Standard Competition 12 Months

3

Click here to load reader

Transcript of Standard Competition 12 Months

Page 1: Standard Competition 12 Months

ID Task Name Duration Start Finish1 Initiate Competition Project 0 days Thu 1/1/04 Thu 1/1/04

2 Notify Union and Inform Congressional Affairs Office 5 days Fri 1/2/04 Thu 1/8/04

3 Preliminary Planning Completed 26 days Fri 1/2/04 Mon 2/9/04

4 Identify Project Scope and Activities Groupings 21 days Fri 1/9/04 Mon 2/9/04

5 Assess Project Workload and Data Systems 21 days Fri 1/2/04 Mon 2/2/04

6 Determine and Document Activity Baseline Costs 21 days Fri 1/2/04 Mon 2/2/04

7 Develop and Document Initial Project Schedule 21 days Fri 1/2/04 Mon 2/2/04

8 Determine Participant Roles and Responsibilities Including Support Consultants 21 days Fri 1/2/04 Mon 2/2/04

9 Appoint Competition Officials 21 days Fri 1/2/04 Mon 2/2/04

10 Develop, Document, and Receive Approval for Acquisition Strategy 21 days Fri 1/2/04 Mon 2/2/04

11 Conduct Workforce Briefings 2 days Tue 2/3/04 Wed 2/4/04

12 Announce Competition in Fed Biz Opps 1 day Thu 2/5/04 Thu 2/5/04

13 Solicitation Developed and Issued 145 days Fri 2/6/04 Tue 8/31/04

14 Designate and Train PWS Team Members and Assign Roles 10 days Fri 2/6/04 Fri 2/20/04

15 Develop Performance Work Statement 45 days Mon 2/23/04 Fri 4/23/04

16 Collect and Refine Requirements and Workload Data 45 days Mon 2/23/04 Fri 4/23/04

17 Develop Government Furnished Items List 45 days Mon 2/23/04 Fri 4/23/04

18 Develop List of Offered Supplies 45 days Mon 2/23/04 Fri 4/23/04

19 Develop Performance Measures and Identify Performance Requirements Summary Items

45 days Mon 2/23/04 Fri 4/23/04

1/1

2/5

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Progress

Deadline

U.S. Department ofDraft Standard Competition

12 Month Format

Page 1

Project: Draft 2004 Standard CompetitDate: Sun 1/22/17

Page 2: Standard Competition 12 Months

ID Task Name Duration Start Finish20 Develop Quality Assurance Surveillance Plan 45 days Mon 2/23/04 Fri 4/23/04

21 Issue Sources Sought and Presolicitation Notices in FedBizOps 2 days Mon 4/19/04 Tue 4/20/04

22 Prepare Solicitation Documents 45 days Mon 4/26/04 Mon 6/28/04

23 Issue Solicitation, Conduct Source Selection, and Receive Proposals 45 days Tue 6/29/04 Tue 8/31/04

24 Conduct Site Visit 3 days Mon 7/26/04 Wed 7/28/04

25 Agency Tender Developed 52 days Mon 6/21/04 Wed 9/1/04

26 Designate and Train MEO Team Members and Assign Roles 10 days Mon 6/21/04 Fri 7/2/04

27 Review Solicitation and Prepare Questions for CO 10 days Tue 7/6/04 Mon 7/19/04

28 Conduct Market Research 41 days Tue 7/6/04 Tue 8/31/04

29 Perform Data Collection 41 days Tue 7/6/04 Tue 8/31/04

30 Document Current Organization and Operation 41 days Tue 7/6/04 Tue 8/31/04

31 Develop Competitive Strategy and Document Proposed Technical Approach 41 days Tue 7/6/04 Tue 8/31/04

32 Document Phase-in Plan 41 days Tue 7/6/04 Tue 8/31/04

33 Prepare Labor Market Analysis (HRA) 41 days Tue 7/6/04 Tue 8/31/04

34 Document Employee Transition Plan (HRA) 41 days Tue 7/6/04 Tue 8/31/04

35 Document Proposed Costs using Win.COMPARE2 41 days Tue 7/6/04 Tue 8/31/04

36 Prepare Quality Control Plan 41 days Tue 7/6/04 Tue 8/31/04

37 Prepare Phase-in Plan 41 days Tue 7/6/04 Tue 8/31/04

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Progress

Deadline

U.S. Department ofDraft Standard Competition

12 Month Format

Page 2

Project: Draft 2004 Standard CompetitDate: Sun 1/22/17

Page 3: Standard Competition 12 Months

ID Task Name Duration Start Finish38 Submit Agency Tender 1 day Wed 9/1/04 Wed 9/1/04

39 Source Selection Activities Completed 31 days Mon 8/16/04 Tue 9/28/04

40 Designate and Train Source Selection Evaluation Board Members and Assign Roles 5 days Mon 8/16/04 Fri 8/20/04

41 Evaluate Bids and Offers 14 days Mon 8/23/04 Fri 9/10/04

42 Conduct Oral Presentations 2 days Mon 9/13/04 Tue 9/14/04

43 Conduct Discussions/Negotiations with Offerors and Evaluate Final Revisions 5 days Wed 9/15/04 Tue 9/21/04

44 Make Source Selection 1 day Wed 9/22/04 Wed 9/22/04

45 Prepare Procurement Summary and Route to CSO for Approval 4 days Thu 9/23/04 Tue 9/28/04

46 Performance Decision Made 29 days Wed 9/29/04 Tue 11/9/04

47 Issue Contract or Letter of Obligation to ATO 1 day Wed 9/29/04 Wed 9/29/04

48 Make FedBizOps Announcement to Issue Letter of Obligation or Award Contract 1 day Thu 9/30/04 Thu 9/30/04

49 Conduct Reduction-in Force Actions (HRA) 21 days Fri 10/1/04 Mon 11/1/04

50 Conduct Right of First Refusal Actions 5 days Tue 11/2/04 Mon 11/8/04

51 Initiate Phase-in Actions 1 day Tue 11/9/04 Tue 11/9/04

52 Complete Competition Project 0 days Tue 11/9/04 Tue 11/9/04

9/30

11/9

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Progress

Deadline

U.S. Department ofDraft Standard Competition

12 Month Format

Page 3

Project: Draft 2004 Standard CompetitDate: Sun 1/22/17