification - MCV = MPV + MUV

  • 7/29/2019 Standard Costing Final

    22/34

    22

    Material Mix VarianceAccording to C.I.M.A., London Mix variance isthe portion of the direct material usage variance which is due to the difference

    between the standard and actual composition of mixture.

    Any one of the following situations may be there as regards material mix:

    1. When total quantity of materials actually used is equal to the total standardquantity, but the mixture ratio differs;

    2. When total quantity of materials actually used is not equal to the total standardquantity, and also the mixture ratio differs; or

    3. When total quantity of materials actually used is not equal to the total standardquantity, but mixture ratio is same.

    In the third case, as the mixture ratio is same, therefore material mix variance is not

    to be calculated. In the first and second cases only, material mix variance is

    calculated.

    First Situation : MMV = ( SQMAQM ) * SP

    Second Situation : MMV = ( RSQAQ ) * SP

    RSQ ( Revised Standard Quantity)

    RSQ = Total Actual Qty. Consumed * Std. Qty. of Particular Material

    Total Std. Qty. of all the Materials

    Example 1- Calculate Material Mix Variance

    Standard Mix for one Unit of product X is:

    Material A 50 kg. @ Rs. 10 per kg.

    Material B 75 kg. @ RS. 20 per kg.

    125 kg.

    Actual Mix used was

  • 7/29/2019 Standard Costing Final

    23/34

    23

    Material A 60 kg. @ Rs. 12 per kg.

    Material B 65 kg. @ Rs. 18 per kg.

    125 kg.

    Solution-

    MMV = ( SQMAQM ) * SP

    Here, SQM = Standard Quantity Mix & AQM = Actual Quantity Mix

    For Material A : ( 5060 ) * Rs. 10 = Rs. 100 ( A )

    For Material B : ( 7565 ) * Rs. 20 = Rs. 200 ( F )

    Rs. 100 ( F )

    Here, (F) means Favorable (+) & (A) means Adverse (-)

    Example 2 - Calculate Material Mix Variance

    Standard Mix for one unit of Product X is : Material A 50 kg. @ Rs. 10 per kg.

    Material B 75 kg. @ Rs. 20 per kg.

    125 kg.

    Actual Mix used was : Material A 60 kg. @ Rs. 12 per kg.

    Material B 70 kg. @ Rs. 18 per kg.

    130 kg.

  • 7/29/2019 Standard Costing Final

    24/34

    24

    Solution

    Here actual used (130 kg) & standard Mix (125 kg) are different also the actual mix

    ratio (6:7) differs from the standard mix ratio (2:3). In such case RSQ will be

    calculated as follows:

    MMV = ( RSQAQ ) * SP

    RSQ = Total Actual Qty. Consumed * Std. Qty. of Particular Material

    Total Std. Qty. of all the Material

    RSQ for Material A = 130 kg * 50/125 = 52 kg.

    RSQ for Material B = 130 kg * 75/125 = 78 kg.

    MMV for Material A = ( 5260 ) * Rs. 10 = Rs. 80 (A)

    MMV for Material B = ( 7870 ) * Rs. 20 = Rs. 160 (F)

    Rs. 80 (F)

    Material Sub-usage VarianceWhen a product is produced from a mixture of two or more kinds of material, there

    may arise material sub-usage variance. It should be noted that material sub-usage

    variance is calculated only when quantity of wastage or output is not given. When

    these quantities are given, this variance will be the same as material yield variance.

    This variance is also known Material Revised Usage Variance or Material Quantity

    Variance.

    There can be two possibilities :

    1. Total quantity of material consumed and standard quantity are not equal, butmix ratios are also different;

    2. Total quantity of material consumed and standard quantity are not equal, butmix ratios are equal.

    MSUV = ( SQRSQ ) * SP

  • 7/29/2019 Standard Costing Final

    25/34

    25

    Material Yield VarianceAccording to C.I.M.A., London Material yieldvariance is that portion of direct material usage variance which is due to the

    difference between the standard yield and the actual yield obtained

    MYV = ( AYSY ) * SR

    SR = Total cost of Standard Mix

    Net Standard Output

    Example- 3 Calculate Material Sub-usage Variance :

    Standard Mix Actual Mix

    Material A 100 kg. @ Rs. 5 per kg. 120 kg. @ Rs. 7 per kg.

    Material B 150 kg. @ Rs. 10 per kg. 180 kg. @ Rs. 9 per kg.

    250 kg. 300 kg.

    Solution Here total of standard mix (250 kg) and actual mix (300 kg) are different,

    but material mix ratio ( 2 : 3 ) is same. Therefore, RSQ for each material has been

    calculated as follows :

    Material Sub-Usage Variance = ( SQRSQ ) * SP

    RSQ = Total Actual Mix * Particular Standard Mix Material / Total Standard Mix

    RSQ for Material A = 300 * 100 / 250 = 120 kg

    RSQ for Material B = 300 * 150 / 250 = 180 kg

    AQ and RSQ of each material is same. Therefore,

    MSUV for Material A = ( 100120 ) * Rs. 5 = Rs. 100 (A)

    MSUV for Material B = ( 150180 ) * Rs. 10 = Rs. 300 (A)

    Rs. 400 (A)

  • 7/29/2019 Standard Costing Final

    26/34

    26

    Some authors use AQ in place of RSQ in the above formulate because RSQ and AQ

    are equal.

    Example 4Calculate Material Variance from the following details available-

    Standard Actual for 10 Mixes

    Material X 40 kgs. @ Rs. 6 Material X 600 kgs. @ Rs. 4

    Material Y 60 kgs. @ Rs. 4 Material Y 400 kgs. @ Rs. 6

    Process Loss 20% Process Loss 30%

    Solution - First of all standards will be set for 10 mixes as follows :

    Standard for 10 Mixes Actual for 10 Mixes

    Material X : 40 * 10 * 6 = Rs 2400 600 * 4 = Rs 2400

    Material Y : 60 * 10 * 4 = Rs 2400 400 * 6 = Rs 2400

    Total 1000 kgs Rs 4800 1000 kgs Rs 4800

    Loss 200 kgs 300 kgs

    Output 800 kgs 700 kgs

    (i) Calculation of Material Cost Variance (MCV) :MCV = TSCTAC

    TSC = Actual Output * SR

    SR = Total Cost of Standard Mix / Net Standard output

    SR = 4800/800 = Rs. 6 per unit,

    TSC = 700 * 6 = Rs. 4200, TAC = Rs. 4800(given)

    (iv) Calculation of Material Mix Variance (MMV)

    MMV = ( SQMAQM ) * SP

  • 7/29/2019 Standard Costing Final

    27/34

    27

    MMV for Material X = ( 400600 ) * 6 = Rs. 1,200 (A)

    MMV for Material Y = ( 600400 ) * 4 = Rs. 800 (F)

    Rs. 400 (A)

    (v) Calculation of Material Yield Variance (MYV)

    MYV = ( AYSY ) * SR

    MYV = ( 700800 ) * 6 = 600 (A)

    Verification : MCV = MPV + MMV + MYV

    600 (A) = 400 (F) + 400 (A) + 600 (A)

    Material Price

    Possible causes

    Inefficient buying or failure to make timely purchases Increase in market price Emergency purchases Bulk purchases Change in transport cost Non-availability of standard quality Loss of cash discount Change in the method of material collection

  • 7/29/2019 Standard Costing Final

    28/34

    28

    Direct Labour Variance

    The standard direct labor cost per unit is calculated as follows

    Labour Cost Variance - According to C.I.M.A. London, Labour CostVariance is the difference between standard cost of labour specified and actual

    cost of labour employed.

    LCV = ( Total Standard Labour CostTotal Actual Labour Cost )

    Labour Rate Variance According to C.I.M.A. London, Labour RateVariance is that portion of labour cost variance which is due to the difference

    between standard rate specified and actual rate paid.

    LRV = ( Standard rate per hourActual rate per hour )

    Labour Efficiency Variance - According to C.I.M.A. London, LabourEfficiency Variance is that portion of labour cost variance which is due to the

    difference between standard labour hours for output achieved and actual

    labour hours spent. it is also known as Labour Time Variance, Labour

    Quantity Variance, Labour Usage Variance, Labour Spending Variance, etc.

    LEV = ( Standard TimeActual Time ) * Standard rate per hour

    Here, Actual time means hours obtained on subtracting abnormal idle-time hours from

    labour hours actually paid for.

    Labour Idle Time VarianceIdle time variance is that portion of labour costwhich arises due to abnormal idle time of the workers specified. This idle time

  • 7/29/2019 Standard Costing Final

    29/34

    29

    is possible due to many reasons, such as, workers sitting free because of

    machine break-down, power failure, etc. it should be noted that this variance

    always shows adverse position.

    LITV = ( Abnormal Idle Time * Standard rate per hour )

    Varification - LCV = LRV + LEV + LITV

    Labour Yield Variance - When the actual yield is less or more than thestandard yield, it gives rise to labour yield variance.

    LYV = ( Actual YieldStandard Yield ) * Standard rate per unit

    Here, Standard Yield = Total actual time * Std. yield from Std. mix

    Total standard time

    Standard rate per unit = Std. cost of standard mix / Std. yield from Std. mix

    Example5 Calculate Labour Yield Variance from the following details :

    Standard Actual

    Skilled 180 workers @ Rs. 3 per hour 160 workers

    Unskilled 120 workers @ Rs. 1 per hour 140 workers

    Budgeted hours for one month 200. actual hours during the month 180; Budgeted

    production 5,000 units less standard loss 20%, Actual production 4,200 units.

    Solution - Standard production (yield) = 5,000 units20% (1,000) = 4,000 units

    Actual production (AY) = 4,200 units

    Calculation of Standard Hours Calculation of Actual Hours

    Budgeted hours No. of workers Total Hr Actual hour No. of worker Total Hr

    Skilled 200 * 180 = 36,000 180 * 160 = 28,800

    Unskilled 200 * 120 = 24,000 180 * 140 = 25,200

  • 7/29/2019 Standard Costing Final

    30/34

    30

    Total 300 60,000 300 54,000

    Labour Yield Variance = ( AYSY ) * SR per unit

    Standard Yield (SY) = Total actual time * Std. yield from Std. mix

    Total standard time

    SY = 54,000 hours * 4,000 units / 60,000 hours = 3,600 units

    SR = Standard cost of standard mix / Standard yield from standard mixStandard

    Wages :

    Skilled workers = 36,000 hours * Rs. 3 = Rs. 1,08,000

    Unskilled workers = 24,000 hours * Rs. 1 = Rs. 24,000

    Total = Rs. 1,32,000

    SR = Rs. 1,32,000 / 4,000 = Rs. 33

    LYV = ( 4,2003,600 ) * Rs. 33 = Rs. 19,800 (F)

    Labour Mix Variance - Different types of workers are generally required in aproduction, e.g., skilled, unskilled, men, women, children, etc. keeping in view

    the production efficiency of the factory and to control the labour cost, a

    standard mix ratio is specified for various type of workers. But in actual

    practice it is not possible to follow this standard because of some difficulties (

    such as non-availability of desired type of workers, etc. ) Thus, labour mix

    variance arises. It is also known as Gang Composition Variance.

    It can be calculated in following two situations :

    1. When the totals of standard labour mix and actual labour mix are same but thetwo mix ratios are different.

    2. When the totals of standard labour mix and actual labour mix are different butthe two mix ratios are also different.

  • 7/29/2019 Standard Costing Final

    31/34

    31

    When the totals of standard labour mix and actual labour mix are different but the two

    mix ratios are same, there will be no labour mix variance.

    First Situation LMV = ( Standard time mixActual time mix ) * Std. rate per hour.

    Second Situation LMV = ( RSTActual Time ) * Standard rate per hour

    Here, RST ( Revised Standard Time )

    RST = Total actual time * Standard time of particular labour

    Total standard time of all the labour

    Example 6The budget of labour hours for the week ending June 30, 2011 is of 50

    hours. The other details are as follows ;

    Standard Actual

    Grade A 100 workers @ Rs. 3 per hour 120 workers @ Rs. 2.50 per hour

    Grade B 200 workers @ Rs. 1 per hour 180 workers @ Rs. 1.50 per hour

    The actual production is for 50 hours during the week. Calculate Labour Mix

    Variance.

    Solution - Calculation of Standard Time Calculation of Actual Time

    Grade A workers 100 * 50 = 5,000 Hours 120 * 50 = 6,000 Hours

    Grade B workers 200 * 50 = 10,000 Hours 180 * 50 = 9,000 Hours

    Total 15,000 Hours 15,000 Hours

    As the total of standard labour time mix (15,000 hours) and actual labour time mix

    (15,000 hours) is same, but standard labour mix ratio (1 : 2) and actual labour mix

    ratio (2 : 3) are different, therefore situation first is applicable

    Labour Mix Variance = ( Standard time mixActual time mix ) * Std. rate per hour

    LMV for Grade A workers = ( 5,0006,000 ) * Rs. 3 = Rs. 3,000 (A)

  • 7/29/2019 Standard Costing Final

    32/34

    32

    LMV for Grade B workers = ( 10,0009,000 ) * Rs. 1 = Rs. 1,000 (F)

    Total = Rs. 2,000 (A)

    Example7 In above Example No. 6 let assumed that the actual number of grade B

    workers is 210 in place of 180. then calculate labour mix variance.

    Solution- Calculation of Standard Time Calculation of Actual Time

    Grade A workers 100 * 50 = 5,000 Hours 120 * 50 = 6,000 Hours

    Grade B workers 200 * 50 = 10,000 Hours 210 * 50 = 10,500 Hours

    Total 15,000 Hours 16,500 Hours

    As the totals of standard labour time mix (15,000 hours) and actual labour time mix

    (16,500 hours) are different, and standard labour mix ratio (1 : 2) and actual labour

    mix ratio (60 : 105) are also different, therefore second situation applicable

    Labour Mix Variance = ( RSTAT ) * SR

    RST = Total actual time * Standard time of particular labour

    Total standard time of all the labour

    RST for Grade A workers = 16,500 * 5,000 / 15,000 = 5,500 hours

    RST for Grade B workers = 16,500 * 10,000 / 15,000 = 11,000 hours

    LMV for Grade A workers = ( 5,5006,000 ) * Rs. 3 = Rs. 1,500 (A)

    LMV for Grade B workers = ( 11,00010,500 ) * Rs. 1 = Rs. 500 (F)

    Total = Rs. 1,000 (A)

    Example8 Calculate Direct Labour Variance from the following :

    Standard Actual

    Workman A : 20 hours @ Rs. 3 = Rs. 60 30 hours @ Rs. 4 = Rs. 120

    Workman B : 20 hours @ Rs. 7 = Rs. 140 25 hours @ Rs. 6 = Rs. 150

  • 7/29/2019 Standard Costing Final

    33/34

    33

    40 hours Rs. 200 55 hours Rs. 270

    In actual production, 3 hours (included in above) have been lost on account of

    machine breakdown.

    Solution

    (i) Labour Cost Variance = Total Standard labour CostTotal Actual LabourCost

    LCV = ( Rs. 200Rs. 270 ) = Rs. 70 (A)

    (ii) Labour Rate Variance = ( Std. rate per hrActual rate per hr ) * Actual time

    LRV for A = ( Rs. 3Rs. 4 ) * 30 hours = Rs. 30 (A)

    LRV for B = ( Rs. 7Rs. 6 ) * 25 hours = Rs. 25 (F)

    Rs. 5 (A)

    (iii) Labour Efficiency Variance = ( Standard timeActual time ) * SR per hour

    LEV for A = ( 20 hours27 hours ) * Rs. 3 = Rs. 21 (A)

    LEV for B = ( 20 hours22 hours ) * Rs. 7 = Rs. 14 (A)

    Rs. 35 (A)

    (iv) Labour Idle time Variance = Idle time * Standard Rate per hour

    LITV for A = 3hours * Rs. 3 per hour = Rs. 9 (A)

    LITV for B = 3 hours * Rs. 7 per hour = Rs. 21 (A)

    Rs. 30 (A)

    Verification

    Labour Cost Variance = Labour rate Variance + Labour Efficiency Variance +

    Labour Idle time Variance

    Rs. 70 (A) = Rs. 5 (A) + Rs. 35 (A) + Rs. 30 (A)

  • 7/29/2019 Standard Costing Final

    34/34

    Labour Efficiency

    Possible causes

    Inefficient/Untrained workers Machinery breakdown Poor quality of material Inefficient supervision Hours lost in waiting, delay in routing material, tools, instructions and

    improper production scheduling

    Poor working conditions Change in design, quality standard of product.

    Conclusion

    A standard cost is a predetermined cost of manufacturing, servicing, or marketing an item

    during a given future period

    It is based on current and projected future conditions

    The norm is also dependent on quantitative and qualitative measurements

    Standards may be based on engineering studies looking at time and motion.

    The formulated standard must be accurate and useful for control purposes.