STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID...

191
INTERNATIONAL CENTRE FOR SETTLEMENT OF INVESTMENT DISPUTES In the arbitration proceeding between STANDARD CHARTERED BANK (HONG KONG) LIMITED Claimant and UNITED REPUBLIC OF TANZANIA Respondent ICSID Case No. ARB/15/41 AWARD Members of the Tribunal Professor Lawrence Boo, President Justice David Unterhalter SC, Arbitrator Dr Kamal Hossain, Arbitrator Secretary of the Tribunal Ms Geraldine R. Fischer Assistant to the President of the Tribunal Ms Sukriti Slehria Date of dispatch to the Parties: 11 October 2019

Transcript of STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID...

Page 1: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

INTERNATIONAL CENTRE FOR SETTLEMENT OF INVESTMENT DISPUTES

In the arbitration proceeding between

STANDARD CHARTERED BANK (HONG KONG) LIMITED

Claimant

and

UNITED REPUBLIC OF TANZANIA

Respondent

ICSID Case No. ARB/15/41

AWARD

Members of the Tribunal Professor Lawrence Boo, President

Justice David Unterhalter SC, Arbitrator Dr Kamal Hossain, Arbitrator

Secretary of the Tribunal Ms Geraldine R. Fischer

Assistant to the President of the Tribunal Ms Sukriti Slehria

Date of dispatch to the Parties: 11 October 2019

Page 2: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

i

REPRESENTATION OF THE PARTIES

Representing Standard Chartered Bank (Hong Kong) Limited:

Representing the United Republic of Tanzania:

Mr Matthew Weiniger QC Linklaters LLP One Silk Street London EC2Y 8HQ United Kingdom Mr Iain Maxwell Mr Aaron McDonald Ms Elizabeth Kantor Mr Harry Ormsby Mr Gavin Creelman Herbert Smith Freehills LLP Exchange House Primrose Street London EC2A 2EG United Kingdom

Dr Adelardus Kilangi, Attorney General Dr Clement Mashamba, Solicitor General Attorney General’s Chambers 20 Kivukoni Road P.O. Box 9050 11492 Dar es Salaam Tanzania Mr Beredy Malegesi Crax Law Partners Ami Building 2nd Floor Samora/Mkwepu Street P.O. Box 14605 Dar Es Salaam Tanzania Mr Richard Karumuna Rweyongeza R.K. Rweyongeza & Co. Advocates Avalon Building 3rd Floor Zanaki/Sokoine Street P.O. Box 75192 Dar Es Salaam Tanzania Mr Galileo Pozzoli Mr Mark Handley Prof Tullio Treves Ms Luciana Ricart Ms Irene Petrelli Mr Renato Treves Mr Valerio Salvatori Curtis, Mallet-Prevost, Colt & Mosle LLP 99 Gresham Street London EC 2V 7NG United Kingdom

Page 3: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

ii

TABLE OF CONTENTS

I. INTRODUCTION AND PARTIES ............................................................................................................................. 1

II. PROCEDURAL HISTORY ............................................................................................................................................ 1

III. FACTUAL BACKGROUND .......................................................................................................................................... 9

A. The Facility and Key Agreements ................................................................................................................ 9

(1) Power Purchase Agreement .......................................................................................................... 10

(2) Implementation Agreement .......................................................................................................... 10

(3) Facility Agreement ............................................................................................................................ 11

(4) Security Deed ....................................................................................................................................... 11

(5) Shareholder Support Deed ............................................................................................................. 11

(6) Charge of Shares ................................................................................................................................. 12

(7) Lenders and Security Agents ......................................................................................................... 12

B. International Proceedings, Tanzanian Court Proceedings and Other Disputes .................... 13

(1) ICSID 1 Proceedings .......................................................................................................................... 13

(2) Shareholder Dispute and Winding Up Petition ..................................................................... 13

(3) Tariff Dispute ....................................................................................................................................... 14

(4) Interpretation Proceedings and the Revised Administration Petition ........................ 14

(5) Interim PPA .......................................................................................................................................... 15

(6) PPA Arbitration ................................................................................................................................... 15

(7) Proceedings in Malaysia and in the British Virgin Islands (“BVI”) ................................ 16

(8) Winding Up Order and Setting Aside ......................................................................................... 17

(9) Winding Up Order in Respect of Mechmar .............................................................................. 18

(10) Utamwa J Order .................................................................................................................................. 18

(11) English Proceedings and Flaux J’s Judgment .......................................................................... 20

C. Post-2013 IPTL Events .................................................................................................................................. 20

(1) PAP’s Registration as Owner of Mechmar’s Shareholding in IPTL ................................ 20

(2) Payment of the Funds Held in the Escrow Account to PAP .............................................. 21

(3) Investigations in Tanzania ............................................................................................................. 21

IV. PARTIES’ REQUESTS FOR RELIEF ...................................................................................................................... 22

V. JURISDICTION ............................................................................................................................................................. 23

A. The Claimant’s Status as a Legal Assignee ............................................................................................. 24

(1) Contractual Assignment .................................................................................................................. 24

(2) Statutory Assignment under Tanzanian Law ......................................................................... 40

(3) Tribunal’s Finding on the Claimant’s Status as Legal Assignee ...................................... 61

Page 4: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

iii

B. Jurisdiction Under Article 25 of the ICSID Convention .................................................................... 62

(1) National of Another Contracting State ...................................................................................... 63

(2) Whether the Dispute Arises out of an “Investment” within the Meaning of Article 25(1) of the ICSID Convention ....................................................................................... 65

(3) Tribunal’s Decision on Jurisdiction under Article 25 of the ICSID Convention ........ 86

VI. LIABILITY ...................................................................................................................................................................... 87

A. Expropriation Claim Under Article 16 of the Implementation Agreement ............................. 87

(1) Scope of Expropriation Under Article 16.2 of the Implementation Agreement ...... 87

(2) Claimant’s Expropriation Allegations ........................................................................................ 98

(3) Tribunal’s Decision on Expropriation .................................................................................... 126

B. Discrimination Claim under Article 16.1 of the Implementation Agreement ..................... 126

(1) Is SCB HK Entitled to Bring a Discrimination Claim under Article 16.1 of the Implementation Agreement? ..................................................................................................... 128

(2) Does the Discriminatory Action Require a Comparator? ............................................... 129

(3) Meaning of the Reference to “GOT” in Article 16.1 of the Implementation Agreement .......................................................................................................................................... 132

(4) Intention to Discriminate ............................................................................................................ 134

(5) The Factual Basis of the Discrimination Claim: Alleged Discriminatory Actions . 135

(6) Tribunal’s Decision on Discrimination ................................................................................... 145

C. Claim under Article 15.3 of the Implementation Agreement: Failure to Provide Security ............................................................................................................................................ 146

(1) Parties’ Submissions ...................................................................................................................... 146

(2) Tribunal’s Analysis ......................................................................................................................... 147

D. Termination .................................................................................................................................................... 148

(1) GoT Events of Default and Notice Requirements ............................................................... 149

(2) Whether the Claimant is Entitled to Claim Compensation under Row 2 of Schedule 2 of the Implementation Agreement without Transferring the Facility to the Respondent? ...................................................................................................................................... 160

VII. QUANTUM ................................................................................................................................................................ .. 161

A. Calculation of Damages .............................................................................................................................. 163

(1) Damage Related to the Amounts covered by the PPA Award (Tariff Payments for the Period up to September 2013) .......................................................................................... 165

(2) Damages Relating to the PPA tariff for the Period after September 2013: October 2013 to January 2022 .................................................................................................. 166

B. Compensation for Termination ............................................................................................................... 169

(1) Element (a) – Outstanding Loan ............................................................................................... 170

(2) Element (b) – Initial Capital ........................................................................................................ 172

Page 5: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

iv

C. Potential Overlap between Damages and Compensation ............................................................ 173

VIII. COSTS ........................................................................................................................................................................... 178

A. Parties’ Submissions .................................................................................................................................... 178

B. Tribunal’s Analysis ....................................................................................................................................... 182

IX. AWARD ....................................................................................................................................................................... 183

Page 6: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

v

TABLE OF KEY ABBREVIATIONS/DEFINED TERMS

Arbitration Rules or ICSID Arbitration Rules

ICSID Rules of Procedure for Arbitration Proceedings 2006

BoT Bank of Tanzania

BRELA Business Registrations and Licensing Agency of Tanzania

Charge of Shares The Charge of Shares dated 28 June 1997, executed by Mechmar and VIP over of their shares in IPTL to the Security Agent as security for the Loan

Claimant or SCB HK Standard Chartered Bank (Hong Kong) Limited

Danaharta Danaharta Managers (L) Ltd

Escrow Agreement Escrow Agreement dated 5 July 2006 between the Government of Tanzania, IPTL and Bank of Tanzania

Escrow Account An account established by GoT pursuant to the Escrow Agreement

Hearing Hearing on Jurisdiction and Merits held on 16-23 July 2018

Facility Agreement “Loan Facility Agreement relating to the 100 MW Tegeta Power Project” dated 28 June 1997 between IPTL and a consortium of lenders (several Malaysian banks)

ICSID Convention Convention on the Settlement of Investment Disputes Between States and Nationals of Other States dated 18 March, 1965

ICSID or the Centre International Centre for Settlement of Investment Disputes

ICSID 1 Award Final Award in ICSID Case No. ARB/98/8 dated 12 July 2001 between TANESCO and IPTL

Implementation Agreement/IMA Implementation Agreement dated 8 June 1995 between IPTL and GoT

IPTL Independent Power Tanzania Limited

LCIA Award Award in LCIA Arbitration No. 2353 dated 26 August 2003 between Mechmar and VIP

Mechmar Mechmar Corporation (Malaysia) Berhad

Page 7: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

vi

Mechmar Shares The 70% shares held by Mechmar in IPTL

PAP Pan Africa Power Solutions (T) Limited

PPA Power Purchase Agreement dated 26 May 1995, between IPTL and TANESCO

PPA Award Final Award of the Tribunal in ICSID Case No ARB/10/20 dated 12 September 2016 between SCB (HK) and GoT

Respondent, Tanzania or GoT The Government of the United Republic of Tanzania

Security Deed Security Deed executed by IPTL as borrower dated 28 June 1997 in favour of SIME Berhad (Singapore office) as Security Agent

TANESCO Tanzania Electric Supply Company Limited

VIP VIP Engineering and Marketing Limited

VIP Shares The 30% shares held by VIP in IPTL

Page 8: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

1

I. INTRODUCTION AND PARTIES

This is a dispute submitted to the International Centre for Settlement of Investment Disputes

(“ICSID” or the “Centre”) on the basis of the Implementation Agreement between the

Government of the United Republic of Tanzania and Independent Power Tanzania Limited

(“IPTL”) dated 8 June 1995 (“Implementation Agreement” or “IMA”) and the Convention

on the Settlement of Investment Disputes between States and Nationals of Other States (the

“ICSID Convention”). This dispute relates to the Claimant’s allegations against the

Respondent of breach of Articles 15 and 16 of the Implementation Agreement and the validity

of the Claimant’s termination of the Implementation Agreement.

The claimant is Standard Chartered Bank (Hong Kong) Limited (“SCB HK” or the “Claimant”),

a corporation registered under the laws of Hong Kong.

The respondent is the United Republic of Tanzania (“Tanzania” or “GoT” or the

“Respondent”).

The Claimant and the Respondent are collectively referred to as the “Parties”. The Parties’

representatives and their addresses are listed above on page i.

II. PROCEDURAL HISTORY

Date Event

18 September 2015 ICSID received a request for arbitration dated 15 September 2015

from SCB HK against the United Republic of Tanzania together with

exhibits C-001 through C-046 and legal authority CL-001

(“Request”).

30 September 2015 The Secretary-General of ICSID registered the Request in

accordance with Article 36(3) of the ICSID Convention and notified

the Parties of the registration, wherein the Parties were invited to

constitute an arbitral tribunal as soon as possible pursuant to Rule

7 of ICSID’s Rules of Procedure for the Institution of Conciliation

and Arbitration Proceedings (“Institution Rules”).

Page 9: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

2

19 May 2016 The Secretary-General, in accordance with Rule 6(1) of the ICSID

Rules of Procedure for Arbitration Proceedings (“ICSID

Arbitration Rules”), notified the Parties that the Tribunal was

constituted pursuant to Article 37(2)(a) of the ICSID Convention.

The Tribunal was composed of Prof Lawrence Boo Geok Seng, a

national of Singapore, President, appointed by the Chairman of the

ICSID Administrative Council in accordance with Article 38 of the

ICSID Convention; Sir Stanley Burton, a national of the United

Kingdom, appointed by the Claimant; and Dr Kamal Hossain, a

national of Bangladesh, appointed by the Respondent. On the same

date, Ms Aurélia Antonietti, Legal Counsel, ICSID, was designated to

serve as Secretary of the Tribunal.

27 June 2016 The Tribunal issued Procedural Order No. 1 (“PO 1”) pursuant to

the Parties’ agreement in their letters of 14 and 27 June 2016. PO 1

provides, inter alia, that the applicable Arbitration Rules would be

those in effect from 10 April 2006; the procedural language is

English; and the place of proceeding would be London, England.

29 June 2016 The Respondent filed its proposal for the disqualification of Sir

Stanley Burnton, along with Annexes 1 through 11, pursuant to

Article 57 of the ICSID Convention and ICSID Arbitration Rule 9,

on the grounds that his appointment was inconsistent with the

arbitration clause contained in Article 21.2 of the Implementation

Agreement.

30 June 2016 The Parties were informed that the proposal to disqualify Sir

Stanley Burnton would be decided according to Article 58 of the

ICSID Convention, and the proceeding was suspended until such

decision was made, in accordance with ICSID Arbitration Rule 9(6).

5 July 2016 The Claimant filed observations on the proposal for

disqualification.

7 July 2016 The Tribunal consented to the resignation of Sir Stanley Burnton, in

accordance with ICSID Arbitration Rule 8(2) and the Secretary-

General notified the Parties of the vacancy on the Tribunal and

invited the Claimant to appoint the missing arbitrator.

Page 10: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

3

8 July 2016 The Claimant appointed Justice David Unterhalter SC, a national of

South Africa.

11 July 2016 Following Justice David Unterhalter’s acceptance of his

appointment as arbitrator, the Tribunal was reconstituted.

July - August 2016 Correspondence was exchanged between the Parties and the

Tribunal regarding a date for the first session, which was set for 5

August 2016.

3 August 2016 The Respondent’s request for adjournment, based on the Attorney

General of Tanzania not being available, was rejected by the

Tribunal on 3 August 2016.

4 August 2016 The Respondent informed the Tribunal that the Attorney General

of Tanzania had instructed counsel to not attend the first session in

his absence.

5 August 2016 The Tribunal held the first session at the IDRC in London and the

participants were the Members of the Tribunal, Mr Francisco

Abriani, ICSID Legal Counsel, and counsel for the Claimant.

15 August 2016 The Respondent filed a request to address the Respondent’s

objections to jurisdiction and admissibility as preliminary

questions (“Respondent’s Application for Bifurcation”) with

legal authorities RL-001 through RL-010.

2 September 2016 The Claimant submitted its Response to the Respondent’s

Application for Bifurcation (“Claimant’s Response to the

Application for Bifurcation”) with exhibits C-047 through C-075

and legal authorities CL-002 through CL-004.

15 and 20 September

2016

On 15 and 20 September 2016, the Claimant submitted additional

exhibits, C-076 and C-077.

23 September 2016 The Tribunal held the Hearing on Bifurcation in London at the IDRC.

The following persons participated to the hearing:

Members of the Tribunal: Prof Lawrence Boo, President of the Tribunal Mr David Unterhalter SC, Arbitrator Dr Kamal Hossain, Arbitrator ICSID Secretariat: Mr Marco Tulio Montañés-Rumayor, Legal Counsel

Page 11: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

4

On behalf of the Claimant: Mr Joseph Casson, Standard Chartered Bank (Hong Kong) Limited Mr James Denham, Standard Chartered Bank Mr Matthew Weiniger QC, Linklaters LLP Mr Iain Maxwell, Herbert Smith Freehills LLP Mr Dominic Kennelly, Herbert Smith Freehills LLP Mr Adam McWilliams, Herbert Smith Freehills LLP Mr Divyanshu Agrawal, Herbert Smith Freehills LLP On behalf of the Respondent: Mr Beredy Malegesi, Crax Law Partners Prof Bonaventure Rutinwa, R.K. Rweyongeza & Co. Advocates Mr David Hesse, Curtis, Mallet-Prevost, Colt & Mosle LLP Mr Galileo Pozzoli, Curtis, Mallet-Prevost, Colt & Mosle LLP Ms Luciana Ricart, Curtis, Mallet-Prevost, Colt & Mosle LLP Mr James Cockburn, Curtis, Mallet-Prevost, Colt & Mosle LLP Mr Valerio Salvatori, Curtis, Mallet-Prevost, Colt & Mosle LLP Ms Rebecca Johnston, Curtis, Mallet-Prevost, Colt & Mosle LLP Mr Dav Holat, IT technician, Curtis, Mallet-Prevost, Colt & Mosle LLP

26 September 2016 The Claimant submitted an additional legal authority, CL-005, and

several additional exhibits, C-078 and C-079.

11 October 2016 The Tribunal issued Procedural Order No. 2 (“PO 2”) concerning

procedural matters. On the same date, the Tribunal issued

Procedural Order No. 3 (“PO 3”) setting forth its decision not to

bifurcate the proceedings.

16 December 2016 The Claimant filed its Memorial on the Merits (“Claimant’s

Memorial”) with the witness statement of Mr Gaspar Asheri Nyika,

dated 16 December 2016, the expert reports of Mr Colin Johnson

and Mr Nicholas Zervos, dated 16 December 2016, exhibits C-080

through C-218 and legal authorities CL-006 through CL-055.

26 June 2017 The Respondent filed its Memorial on Objections to Jurisdiction and

Counter-Memorial on the Merits (“Respondent’s Counter-

Memorial”) together with exhibits R-001 through R-071 and legal

authorities RL-011 and RL-094.

17 July 2017 The Tribunal issued Procedural Order No. 4 (“PO 4”) concerning

the procedural calendar, ordering that the Claimant’s Rejoinder on

Jurisdiction would be due on 2 March 2018.

Page 12: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

5

11 September 2017 The Tribunal issued Procedural Orders 5a (“PO 5a”) and 5b (“PO

5b”) on production of documents by the Respondent and the

Claimant respectively.

10 November 2017 The Claimant filed its Counter-Memorial on Jurisdiction and Reply

on the Merits ( “Claimant’s Reply”), along with the second witness

statement of Mr Gaspar Asheri Nyika, dated 9 November 2017, the

witness statement of Mr Kieran Day, dated 10 November 2017, the

witness statement of Mr Joseph Wesley Casson dated 15 November

2017, the expert report of Mr David Chivers QC, dated 8 November

2017, the second expert report of Mr Nicholas Zervos, dated 10

November 2017, exhibits C-219 through C-399 and legal

authorities CL-056 through CL-189.

7 December 2017 The Respondent requested an extension of “at least three months”

to file its Rejoinder on the Merits and Reply on Jurisdiction due on

29 January 2018.

12 December 2017 The Claimant objected to this extension request.

4 January 2018 The Tribunal granted the Respondent’s requested time extension

for filing its Rejoinder on Merits and Reply on Jurisdiction.

11 January 2018 The Tribunal confirmed that the April hearing dates were vacated

and that the Hearing on Jurisdiction and Merits would take place in

London from 16-27 July 2018.

16 January 2018 The Tribunal issued Procedural Orders 6a (“PO 6a”) and 6b (“PO

6b”) concerning production of documents.

30 January 2018 The Tribunal issued Procedural Order No. 7 (“PO 7”) concerning

the procedural calendar.

1 March 2018 Curtis, Mallet-Prevost, Colt & Mosle LLP informed the Tribunal that

they were no longer representing the Respondent.

2 May 2018 The Tribunal granted the Parties’ April 2018 requests for an

extension of time to file their submissions and informed the Parties

that it would have an organizational conference call.

17 May 2018 The President held an organizational conference call with the

Parties to receive updates and clarifications regarding the

Page 13: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

6

Respondent’s representation in these proceedings and to discuss

procedural issues related to this matter.

23 May 2018 The Respondent filed its Rejoinder on the Merits and Reply on

Jurisdiction (“Respondent’s Rejoinder”), along with exhibits R-

072 through R-097 and legal authorities RL-095 through RL-142.

1 June 2018 Further to the Parties’ respective letters of 25 and 31 May 2018, the

Tribunal informed the Parties that further evidence shall only be

permitted if and when the Tribunal so directs.

14 June 2018 The Parties were invited to consider the appointment of Ms

Elizabeth Wu as assistant to the President, as well as the

appointment of Mr Moin Ghani, as assistant to Dr Kamal Hossain.

The Parties were also invited to provide their position on the

attendance of the above-mentioned individuals and Ms Chloé

Terrapon Chassot, as observer, to the Hearing on Jurisdiction and

Merits.

20 and 27 June 2018 The Parties confirmed that they did not object to the appointment

of Ms Elizabeth Wu and Mr Moin Ghani as assistants nor to the

attendance of Ms Chloe Terrapon Chassot at the hearing.

2 July 2018 The Claimant filed its Rejoinder on Jurisdiction (“Claimant’s

Rejoinder on Jurisdiction”) with exhibits C-403 through C-408

and legal authorities CL-190 through CL-208.

4 July 2018 The President held a pre-hearing organizational meeting with the

Parties by telephone conference.

5 July 2018 The Parties were requested to clarify their positions regarding how

the Claimant’s witness statements ought to be evidentiarily treated,

given that the Respondent did not intend on cross-examining any

of the Claimant’s witnesses or experts.

6 and 8 July 2018 The Parties submitted their positions regarding the issue of the

Claimant’s witnesses.

10 July 2018 The Respondent confirmed that Curtis, Mallet-Prevost, Colt & Mosle

LLP was retained to represent it. On the same date, the Tribunal

decided that the Hearing on Jurisdiction and Merits would take

Page 14: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

7

place from 16-24 July 2018 and decided on the issue of the

Claimant’s witnesses.

12 July 2018 A letter said to be from Mr Harbinder Singh Sethi on IPTL letterhead

addressed to the Secretary of the Tribunal, was sent by email

through the Ukonga Central Prison at Dar Es Salaam seeking the

Tribunal’s permission to “join IPTL/PAP or alternatively for

IPTL/PAP to be called as witnesses in the pending proceedings”. Upon

the confirmation from the Parties during the Hearing, the Tribunal

declined to accede to the request.1

16 July 2018 At the Hearing on Jurisdiction and Merits, Ms Elizabeth Wu, Mr

Moin Ghani and Ms Chloe Terrapon Chassot provided the Parties

with their respective signed terms of reference and declarations of

their independence and impartiality.

On the same date, the Tribunal granted the Parties’ requests, of 12

and 13 July 2018, to admit RL-143 and RL-144 and C-409 onto the

record.

16-23 July 2018 A Hearing on Jurisdiction and Merits was held, at the IDRC in

London. The following persons participated at the hearing:

Members of the Tribunal: Prof Lawrence Boo, President of the Tribunal Justice David Unterhalter SC, Arbitrator Dr Kamal Hossain, Arbitrator Tribunal Assistants / Observer: Ms Elizabeth Wu, Assistant to Mr Lawrence Boo, President Mr Moin Ghani, Assistant to Dr Kamal Hossain, Co-Arbitrator Ms Chloé Terrapon Chassot, Observer ICSID Secretariat : Ms Geraldine Fischer, Acting Secretary of the Tribunal On behalf of the Claimant: Counsel: Mr Matthew Weiniger QC, Linklaters LLP Mr Iain Maxwell, Herbert Smith Freehills LLP Ms Elizabeth Kantor, Herbert Smith Freehills LLP Mr Aaron McDonald, Herbert Smith Freehills LLP Mr Harry Ormsby, Herbert Smith Freehills LLP

1 Tr. Day 6 [1304:8-15].

Page 15: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

8

Mr Gavin Creelman, Herbert Smith Freehills LLP Mr Joel Fenster, Herbert Smith Freehills LLP Ms Olga Timiryasova, Herbert Smith Freehills LLP Parties: Mr James Denham, Standard Chartered Bank Mr Oliver Perez, Standard Chartered Bank Mr Daniel Knowles, Standard Chartered Bank Witnesses: Mr Joseph Casson, Standard Chartered Bank (Hong Kong) Ltd Mr Kieran Day, The Business Advisory Group Mr Gaspar Nyika, IMMA Advocates Experts: Mr Colin Johnson, Charles River Associates Mr Sandy Cowan, Grant Thornton Mr Nicholas Zervos, Velma Law On behalf of the Respondent: Counsel: Mr Galileo Pozzoli, Curtis, Mallet-Prevost, Colt & Mosle LLP Mr Tullio Treves, Curtis, Mallet-Prevost, Colt & Mosle LLP Mr Mark Handley, Curtis, Mallet-Prevost, Colt & Mosle LLP Ms Luciana Ricart, Curtis, Mallet-Prevost, Colt & Mosle LLP Ms Irene Petrelli, Curtis, Mallet-Prevost, Colt & Mosle LLP Mr Renato Treves, Curtis, Mallet-Prevost, Colt & Mosle LLP Mr Valerio Salvatori, Curtis, Mallet-Prevost, Colt & Mosle LLP Ms Neza Hren, Curtis, Mallet-Prevost, Colt & Mosle LLP Ms Clarissa Manfré, Curtis, Mallet-Prevost, Colt & Mosle LLP Mr Dav Holat, Curtis, Mallet-Prevost, Colt & Mosle LLP Mr Lee Southon, Curtis, Mallet-Prevost, Colt & Mosle LLP Mr Omar Gargash, Curtis, Mallet-Prevost, Colt & Mosle LLP Mr Beredy Malegesi, Crax Law Partners in Association with RK Rweyongeza and Co. Advocates Mr Makubi Kunju Makubi, Crax Law Partners in Association with RK Rweyongeza and Co. Advocates Mr Andrea Cardani, EconOne Mr Brendan Moore, EconOne Parties: Mr Clement Mashamba, United Republic of Tanzania Mr George Mandepo, United Republic of Tanzania Ms Hosana Jacob Mgeni, United Republic of Tanzania

Page 16: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

9

23 July 2018 The Tribunal granted the Claimant’s request to admit exhibits C-

410 through C-414, and legal authorities, CL-209 through CL-212.

8 August 2018 The Parties were informed that Ms Geraldine Fischer, ICSID Legal

Counsel, had been assigned to serve as Secretary of the Tribunal.

7 September 2018 The Parties filed simultaneous Post-Hearing Briefs (“PHB”) with

the accompanying exhibits and legal authorities. The Claimant also

filed an updated expert report of Mr Colin Johnson.

21 September 2018 The Parties filed simultaneous Reply Post-Hearing Briefs (“Reply

PHB”) with the accompanying exhibits and legal authorities

together with their submissions on costs.

27 September 2018 The Parties were invited to consider the appointment of Ms Sukriti

Slehria to replace Ms Wu as assistant to the President. By

correspondence of 27 and 28 September 2018, the Parties

confirmed that they did not object to the appointment, and Ms

Slehria provided the Parties with her signed terms of reference and

declaration of her independence and impartiality.

28 August 2019 The proceeding was declared closed.

III. FACTUAL BACKGROUND

The Tribunal provides below a brief summary of the factual background of the events before

the dispute as set out in the Parties’ submissions in the arbitration. This summary does not

constitute any finding by the Tribunal on any facts disputed by the Parties. A detailed analysis

of the facts relevant to the Tribunal’s determinations on jurisdiction and liability are

contained in Sections V and VI.

A. THE FACILITY AND KEY AGREEMENTS2

On 28 September 1994, Mechmar Corporation (Malaysia) Berhad (“Mechmar”) (a Malaysian

company) and VIP Engineering and Marketing Limited (“VIP”) (a Tanzanian Company)

entered into a Promoters/Shareholders Agreement (“PSA”) wherein the parties agreed “to

2 HB/A/002/035-143: Claimant’s Memorial, paras. 32-40; HB/A/003/144-370: GoT's Memorial on Objections to Jurisdiction and Counter-Memorial on the Merits (“Respondent’s Counter-Memorial”), paras. 10-16.

Page 17: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

10

form a private limited company incorporated in Tanzania”;3 and it was set out that the “main

object” of the company would be to apply for the operating licence to build, construct and

operate a 100 megawatts (“MW”) power plant for 20 years pursuant to the Memorandum of

Understanding signed between Mechmar and the Tanzanian Ministry of Water Energy and

Minerals dated 27 August 1994; with Mechmar contributing 70% of the paid-up capital and

VIP contributing 30% of the paid-up capital for which “cash [USD 300,000 was] to be advanced

by [Mechmar] subject to clause 2(ii)(a)(b)(c) and (d)” of the PSA.4

On 1 November 1994, the company IPTL was “incorporated under the Companies Ordinance

[1921] (Cap. 2012)” in Tanzania as a joint venture company between Mechmar (holding 70%

of the shares) (“Mechmar Shares”) and VIP (holding 30% of the shares) ("VIP Shares").5

Several agreements were entered into in 1995, including financing arrangements.

(1) Power Purchase Agreement

On 26 May 1995, IPTL and Tanzania Electric Supply Company Limited (“TANESCO”),

concluded the Power Purchase Agreement (“PPA”).6 Under the PPA, IPTL undertook to

design, construct, own, operate and maintain an electricity generating facility (“Facility” or

“Power Plant”) with a nominal net capacity of 100 megawatts to be located in Tegeta, Dar es

Salaam for the generation and sale of electricity, and to deliver the electricity it generated to

TANESCO as and when required, for an initial period of 20 years, subject to extensions for

further periods (“Project”). The PPA is governed by Tanzanian law and contains an ICSID

arbitration clause.7

(2) Implementation Agreement

By Implementation Agreement dated 8 June 1995 signed by IPTL and GoT, the GoT gave

various undertakings and assurances in favour of IPTL and “its permitted successors and

assigns”, including undertakings against discriminatory action and expropriation, and

granted IPTL the exclusive right to design, finance, insure, construct, complete, own, operate

3 HB/C/001/001-012: Shareholders Agreement between VIP and Mechmar, 28 September 1994, para. A. 4 HB/C/001/001-012: Shareholders Agreement between VIP and Mechmar, 28 September 1994, paras. 2(a), 2(i)(b). 5 HB/H/002/002: Certificate of Incorporation of IPTL, 1 November 1994; HB/A/002/035-143: Claimant’s Memorial, para. 33; HB/A/003/144-370: Respondent’s Counter-Memorial, para. 11. 6 HB/C/002/013-128: Power Purchase Agreement (“PPA"), 26 May 1995. 7 HB/C/002/013-128: PPA, 26 May 1995, Recitals, Articles 2.1, 2.2, 18.3, 19.4.

Page 18: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

11

and maintain the Facility. The Implementation Agreement is governed by Tanzanian law and

contains an ICSID arbitration clause.8

The GoT also agreed to execute a guarantee, attached as Schedule 1 to the Implementation

Agreement (“Guarantee”), undertaking to pay to IPTL any sums owed by TANESCO under

the PPA should TANESCO failed to pay.9

(3) Facility Agreement

IPTL raised the majority of the funds by means of a loan provided by a consortium of foreign

lenders (several Malaysian banks) under the “Loan Facility Agreement relating to the 100 MW

Tegeta Power Project” dated 28 June 1997 (“Facility Agreement”).10 The loan was to be

repaid from the cash flows generated by IPTL under the PPA. The Facility Agreement

contained a non-exclusive English jurisdiction clause and was governed by English law.11

(4) Security Deed

By Security Deed dated 28 June 1997 (“Security Deed”),12 IPTL assigned all its present and

future rights, title and interest in and to the Assigned Contracts (which included the PPA and

the Implementation Agreement) to the lenders’ nominated Security Agent as security for the

loan. The Security Deed contained a non-exclusive English jurisdiction clause and was subject

to English law.13

(5) Shareholder Support Deed

By a “Shareholder Support Deed”14 dated 28 June 1997, Mechmar and VIP agreed to

subscribe to the shareholders’ funds of IPTL and bound themselves not to sell, transfer or

otherwise dispose the Shareholders’ Funds and undertook, inter alia, not to take any action

in furtherance of the winding up, liquidation or dissolution of IPTL.

8 HB/C/004/132-191: Signed Implementation Agreement (without Schedules), 8 June 1995, Articles XXI, 24.8. 9 HB/C/004/132-191: Signed Implementation Agreement (without Schedules), 8 June 1995, Article XXII. 10 HB/C/008/280-365: Facility Agreement, 28 June 1997. 11 HB/C/008/280-365: Facility Agreement, 28 June 1997, Clause 33. 12 HB/C/009/366-457: Security Deed, 28 June 1997, Clause 3.2. 13 HB/C/009/366-457: Security Deed, 28 June 1997, Clause 20. 14 HB/C/011/474-511: Shareholder Support Deed between Mechmar and VIP (as Shareholders) and IPTL (as Borrower) and SIME Bank (as Security Agent), 28 June 1997.

Page 19: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

12

(6) Charge of Shares

By a “Charge of Shares” dated 28 June 1997, Mechmar and VIP charged their shares in IPTL

to the Security Agent as security for the loan and agreed that, in an “Event of Default” under

the Facility Agreement, the shareholders would cease to be authorised to exercise rights with

respect to the shares, and the Security Agent alone would be entitled to exercise such rights.

The Charge of Shares contained a non-exclusive English jurisdiction clause and was governed

by Tanzanian law.15

(7) Lenders and Security Agents

The original lenders were a consortium of Malaysian banks.16 The Facility Agreement and the

other related documents were restructured between 1999 and 2005.17

In 2001 and 2003, IPTL and Danaharta Managers (L) Ltd (“Danaharta”) (which had

succeeded the Malaysian banks under the Facility Agreement) restructured the loan due

under the Facility Agreement into two new loans (“Term Loan 1” and “Term Loan 2”)

(collectively referred to as the “Loan” or “Term Loans” or “Loans”). These loans globally

amounted to USD 120 million.18

In August 2005, SCB HK acquired the Loan and related security from Danaharta under a “Sale

and Purchase Agreement (Loan Account – Independent Power Tanzania Limited)” dated

August 2005.19

15 HB/C/010/458-473: Charge of Shares between (1) Mechmar Corporation (Malaysia) Berhad, (2) VIP engineering and Marketing Limited and (3) Sime Bank Berhad, 28 June 1997, Clauses 5, 16.1 and 16.2. 16 See paras. 75 to 77 below. 17 See paras. 82 to 86 below. 18 HB/A/002/035-143: Claimant’s Memorial, paras. 57-58; HB/A/003/144-370: Respondent’s Counter-Memorial, para. 28. 19 HB/C/013/535-551: Sale and Purchase Agreement for Loan Account – IPTL between Danaharta Managers and SCB, 4 August 2005.

Page 20: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

13

B. INTERNATIONAL PROCEEDINGS, TANZANIAN COURT PROCEEDINGS AND OTHER DISPUTES

(1) ICSID 1 Proceedings20

On 25 November 1998, TANESCO commenced ICSID arbitration proceedings against IPTL

under the PPA, claiming that it was entitled to terminate the PPA on account of breaches by

IPTL, and sought for the tariff to be adjusted (“ICSID 1 Proceedings”).21

The tribunal in the ICSID 1 proceedings (“ICSID 1 Tribunal”) upheld the PPA as a “valid and

effective contract,” but also ruled that IPTL could not recover certain costs incurred during

the construction phase through the tariff charges under the PPA. The ICSID 1 Award issued

on 12 July 200122 incorporated a financial model (Appendix F annexed to the ICSID 1 Award),

which was in accordance with the parties’ agreement and “was to act as the method for

calculating the tariff payments to be made by Tanesco to IPTL following the commencement of

commercial operations” under the PPA.23

(2) Shareholder Dispute and Winding Up Petition24

After the ICSID 1 Award, disputes arose between VIP and Mechmar relating to the attribution

of the construction costs that the ICSID 1 Tribunal had decided were not recoverable. On 25

February 2002, VIP filed a petition with Tanzanian courts seeking the winding up of IPTL,

among other things, on the ground that IPTL was being “run as an incorporated partnership

(quasi-partnership)” (“Winding Up Petition”).25 IPTL applied to stay and dismiss this

petition. Mechmar commenced an arbitration under the rules of the LCIA pursuant to the

terms of the PSA. The tribunal in the LCIA arbitration ordered VIP to discontinue the Winding

Up Petition in its final award dated 26 August 2003 (“LCIA Award”).26 Mechmar then filed an

application before the High Court of Tanzania seeking enforcement of the LCIA Award, and

20 HB/A/002/035-143: Claimant’s Memorial, paras. 60-65; HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 19-21. 21 HB/D/002/066-299 at pg. 74: Final Award, ICSID Case No. ARB/98/8 (“ICSID 1 Award”), 12 July 2001, para. 19. 22 HB/D/002/066-299: ICSID 1 Award, 12 July 2001. 23 HB/A/002/035-143: Claimant’s Memorial, paras. 54-55. 24 HB/A/002/035-143: Claimant’s Memorial, paras. 60-65. 25 HB/H/037/709-725 at pg. 723: VIP Engineering and Marketing Ltd v Independent Power Tanzania Limited, High Court of Tanzania, Misc. Civ. Cause No. 49 of 2002, Petition under Sections 163 and 167(b) & (f) of the Companies Ordinance, Cap. 212 (“Winding Up Petition”), 25 February 2002. 26 HB/D/007/616-639: Award in LCIA Arbitration No. 2353 between Mechmar and VIP (“LCIA Award”), 26 August 2003.

Page 21: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

14

this application was eventually dismissed with “costs for Mechmar’s failure to prosecute its

case” on 31 October 2008.27

(3) Tariff Dispute28

On 5 July 2006, GoT, IPTL and the Bank of Tanzania (“BoT”) (as the Escrow Agent) entered

into an Escrow Agreement, which established an account for GoT to pay into (“Escrow

Account”)29 and maintain a two-months equivalent of tariff payments due to IPTL under the

PPA as GoT’s fulfilment of its obligation to provide security.

Following certain tariff disputes between TANESCO and IPTL, as from May 2007 (“Tariff

Dispute”), TANESCO stopped making tariff payments under the PPA and instead made

payments into the Escrow Account.30

(4) Interpretation Proceedings and the Revised Administration Petition31

In June 2008, IPTL started proceedings seeking an interpretation of the ICSID 1 Award

pursuant to Article 50 of the ICSID Convention (“Interpretation Proceedings”), which were

ultimately discontinued on 19 August 2010, following various events.32 The Claimant sought

to intervene in the Interpretation Proceedings, but its efforts (so it contends) were frustrated

by the actions of TANESCO and GoT, which conspired with Mechmar to purchase the

Mechmar Shares in return for Mechmar withdrawing the Interpretation Proceedings.33 This

is contested by the Respondent.34 In this context, the Claimant filed two applications with the

High Court of Tanzania for the appointment of an administrator to IPTL; the first

administration petition was allowed by Mihayo J’s Ruling35 and Mihayo J’s Ruling was

overturned by the Court of Appeal in its Ruling of 9 April 200936 and then the second petition

27 HB/H/097/1020-1030 at pgs. 1028-1030: Judgment of Oriyo J in the Tanzanian Court, 31 October 2008. 28 HB/A/002/035-143: Claimant’s Memorial, paras. 71-72. 29 HB/C/015/558-582: Escrow Agreement between GoT, IPTL, and Bank of Tanzania (“BoT”), 5 July 2006. 30 HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 39 and 95. 31 HB/A/002/035-143: Claimant’s Memorial, paras. 73-84. 32 See paras. 310 to 311 below. 33 HB/A/002/035-143: Claimant’s Memorial, paras. 88-90. 34 HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 39-52. 35 HB/H/112/1185-1195: Order of the High Court of Tanzania, 27 January 2009. 36 HB/H/117/1205-1231: Ruling of Court of Appeal of Tanzania, 9 April 2009.

Page 22: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

15

was filed by the Claimant on 17 September 2009 (“Revised Administration Petition”)

which it withdrew in 2013.37

On 15 December 2008, SCB HK appointed a receiver over VIP’s shares in IPTL,38 and later

appointed a receiver over Mechmar’s shares in IPTL.39

(5) Interim PPA40

On 16 December 2008, the High Court of Tanzania appointed the “Administrator

General/Official Receiver”, Mr T Rugonzibwa as the provisional liquidator (“First Provisional

Liquidator” or “First PL”) of IPTL pursuant to the Winding Up Petition.41 In October or

November 2009, the First PL resumed operation of the Power Plant in response to power

shortages in Tanzania. The First PL on behalf of IPTL entered into an interim power purchase

agreement with TANESCO (“Interim PPA”) on 5 February 2010.42

(6) PPA Arbitration43

Following the discontinuation of the Interpretation Proceedings on 19 August 2010, the

Claimant initiated ICSID proceedings on 15 September 2010 against TANESCO to recover

sums under the PPA in its capacity as assignee of the PPA (“PPA Arbitration”). The tribunal

in the PPA Arbitration (“PPA Tribunal”) issued its Decision on Jurisdiction and Liability on

12 February 2014 (“PPA Decision”),44 and in its Final Award dated 12 September 2016

(“PPA Award”)45 found, among other things, that “payment out of the Escrow Account to

IPTL/ PAP did not discharge TANESCO’s obligation to SCB HK under the PPA” and ordered

37 HB/H/353/4954-4964: Standard Chartered Bank (Hong Kong) Limited v IPTL and others, High Court of Tanzania, Misc. Civil Cause No. 112 of 2009, Ruling (Utamwa J), 6 December 2013. 38 HB/H/101/1051-1075 at pg. 1052: Letter from RHB Bank Berhad to ICSID, 15 December 2008. 39 HB/A/002/035-143: Claimant’s Memorial, para. 78. 40 HB/A/002/035-143: Claimant’s Memorial, paras. 85-87; HB/A/003/144-370: Respondent’s Counter-Memorial, para. 55. 41 HB/H/104/1583-1599 at pg. 1599: High Court of Tanzania's Appointment of PL, 16 December 2008; HB/A/002/035-143: Claimant’s Memorial, para. 79. 42HB/H/142/1972-1974: Letter from the Ministry of Energy and Minerals, Tanzania to the Provisional Liquidator, IPTL, 12 March 2010. 43 HB/A/002/035-143: Claimant’s Memorial, paras. 20 and 91. 44 HB/D/004/367-479: Decision on Jurisdiction and Liability in ICSID Case No. ARB/10/20 (“PPA Decision”), 12 February 2014. 45 HB/D/005/480-586: Final Award of the Tribunal in the PPA Arbitration (“PPA Award”), 12 September 2016.

Page 23: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

16

TANESCO to pay to SCB HK an amount of USD 148.4 million plus interest.46 TANESCO filed an

application for annulment of the PPA Award on 6 January 2017.47

The ICSID ad hoc Annulment Committee dismissed TANESCO’s annulment application on 22

August 2018.48

(7) Proceedings in Malaysia and in the British Virgin Islands (“BVI”)49

In August 2010, SCB HK filed proceedings in Malaysia seeking interim relief against Mechmar

alleging that Mechmar had breached the Charge of Shares and “threatened to sell the Subject

Shares [Mechmar Shares] to the Government of Tanzania.”50 The High Court of Malaya

(“Malaysian Court”) issued an interlocutory injunction restraining Mechmar from

transferring the Mechmar Shares.51 Mechmar’s legal representatives informed SCB HK that

the Mechmar Shares were sold by Mechmar on 9 September 2010.52 Pursuant to an Ex parte

Injunction Order by the Malaysian Court53 ordering Mechmar to furnish documents regarding

the sale of Mechmar Shares, it produced the Share Sale Agreement dated 9 September 2010

entered between Mechmar and Piper Link Investments Ltd (“Piper Link”) (a company

incorporated in BVI).

Ms Martha Renju, in her capacity as receiver of shares of IPTL, then applied for and obtained

an ex parte order in BVI against Piper Link to deliver the share certificates to the High Court

of the BVI (“BVI Court”) and to take no further steps to transfer, dispose of or otherwise deal

with the Mechmar Shares pending trial.54

On 11 April 2011, the BVI Court ordered summary judgment in favour of Martha Renju.55

46 HB/D/005/480-586 at pgs. 584 and 585: PPA Award, 12 September 2016. 47 HB/H/459/6911-6930: PPA Arbitration, TANESCO’s Application for Annulment, 6 January 2017. 48 Exhibit CL-216: Standard Chartered Bank (Honk Kong) Limited v Tanzania Electric Supply Company Limited, ICSID Case No. ARB/10/20, Decision on Annulment, 22 August 2018 (filed along with Claimant’s Post-Hearing Brief (“Claimant’s PHB”)). 49 HB/A/002/035-143: Claimant’s Memorial, paras. 92-100; HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 62-64. 50 HB/H/153/2113-2119: Amended Statement of Claim in SCB HK v Mechmar before the High Court of Malaya, 9 August 2010, para. 13. 51HB/D/008/640-642: Interlocutory Injunction Order of the High Court of Malaya in SCB HK v Mechmar, 4 October 2010. 52 HB/H/159/2232: Letter from Teh & Associates to M/s SK Yeoh & Partners, 12 October 2010. 53 HB/D/010/647-654: Ex Parte Injunction Order of the High Court of Malaya in SCB HK v Mechmar, 19 October 2010. 54 HB/D/014/665-671: Freezing and Custody Order of the High Court of British Virgin Islands (“BVI Court”) in Renju v Piper Link, 8 November 2010. 55 HB/D/015/672-674: BVI proceedings (Renju v Piper Link), Order for Summary Judgment, 11 April 2011.

Page 24: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

17

(8) Winding Up Order and Setting Aside56

On 15 July 2011, the High Court of Tanzania ordered the winding-up of IPTL (“Winding Up

Order”) on the application of VIP’s 2002 petition (see paragraph 21 above) and appointed

the “[Administrator General/]Official Receiver, Mr Philip Saliboko as the “Liquidator” of

IPTL.57

After the Winding Up Order, the Claimant, submitted a proof of debt to the Liquidator wherein

it stated, among other things, that it was owed by IPTL a sum of “US$ 125,970,570.67 for

monies advanced pursuant to the […] loan Agreement […] (including interest) together with

insurance premia and enforcement costs […]”;58 and referred to “Security” documents

(including the Charge of Shares and Security Deed) which it highlighted secured “all monies,

debts and liabilities” owed by IPTL to it.59 Pricewaterhouse Coopers produced a report dated

March 2012 (“PwC Report”)60 in its advice to the Liquidator, in which they confirmed the

validity of the loan, and made their conclusions on SCB HK’s security, including that SCB HK

“is a valid creditor of IPTL.”61 The Parties dispute the consequences of the PwC Report’s

conclusions.62

On 17 December 2012, the Winding Up Order was set aside63 by the Tanzanian Court of

Appeal.64 The Court declared all proceedings (viz. proceedings in Misc. Civil Cause No 49 of

2002 and Misc. Civil Cause No. 243 of 2003) a “nullity”; rulings and orders made therein

relating to VIP’s Winding Up Petition that post-dated the Claimant’s Revised Administration

Petition were “…quashed and set aside”, and ordered that Claimant’s Revised Administration

Petition be heard expeditiously by the High Court of Tanzania. Consequently, IPTL reverted

56 HB/A/002/035-143: Claimant’s Memorial, paras. 101-102, 105-115. 57 HB/H/184/2508-2512: Winding Up Order of Kaijage J., 15 July 2011. 58 HB/H/218/3133-3137 at pg. 3133: Proof of Debt submitted by SCB HK to the Liquidator, 24 April 2012. 59 HB/H/218/3133-3137 at pg. 3135: Proof of Debt submitted by SCB HK to the Liquidator, 24 April 2012. 60 HB/H/220/3140-3213: Price Waterhouse Cooper’s Report entitled "IPTL Creditor Claim Assessment", 29 April 2012. 61 HB/H/220/3140-3213: Price Waterhouse Cooper’s Report entitled "IPTL Creditor Claim Assessment", 29 April 2012, para. 1.2.1. 62 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 69. 63 HB/H/258/3725-3752: Decision of the Court of Appeal of Tanzania, 17 December 2012. 64 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 73.

Page 25: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

18

to the state it was before the Winding Up Order and Mr Saliboko was appointed as provisional

liquidator (“Second Provisional Liquidator” or “Second PL”) of IPTL.65

On 9 April 2013, Mr Lutema served a petition on behalf of Mechmar to enforce the LCIA

Award (“Lutema Petition”)66 and sought the discontinuance of Misc. Civil Cause No. 49 and

Misc. Civil Cause No. 254 of 2003.67 The Lutema Petition and the Revised Administration

Petition were consolidated on 3 May 2013.68 On 5 May 2013, Utamwa J in his Order dated 7

May 2013, directed that the Provisional Liquidator of IPTL and Mechmar be both entitled to

be heard in respect of SCB HK’s Revised Administration Petition.69

(9) Winding Up Order in Respect of Mechmar

On 18 May 2012, a winding up order in respect of Mechmar was made by the Malaysian

Court.70 According to the Claimant, since late 2011, Mr Sethi and his advocate Mr Lutema had

been acting for and representing Mechmar in various court proceedings in Tanzania.

Mechmar’s liquidators informed Mr Lutema that only the liquidators had authority to act for

Mechmar. 71 Mechmar’s liquidators72 obtained, on 16 April 2013, directions from the

Malaysian Court (High Court of Malaya) that they had sole power to act on behalf of

Mechmar.73

(10) Utamwa J Order

On 26 August 2013, VIP gave notice that it would be applying to withdraw the Winding Up

Petition over IPTL and all ancillary applications by VIP in consolidating Misc. Civil Cause No.

49 of 2002 and Misc. Civil Cause No. 254 of 200374 enclosing the Share Purchase Agreement

65 HB/H/274/4319-4228 at pgs. 4321-4322: Letter from Mr Saliboko, The Official Receiver and Provisional Liquidator of IPTL, to the Tribunal in ICSID ARB/10/20 (PPA Arbitration), para. 6; HB/A/002/035-143: Claimant’s Memorial, para. 114; HB/A/003/144-370: Respondent’s Counter-Memorial, para. 68. 66 HB/A/002/035-143: Claimant’s Memorial, para. 119. 67 HB/H/266/4245-4282: Petition filed before the High Court of Tanzania by Asyla Attorneys, 9 April 2013. 68 HB/H/272/4311-4314 at pg. 4314: Order of the High Court of Tanzania (Utamwa J), 7 May 2013. 69 HB/H/272/4311-4314: Order of the High Court of Tanzania (Utamwa J), 7 May 2013; HB/A/002/035-143: Claimant’s Memorial, paras. 118-125. 70 HB/D/012/660-661: Order of the High Court of Malaya, 18 May 2012. 71 HB/A/002/035-143: Claimant’s Memorial, paras. 116-117. 72 Heng Ji Keng and Michael Joseph Monteiro were the Liquidators of Mechmar. 73 HB/D/013/662-664: Directions from the High Court of Malaya, 16 April 2013. 74 HB/H/288/4507-4537: Application by VIP to the High Court of Tanzania, 26 August 2013.

Page 26: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

19

dated 15 August 201375 entered between VIP and PAP for the sale of VIP’s 30% shareholding

in IPTL to PAP (“VIP-PAP-SPA”), and on 30 August 2013 VIP also tendered before the High

Court the draft terms of order to be made by the Court.76

On 5 September 2013, Utamwa J granted this application and ordered inter alia that all of

IPTL’s affairs, including the PPA and the control of the Facility, be transferred to PAP

(“Utamwa J Order”).77 The Utamwa J Order was rendered in the proceedings Misc. Civil

Cause Nos. 49 of 2002 and 254 of 2003 that corresponded to IPTL’s Winding Up Petition and

an application to set aside the LCIA Award, both commenced by VIP, and to which the

Claimant was not party to either of those two proceedings.78

The Utamwa J Order is one of the principal matters relied on by the Claimant in this

arbitration to support its claim relating to expropriation. The Claimant contends that the

reasoning is “inexplicable” and that the proceeding leading up to it was “unjust”, for several

reasons: (i) it was made without notice to interested parties; (ii) it was made without giving

the interested parties an opportunity to be heard; (iii) it was made in disregard of the Court

of Appeal’s judgment of 17 December 2012 described above; (iv) it was inconsistent with

Utamwa J’s own earlier order dated 5 June 2013; (v) it was made pursuant to the VIP-PAP-

SPA notwithstanding the fact that the assertion in the VIP-PAP-SPA that PAP purchased the

Mechmar Shares in 2011 was contrary to the evidence; (vi) it was made with the express

consent of the Second PL, who was on notice of SCB HK’s rights; and (vii) it did not explain

the legal basis on which control of IPTL and its assets could be passed to PAP on the

application of VIP (as minority shareholder), without reference to SCB HK’s rights.79

The Respondent rejects these contentions.80 According to the Respondent, SCB HK, despite

not being a party to Misc. Civil Cause Nos. 49 of 2002 and 254 of 2003, was put on notice and

granted an opportunity to monitor the proceedings and, if it had wished to do so, file a

petition to intervene in those proceedings and counter VIP’s application to withdraw the

75 HB/H/283/4422-4445: VIP-PAP Share Purchase Agreement (“VIP-PAP-SPA”), 15 August 2013. 76 HB/H/301/4620-4630: Draft Order submitted by VIP before the High Court of Tanzania, 30 August 2013. 77 HB/H/311/4733-4748: Ruling by Utamwa J in the High Court of Tanzania (“Utamwa J Order”), 5 September 2013. 78 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 75. 79 HB/A/002/035-143: Claimant’s Memorial, paras. 134-139. 80 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 77 et seq.

Page 27: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

20

Winding Up Petition, including its request that the High Court order the handing over of all of

IPTL’s affairs and assets to PAP.81

(11) English Proceedings and Flaux J’s Judgment82

In December 2013, Standard Chartered Bank Malaysia Berhad and SCB HK started

proceedings in the High Court of England and Wales against IPTL, VIP and PAP under the

Facility Agreement, Security Deed, Charge of Shares and Shareholder Support Deed, seeking

confirmation of the validity of SCB HK’s loan to IPTL and of its security over that loan.

IPTL, VIP and PAP raised jurisdictional challenges, which were rejected by Flaux J, and on 16

November 2016,83 Flaux J declared inter alia that: (i) the Facility Agreement, Security Deed,

Shareholder Support Deed, and Charge of Shares were valid; (ii) Standard Chartered Bank

Malaysia Berhad had been the Facility Agent since 21 October 2005; (iii) SCB HK had been

the Security Agent since 4 December 2009; and (iv) all the rights, title and interest of the

banks under the Facility Agreement, the Security Deed, the Shareholder Support Deed and

the Charge of Shares became vested in SCB HK with effect from 17 August 2005 “as assignee

of Danaharta pursuant to the Deed of Assignment […]; and with effect from 25th October 2005,

as sole Bank pursuant to the Novation Notice.”84

C. POST-2013 IPTL EVENTS

(1) PAP’s Registration as Owner of Mechmar’s Shareholding in IPTL

On 6 September 2013, PAP replaced the board of directors of IPTL with its own nominees

(including Mr Sethi) as “First Directors Post Provision Liquidation” and transferred VIP’s 30%

shareholding and Mechmar’s 70% shareholding to itself. This was registered with the

Business Registrations and Licensing Agency of Tanzania (“BRELA”).85

81 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 77. 82 HB/A/002/035-143: Claimant’s Memorial, paras. 22-30. 83 HB/D/018/755-793: Judgment of the English Commercial Court in SCB HK and another v IPTL and others, [2016] EWHC 2908 (Comm) (“Flaux J Judgment”), 16 November 2016; HB/D/019/794-799: Order of the English Commercial Court in SCB (HK) and another v IPTL and others, 16 November 2016. 84 HB/D/019/794-799 at pgs. 795-796: Order of the English Commercial Court in SCB (HK) and another v IPTL and others, 16 November 2016. 85 HB/H/313/4758-4760: Minutes of IPTL Board Meeting, 6 September 2013; HB/H/347/4923-4931: BRELA Registration Document, 18 November 2013; HB/H/349/4936-4940: BRELA Registration Document, 27 November 2013; HB/H/359/5109-5115: BRELA Registration Document, 6 January 2014.

Page 28: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

21

(2) Payment of the Funds Held in the Escrow Account to PAP

In October 2013, TANESCO and IPTL entered into a settlement agreement with regard to the

Tariff Dispute.86

On 21 October 2013, the Permanent Secretary of the Ministry of Energy and Minerals (“PS

MEM”), on behalf of the Government of Tanzania and IPTL (controlled by PAP) entered into

an “Agreement for Delivery of Funds to [IPTL]”.87

On 28 November and 6 December 2013, the funds of the Escrow Account were transferred to

PAP.88 The Claimant contends that PAP used USD 75 million of the funds obtained from the

Escrow Account to pay VIP’s 30% shareholding in IPTL instead of using it to satisfy

TANESCO’s payment obligations to SCB HK under the PPA and to pay down the loan.89

(3) Investigations in Tanzania90

The actions of the GoT and TANESCO led to a number of investigations in Tanzania, including

a report submitted by the Auditor General to the Speaker’s office of the Tanzanian Parliament

on 14 November 2014 (“CAG Report”)91 and a report by the Public Accounts Committee on

17 November 2014 (“PAC Report”).92 The Parties dispute the evidentiary relevance of these

reports and interpret their contents differently.93

TANESCO continued making payments to IPTL (then controlled by PAP) but the loan

remained undischarged.94

86 HB/A/002/035-143: Claimant’s Memorial, para. 148; HB/H/334/4855-4861: Minutes of 8 October 2013 meeting between Tanesco and IPTL, 9 October 2013. 87 HB/A/002/035-143: Claimant’s Memorial, para. 148; HB/H/338/4877-4882: Agreement between GoT and IPTL for delivery of escrow funds, 21 October 2013. 88 HB/H/398/5588-5652 at pg. 5609: CAG Report (English), 14 November 2014; HB/H/400/5769-5826 at pg. 5795: PAC Report (English), 17 November 2014; HB/A/002/035-143: Claimant’s Memorial, para. 148. 89 HB/A/002/035-143: Claimant’s Memorial, paras. 153-157. 90 HB/A/002/035-143: Claimant’s Memorial, paras. 168-175. 91 HB/H/398/5588-5652: CAG Report (English), 14 November 2014. 92 HB/H/400/5769-5826: PAC Report (English), 17 November 2014. 93 HB/A/002/035-143: Claimant’s Memorial, paras. 168-175; HB/A/003/144-370: Respondent’s Counter-Memorial, para. 106 et seq. 94 HB/A/002/035-143: Claimant’s Memorial, paras. 176-178.

Page 29: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

22

IV. PARTIES’ REQUESTS FOR RELIEF

The Claimant requests the following relief in its Request dated 15 September 2015:95

(1) A declaration that the United Republic of Tanzania has breached Articles 16.1 and 16.2 of the Implementation Agreement.

(2) An order that the United Republic of Tanzania shall pay SCB HK compensation for its breaches of the Implementation Agreement in an amount to be determined by the Tribunal.

(3) An order that the United Republic of Tanzania pay the cost of these arbitration proceedings, including the fees and expenses of the Tribunal and costs of legal representation and interest thereon.

The Claimant requests the following relief in its Post-Hearing Brief dated 7 September

2018:96

i. a declaration that the United Republic of Tanzania has breached Articles 15.3, 16.1 and 16.2 of the Implementation Agreement;

ii. a declaration that, as a result of the United Republic of Tanzania's breaches of the Implementation Agreement, SCB HK is entitled to damages of US$352,514,258, or such other amount as shall be determined by the Tribunal;

iii. a declaration that the Implementation Agreement terminated on 6 July 2018 pursuant to SCB HK's Termination Notice;

iv. a declaration that, as a consequence of that termination, SCB HK is entitled to compensation calculated pursuant to Row 2 of Schedule 2 of the Implementation Agreement, together with a declaration of the amount of compensation thereby due to SCB HK;

v. in the alternative to the relief claimed at points ii and iv above, a declaration that the damages and/or compensation due to SCB HK is greater than the amount outstanding under the Facility Agreement;

vi. an order that, out of the sums declared due under points ii, iv, and/or v above, the United Republic of Tanzania shall pay SCB HK the sum calculated by SCB HK as necessary to pay off the amount due under the

95 HB/A/001/001-034: Claimant’s Request for Arbitration, para. 134. 96 Claimant’s PHB, para. 227.

Page 30: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

23

Facility Agreement, which as at the date of these Post-Hearing Submissions is US$187,269,605; and

vii. an order that, to the extent not covered by the relief granted under point vi above, the United Republic of Tanzania pay the cost of these arbitration proceedings, including the fees and expenses of the Tribunal and costs of the parties' legal representation and interest thereon.

The Claimant states in its Reply PHB that its relief sought in the Claimant’s PHB at paragraph

227 is subject to its request in paragraph 126 of its Reply PHB “that GoT be ordered to pay the

entire amount of damages and compensation due under the Implementation Agreement in the

event that that the Tribunal is not agreeable to making an order for payment of the amount due

under the Facility Agreement without further analysis of that amount.”97

The Respondent in its Counter-Memorial dated 26 June 2017 and Reply PHB dated 21

September 2018 requests the Tribunal to:98

(i) decline to exercise jurisdiction in the present case;

(ii) to the extent that the Tribunal proceeds to examine the merits of the case, dismiss Claimant’s claims in their entirety;

(iii) declare that Respondent owes no damages or compensation to Claimant; and

(iv) order Claimant to pay the totality of costs relating to this Arbitration.

V. JURISDICTION

The Respondent raises several grounds to challenge the Claimant’s standing in this

arbitration. It says firstly that the Claimant lacks capacity to make any claim as it is neither a

legal assignee under the Implementation Agreement (discussed at paragraphs 57 to 106

below) nor has it satisfied the requirements of Tanzanian law as a statutory assignee

(discussed at paragraphs 107 to 175 below). It also asserts that the Tribunal lacks jurisdiction

ratione personae and ratione materiae under Article 25 of the ICSID Convention (discussed at

paragraphs 176 to 252 below).

97 Claimant’s Reply Post-Hearing Brief (“Claimant’s Reply PHB”), para. 163. 98 Respondent’s Reply Post-Hearing Brief (“Respondent’s Reply PHB”), para. 132.

Page 31: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

24

A. THE CLAIMANT’S STATUS AS A LEGAL ASSIGNEE

The Claimant brings its claim against the Respondent as the assignee of IPTL's rights under

the Implementation Agreement, which rights it submits were assigned to the Security Agent

(now the Claimant) pursuant to the Security Deed. The Claimant argues that, as the statutory

assignee of IPTL’s rights under the Implementation Agreement, it can step into the shoes of

IPTL and directly enforce IPTL's rights against the Respondent.99

The Respondent raises two main grounds of challenge in this respect. First, it argues that the

assignment is ineffective as the IPTL did not obtain the Respondent’s consent to the initial

and successive assignments of IPTL’s rights, as required under Article 15 of the

Implementation Agreement.100 This is described by the Respondent as the “Contractual

Assignment” issue. Second, the Respondent argues that the Claimant is not a valid assignee

under Tanzanian Law, as the Claimant is not a statutory assignee for failing to comply with

the requirements contemplated under the Supreme Court of Judicature Act 1873 (“Judicature

Act 1873”)101 in each of the successive assignments. The Respondent terms this as the

“Statutory Assignment” issue. Third, the Respondent raises the “non-registration” issue as to

whether the assignment of the rights to the Implementation Agreement was a registrable

charge and the impact of its undisputed non-registration. Fourth, the Respondent submits

that the assignment was made void by reason of it being a disposition of property after

commencement of IPTL’s winding up proceedings, or the “Winding-up Issue.”102

A summary of the Parties’ arguments and the Tribunal’s analysis on these issues are set out

below.

(1) Contractual Assignment

Articles 15.1 and 15.2(a) of the Implementation Agreement103 provide as follows:

15.1 Assignment

No assignment or transfer by a Party of this Agreement or such Party’s rights or obligations hereunder shall be effective without the prior written consent of the other Party.

99 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, para. 9. 100 HB/A/005/604-827 at pgs. 684-737: Respondent’s Rejoinder, para. 124 et seq. 101 HB/G/143/11025-11026: Extract from the Supreme Court of Judicature Act 1873. 102 HB/A/005/604-827 at pgs. 711-737: Respondent’s Rejoinder. 103 HB/C/004/132-191: Signed Implementation Agreement (without Schedules), 8 June 1995 (emphasis in original).

Page 32: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

25

15.2 Creation of Security (a) Notwithstanding the provisions of Article 15.1, for the purpose of financing the construction and operation of the Facility, the Company may, upon prior written approval of the GOT, whose consent shall not be unreasonably withheld, assign or create a security interest to the Lenders pursuant to the Financing Documents in, its rights and interests under or pursuant to: (i) this Agreement; (ii) any agreement included within the Security Package; (iii) the Facility; (iv) the Site; (v) the movable property and intellectual property of the Company;

or (vi) the revenues or any of the rights or assets of the Company.

a. Parties’ Submissions

The Respondent contends that it has never provided either its “prior written consent”

pursuant to Article 15.1 of the Implementation Agreement or its “prior written approval”

pursuant to Article 15.2 of the Implementation Agreement, to any of the purported

assignments of the Implementation Agreement, and that therefore SCB HK is not a valid

assignee of IPTL’s rights under the Implementation Agreement.104 Further, the Respondent

submits that if properly construed, Articles 15.1 and 15.2 of the Implementation Agreement

both expressly require consent, with the consequence that lack of consent invalidates an

assignment.105 Also, the Respondent argues that the failure to obtain such consent renders

any assignment ineffective as against GoT.106 The Respondent rejects the Claimant’s

contentions that it had been estopped from asserting that no prior consent was given when

it maintained silence when notified of the assignment to the Lenders in 1997. In its view, GoT

had no “duty to speak”, and, in any event, estoppel could only be personal to “the parties and

their privies”. SCB HK therefore could not take the benefit of an estoppel.107 The Respondent

also rejects the Claimant’s assertion that that Article 15.2(a) should be interpreted as a mere

undertaking not to assign, the breach of which would only result in damages.108

104 HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 142-143. 105 HB/A/005/604-827: Respondent’s Rejoinder, para. 126. 106 HB/A/005/604-827: Respondent’s Rejoinder, paras. 124–144. 107 Respondent’s PHB, paras. 45-46 referring to RL-145, RL-153 and RL-146. 108 HB/A/005/604-827: Respondent’s Rejoinder, para. 126.

Page 33: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

26

The Respondent relies, inter alia, on Linden Gardens Trust Limited v Lenesta Sludge Disposals

Limited, [1994] 1 AC 85 (“Linden Gardens”),109 which sets out four possible effects of a

contractual prohibition on assignments, depending on the construction of the clause in

question. This could be: “(i) a mere personal undertaking having no effect on the validity of the

assignment, with a breach sounding only in damages; (ii) a stipulation that the assignment is to

be ineffective against the debtor without affecting relations between assignor and assignee inter

se; (iii) a purported bar even on the transfer of ownership of the right or its fruits as between

assignor and assignee; or (iv) a stipulation, the breach of which is to entitle the debtor not

merely to recover damages but to terminate the contract.”110

The Respondent places emphasis on Lord Browne-Wilkinson’s observation in Linden Gardens

that categories (i) and (iv) are “very unlikely to occur”111 in support of its contention that

Article 15.2(a) is not a mere undertaking not to assign. It takes the view that it would be unfair

to interpret Article 15.2(a) as an undertaking not to assign, because breach of such a

provision would be unlikely to lead to any recoverable damage, allowing the Claimant to

breach the provision with little risk of consequences.112

The Respondent argues that the commercial reason for a prohibition on an assignment of a

contract is that a contracting party has a genuine commercial interest in knowing the identity

of the party who can decide to sue him. Where a party is a sovereign State, this interest

amounts to a matter of national security and public policy.113 The Respondent would have a

genuine and legitimate interest in, and concern about, the identity, nature and nationality of

its contractual counterparties, particularly in relation to a power generation project such as

the Facility.114

In addition, according to the Respondent, the Respondent was not a party to and had no

negotiating power over the provisions of the Security Deed and the other financing

109 HB/G/187/13232-13264: Linden Gardens Trust Limited v Lenesta Sludge Disposals Limited [1994] 1 AC 85, 22 July 1993. 110 HB/A/005/604-827: Respondent’s Rejoinder, paras. 135-137; HB/G/316/15426-15444: Roy Goode, “Contractual Prohibitions Against Assignment”, 2009(3) Lloyd’s Maritime and Commercial Law Quarterly 300. 111 HB/A/005/604-827: Respondent’s Rejoinder, para. 137; HB/G/187/13232-13264 at pg. 13251: Linden Gardens Trust Limited v Lenesta Sludge Disposals Limited [1994] 1 AC 85, 22 July 1993. 112 HB/A/005/604-827: Respondent’s Rejoinder, para. 131. 113 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 149. 114 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 150; HB/A/005/604-827: Respondent’s Rejoinder, para. 130.

Page 34: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

27

documents. The Respondent submits that the only effective protection for the Respondent to

be able to control future assignments and to protect itself in that review and approval process

was the inclusion of the provisions of Article 15.1 and 15.2(a) of the Implementation

Agreement.115 In light of this, the Respondent argues that Article 15.2 should be construed

such that lack of consent by the Respondent will invalidate an assignment.

Furthermore, even in the absence of an express term to obtain consent with every

assignment, this requirement can be impliedly read into Article 15.2(a) of the

Implementation Agreement. In the Respondent’s view, every time a private party enters into

a contract with a “sovereign in relation to major infrastructure public utilities projects, it is

implied in the negotiations and the final agreements that the counterparty would not change

without the sovereign’s approval.”116

The Respondent is of the view that its consent was never sought for the assignment made in

1997 to the original Malaysian lenders.117 Consequently, it asserts that any subsequent

assignments by the lenders could also not be effective. The Respondent also submits that in

any event, all subsequent assignments were ineffective since the Respondent’s consent was

not sought for each of these.118 As a result, it argues the Claimant has no standing to invoke

the arbitration clause of the Implementation Agreement.119 Further, it submits that the

Claimant does not meet the contractual requirements of a Security Agent, particularly under

Clause 22(H)120 of the Loan Facility Agreement.121 According to the Respondent, the result is

that IPTL is the only entity capable of initiating arbitration proceedings against the

Respondent under the Implementation Agreement.

Finally, the Respondent argues that even if Article 15.2(a) of the Implementation Agreement

does not require its consent for the transfer of an existing security interest to a successor

Security Agent, the Claimant would still not be entitled to invoke the arbitration clause of the

115 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 151; HB/A/005/604-827: Respondent’s Rejoinder, para. 130. 116 HB/A/005/604-827: Respondent’s Rejoinder, para. 125. 117 HB/A/005/604-827: Respondent’s Rejoinder, para. 142. 118 HB/A/005/604-827: Respondent’s Rejoinder, para. 124; HB/A/003/144-370: Respondent’s Counter-Memorial, para. 153. 119 HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 169-170. 120 HB/C/008/280-365 at pgs. 338-339: Facility Agreement, 28 June 1997, Clause 22(H). 121 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 154.

Page 35: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

28

Implementation Agreement, since the word “Lender” is neither mentioned in the arbitration

clause itself, nor in the definition of “Parties” or “Company.” In addition, the Respondent refers

to Article 24.6122 of the Implementation Agreement, which it submits expressly states that

the agreement “shall not confer any right of suit or action whatsoever on any third party, except

for the specific rights granted to the Lenders pursuant to Articles 15.2, 18.2 and 19.4.”123 It

points out that none of these provisions confer on the “Lender” any right to submit disputes

to arbitration.124

The Claimant relies on Linden Gardens as well, but argues that Article 15.2(a) of the

Implementation Agreement, on its proper construction, is an undertaking not to assign

without prior consent, breach of which sounds in damages. It distinguishes Article 15.2(a)

from Article 15.1, noting that Article 15.1 explicitly states that "[n]o assignment […] shall be

effective" without prior consent while Article 15.2(a) does not use such language. In the

Claimant’s view, if Article 15.2(a) was intended to render assignments ineffective in the same

manner as Article 15.1, the Parties would be expected to have used the same explicit

language. Hence, it argues that Article 15.2(a) must be an undertaking not to assign.125

Further, the Claimant submits that Article 15.2(a) of the Implementation Agreement does not

only restrict the assignment of (and creation of security interests in respect of) the

Implementation Agreement, it also applies to contracts to which the Respondent is not a party

to (such as the PPA and the Facility Agreement) and to noncontractual property of IPTL (such

as the Site, Facility, movable property and intellectual property). The Claimant contends that,

as a matter of law, Article 15.2(a) cannot render such assignments invalid; the most that

Article 15.2(a) can do is render IPTL liable to pay damages for breach of contract in respect

of such assignments. This according to the Claimant indicates that Article 15.2(a) must have

been intended to operate as an undertaking not to assign, rather than as a prohibition on

assignment.126

122 HB/C/004/132-191 at pg. 188: Signed Implementation Agreement (without Schedules), 8 June 1995, Article 24.6. 123 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 171. 124 HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 171-172. 125 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, para. 34(ii). 126 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, para. 34(i).

Page 36: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

29

The Claimant points out127 that GoT had been given Notice of Assignment of the

Implementation Agreement to the Security Agent in 1997, and that GoT (by the Ministry of

Water, Energy and Minerals) had acknowledged the same by, amongst others, countersigning

on the Notice of Assignment in the form essentially as contemplated in the Security Deed,128

thus constituting an estoppel or waiver129 of the need for “prior” written consent. The

Claimant contends that the same conduct may give rise to a waiver or estoppel and that the

distinction between waiver and estoppel is more theoretical than real. In this regard, the

Claimant cited in support the English Court of Appeal decisions in Brikom Investments Ltd v

Carr130 and Business Environment Bow Lane Ltd v Deanwater Estates Ltd.131

As for the Respondent’s interest in controlling the identity of lenders in light of broader public

policy concerns, the Claimant contends that these alleged concerns are subjective and after-

the-event statements of the Respondent’s motivations in agreeing to Article 15.2(a) of the

Implementation Agreement. It notes IPTL’s conflicting subjective interest – that of having the

ability to raise finance (including providing security) with minimal interference from the

Respondent - and takes the view that the construction of Article 15.2(a) depends on the

objective intention as to what the Parties agreed, as evidenced by the language of Article

15.2(a).132

Additionally, the Claimant argues that the fact that the PPA permitted its assignment to

lenders without prior consent shows that the identity of the lenders to the project as a whole

was not critical to GoT and TANESCO. This is particularly since the PPA was negotiated in the

presence of GoT representatives.133 Further, the Claimant argues that Article 15.2(a) of the

Implementation Agreement cannot operate to invalidate the assignment of contracts to

which GoT is not a party. According to the Claimant, regardless of whether Article 15.2(a)

operates as an undertaking not to assign or a prohibition on assignment in respect of the

127 HB/A/002/035-143: Claimant’s Memorial, paras. 313-326. 128 HB/C/014/552-557 at pg. 556: Form of Deed of Assignment Made between Danaharta Managers (L) Ltd and SCB HK, 17 August 2005, Schedule One, para. 3. 129 HB/A/002/035-143: Claimant’s Memorial, para. 323. 130 Exhibit CL-210: Brikom Investments Ltd v Carr [1979] 1 QB 467 at 488G-489A (submitted at the Hearing). 131 Exhibit CL-211: Business Environment Bow Lane Ltd v Deanwater Estates Ltd [2007] EWCA Civ 622 at 176 [51] per the Chancellor. 132 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, paras. 37-39. 133 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, para. 41, referring to HB/H/011/027-267 at pg. 113: Memorandum on the IPTL Power Project by Patrick Rutabanzibwa, 1 July 1996.

Page 37: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

30

Implementation Agreement, it cannot prevent the lenders from taking control of the Facility

pursuant to security granted by IPTL to the lenders in respect of the PPA, the Site and the

Facility. In the Claimant’s view, the argument that Article 15.2(a) of the Implementation

Agreement must be interpreted as a prohibition on assignment in order to control the

identity of the lenders is misconceived, because the provision, however it is interpreted,

cannot achieve that outcome.134

Further, the Claimant argues that, as a matter of general principle, there is no reason why a

breach of an undertaking not to assign would be unlikely to lead to recoverable damages, and

hence this should not be a reason to not construe Article 15.2 as an undertaking not to assign.

In the present case, it so happens that the Respondent demonstrated by its conduct in 1997

that it would have given prior consent to the assignment had it been requested, so there is no

loss and hence no recoverable damages.135

The Claimant rejects the Respondent’s contention that every time a private party contracts

with a sovereign in relation to major infrastructure public utilities projects, there is an

implied term that the counterparty will not change without the sovereign's approval. It notes

that the Respondent has provided no expert evidence or authority in support of this, nor any

explanation of how this satisfies recognised tests for the implication of terms. Further, since

Articles 15.1 and 15.2(a) already expressly address the assignment of the Implementation

Agreement, there is no room to imply a further consent requirement into the contract.136

Finally, the Claimant takes the view that no consent is required for subsequent

assignments,137 and that it meets the contractual requirements of a Security Agent.138 As for

the Respondent’s argument that the assignee cannot invoke the arbitration clause because

the arbitration clause refers only to "Parties" and does not refer to the "Lenders", according

to the Claimant, this argument is wrong and reflects a misunderstanding of the law of

assignment. The Claimant submits that the effect of a statutory assignment is that the

assignee (SCB HK) becomes the legal owner of the benefit of the assigned contract and is

entitled to exercise the assignor’s rights under the contract, including the right to invoke the

134 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, para. 42. 135 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, para. 44. 136 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, paras. 46-47. 137 HB/A/002/035-143: Claimant’s Memorial, paras. 327–331. 138 HB/A/004/371-603: Claimant’s Reply, paras. 267-270.

Page 38: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

31

arbitration clause and bring an action in its own name. It does not matter that the arbitration

clause only refers to the assignor and does not mention the assignee, because the assignee is

stepping into the shoes of the assignor.139

b. Tribunal’s Analysis

(i) From Original Lenders to Danaharta

The Implementation Agreement was entered into by GoT as part of the package of incentives

and assurances that GoT had given to IPTL to undertake the Project.

On 28 June 1997, IPTL and a syndicate of Malaysian banks entered into the Facility

Agreement.140 IPTL was the borrower of the USD 105,000,000 Loan Facility Agreement

relating to the 100 MW Tegata Power Project.

The banks under the Facility Agreement were:

i. Bank Bumiputra Malaysia Berhad, Kuala Lumpur (“BBMB”);

ii. Sime Bank Berhad, Kuala Lumpur (“Sime Bank”);

iii. BBMB International Bank (L) Ltd, Labuan (“BBMB International”); and

iv. SIME International Bank (L) Ltd, Labuan (“Sime International”).

BBMB was the Facility Agent and Sime Bank Berhad (Singapore Main Office) (“Sime

Singapore”) was the Security Agent.141

A Security Deed142 was simultaneously executed under which IPTL assigned to the Security

Agent “all its present and future right, title and interest in and to the Assigned Contracts […]”.

Amongst the Assigned Contracts was the Implementation Agreement.143

The Parties do not dispute that no “prior” written consent was given by GoT to assign any of

IPTL’s rights under the Implementation Agreement.

139 HB/A/004/371-603: Claimant’s Reply, paras. 376-380. 140 HB/C/008/280-365: Facility Agreement, 28 June 1997. 141 HB/C/008/280-365 at pg. 283: Facility Agreement, 28 June 1997. 142 HB/C/009/366-457: Security Deed, 28 June 1997, Clause 3.2. 143 HB/C/009/366-457: Security Deed, 28 June 1997, Clause 1.1.

Page 39: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

32

On 3 October 1997, the Notice of Assignment of the Implementation Agreement was given

and acknowledged by the Ministry of Water, Energy and Minerals.144

The Respondent had, in its Post-Hearing Brief, remarked145 that how Danaharta had acquired

its interest in the Implementation Agreement needed to be explained before the Claimant

could stake its claim as the assignee of the Implementation Agreement.

To address this, the Tribunal has examined the documents submitted and ascertained that:

i. On 11 January 1999, the Sime International underwent a name change to Danaharta

Managers (L) Ltd.146

ii. On 30 June 1999, pursuant to the Order of the High Court of Malaya at Kuala Lumpur,

Malaysia,147 the entire banking business of Sime Bank Berhard, in Malaysia, Brunei,

Thailand, Singapore and other countries, pursuant to a merger agreement between

Sime Bank Berhad and RHB Bank Berhad (“RHB Bank”), was transferred to RHB

Bank. The order has the effect of transferring the rights under the Implementation

Agreement, and the office of Security Agent (then Sime Singapore), to RHB Bank.

iii. On 3 September 1999, pursuant to the Order of the High Court of Malaya at Kuala

Lumpur, Malaysia,148 the court approved a scheme of transfer, under which certain

assets and liabilities of BBMB, its shares in subsidiaries and associated companies

(other than its Islamic banking business) were transferred to the Bank of Commerce

(M) Berhad (“BOC”) such that any BBMB instrument shall be construed as and have

effect as if for any reference therein to BBMB there was substituted with a reference

to BOC.

144 HB/H/021/315: Notice of Assignment, 3 October 1997. 145 See Respondent’s PHB at pg. 2, footnote 2. 146 HB/H/134/1296-1917 at pg. 1807: Copy of the Submission for ICSID Interpretation Proceedings, 17 December 2009 (“SCB HK’s Submission on Standing in Interpretation Proceedings”). 147 HB/H/134/1296-1917 at pgs. 1814-1833: SCB HK’s Submission on Standing in Interpretation Proceedings. 148 HB/H/134/1296-1917 at pgs. 1837-1853: SCB HK’s Submission on Standing in Interpretation Proceedings.

Page 40: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

33

iv. By Novation Notice,149 signed by Danaharta and BBMB International on 1 September

1999, and by BBMB as Facility Agent on 15 September 1999, BBMB International’s

interest in the Facility Agreement was novated to Danaharta.150

v. On 30 September 1999, BOC was renamed as Bumiputra-Commerce Bank Berhad

(“Bumiputra-Commerce”).151

vi. By Novation Notice signed by Danaharta (as New Bank) on 11 July 2001, and by RHB

Bank (Singapore Branch) as existing bank and by Bumiputra-Commerce as Facility

Agent on 16 July 2001,152 the interest of RHB Bank in the Facility Agreement was

confirmed as having been novated to Danaharta. RHB Bank (Singapore Branch) (Sime

Singapore, renamed following the 29 June 1999 Order153) remained the Security

Agent.154

Through these arrangements, Danaharta eventually had become by July 2001 the sole Bank

and lender under the Facility Agreement, with Bumiputra-Commerce (formerly BBMB)

remaining as the Facility Agent and RHB Bank Singapore) (formerly Sime Singapore) as

Security Agent.

It is clear to the Tribunal that Danaharta (formerly Sime International) was not a stranger to

this transaction nor to GoT. It was an original lender (a “Bank” and “Secured Creditor” as

defined in the Facility Agreement which definitions are adopted by the Security Deed)155

which had subsequently acquired the interests of all the other banks and novated all the

rights of the other RHB Banks (formerly Sime Bank and Bumiputra-Commerce (formerly

BBMB)). There is no doubt in the Tribunal’s mind that Danaharta acquired the full legal and

beneficial title including the rights under the Security Deed and the assets represented

thereunder, such as the Implementation Agreement.

149 HB/H/134/1296-1917 at pgs. 1809-1812: SCB HK’s Submission on Standing in Interpretation Proceedings. 150 HB/H/134/1296-1917 at pg. 1809-1812: SCB HK’s Submission on Standing in Interpretation Proceedings. 151 HB/H/134/1296-1917 at pgs. 1855, 1857: SCB HK’s Submission on Standing in Interpretation Proceedings. 152 HB/H/134/1296-1917 at pgs. 1835-1836: SCB HK’s Submission on Standing in Interpretation Proceedings. 153 HB/H/134/1296-1917 at pgs. 1814-1833: SCB HK’s Submission on Standing in Interpretation Proceedings. 154 HB/H/134/1296-1917 at pgs. 1760-1761: SCB HK’s Submission on Standing in Interpretation Proceedings. 155 HB/C/009/366-457: Security Deed, 28 June 1997, Clause 1.3; HB/C/008/280-365: Facility Agreement, 28 June 1997, Clause 1(A).

Page 41: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

34

(ii) From Danaharta to SCB HK

By a Sale and Purchase Agreement dated 4 August 2005,156 Danaharta agreed to sell and the

Claimant agreed to purchase for USD 76.1 million, the assets set out in the agreement,

representing the loans and interests outstanding due from IPTL and the associated security.

Upon completion of the Sale and Purchase Agreement, Danaharta executed a Deed of

Assignment (“2005 Deed”) in favour of the Claimant on 17 August 2005.157 The

Implementation Agreement was among the “Asset Documentation” assigned to the Claimant.

By a Novation Notice158 signed by the Claimant as the “New Bank” on 11 August 2005 and by

Danaharta on 17 August 2005, the Claimant became the sole Bank under the Facility

Agreement. RHB Bank Singapore remained the Security Agent.

By letter dated 22 September 2005,159 Bumiputra-Commerce resigned from the role of

Facility Agent and Standard Chartered Bank (Malaysia) Berhad agreed and signed the same

letter on 17 October 2005 taking on the role as Facility Agent.

By letter dated 29 October 2009,160 the Claimant removed RHB Bank Singapore as Security

Agent and appointed Standard Chartered Bank Malaysia Berhad, in its stead. On 4 December

2009, the Claimant became the Security Agent.161

The validity of the Facility Agreement and Security Deed, the transfer of rights and liabilities

under the Facility Agreement and the liability of IPTL under it to the Claimant have been the

subject matter before the English High Court162 and resolved in favour of the Claimant in Case

CL-2013-000411 with the holding that the “Security Deed has become and is enforceable in

accordance with the terms of the Security Deed” and that IPTL was indebted to the Claimant in

the sum of USD 168.8 million.163

156 HB/C/013/535-551: Sale and Purchase Agreement for Loan Account – IPTL between Danaharta Managers and SCB, 4 August 2005. 157 HB/C/014/552-557: Form of Deed of Assignment Made between Danaharta Managers (L) Ltd and SCB HK, 17 August 2005. 158 HB/H/134/1296-1917 at pgs. 1868-1869: SCB HK’s Submission on Standing in Interpretation Proceedings. 159 HB/H/134/1296-1917 at pg. 1874: SCB HK’s Submission on Standing in Interpretation Proceedings. 160 HB/H/129/1288: Letter from SCB HK to RHB Bank Berhad, 29 October 2009. 161 HB/H/132/1292-1293: Letter from SCB HK to SCB HK, 4 November 2009. 162 HB/D/018/755-793: Flaux J Judgment, 16 November 2016. 163 HB/D/019/794-799 at pg. 796: Order of the English Commercial Court in SCB (HK) and another v IPTL and others, 16 November 2016.

Page 42: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

35

The issue of the assignability of the Implementation Agreement stands independently from

the English Court’s ruling on the validity and enforceability of the Facility Agreement and the

Security Deed.

(iii) Prior Written Consent for First Assignment

The Respondent’s first objection is that no “prior written consent” was first obtained when

the parties entered into the Security Deed purporting to assign the Implementation

Agreement. It urges the Tribunal to take cognizance of the fact that the Respondent as a

sovereign State, should be made aware of and be given the opportunity to know who they

would be dealing with as a matter of national security and public policy.

As such, “prior” written consent is mandatory. The Tribunal has some sympathy with the

submission that GoT has a legitimate interest in knowing the assignee and the purpose or

need for such an assignment. In this regard, the Tribunal takes the view that such a concern

is fully addressed in Article 15.1 of the Implementation Agreement where any purported

assignment would be rendered ineffective unless “prior written consent” was given.

The words of Article 15.1 of the Implementation Agreement are clear. It is a prohibition that,

absent prior written consent, “[n]o assignment or transfer [...] of this Agreement” or the “rights

or obligation” under it “shall be effective.” The words clearly require that to effect a valid

assignment or transfer rights and obligations under the Implementation Agreement the

“other Party[’s]” prior written consent must be obtained. By this wording, GoT was assured

that it would not be dealing with any Party other than IPTL or such other person that GoT

approved, thus safe-guarding GoT’s national and security interest, as it has urged upon the

Tribunal.

Article 15.2 of the Implementation Agreement however, creates the exception, that

“Notwithstanding the provisions of Article 15.1[…]”, “the Company” (viz. IPTL), could “for the

purpose of financing the construction and operation of the Facility […] assign or create a

security interest to the Lenders pursuant to the Financing Documents in, its rights and

interests under or pursuant to” inter alia, the Implementation Agreement, if IPTL had

obtained “prior written consent.”

It is clear from Article 15.2, that GoT accepted that IPTL would need financing for the Facility

and had, by this provision, agreed that for that purpose, IPTL could “assign or create a security

Page 43: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

36

interest” in favour of its “Lenders” subject only to IPTL having obtained “prior written consent”

from GoT.

It is common ground that no “prior” written consent was given. It could not, however, be

disputed that “written consent” was subsequently given in the form of:

i. Notice of Assignment dated 3 October 1997164 given by IPTL and Sime Bank Berhard

Singapore which was signed by the Ministry of Water, Energy and Minerals. In it GoT

“acknowledge[d] the receipt of the Notice of Assignment” and agreed –

“not [to] terminate the IMA [i.e. Implementation Agreement] except as provided in Article 19.4 of the IMA;”

and

“send to the Security Agent, a copy of any notice required to be given to IPTL pursuant to Articles 19.1 and 19.2 of the IMA.”

ii. Letter from the Minister of Finance dated 13 October 1997165 addressed to IPTL and

copied to the Prime Minister, Minister of Energy and Minerals, Minister-Planning,

Attorney-General, Chief Secretary, and MD TANESCO expressing that –

a) “In accordance with Article 15.2 of the Implementation Agreement, all relevant authorities will agree to the execution of the assignments of the Implementation Agreement, the Power Purchase Agreement, the Licence and consents relating to the Project.”

b) “Unless you have been notified in writing by us to the contrary, all Project agreements, approvals, licences and consents executed between the Government and IPTL or granted to IPTL remain in full force and effect.”

iii. Diplomatic Note dated 28 October 1997166 from the Tanzanian Ministry of Foreign

Affairs to the Malaysian Ministry of Foreign Affairs re-affirming GoT’s position set out

in (ii)(a) and (b) above.

These acknowledgments of GoT clearly recognise that it consented to the assignment of the

Implementation Agreement. The acknowledgements constitute both consent to the

164 HB/H/021/315: Notice of Assignment, 3 October 1997. 165 HB/H/022/316-317: Letter from Daniel Yona, Minister of Finance, to IPTL, 13 October 1997. 166 HB/H/023/318: Diplomatic Note from the Ministry of Foreign Affairs of Tanzania to the Ministry of Foreign Affairs of Malaysia, 28 October 1997.

Page 44: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

37

assignment and the relinquishment of the right to require prior consent. The consent is given

by GoT with express reference to Article 15.2 of the Implementation Agreement, and thus in

contemplation of the requirement of prior consent. This, in the Tribunal’s view, amounts to a

waiver by GoT of the lack of prior written consent. Accordingly, the Tribunal finds that the

absence of prior written consent by GoT is not fatal to the validity of the assignment.

The Respondent submits that even if the Tribunal should so find, the Claimant may not rely

upon an estoppel, because, under Tanzanian law, estoppel is personal to the representee and

may not be relied upon by an assignee. In its view, “SCB HK could not take an assignment of

the benefit of an estoppel.” As pointed by the Claimant this position was incorrectly taken. The

case cited by the Respondent167 to support its contention was not one concerned with

whether estoppel could be relied upon by an assignee on a representation made to the

assignor. In that case, the court was dealing with a lessee who had wanted to assign the lease

to a third-party and had meanwhile permitted the intended assignee to occupy and use the

premises and paying rent directly to the lessor. It was said that by accepting the rents, the

lessor had represented to the lessee that the third party was the assignee and would therefore

be estopped from denying that there was a valid assignment. This was rejected by the court.

In doing so the court made the statement that an “estoppel by representation is personal to the

parties” in accepting the rent payments made by the third-party it could not have made any

representation to the lessee. There was in that case no assignment to be found much less any

suggestion that it was a decision to the effect that an assignee could not take the benefit of an

estoppel. In this arbitration, however, it was GoT who had signed and acknowledged the

Notice of Assignment and returned it to the lender’s Security Agent. GoT could not now be

permitted to go back to say that it could not be relied on by the assignee.

In any event, even if it could be said that estoppel could not be established because estoppel

could be said to operate in favour of the original representee, the Tribunal nevertheless finds

that the consent of GoT given by its signing of the Notice of Assignment amounts to a waiver

of any lack of prior consent. It could not then be permitted to rely on any lack of prior written

notice to vitiate the consent expressly given. Such a waiver subsists notwithstanding any

subsequent assignment.168

167 Exhibit RL-145: Lankester & Son Ltd v Rennie and another [2014] EWCA Civ 1515 (submitted at the Hearing). 168 Exhibit CL-210: Brikom Investments Ltd. v Carr [1979] 1 QB 467.

Page 45: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

38

(iv) Prior Written Consent for Successive Assignments

The Respondent’s second argument under the Contractual Assignment issue is that the

requirement for prior written approval was not obtained between 1997 and 2005 “for each

of the successive assignments.” It is the Respondent’s case that the Implementation Agreement

is structured on the basis that IPTL’s rights might be successively assigned but that each

assignment requires prior written approval to be effective. In support of this, the Respondent

cited in its Post-Hearing Brief169 the case of Barbados Trust Company Ltd v Bank of Zambia

and Bank of America170 to suggest that a similar provision in that case had been interpreted

to require each and any subsequent assignment by each of the banks to first obtain “prior

written consent.” The Tribunal notes however that the specific provision in that case was

worded differently in that it required –

(A) Each Bank may at any time and from time to time assign all or any part of its rights and benefits in respect of the Facility to any one or more banks or other financial institutions (an “Assignee”), provided that any such assignment may only be effected if […] the prior written consent thereto of the Borrower shall have been obtained (such consent not to be unreasonably withheld and to be deemed to have been given if no reply is received from the Borrower within fifteen days after the giving of a request for consent by a Bank) […].171

The Tribunal notes that the issue before the English court related primarily to the

requirement for a request being made and “deemed consent” following a period of lapse. The

court was not dealing with the need for successive consents. In addition, the intervening

assignments were made to and by non-financial institutions in breach of the contractual

restrictions. There is, therefore, no useful analogical reasoning that can be drawn from that

decision to assist the case before this Tribunal.

In the Tribunal’s view, Article 15.2 of the Implementation Agreement must be construed by

the plain words and in its functional role as an exception to the prohibition set out in Article

15.1 of the Implementation Agreement. Article 15.2 sets out:

i. the purpose for which an assignment is to be allowed as - “financing the construction

and operation of the Facility”;

169 Respondent’s PHB, paras. 34-36. 170 Exhibit RL-152: Barbados Trust Company Ltd v Bank of Zambia and Bank of America [2006] EWHC 222 (Comm) (filed along with Respondent’s PHB). 171 Exhibit RL-152: Barbados Trust Company Ltd v Bank of Zambia and Bank of America [2006] EWHC 222 (Comm), para. 7.

Page 46: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

39

ii. the permissible assignees: the “Lenders pursuant to the Financing Documents”; and

iii. the party required to seek consent: “the Company” (viz. IPTL was to be the borrower

under the Financing Documents).

It appears clear to the Tribunal that Article 15.2 of the Implementation Agreement

specifically made an exception for IPTL to “assign or create a security interest” as required

under the Financing Documents. To avail itself of this right to assign, IPTL must satisfy the

elements listed in paragraph 102(i) to (iii) above.

The Respondent has argued that the Implementation Agreement is designed so that IPTL’s

rights might be assigned on multiple occasions on the basis that the definition of “Company”

includes not only IPTL but also “its permitted successors and assigns.” Thus, when this

provision states that “the Company” may assign “upon prior written approval of the GOT,” this

ability, and this restriction on that ability applies to any entity that is a successor or assignee,

which had first obtained the rights through a permitted assignment. The Respondent’s

argument, however, ignores the definition of “Lenders” in the Implementation Agreement,

which is defined as “the lenders party to the Financing Documents, together with their

successors and assigns”172 (with no “permitted” preceding the term).

In this context, the Tribunal’s view is that any subsequent assignment by the banks would be

an assignment by the banks qua lender holding the rights and interest of the Implementation

Agreement qua lender under the Security Deed and not as a “permitted assignee” of the

Company as GoT has asserted. It follows that any subsequent assignment by the original

banks to other banks would not require any further consent from GoT. In other words, the

carve out in Article 15.2 of the Implementation Agreement is that once the lenders acquire

rights, the lenders do not have to secure further approvals from the parties to validly transfer

their rights.

Counsel for the Parties spent much time on the consequences of non-compliance with the

“prior written consent” requirement under Article 15.2 of the Implementation Agreement,

arguing whether the same merely sounds in damages or would render any such assignment

invalid or ineffective against GoT. Interesting observations have been made in particular to

the English House of Lord’s decision in Linden Gardens. In view of the Tribunal’s finding that

172 HB/C/005/192-267 at pg. 196: Unsigned copy of Implementation Agreement (including Schedules), 8 June 1995.

Page 47: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

40

the assignment of the Implementation Agreement received express written consent from GoT

under Article 15.2, the consequences for non-compliance with the prior consent requirement

under Article 15.2 of the Implementation Agreement requires no further determination.

(2) Statutory Assignment under Tanzanian Law

The Respondent has raised several grounds upon which it relies to challenge the validity of

the assignment in favour of the Claimant under the laws of Tanzania. These are discussed

under the following sub-heads: (a) requirements of the Judicature Act 1873; (b) notice of

assignment; (c) status of the Security Agent; (d) non-registration of charge in violation of

Section 79 of the Companies Ordinance; and (e) disposition in winding-up in breach of Section

172 of the Companies Ordinance.

a. Requirements of the Judicature Act 1873

(i) Parties’ Submissions

Clause 3.2.1 of the Security Deed provides:173

3.2 Assignments: The Borrower [IPTL] with full title guarantee and as continuing security for the payment and discharge of all Liabilities hereby assigns to the Security Agent [now SCB HK] for the benefit of the Secured Creditors:

3.2.1 all its present and future right, title and interest in and to the Assigned Contracts, including all moneys which at any time may be or become payable to the Borrower pursuant thereto and the net proceeds of any claims, awards and judgements which may at any time be receivable or received by the Borrower pursuant thereto; […]

The Parties are in agreement174 that the assignment of the Implementation Agreement to the

Security Agent pursuant to Clause 3.2.1 of the Security Deed must comply with the

requirements of Section 25(6)175 of the Judicature Act 1873, the legislation applicable to

statutory assignments in Tanzania.176

173 HB/C/009/366-457 at pg. 369: Security Deed, 28 June 1997. 174 HB/A/003/144-370 at pgs. 242-243: Respondent’s Counter-Memorial, para. 174; Claimant’s PHB, para. 79. 175 HB/G/143/11025-11026: Extract from the Supreme Court of Judicature Act 1873. 176 Due to its enactment prior to 22 July 1920.

Page 48: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

41

The Respondent argues that the security interest created by Clause 3.2.1 of the Security Deed

is not absolute as it is by way of charge only and, therefore, does not operate to transfer any

proprietary interest.177 Furthermore, it submits that on a proper construction of the Security

Deed, various provisions including Clauses 4.1, 4.2 to 4.6, 5.4.4, 9.3, 11 and 12 indicate that

the assignment was by way of charge only.178

The Respondent also contends that the activities of IPTL demonstrate that the Security Deed

does not provide for more than a charge. In particular, IPTL continued to run its activities, to

issue invoices to and to collect payments from TANESCO for years after the execution of the

Security Deed,179 actively participated in the ICSID 1 arbitration against TANESCO,

commenced the Interpretation Proceedings against TANESCO, and attempted to bring claims

against GoT under the Guarantee.180 According to the Respondent, case law demonstrates

that an assignor maintaining its rights under the assigned contract up until the moment when

it defaults on its obligations vis-à-vis the assignee is a “typical example of non-absolute

assignment.”181

The Respondent also refutes the Claimant’s attempt to rely on the PPA Decision, as the

Claimant has noted that the tribunal in the PPA Arbitration ruled that Clause 3.2.1 of the

Security Deed constitutes a valid statutory assignment,182 and that counsel for TANESCO

expressly conceded likewise.183 The Respondent contends that this decision is wrong because

the PPA Tribunal disregarded key passages of the relevant authorities and TANESCO's expert

evidence. It maintains that the exchange between counsel for TANESCO and the PPA Tribunal

was unclear, that counsel did not concede, or did not intend to concede, the point, and that

the PPA Tribunal should not have reached its decision on the basis of this unclear exchange.184

177 HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 174-178. 178 HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 178–180; HB/A/005/604-827:Respondent’s Rejoinder, paras. 181-182. 179 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 181. 180 HB/A/005/604-827: Respondent’s Rejoinder, paras. 175-177. 181 HB/A/005/604-827: Respondent’s Rejoinder, paras. 177-180. 182 HB/A/002/035-143: Claimant’s Memorial, para. 298. 183 HB/A/004/371-603: Claimant’s Reply, para. 313. 184 HB/A/005/604-827: Respondent’s Rejoinder, paras. 183-184.

Page 49: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

42

Finally, the Respondent argues that the notice requirement was not satisfied as there are

doubts as to the authenticity of the Notice of Assignment, and the Notice of Assignment was

contradicted by various activities of IPTL as stated in paragraph 111 above.185

The Claimant contests the Respondent’s construction of the Security Deed, taking the view

that various provisions of the Security Deed are indicative of an absolute assignment, while

others do not indicate that the assignment is by way of charge only.186 In particular, the

Claimant contends that the Respondent’s arguments are based on a misapprehension that,

because IPTL remains responsible for performing the assigned contract, the assignment was

not absolute. The Claimant draws a distinction between the transfer of the benefit of a

contract (an assignment) and the transfer of the benefits and burdens of the contract (a

novation).187 Further, the Claimant contends that the Respondent fails to distinguish between

provisions of the Security Deed which relate specifically to assigned contracts, and general

provisions that relate to the broader variety of security created by the Security Deed.188

The Claimant disagrees that the activities of IPTL demonstrate that the security interest

created by Clause 3.2.1 of the Security Deed is by way of charge only. In its view, the nature

of the assignment under the Security Deed is a matter of construction. Further, it submits that

post-contractual conduct is irrelevant to the construction of the contract.189

In any event, in the Claimant’s view, the conduct relied upon by the Respondent is not

inconsistent with an absolute assignment. The fact that IPTL may have carried out the

mechanical process of invoicing and collecting payments under the PPA does not mean that

the Security Agent was not the legal owner of the rights under the PPA. As for the ICSID 1

arbitration, that was brought by TANESCO against IPTL on the basis that IPTL was in default

of its obligations under the PPA. The Claimant submits that this was appropriate as IPTL

remained party to the PPA and was responsible for performing its obligations under the

PPA.190

185 HB/A/005/604-827: Respondent’s Rejoinder, para. 175. 186 HB/A/004/371-603: Claimant’s Reply, paras. 282-290; HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, paras. 93-94, 113-134, 135-173. 187 HB/A/004/371-603: Claimant’s Reply, para. 288(i). 188 HB/A/004/371-603: Claimant’s Reply, para. 288(ii). 189 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, paras. 101-106. 190 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, para. 107.

Page 50: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

43

Similarly, the Claimant contends that as the Interpretation Proceedings were to interpret the

ICSID 1 Award between TANESCO and IPTL, it was appropriate for the interpretation request

to be made by IPTL. As for IPTL's conduct in respect of the Guarantee, the Claimant asserts

that this has no bearing on the contracts assigned under the Security Deed, and the Claimant

has not sought to bring a claim against the Respondent under the Guarantee.191 Finally, even

if post-assignment conduct was relevant, the Claimant submits that, none of the conduct

related to the assignment of the Implementation Agreement.192

As for the PPA Tribunal’s decision, the Claimant contends that it was a reasoned, robust and

correct decision.193 According to the Claimant, the PPA Tribunal did not ignore relevant

authorities or expert evidence, and TANESCO also clearly conceded that the assignment was

a statutory assignment.194 Finally, the Claimant rejects the Respondent’s doubts as to the

authenticity of the Notice of Assignment as baseless, and maintains that the requirement of

notice was satisfied. The Claimant also notes that there is no requirement under the

Judicature Act 1873 that the notice be countersigned or acknowledged by the counterparty to

the assigned contract.195

(ii) Tribunal’s Analysis

Section 25(6) of the Judicature Act 1873196 provides that:

Any absolute assignment, by writing under the hand of the assignor (not purporting to be by way of charge only), of any debt or other legal chose in action, of which express notice in writing shall have been given to the debtor, trustee, or other person from whom the assignor would have been entitled to receive or claim such debt or chose in action, shall be, and be deemed to have been effectual in law (subject to all equities which would have been entitled to priority over the right of the assignee if this Act had not passed,) to pass and transfer the legal right to such debt or chose in action from the date of such notice, and all legal and other remedies for the same, and the power to give a good discharge for the same, without the concurrence of the assignor: Provided always, that if the debtor, trustee, or other person liable in respect of such debt or chose in action shall have had notice that such assignment is disputed by the assignor or any one claiming under him, or of any other opposing or conflicting claims to such debt or chose in action, he shall be entitled,

191 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, paras. 107-108. 192 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, paras. 109-112. 193 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, paras. 186-188. 194 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, paras. 177-185. 195 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, paras. 79-81, 89. 196 HB/G/143/11025-11026: Extract from the Supreme Court of Judicature Act 1873.

Page 51: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

44

if he think fit, to call upon the several persons making claim thereto to interplead concerning the same, or he may, if he think fit, pay the same into the High Court of Justice under and in conformity with the provisions of the Acts for the relief of trustees.

The Respondent’s submission is that Tanzanian law requires that a statutory assignment

must comply with the requirements under Section 25(6) of the Judicature Act 1873 and that

“any absolute assignment […] of any debt or other legal chose in action” must be: (i) an absolute

assignment and not a mere charge; (ii) in writing; (iii) signed by the assignor; and with (iv)

express notice to the debtor.

The Respondent asserts that the assignment of the Implementation Agreement under the

Security Deed was (i) not absolute but by way of charge only; and (ii) that there was no

express notice given to that effect.

The Tribunal notes that it cannot be disputed that in order to determine whether an

assignment is absolute or by way of charge only, one must analyse by the words of the written

assignment, in this case by the Security Deed.

In examining the Security Deed, the Tribunal notes that Clause 3.1197 of the Security Deed

indeed creates “charges in favour of the Security Agent […].” Further, Clauses 1.1, 3.1, 3.2, 4.1

(3) of the Security Deed provide as follows -

1.1 “Assigned Contracts” means the EPC Contract, the EPC Performance Bond, the O&M Contract, the O&M (Sub) Guarantee, the FSA, the FSA Performance Bond, the IMA, the PPA and all Consents and the Licence. […]

3.1 Charging Provision: The Borrower with full title guarantee and as continuing security for the payment and discharge of all Liabilities hereby charges in favour of the Security Agent for the benefit of the Secured Creditors:

3.1.1 by way of mortgage of the right of occupancy […] the Real Property in Tanzania now belonging to it;

3.1.2 by way of first fixed equitable charge, all Real Property now belonging to it […] and all Real Property acquired by it after the date of this Security Deed.

197 HB/C/009/366-457 at pg. 369: Security Deed, 28 June 1997.

Page 52: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

45

3.1.3 by way of first fixed charge:

(i) all Book Debts;

(ii) all its present and future Permitted Investments, Rights attaching or relating to Permitted Investments and all Assets hereafter belonging to the Borrower and deriving from Permitted Investments or such Rights;

(iii) all its present and future goodwill and uncalled capital for the time being;

(iv) all its present and future Intellectual Property and the benefit of all present and future licences and sub-licences of Intellectual Property granted either by or to it;

3.1.4 by way of first floating charge, its undertaking and all its Assets, both present and future (including Assets expressed to be charged by paragraphs 3.1.1 to 3.1.3 above).

3.2 Assignments: The Borrower with full title guarantee and as continuing security for the payment and discharge of all Liabilities hereby assigns to the Security Agent for the benefit of the Secured Creditors:

3.2.1 all its present and future right, title and interest in and to the Assigned Contracts, including all moneys which at any time may be or become payable to the Borrower pursuant thereto and the net proceeds of any claims, awards and judgements which may at any time be receivable or received by the Borrower pursuant thereto;

3.2.2.all its present and future right, title and interest in and to all insurances and all proceeds in respect of Insurances and all benefits thereof (including all claims of whatsoever nature relating thereto and returns of premiums in respect thereof);

3.2.3. all its present and future Rights in relation to its Real Property (except those charged by Clauses 3.1.1), including all Rights against all past, present and future undertenants of its Real Property and their respective guarantors and/or sureties; and

3.2.4. all its present and future Right, title and interest in and to the Bank Accounts.

3.3 Ranking: The floating Charge created by Clause 3.1.4 shall rank behind all the fixed Charges created by or pursuant to this Security Deed but shall rank in priority to any other security hereafter created by the

Page 53: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

46

Borrower except for security permitted by Clause 4.2 and except for security ranking in priority in accordance with Clause 9.3.5.

[…]

4.1(3) Notwithstanding any other provision hereof the Security Agent shall not by virtue of the Security created by or pursuant to this Security Deed be or become obliged or liable under or in respect of the Secured Property or any part thereof:

(a) to perform or observe any of the obligations of the Borrower hereunder;

(b) to make any payment or any enquiry in connection therewith; or

(c) to present or file any claim or take any other action to collect or enforce any payment due to the Borrower or, by virtue, of the Security created by or pursuant to this Security Deed, to the Security Agent.

There can be no dispute that Clause 3.1 of the Security Deed is intended to create a charge

over the Assets which when so charged constitutes the “Charged Assets” as defined in Clause

1.1., Clause 3.3 further provides for the ranking of the charges referred to in Clauses 3.1, 4.2

and 9.3.5.

The Security Deed thus makes a clear distinction between the charges created in relation to

the “Assets” as described in Clause 3.1 and the assignment created under Clause 3.2, which

uses the term “assigns” without any condition or qualification of “all its present and future

right, title and interest in and to the Assigned Contracts.” The term “Assigned Contracts” as

defined falls outside the scope of Assets contemplated under Clause 3.1. On a plain reading,

the Tribunal is satisfied that Clause 3.2 creates an absolute assignment and not an assignment

by way of charge only.

The Respondent in its Post-Hearing Brief also submitted that Clause 4.1(3)(c) of the Security

Deed was a “retention of rights by IPTL including the right to bring claims” as another

indication that the assignment was not absolute but one by way of charge. In the Tribunal’s

view this is incorrect. Clause 4.1(3)(c) is not a retention of right in favour of IPTL. It is instead

a reservation that, notwithstanding the assignment, the Security Agent is under no obligation

to take action to present or file claims against any other party. It does not, however, deprive

the assignee of the right to do so if it so wishes.

Page 54: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

47

The Tribunal also does not agree that the mere fact that the Security Deed provides for the

continuing performance by IPTL of the “Assigned Contracts” supports the Respondent’s

suggestion that the assignment could not be an absolute one. Such an argument ignores the

very attribute of an assignment as transferring rights and not burdens and obligations. The

Tribunal is satisfied that there is nothing in the Security Deed that qualifies or limits in any

manner the assignment of the Assigned Contracts (which by definition include the

Implementation Agreement).

b. Notice of Assignment

There can no longer be any argument that notice was not given by the Security Agent in a

formal Notice of Assignment of the Implementation Agreement under the Security Deed as it

was acknowledged by the GoT.198 The Respondent could argue that there is a requirement

that at each and every step in the chain of assignments, leading to and concluding with the

2005 Deed from Danaharta to SCB HK, must comply with the requirement of notice to the

Government. The Respondent submits that a notice sent to the Government after the 2005

Deed would not only need to notify the Government of the details of that assignment, but also

of any earlier steps which had not previously been expressly notified. It also cites in support

the decision of the English Court of Appeal in E Pellas v Neptune Marine199 to argue for “each

successive assignment [had] to comply with the 1873 Act.”200 In that case, the assignor of an

insurance policy taken out by the insured, had sued the insurer for the proceeds after the

perils insured had occurred. The insured had incurred unpaid premiums due on other

policies taken out with the insurer and sought to set-off these amounts against the sum due

to the assignee. The Court of Appeal rejected the plea of set-off even though the insurer

argued that it was prejudiced by lack of notice of the assignment prior to extending the credit

to the insured. Admittedly, the court was concerned with the Policies of Marine Insurance Act

1868 rather than the Judicature Act 1873. The court did nevertheless say in obiter, that – “[t]he

plaintiffs cannot succeed as assignees of a debt or chose in action pursuant to the Supreme Court

of Judicature Act, 1873, s. 25, sub-s. 6, because the defendants have had no notice of the

198 HB/H/021/315: Notice of Assignment, 3 October 1997. 199 Exhibit RL-143: E Pellas & Co v Neptune Marine Insurance Co (1879) 5 CPD 34 (submitted at the Hearing). 200 Respondent’s PHB, para. 13.

Page 55: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

48

assignments […].”201 Still, there is nothing in the statement to suggest that the each and every

assignment must require a separate notice of assignment.

GoT also quoted Lord Denning’s statement in WF Harrison & Co Ltd v Burke202 as support –

[T]he notice in writing of the assignment is an essential part of the transfer of title to the debt, and, as such, the requirements of [Section 136 of] the [Law of Property] Act [1925] must be strictly complied with, and the notice itself, I think, must be strictly accurate – accurate in particular in regard to the date which is given for the assignment; and even though it is only one day out, as in this case, the notice of assignment is bad.

The Tribunal agrees with GoT that the mischief which the Judicature Act 1873 targeted was a

debtor faced with claims by assignees it did not know; the “key requirement is the full

knowledge of the debtor so as to avoid confusion.”203

The Claimant had at the hearing pointed out that GoT was notified of the Claimant’s interest

at the latest by 17 December 2009204 when it informed GoT that –

SCB HK has also been assigned the Implementation Agreement dated 8 June 1995 (the “Implementation Agreement”) entered into between IPTL and the Government of Tanzania (“GOT”).

The Respondent then took the position that this notice made no mention of when the rights

to the Implementation Agreement had left Sime Bank, or any details in between and therefore

fell short of the notice required under the Judicature Act 1873.

The Claimant had also tendered its letter of 3 December 2013205 in which it notified GoT of

the occurrence of certain “Events of Default” under the Implementation Agreement and in

particular that –

By a Security Deed dated 28 June 1997, IPTL assigned all of its present and future right, title and interest in and to the Implementation Agreement to the Security Agent in connection with a US$ 105,000,000 Loan Facility Agreement provided to IPTL by a consortium of foreign

201 Exhibit RL-143 at pg. 37: E Pellas & Co v Neptune Marine Insurance Co (1879) 5 CPD 34. 202 Exhibit RL-148 at pg. 421: WF Harrison & Co Ltd v Burke [1956] 1 WLR 419 (CA) (submitted along with Respondent’s PHB). 203 Respondent’s PHB, para. 15. 204 Exhibit C-411: Letter from Herbert Smith to the Attorney General of Tanzania, 17 December 2009 (submitted at the Hearing). 205 HB/H/352/4948-4953 at pg. 4948: Letter from SCB HK to Principal Secretary, Ministry of Water, Energy and Minerals, 3 December 2013, para. 2.

Page 56: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

49

lenders. The GoT was given notice of the assignment on 3 October 1997, which the GoT acknowledged. Standard Chartered Bank (Hong Kong) Limited (“SCB HK”) is now the Security Agent, having acquired the loan (and related security) from the previous lenders in 2005. SCB HK is therefore entitled (as assignee) to exercise all rights and remedies granted to IPTL under the Implementation Agreement.

The Respondent maintained that this letter still left it confused as to how SCB HK is supposed

to have acquired the rights under the Implementation Agreement and that there was no

mention of the assignment from Sime Bank to RHB Bank.

From these documents, it is clear to the Tribunal that GoT had, at the very latest, since 3

December 2013 (if not by 17 December 2009) been aware that the Claimant asserted its

interest in the Implementation Agreement as assignee and the GoT could not therefore

complain that it did not know or had no notice of who the assignee was nor should it be

confused by any possible adverse claim by any competing claimant under the

Implementation Agreement. In fact, GoT has not identified any competing claim.

c. Status of the Security Agent

The Respondent had also raised the fact that the Security Agent was changed from Sime

Singapore to RHB Bank Singapore and then to the Claimant. The Tribunal notes that (as

discussed in paragraph 82(ii) above), there was in fact no entity change from Sime Singapore

to RHB Bank Singapore. It was the re-naming of Sime to RHB following a merger sanctioned

by the Malaysian High Court. The change in entity of the Security Agent also did not occur in

2005 following the sale by Danaharta to SCB HK.206

This then led GoT to argue that when Danaharta assigned the rights to SCB HK, Danaharta did

not and could not have assigned its role as Security Agent to SCB HK. The Respondent further

argues that “RHB remained the Security Agent until 29 October 2009, when it was removed from

such position by SCB HK” and SCB HK became the Security Agent on 4 November 2009 by

naming itself as the Security Agent.207 The Tribunal notes that this letter208 was not

communicated to GoT.

206 See para. 82 above. 207 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 38; HB/H/129/1288: Letter from SCB HK to RHB Bank Berhad, 29 October 2009; HB/H/132/1292-1293: Letter from SCB HK to SCB HK, 4 November 2009. 208 HB/H/132/1292-1293: Letter from SCB HK to SCB HK, 4 November 2009.

Page 57: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

50

In this regard, the Tribunal notes that the Implementation Agreement was signed by Sime

Singapore as the Security Agent, but it was expressly described as -

[…] in its capacity as Security Agent under the Facility Agreement (the “Security Agent”) which expression includes any successor appointed as Security Agent.209

The role of the Security Agent as spelt out in Article 22 of the Facility Agreement210 is

described as that of an “agent and principal” only. In other words, the Security Agent’s role is

merely to hold the security only on behalf of the principal lenders, following the sale by

Danaharta to SCB HK, the sole lender was SCB HK. According to Article 22(H) of the Facility

Agreement,211 the right to appoint and remove the Security Agent lies with the “Majority

Banks”,212 which by 2009 was only SCB HK and no other. In the Tribunal’s view, the change

of Security Agent from RHB Bank Singapore to SCB HK does not impact upon the right of SCB

HK as the assignee as Lender under the Facility Agreement and the assignee of the rights

under the Implementation Agreement.

The Tribunal is satisfied that:

i. the Notice of Assignment of 3 October 1997213 was sufficient notice to GoT of the

assignment by IPTL of the Implementation Agreement to the lenders and the Security

Agent;

ii. the subsequent notices of SCB HK on 17 December 2009214 and 3 December 2013215

to GoT were sufficient to inform GoT of the Claimant’s interest as sole lender and

Security Agent referred to under the Implementation Agreement; and

iii. the assignment made under Clause 3.2.1 of the Security Deed is in the nature of an

absolute assignment and not by way of a charge, compliant with the Section 25(6) of

the Judicature Act 1873.

209 HB/C/009/366-457 at pg. 367: Security Deed, 28 June 1997. 210 HB/C/008/280-365 at pgs. 335-339: Facility Agreement, 28 June 1997. 211 HB/C/008/280-365 at pgs. 338-339: Facility Agreement, 28 June 1997. 212 Clause 1 of the Facility Agreement provides: ““Majority Banks” means from time to time such banks voting or deciding the same way on a particular point holding in the aggregate not less than 66.67% of the aggregate of the Outstandings”; HB/C/008/280-365 at pg. 293: Facility Agreement, 28 June 1997. 213 HB/H/021/315: Notice of Assignment, 3 October 1997. 214 Exhibit C-411: Letter from Herbert Smith to the Attorney General of Tanzania, 17 December 2009. 215 HB/H/352/4948-4953 at pg. 4948: Letter from SCB HK to Principal Secretary, Ministry of Water, Energy and Minerals, 3 December 2013.

Page 58: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

51

d. Non-Registration of Charge under Section 79 of the Companies Ordinance 1921

(i) Parties’ Submissions

It is common ground that the assignment of the Implementation Agreement to the Security

Agent under Clause 3.2.1 of the Security Deed was not registered with BRELA as a charge

under Section 79 of the Companies Ordinance 1921 (Tanzania). However, the Parties disagree

as to the requirement for such registration, as well as, the effect of the non-registration on

the validity of the assignment of the Implementation Agreement.

Sections 79(1) and (2) of the Companies Ordinance 1921 (Tanzania) states as follows:

(1) Subject to the provisions of this Part of this Act, every charge created after the fixed date by a company registered in Tanzania and being a charge to which this section applies shall, so far as any security on the company’s property or undertaking is conferred thereby, be void against the liquidator and any creditor of the company, unless the prescribed particulars of the charge, together with the instrument, if any, by which the charge is created or evidenced, or a copy thereof verified in the prescribed manner are delivered to or received by the Registrar for registration in manner required by this Act within forty two days after date of its creation, but without prejudice to any contract or obligation for repayment of the money thereby secured, and when a charge becomes void under this section the money secured thereby shall immediately become payable.

(2) This section applies to the following charges –

(a) a charge for the purpose of securing any issue of debentures;

(b) a charge on uncalled share capital of the company;

(c) a charge created or evidenced by an instrument which, if executed by an individual, would require registration as a bill of sale;

(d) a charge on immovable property wherever situate, or any interest therein;

(e) a charge on book debts of the company;

(f) a floating charge on the undertaking or property of the company;

(g) a charge on calls made but not paid;

Page 59: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

52

(h) a charge on a ship or any share in a ship;

(i) a charge on goodwill, a patent or a licence under a patent, on a trademark or on a copyright or a licence under a copyright. [...]216

The Respondent argues that even if the Tribunal were to hold that Clause 3.2.1 of the Security

Deed effects a statutory assignment, the security interest created is void under Tanzanian law

as it was not registered as required under Section 79 of the Companies Ordinance 1921

(Tanzania). It contends that this interpretation is confirmed by the PwC Report relied on by

the Claimant.217

The Respondent relies on the wording of Section 79, as well as Tanzanian case law, in

particular the decision of the Court of Appeal of Tanzania in Shinyanga Regional Trading

Company Limited and Another v National Bank of Commerce (“Shinyanga”),218 to support the

contention that the failure to register a registrable charge voids it not only against liquidator

or secured creditor, but against any creditor.219

The Respondent rejects the Claimant’s contention that Shinyanga was decided per incuriam.

It notes that stare decisis is an essential feature of Tanzanian law, and points out that in the

similar case of Marungu Sisal Estate Limited v CRDB Bank Limited (“Marungu”),220 no appeal

was made to the Court of Appeal on the basis that Shinyanga had been decided per

incuriam.221 It urges the Tribunal not to give weight to Flaux J’s view that Shinyanga was

decided per incuriam, because until the Court of Appeal of Tanzania overrules Shinyanga, the

interpretation of Tanzanian law is that that decision is binding law in Tanzania.222 Further,

any concessions made by TANESCO’s counsel in the PPA Arbitration on this point were made

in passing, and in any event, the Respondent is not bound by them.223

216 HB/G/168/11681-11850 at pgs. 11721-11722: Companies Ordinance 1921 (Tanzania), Chapter 212. 217 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 195. 218 HB/G/283/14764-14780: Shinyanga Regional Trading Company Limited and Another v National Bank of Commerce [1997] TLR 78, Judgment, 28 February 1997. 219 HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 191-195 ; HB/A/005/604-827: Respondent’s Rejoinder, paras. 186-188. 220 HB/G/246/14090-14125: Marungu Sisal Estate Limited v CRDB Bank Limited, Civil Case No 7 of 2000. 221 HB/A/005/604-827: Respondent’s Rejoinder, paras. 187-188. 222 HB/A/005/604-827: Respondent’s Rejoinder, para. 190. 223 HB/A/005/604-827: Respondent’s Rejoinder, para. 189.

Page 60: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

53

The Respondent is also of the view that the assignment of the Implementation Agreement

was a charge on book debts that should have been registered under Section 79 of the

Companies Ordinance 1921 (Tanzania). The Respondent asserts that as the PPA was held by

the PPA Tribunal to amount to a charge on book debts, the Implementation Agreement is

likewise registrable, because the two agreements were designed to work together and form

one and the same transaction. Further, the Respondent contends that the PPA Tribunal found

that Clause 3.2.1 of the Security Deed as a whole needed to be registered under Section 79 of

the Companies Ordinance 1921 (Tanzania). Additionally, the fact that the Security Deed has a

separate provision addressing the assignment of insurance contracts, according to the

Respondent, indicates that the Implementation Agreement is not a contingent contract but a

book debt.224 Finally, due to the integrated nature of the Security Deed, the Respondent

submits that it is not possible to sever valid charges, if any, from charges that are invalid for

want of registration.225

Alternatively, the Respondent submits that, if the Tribunal finds that such security should be

granted relative effect despite its lack of registration, the Respondent contends that such

effect is confined to the relationship between the Claimant and IPTL and that the Claimant is

unable to derive any rights therefrom vis-à-vis GoT.

The Claimant argues that the assignment of the Implementation Agreement was not a charge

on book debts within the meaning of Section 79(2) of the Companies Ordinance 1921

(Tanzania) and was not required to be registered. While the PPA might be regarded as

entailing a book debt due to the expectation of capacity payments, this is not the case for the

Implementation Agreement. Rather, the Implementation Agreement is a contingent contract

insofar as payments only become due from the Respondent as damages or compensation, in

the event that the protections guaranteed by the Respondent are breached. 226 Although both

agreements are part of a suite of project agreements, they are fundamentally distinct in

nature.227 The security created by the assignment of the Implementation Agreement was not

a charge on book debts. Further, it asserts that the Respondent’s reliance on the PPA

224 HB/A/005/604-827: Respondent’s Rejoinder, para. 191. 225 HB/A/005/604-827: Respondent’s Rejoinder, para. 192. 226 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, paras. 199, 210-213. 227 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, para. 204.

Page 61: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

54

Tribunal’s ruling is misplaced, as the PPA Tribunal did not decide that all security created by

Clause 3.2.1 of the Security Deed was registrable.228

The Claimant also submits that to the extent that Clause 3.2.1 of the Security Deed created

other charges which were registrable, and assuming that those charges are invalid for want

of registration,229 those invalid charges may be severed from the valid charge in respect of

the assignment of the Implementation Agreement. Further, the Claimant submits that this

was the position taken in the PPA Decision and is supported by pre-reception English

authority (binding as a matter of Tanzanian law), and subsequent English and Australian

cases. In the Claimant’s view, the principle of severability applies even when security is

created in the same instrument, arises in respect of the same project, and relates to the same

underlying property. This according to the Claimant is reinforced by the language of Section

79(1) of the Companies Ordinance 1921 (Tanzania), which distinguishes between the

“charge”, which will be void against the liquidator or secured creditor, and the "instrument …

by which the charge is created or evidenced, which is not so voided.”230

Alternatively, the Claimant submits that even if the assignment of the Implementation

Agreement was required to be registered, or even if the charge created by the assignment of

the Implementation Agreement cannot be severed from charges that required registration,

the effect of non-registration is not to invalidate the charge against the whole world.

According to the Claimant, Section 79 of the Companies Ordinance 1921 (Tanzania) only

operates to invalidate registrable but unregistered charges against a liquidator,

administrator or secured creditor. It argues that this is clear from the plain language of

Section 79 and supported by English authorities.231 As IPTL was not in liquidation, and there

was no secured creditor with an interest in the benefit of the “Assigned Contracts”, the charges

created by Clause 3.2.1 of the Security Deed remain valid. Further, it asserts that no reliance

can be placed by the Respondent on the position in the PwC Report on this point, because at

the time the Report was issued, a Liquidator had been appointed over IPTL.232

228 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, paras. 206-209. 229 Which the Claimant denies; See HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, para. 227. 230 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, para. 226. 231 Which are binding on Tanzanian Courts pre-reception date and are persuasive authority post-reception date; HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, para. 231. 232 HB/A/004/371-603: Claimant’s Reply, para. 329.

Page 62: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

55

The Claimant also argues that the decision in Shinyanga is per incuriam, as it does not

properly reflect Tanzanian law, and the Tribunal is entitled not to apply it.233 The decision

ignores the plain language of the legislation, and it was made without reference to binding

pre-reception date authorities and other persuasive authorities, and nor is it supported by

Marungu. According to the Claimant, Flaux J correctly rejected the Shinyanga decision, and

the PPA Tribunal correctly held that the unregistered charge remained valid in the absence

of a liquidator. Additionally, TANESCO’s counsel did in fact concede that a failure to register

a registrable charge would not invalidate the charge unless the company was in

liquidation.234

(ii) Tribunal’s Analysis

On the basis of the Tribunal’s finding that the assignment made under Clause 3.2.1 of the

Security Deed is in the nature of an absolute assignment and not by way of a charge, this

question requires no further consideration. However, as the Parties have debated this issue

extensively, the Tribunal will proceed to deal with them in the following paragraphs.

The key question that requires the Tribunal’s determination is whether the assignment of the

Implementation Agreement, even if it amounts to a charge only, is a “charge to which Section

79(2)” of the Companies Ordinance 1921 (Tanzania) applies.

From the list enumerated in Section 79(2), only the descriptive of “book debts” appears to be

the closest possible category into which the Implementation Agreement could fall into.

Under the Implementation Agreement, the bundle of rights that have been promised by the

GoT to IPTL could be described as follows:235

i. Article V: The “exclusive right to design, finance, insure, construct, complete, own,

operate, and maintain the Facility in accordance with the terms and conditions

contained in this Agreement and the Laws of Tanzania”.

ii. Article VII: Support of GoT to:

a) obtain consents from regulatory agencies;

b) use its good offices to support IPTL’s performance of its obligations;

233 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, para. 233. 234 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, paras. 236-241. 235 HB/C/005/192-267: Unsigned copy of Implementation Agreement (including Schedules),8 June 1995.

Page 63: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

56

c) attach non-discriminatory terms and conditions to the issuance or renewal of

any of the Consents as are in accordance with the Laws of Tanzania;

d) take actions as are reasonable and appropriate under the circumstances to

ensure that IPTL receives the fiscal incentives, concessions, financial

arrangements, and any other benefits provided under the “Policy Framework”.

iii. Article IX (9.7): Avoiding “Double Jeopardy” – “Settlement or waiver in writing by

TANESCO of any dispute or breach under the Power Purchase Agreement shall be

binding on the GOT with respect to the identical issue or claim.”

iv. Article XI: Assistance with immigration controls.

v. Article XIII: Entitlement for imports and exports of items needed.

vi. Article XIV: Consent to open and operate Foreign Currency Accounts.

vii. Article XVI: Assurances against discriminatory actions, expropriation, compulsory

acquisition and nationalisation of capital or assets of IPTL.

viii. Article XVII (17.7): Special compensation for Force Majeure events.

ix. Article XVIII: Tax exemptions.

x. Article XXII and Schedule 1: Undertaking to Guarantee.

xi. Article XXIV (24.10): “Most Favoured Nation” treatment.

The concept of a “book debt” normally refers to the money received or receivable in the

ordinary course of business of a company. These would normally include, among others, any

money or receivables for sale of services or goods, proceeds of dispositions, or, hire, bank

balances, in cash or cash equivalent and so forth. An assignment of a long-term contract for

the sale of power under the PPA would no doubt give rise to receivables and constitute book

debts. It is, however, rather implausible to suggest the bundle of rights and privileges and

promises of support set out in the Implementation Agreement are “book debts” contemplated

under Section 79 of the Companies Ordinance 1921 (Tanzania). None of the evidence or

arguments show in what manner the rights given by GoT under the Implementation

Agreement are akin to receivables and could constitute “book debts”.

On first principles even if the assignment of the Implementation Agreement constitutes some

form of “charge”, it is nevertheless not a charge of a “book debt” or any other kind of charge

under Section 79(2) of the Companies Ordinance 1921 (Tanzania). There is accordingly no

requirement for the “charge” to be registered. It follows that there is no need for the

Page 64: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

57

consideration of whether a failure to register would render the same void against GoT or only

against the liquidator.

e. Breach of Section 172 of the Companies Ordinance

(i) Parties’ Submissions

The Respondent argues that that the transfer of the loan from Danaharta to SCB HK in 2005

was invalid, because it breached Section 172 of the Companies Ordinance 1921 (Tanzania).

Section 172 of the Companies Ordinance 1921 (Tanzania) states that:236

172. Avoidance of dispositions of property, etc., after commencement of winding up In a winding up by the court, any disposition of the property of the company, including actionable claims, and any transfer of shares, or alteration in the status of the members of the company, made after the commencement of the winding up, shall, unless the court otherwise orders, be void.

According to the Respondent, this provision prohibits the transfer of assets and interests,

including actionable claims, of a company undergoing winding up proceedings. Any such

transfer is null and void if performed without the leave of the High Court of Tanzania.

The Respondent argues that since IPTL was in winding up proceedings at the time of the

purported acquisition of the loan by the Claimant from Danaharta, and the permission of the

High Court of Tanzania was not sought regarding this acquisition, the transfer is null and void.

The High Court has continuous supervisory powers once a winding up petition has been

commenced, and permission for any disposition must be obtained while the winding up

proceedings are ongoing, and not merely after the court has declared the company wound up.

The Respondent submits that this interpretation of Section 172 was also put forward by

Martha Renju in proceedings in the British Virgin Islands in 2010. Further, it asserts that

Danaharta and the Claimant were warned that the transfer of the loan to SCB HK in 2005

could be invalidated by Section 172 but chose to ignore such advice.237

The Respondent also contends that the transfer of the loan was an “actionable claim” covered

by Section 172, as it comprised a right to bring a claim as security for a loan granted in favour

of a company. It further takes the view that the validity of the transfer of the loan is not a

236 HB/G/168/11681-11850 at pg. 11760: Companies Ordinance 1921 (Tanzania), Chapter 212 (emphasis in original). 237 HB/A/005/604-827: Respondent’s Rejoinder, paras. 193-195.

Page 65: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

58

question to be governed by English law (the law applicable to the Facility Agreement). As the

“transfer took effect in Tanzania with respect to security for a loan granted in favour of a

Tanzanian company which was undergoing winding up proceedings in Tanzania, permission

from the High Court of Tanzania overseeing those winding up proceedings was a necessary

requisite.”238

The Claimant argues that IPTL was not in winding up within the meaning of Section 172 read

with Section 174 of the Companies Ordinance 1921 (Tanzania) when the Term Loans were

transferred from Danaharta to the Claimant in 2005. Section 174 governs the time of

commencement of the winding up order, and states as follows:

174. Commencement of winding up by the court

(1) Where before the presentation of a petition for the winding up of a company by the court a resolution has been passed by the company for voluntary winding up, the winding up of the company shall be deemed to have commenced at the time of the passing of the resolution, and unless the court, on proof of fraud or mistake, thinks fit otherwise to direct, all proceedings taken in the voluntary winding up shall be deemed to have been validly taken.

(2) In any other case, the winding up of a company by the court shall be deemed to commence at the time of the presentation of the petition for the winding up.

The Claimant contends that, according to commentary on equivalent provisions of English

insolvency legislation, this provision operates retrospectively to invalidate property

dispositions made after the winding up petition is presented in the event a winding up order

is made. 239 Where no such order has been made, property dispositions are not invalidated.

In the present case, according to the Claimant, as the Tanzanian Court of Appeal ultimately

quashed the Winding Up Order, the transfer from Danaharta to the Claimant was not

invalidated. The Claimant points out that this was also the conclusion reached by Flaux J.240

Further, it submits that to the extent that Martha Renju took the position stated by the

Respondent, that was incorrect, and in any event, not dispositive of the claim before the BVI

238 HB/A/005/604-827: Respondent’s Rejoinder, para. 196. 239 HB/A/004/371-603: Claimant’s Reply, paras. 360-366. 240 HB/D/018/755-793 at pgs. 766-767: Flaux J Judgment, 16 November 2016, para. 45; See also HB/D/016/675-738 at pgs. 695-696: Judgment of the English Commercial Court in SCB HK and SCB Malaysia Berhad v IPTL, VIP and PAP [2015] EWHC 1640 (Flaux J Jurisdiction Judgment), 9 June 2015, para. 75.

Page 66: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

59

Court. Further, the Claimant disagrees that any such warning of the invalidity of the loan as

asserted by the Respondent was in fact given.241

The Claimant also notes that, from a policy perspective, a provision which invalidated

dispositions made where no winding up order is ultimately made would be pointless as there

would be no need to preserve assets for a pari passu distribution to creditor. Such a provision

would be unjust as companies presented with a winding up petition (however groundless)

would be effectively paralysed by the threat of having perfectly legitimate transactions

invalidated, even if the winding up petition is later dismissed or withdrawn.242

In the Claimant’s view, the transfer of the loan from Danaharta to SCB HK in 2005 was the

transfer of a liability of IPTL, not the transfer of property of IPTL. The transfer thus fell outside

the prohibition on dispositions under Section 172. This it submits was the conclusion reached

in the PwC Report and by Flaux J. Further the Claimant asserts that to the extent that the

Respondent is implying that "actionable claims" include the Claimant’s right to bring a claim

in its capacity as Security Agent as the assignee of the legal benefit of the Implementation

Agreement, this is not relevant as the disposition by IPTL of the legal benefit of the

Implementation Agreement to the Security Agent occurred in 1997 by way of the statutory

assignment. From then onwards, the benefit of the contract was no longer part of the property

of IPTL. The disposition in 1997, made some 5 years before the Winding Up Petition was filed

in 2002, was not a disposition made during the winding up of IPTL.243

In any event, the Claimant contends that Section 172 of the Companies Ordinance 1921

(Tanzania) cannot invalidate the transfer of the loan from Danaharta to SCB HK because the

validity of the transfer is not governed by Tanzanian law. It argues that the Facility Agreement

is governed by English law, and the validity of the transfer is thus also governed by English

law. It also states that pursuant to the non-exclusive jurisdiction clause in the Facility

Agreement, Flaux J determined that the transfer of the loan is governed by English law, which

recognised the transfer as valid.244

241 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, paras. 268-270. 242 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, para. 267. 243 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, paras. 272-280. 244 HB/A/004/371-603: Claimant’s Reply, paras. 373-375; HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, paras. 282-287.

Page 67: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

60

Finally, the Claimant notes the irony in the Respondent’s purportedly improper recognition

of the alleged sale of the Mechmar Shares to PAP when, on its own case, Section 172 would

have invalidated the transfer. The VIP-PAP SPA alleged that PAP had purchased the Mechmar

Shares from Piper Link in 2011,245 and the SPA was countersigned by Mr Saliboko in his

capacity as Second Provisional Liquidator of IPTL. Section 172 expressly applies to “any

transfer of shares”, and the purported transfer allegedly took place after the Winding Up

Petition was filed in 2002 but before the Winding Up Order was quashed in 2012 (or

withdrawn in 2013). Mr Saliboko recognised the purported transfer of the Mechmar Shares,

but refused to recognise the transfer of the loan, even though both would have been invalid

according to the Respondent’s interpretation of Section 172. The Claimant alleges that the

contradictory position taken by Mr Saliboko and the Respondent “highlights the cynicism and

expediency of their stance on the issue.”246

(ii) Tribunal’s Analysis

It is not in dispute between the Parties that a Winding Up Petition was filed against IPTL in

February 2002. The Winding Up Order was made against IPTL on 15 July 2011 by the

Tanzanian High Court (Kaijage J).247 That order for winding-up was, however, set aside by the

Court of Appeal on 17 December 2012248 and finally withdrawn by the petitioner VIP on 26

August 2013.249 It is the Respondent’s case that the transfer from Danaharta to SCB HK took

place in 2005 after the commencement of the winding up proceedings and during such

proceedings and as such is rendered null and void under Section 172 of the Companies

Ordinance 1921 (Tanzania), as it was made without the permission of the Tanzanian High

Court. In its view, it matters not that the Winding Up Order was eventually set aside or that

the Winding Up Petition was withdrawn, as Section 172 of the Companies Ordinance 1921

(Tanzania) prohibits any disposition immediately following the commencement of winding-

up proceedings with no express exceptions save for dispositions made with leave of court.

245 Which the Claimant says was impossible, because the Claimant had successfully enforced its Charge of Shares in respect of the Mechmar Shares in the Malaysian and BVI Courts in 2010 and 2011. 246 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, paras. 288-291. 247 HB/H/185/2513-2542: Ruling of Kaijage J in the High Court of Tanzania, 15 July 2011. 248 HB/H/258/3725-3752: Decision of the Court of Appeal of Tanzania, 17 December 2012. 249 HB/H/290/4571-4577: VIP Engineering and Marketing Ltd v Independent Power Tanzania Limited and others, High Court of Tanzania, Consolidated Misc. Civil Cause Nos. 49 of 2002 and 254 of 2003, Notice by the Petitioner (VIP) of Withdrawing the Petition for Winding Up IPTL and Withdrawing All Ancillary Applications by VIP received by Adept Chambers on behalf of SCB HK, 26 August 2013 and 27 August 2013.

Page 68: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

61

The Tribunal accepts that the scheme contemplated under the winding up provisions of the

Companies Ordinance 1921 (Tanzania) is that when a winding up order is made it enjoys

efficacy to avoid dispositions made after the commencement of the winding-up proceedings.

The intent of the scheme is to avoid the preferential treatment of certain creditors. But when

no winding up order is made and the petition is eventually withdrawn, dispositions are not

rendered void because there remain no proceedings in place that have that effect and any

permission that was needed from the Court is no longer required. Similarly, if an order is

made but subsequently set aside then dispositions made even during the period of the

winding-up would not be rendered void because upon the setting aside of the order, there is

no legal entailment that remains giving rise to the disposition being void.

In any event, the Tribunal also does not accept that the loans constituted under the Facility

Agreement are “the property of the company”. Far from being an asset, they constitute

liabilities of IPTL and would not in the least impact other creditors. The loan remains a

liability of the company and could not become a “right to bring a claim as security for a loan

granted in favour of a company”. Such a right is embodied in the Implementation Agreement

and could be the basis of an “actionable claim” but that had already been assigned absolutely,

to the lenders/banks in 1997, much before the Winding Up Petition was filed.

(3) Tribunal’s Finding on the Claimant’s Status as Legal Assignee

The terms of the Implementation Agreement permit IPTL to “assign or create a security

interest” in favour of its “Lenders” subject only to IPTL having obtained “prior written consent”

from GoT. Although no “prior” written consent was given, the consent was subsequently

given on 3 October 1997 and acknowledged by the signature of its Ministry of Water, Energy

and Minerals on the Notice of Assignment of the Implementation Agreement,250 and by the

letter from its Minister of Finance of 13 October 1997 addressed to IPTL, which was copied

to the Prime Minister, Minister of Energy and Minerals, Minister-Planning, Attorney-General,

Chief Secretary, and MD TANESCO confirming its agreement to “the execution of the

assignments of the Implementation Agreement […]”.251 The Tribunal therefore finds that

consent was given and the requirement for “prior” consent was accordingly waived.

250 HB/H/021/315: Notice of Assignment, 3 October 1997. 251 HB/H/022/316-317: Letter from Daniel Yona, Minister of Finance, to IPTL, 13 October 1997.

Page 69: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

62

The Tribunal also holds that the requirement for consent from GoT for the original banks to

assign their interest in the Implementation Agreement is not required under Article 15.2 of

the Implementation Agreement as any subsequent assignment by the banks would be an

assignment by the banks qua the lender and not as a “permitted assignee” of the Company.

The Tribunal is satisfied that while Clause 3.1 of the Security Deed creates “charges”, Clause

3.2 thereof assigns to the Security Agent for the benefit of the Secured Creditors without any

condition or qualification of “all its present and future right, title and interest in and to the

Assigned Contracts” (which definition includes the Implementation Agreement). The

assignment is an absolute one not an assignment by way of charge only. The notice of such

assignment in relation to the Implementation Agreement was given by the Security Agent on

behalf of the lenders and acknowledged by GoT. GoT was also notified by the Claimant as

successor lender of its interest at the very latest in December 2009 and could not therefore

claim that it was unaware of the Claimant’s claims as under the Implementation Agreement.

Any change in the Security Agent has no impact upon the right of SCB HK as the assignee as

Lender under the Facility Agreement and the assignee of the rights under the Implementation

Agreement.

The assignment is an absolute one and not merely a charge as such it falls outside the

requirement for registration under the Section 79(2) of the Companies Ordinance 1921

(Tanzania). As the Winding Up Order made by Kaijage J was subsequently set aside by the

Court of Appeal and then eventually withdrawn, the rights of SCB HK under the

Implementation Agreement could not be affected and remain actionable. All said, the

Tribunal finds that the Claimant (SCB HK) has all the rights under the Implementation

Agreement assigned to it by Danaharta (as the successor in title of the Lenders) and

accordingly has the title and interest to pursue its claims against GoT for any breach of the

Implementation Agreement in its own name.

B. JURISDICTION UNDER ARTICLE 25 OF THE ICSID CONVENTION

The Respondent contends that the Tribunal lacks jurisdiction under Article 25 of the ICSID

Convention on two grounds: (1) the Claimant is not a “National of another Contracting State”;

and (2) the Claimant does not have an “investment.”

Page 70: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

63

(1) National of Another Contracting State

a. Parties’ Submissions

The Respondent’s response in relation to the Claimant’s assertion that the Claimant’s

nationality should be considered for the purpose of “diversity of nationalities” under Article

25 of the ICSID Convention, is that it did not consent to the assignment of IPTL’s rights under

the Implementation Agreement and so the Claimant is not in fact the statutory assignee of

IPTL pursuant to the Implementation Agreement. Accordingly, it follows then that the

Claimant has no right to bring this arbitration in its own name. According to the Respondent,

in any case, the Implementation Agreement does not permit lenders to bring an arbitration,

and the only nationality that should be considered would be as provided under Article 21.2

of the Implementation Agreement is IPTL’s nationality.252

The Respondent further contends that under Article 21.2 of the Implementation Agreement

(i.e. the arbitration clause), the Parties agreed that IPTL would be treated as a foreign entity

as long as a foreign investor holds at least 35% of its voting stock. In its view, the question of

nationality which must be assessed at the “time of expressing consent to arbitration (i.e. when

signing the Implementation Agreement)” as well as when the request for arbitration was made

in the case.253 It also asserts that as IPTL is now fully owned and controlled by a Tanzanian

entity, namely PAP,254 ICSID’s jurisdiction under Article 25 of the ICSID Convention could not

be invoked as IPTL, as a Tanzanian national, is not “a national of another contracting State.”255

The Claimant says that it is an entity incorporated in Hong Kong and thus is a national of the

People’s Republic of China (a contracting State to the ICSID Convention). Further, it also

argues as the Claimant is bringing this claim as the assignee of IPTL’s rights under the

Implementation Agreement, it is the Claimant’s nationality, and not IPTL’s nationality, that is

relevant.256

The Claimant submits that “foreign control” under Article 25(2)(b) of the ICSID Convention is

an “objective condition” and “must be viewed on its own particular context, on the basis of all of

252 HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 203-204. 253 Respondent’s PHB, para. 74 (citing Exhibit RL-158: Vacuum Salt Products Ltd. v Republic of Ghana, ICSID Case No. ARB/92/1, Award, 16 February 1994). 254 HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 203-204. 255 Respondent’s PHB, para. 75. 256 HB/A/002/035-143: Claimant’s Memorial, paras. 344-346.

Page 71: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

64

the facts and circumstances.”257 The Claimant adds that in any case, even though IPTL is a

Tanzanian corporation, it would still fulfil this requirement because Article 25(2)(b) of the

ICSID Convention extends the meaning of “National of another Contracting State” to include

“[…] any juridical person which had the nationality of the Contracting State party to the dispute

…on that date and which, because of foreign control, the parties have agreed should be treated

as a national of another Contracting State for the purposes of this Convention.” The Claimant

submits that pursuant to Article 21.1 of the Implementation Agreement the parties to the

Implementation Agreement made such an agreement wherein it was set out that “[f]or

purposes of consenting to the jurisdiction of the Convention, the Parties agree that the Company

is a foreign controlled entity unless the amount of the voting stock in the Company held by

Foreign Investors should decrease to less than thirty-five (35) percent of the outstanding voting

stock of the Company.”258

The Claimant also points out that, Mechmar, a Malaysian entity, owns 70% of the shares in

IPTL. It is the Claimant’s position that the transfer of the affairs of IPTL and the sums in the

Escrow Account to PAP on the basis that PAP had purchased the Mechmar Shares was illegal

and fraudulent. Any assertion by the Respondent that PAP has any valid interest in IPTL

would be extraordinary as it would permit the Respondent to rely on its own wrongdoing.259

In response, the Respondent says that PAP was recognised as IPTL’s sole shareholder as per

Utamwa J’s Order which took “judicial notice” of the VIP-PAP- SPA and transferred all affairs

of IPTL to PAP. If the Tribunal accepts the Respondent’s argument that Utama J’s Order is

effective, then IPTL would be under complete Tanzanian control for reasons that cannot be

attributed to the Respondent and the Tribunal would then not have jurisdiction to assess the

Claimant’s claims against it for the alleged violations, including the release of the Escrow

Account.260

b. Tribunal’s Analysis

The Tribunal has discussed in paragraphs 172 to 175 above and reached the finding that the

Claimant is the legal assignee of the Implementation Agreement. It follows that the Claimant

257 Claimant’s PHB, paras. 112-113. 258 HB/A/002/035-143: Claimant’s Memorial, paras. 346-347. 259 HB/A/004/371-603: Claimant’s Reply, paras. 381-385. 260 HB/H/311/4733-4748 at pgs. 4735-4736, 4747: Utamwa J Order, 5 September 2013; Respondent’s PHB, para. 75.

Page 72: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

65

is entitled to enforce the rights thereunder in its own name. Being a Chinese entity, it is

indisputably a “National of another Contracting State.”

In any event, as could be seen from the discussion in paragraphs 349 to 353 below, the

Tribunal has found that the Order of Utamwa J of 5 September 2013 directing that control of

IPTL, including the IPTL Power Plant, be handed to PAP had been made in curious

circumstances, with no regard to the registered shareholder Mechmar or the consequences

of permitting PAP to have control of the disposition of the Escrow Account.

The Tribunal finds that the Claimant satisfies the requirement of a “National of another

Contracting State”, namely China.

(2) Whether the Dispute Arises out of an “Investment” within the Meaning of Article 25(1) of the ICSID Convention

a. Applicable Test for Determining the Meaning of Investment

(i) Parties’ Submissions

The Respondent’s case is that the Claimant does not have a qualifying “investment” within the

objective meaning of investment for the purposes of Article 25(1) of the ICSID Convention.

According to the Respondent, the Claimant merely purports to have acquired accounts

receivables after the Facility was contracted for and built. The acquisition of the loan did not

involve any expectation of receiving an economic return beyond the mere repayment of the

loan with interest. The Respondent characterises the Claimant as a “speculative debt-hunter”

and argues that speculative activities ought not to fall within the jurisdiction of an ICSID

tribunal.261 In the Respondent’s view, the nature of the dispute does not arise “directly out of

an investment.”

The Respondent refers to the “Salini test” or “Salini criteria” (as set out in Salini v

Morocco)262 to suggest that there are essential characteristics for the notion of an

“investment” under Article 25 of the ICSID Convention that all must be met to establish

jurisdiction, which include “(1) the investor’s participation in the risks of the transaction; (2) a

substantial contribution by the investor; (3) a certain minimum duration; and (4) a signification

261 HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 205-206. 262 HB/G/054/5987-6002: Salini Costruttori S.P.A. and Italstrade S.p.A. v Kingdom of Morocco, ICSID Case No. ARB/00/4, Decision on Jurisdiction, 16 July 2001.

Page 73: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

66

contribution to the host State’s economic development.”263 The Respondent argues that these

conditions are not fulfilled in the present case and the purported acquisition of Term Loans

1 and 2 in 2005 does not constitute investment as per the objective criteria, and therefore

there is no investment within the meaning of Article 25(1) of the ICSID Convention.264

The Respondent also refers inter alia to the decision on jurisdiction in Consortium R.F.C.C. v

Royaume du Maroc265 to support its argument that the Parties cannot substitute the objective

requirements of an investment under Article 25(1) of the ICSID Convention.266 The

Respondent also refers to the Report of the Executive Directors on the ICSID Convention,

which it submits indicates that the Parties’ consent alone is not sufficient to establish

jurisdiction under the ICSID Convention.267

The Claimant’s position is that the Salini Test has no basis in the actual text of Article 25(1) of

the ICSID Convention. The Salini Test cannot override party agreement for defining what

constitutes an investment, even though it may be used to define the “outer limits” of what an

investment means under Article 25(1) of the ICSID Convention. It submits that the principal

legal framework to determine the existence of an investment should be the will of the Parties

as set forth in the bilateral investment treaty or investment contract. It refers to the decision

of Pantechniki S.A. Contractors & Engineers v Republic of Albania,268 to support its argument

that the Respondent’s approach based on the Salini Test can increase the risk of arbitrary and

subjective value judgments by a Tribunal.269 The Claimant asserts that, at its highest, the

Salini Test is an exemplary list of the typical features of an investment and not a mandatory

checklist. The Claimant contends that several ICSID tribunals had refused to apply the Salini

Test or have applied it in modified forms.270

263 Respondent’s PHB, para. 79. 264 HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 210, 226. 265 HB/G/088/9327-9360: Consortium R.F.C.C. v Royaume du Maroc, ICSID Case No. ARB/00/6, Decision on Jurisdiction, 16 July 2001. 266 HB/A/005/ 604-827: Respondent’s Rejoinder, para. 202. 267 HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 208-209; HB/G/119/10570-10584 at pgs. 10578-10579: Report of the Executive Directors on the Convention on the Settlement of Investment Disputes between States and Nationals of Other States, 18 March 1965, para. 25. 268 HB/G/337/16712-16736: Pantechniki S.A. Contractors & Engineers v Republic of Albania, ICSID Case No. ARB/07/21, (Award), 30 July 2009. 269 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, para. 337. 270 HB/A/004/371-603: Claimant’s Reply, para. 392; See HB/G/021/1925-2002 at pg. 1992: Philip Morris Brand Sàrl (Switzerland), Philip Morris Products S.A. (Switzerland) and Abal Hermanos S.A. (Uruguay) v Oriental Republic of Uruguay, ICSID Case No. ARB/10/7, Decision on Jurisdiction, 2 July 2013, para. 206; HB/G/022/2003-2157 at pgs. 2066-2067: Hassan Awdi, Enterprise Business Consultants, Inc. and Alfa El Corporation v Romania, ICSID Case No. ARB/10/13, Award, 2

Page 74: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

67

The Claimant argues that the loan constitutes an investment pursuant to Article 25 of the

ICSID Convention. Moreover, in the absence of a definition of “investment” in Article 25(1) of

the ICSID Convention, the tribunals in the cases Fedax N.V. v Republic of Venezuela271

(“Fedax”) and Ceskoslovenska Obchodni Banka, A.S. v Slovak Republic272 (“CSOB”) and Alpha

Projektholding GMBH v Ukraine273 referred to the Parties’ definition of investment in the

relevant “consent-giving” instrument (the bilateral investment treaty), which it submits is the

proper test. The Claimant also rejected the Respondent characterising it as a “debt-hunter” by

stating that this allegation goes to admissibility and is irrelevant to the jurisdictional issue of

what constitutes an investment.274

According to the Claimant, the scope of its “investment” for purposes of ICSID Convention

Article 25 could be made out from analysing the terms of the Implementation Agreement

showing that the Project, the financing of the Project and related security granted in relation

to it, form part of the overall investment.275

Additionally, the Claimant contends that the Parties included an ICSID arbitration clause in

the agreement with the clear expectation that disputes under the Implementation Agreement

would relate to a qualifying “investment” under the ICSID Convention. The Claimant points

out that the Parties to the Implementation Agreement anticipated that the successors and

assigns of the original lenders could become parties to the Implementation Agreement,

including the ICSID arbitration clause.276

(ii) Tribunal’s Analysis

The Claimant has submitted that the Tribunal should apply a “subjective” test to consider if

the Parties had under the terms of the Implementation Agreement accepted that the subject

matter is an “investment”, whereas the Respondent submits that the Tribunal must also apply

March 2015, para. 197; HB/G/023/2158-2229 at pgs. 2218-2219: Inmaris Perestroika Sailing Maritime Services Gmbh and others v Ukraine, ICSID Case No. ARB/08/8, Decision on Jurisdiction, 8 March 2010, paras. 129-131. 271 HB/G/002/021-033: Fedax N.V. v Republic of Venezuela, ICSID Case No. ARB/96/3, Decision of the Tribunal on Objections to Jurisdiction, 11 July 1997. 272 HB/G/008/441-473: Ceskoslovenska Obchodni Banka, A.S. v Slovak Republic, ICSID Case No. ARB/97/4, Decision of the Tribunal on Objections to Jurisdiction, 24 May 1999. 273 HB/G/016/1222-1404: Alpha Projektholding GmbH v Ukraine, ICSID Case No. ARB/07/16, Award, 8 November 2010. 274 HB/A/004/371-603: Claimant’s Reply, paras. 434-435. 275 HB/A/004/371-603: Claimant’s Reply, para. 408. 276 HB/A/002/035-143: Claimant’s Memorial, paras. 347-348, 357-358; HB/A/004/371-603: Claimant’s Reply, paras. 391-407.

Page 75: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

68

an “objective” test to ascertain if the elements of an investment exist in order to establish

jurisdiction under Article 25 of the ICSID Convention.

On the subjective test, the Claimant relies on the Respondent’s expressed consent in the

Implementation Agreement to submit any dispute to ICSID277 under the ICSID Rules. Such a

position is supported by several arbitral tribunals, which took the view that the consent of

the State party as to what constitutes an investment is of primary importance. The tribunal

in CSOB278 put it succinctly:

66[…] an important element in determining whether a dispute qualifies as an investment under the Convention in any given case is the specific consent given by the Parties. The Parties’ acceptance of the Centre’s jurisdiction with respect to the rights and obligations arising out of their agreement therefore creates a strong presumption that they considered their transaction to be an investment within the meaning of the ICSID Convention.

67. The Tribunal must accordingly attach considerable significance to the reference made in Article 7 of the Consolidation Agreement to the BIT and thus to the ICSID arbitration clause contained therein (Article 8). The Parties’ acceptance of the relevance and applicability of the BIT to the Consolidation Agreement expresses their view that the latter transaction relates to an investment within the meaning of the BIT. The contrary conclusion would deprive the reference to the BIT in Article 7 of the Consolidation Agreement of its meaning or effet utile.

The Tribunal notes, however, that the Parties’ consent as reflected in the contract, while of

great importance, could not be the only test and is not conclusive in resolving the issue of

whether there is jurisdiction under Article 25 of the ICSID Convention. The subject matter of

the dispute must nevertheless still be an investment as contemplated by the ICSID

Convention and consent by the Parties alone could not subject an ordinary commercial

transaction or political dispute or non-legal dispute to ICSID for resolution. This is expressed

in the Report by the Executive Directors on the Convention on the Settlement of Investment

Disputes between States and Nationals of Other States 279 −

25. While consent of the parties is an essential prerequisite for the jurisdiction of the Centre, consent alone will not suffice to bring a

277 HB/C/004/132-191 at pg. 182: Signed Implementation Agreement (without Schedules), 8 June 1995, Article 21.2. 278 HB/G/008/441-473 at pg. 464: Ceskoslovenska Obchodni Banka, A.S. v Slovak Republic, ICSID Case No. ARB/97/4, Decision of the Tribunal on Objections to Jurisdiction, 24 May 1999, paras. 66-67 (emphasis added). 279 HB/G/119/10570-10584 at pgs. 10578-10579: Report of the Executive Directors on the Convention on the Settlement of Investment Disputes between States and Nationals of Other States, 18 March 1965, para. 25.

Page 76: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

69

dispute within its jurisdiction. In keeping with the purpose of the Convention, the jurisdiction of the Centre is further limited by reference to the nature of the dispute and the parties thereto.

The Tribunal therefore accepts that for this aspect of jurisdictional competence two

requirements must be met. First, that the subject matter of the dispute constitutes an

investment within the meaning of Article 25 of the ICSID Convention. Second, that the Parties

consented to such a dispute being submitted to ICSID and its Arbitration Rules.

With regard to the second part of the test, the Tribunal has little doubt that the parties to the

Implementation Agreement had considered that the activity it was related to (being the

construction and financing of the Facility) was an “investment” at the time it was entered into

as they had expressly agreed to have all disputes arising thereunder to be submitted to ICSID

and under the ICSID Arbitration Rules. The Tribunal is of the view that the second part of the

test is satisfied.

The first part of the test requires a consideration of the elements that constitute an activity

as an “investment” within the meaning of Article 25 of the ICSID Convention.

b. Elements of an “Investment” under Article 25 of the ICSID Convention

(i) Salini Test

The Tribunal notes that the Salini Test has indeed received a mixed following. For example, it

was followed in Bayindir Insaat Turizm Ticaret Ve Sanayi A.S. v Islamic Republic of Pakistan;280

Jan de Nul N.V. and Dredging International N.V. v Arab Republic of Egypt;281 and Ioannis

Kardassopoulos v Republic of Georgia.282

The following tribunals have taken a different approach:

280 HB/G/089/9361-9433 at pgs. 9395-9397: Bayindir Insaat Turizm Ticaret Ve Sanayi A.S. v Islamic Republic of Pakistan, ICSID Case No. ARB/03/29, Decision on Jurisdiction, 14 November 2005, paras. 130-138. 281 HB/G/090/9434-9473 at pgs. 9461-9462: Jan de Nul N.V. and Dredging International N.V. v Arab Republic of Egypt, ICSID Case No. ARB/04/13, Decision on Jurisdiction,16 June 2006, para. 91. 282 HB/G/092/9504-9576 at pg. 9538: Ioannis Kardassopoulos v Republic of Georgia, ICSID Case No. ARB/05/18, Decision on Jurisdiction, 6 July 2007, para. 116.

Page 77: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

70

− In Abaclat and others v Argentina, the tribunal declined to follow the Salini Test and

suggested that it should “[…] not serve to create a limit, which the Convention itself nor the

Contracting Parties to a specific BIT intended to create.”283

− In Biwater Gauff v Tanzania, the tribunal remarked that “These criteria are not fixed or

mandatory as a matter of law. They do not appear in the ICSID Convention […] it is doubtful

that arbitral tribunals sitting in individual cases should impose one such definition […].” 284

− In Philip Morris Brand Sàrl and others v Oriental Republic of Uruguay, the tribunal said,

“These criteria should not play a role in the Tribunal’s analysis of whether an investment

exists, much less to serve as a jurisdictional requirement.”285

− In MNSS B.V. and Recupero Credito Acciaio N.V. v Montenegro (“MNSS B.V. v

Montenegro”), the tribunal more generously suggested that the “[…] elements of the Salini

test need to be considered flexibly and as a whole in the context of the specific facts of an

investment operation.”286

The Tribunal agrees with the observations of the recent ICSID decisions, that the Salini Test

is a reformulation of the criteria set out by the tribunals in Fedax287 and CSOB,288 with the

additional requirement that there should be some economic contribution to the host country.

These Salini factors are not to be taken as prescriptive or dispositive but merely as indicative

of typical elements that the Tribunal could consider in determining whether the subject

matter from which the dispute has arisen is an “investment” contemplated by the ICSID

Convention. This flexible approach is consistent with the objective of ICSID Convention as set

out in the Executive Director’s Report –

283 HB/G/017/1405-1688 at pgs. 1546-1547: Abaclat and Others v Argentine Republic, ICSID Case No. ARB/07/5, Decision on Jurisdiction and Admissibility, 4 August 2011, paras. 364-365. 284 HB/G/335/16325-16574 at pg. 16417: Biwater Gauff v Tanzania, ICSID Case No. ARB/05/22, Award, 24 July 2008, paras. 312-313. 285 HB/G/021/1925-2002 at pgs. 1986-1987: Philip Morris Brand Sàrl (Switzerland), Philip Morris Products S.A. (Switzerland) and Abal Hermanos S.A. (Uruguay) v Oriental Republic of Uruguay, ICSID Case No. ARB/10/7, Decision on Jurisdiction, 2 July 2013, paras. 185-187. 286 HB/G/014/898-1027 at pgs. 962-963: MNSS B.V. and Recupero Credito Acciaio N.V. v Montenegro, ICSID Case No. ARB(AF)/12/8, Award, 4 May 2016, para. 189. 287 HB/G/002/021-033: Fedax N.V. v Republic of Venezuela, ICSID Case No. ARB/96/3, Decision of the Tribunal on Objections to Jurisdiction, 11 July 1997. 288 HB/G/008/441-473: Ceskoslovenska Obchodni Banka, A.S. v Slovak Republic, ICSID Case No. ARB/97/4, Decision of the Tribunal on Objections to Jurisdiction, 24 May 1999.

Page 78: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

71

Nature of Dispute

26. Article 25(1) requires that the dispute must be a “legal dispute arising directly out of an investment.” The expression “legal dispute” has been used to make clear that while conflicts of rights are within the jurisdiction of the Centre, mere conflicts of interests are not. The dispute must concern the existence or scope of a legal right or obligation, or the nature or extent of the reparation to be made for breach of a legal obligation.

27. No attempt was made to define the term “investment” given the essential requirement of consent by the parties, and the mechanism through which Contracting States can make known in advance, if they so desire, the classes of disputes which they would or would not consider submitting to the Centre (Article 25(4)).289

It is the Respondent’s case that the Claimant had not made an investment as contemplated by

Article 25 of the ICSID Convention, alleging that: the Claimant assumed no operational risk,

was involved in a transitory manner, did not make a substantial contribution and its

involvement did not contribute to the economic development of Tanzania. In the

Respondent’s view, the Claimant’s only link to the Facility was its acquisition of a “purported

claim to accounts receivables” long after the Facility was financed and built.290

Before any discussion of whether these elements have been satisfied, it is necessary to recall

the nature of the transaction and the dispute that had arisen.

Nature of the Transaction

Parties’ Submissions

The Claimant contends that the Article 25(1) ICSID Convention “investment” requirement is

met by the following elements:

i. IPTL’s investment in the Facility;

ii. the Claimant’s loan to IPTL to finance the construction of the Facility;

iii. IPTL’s shares, over which the Claimant has exercised its right under the Charge of

Shares to appoint a receiver; and

289 HB/G/119/10570-10584 at pg. 10579: Report of the Executive Directors on the Convention on the Settlement of Investment Disputes between States and Nationals of Other States, 18 March 1965, paras. 26-27 (emphasis in original). 290 HB/A/005/604-827: Respondent’s Rejoinder, para. 203.

Page 79: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

72

iv. the contractual rights under the Implementation Agreement, the PPA and other

agreements assigned by IPTL to its lenders as security for the loan.291

The Claimant submits that it is widely accepted that a loan will constitute an investment when

it contributes or is closely related to an economic venture comprising an investment and

relies on several cases to support this proposition, including Fedax N.V. v Republic of

Venezuela,292 Ceskoslovenska Obchodni Banka, A.S. v Slovak Republic,293 MNSS B.V. v

Montenegro294 and Alpha Projektholding GMBH v Ukraine.295 Further, the Claimant asserts

that in the present case, the loan was essential to the construction of the Facility, as without

the loan, the Facility would not have been built and the Facility was itself a significant project

intended by the Respondent to develop Tanzania’s infrastructure.296

The Claimant also points out that the Respondent admitted in its Memorial in the “BIT

Arbitration” proceedings (viz. Standard Chartered Bank v United Republic of Tanzania, ICSID

Case No. ARB/10/12) that the original loan was an investment in Tanzania for the purposes

of Article 25(1) of the ICSID Convention. Further it submits that the PPA Tribunal also dealt

with the same issue and decided that it was satisfied that there was an investment by virtue

of the Claimant’s purchase of the debt under the loans to IPTL and assigning of the rights

under the relevant agreements.297

The Claimant submits that the fact that the loan was transferred does not change its nature

as an investment in the hands of the new lender and relies on various legal authorities

291 HB/A/001/001-034: Request for Arbitration, paras. 120-122; HB/A/002/35-143: Claimant’s Memorial, paras. 339-343, 360; HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, paras. 17, 298; Claimant’s Reply PHB, para. 76. 292 HB/G/002/021-033: Fedax N.V. v Republic of Venezuela, ICSID Case No. ARB/96/3, Decision of the Tribunal on Objections to Jurisdiction, 11 July 1997. 293 HB/G/008/441-473: Ceskoslovenska Obchodni Banka, A.S. v Slovak Republic, ICSID Case No. ARB/97/4, Decision of the Tribunal on Objections to Jurisdiction, 24 May 1999. 294 HB/G/014/898-1027: MNSS B.V. and Recupero Credito Acciaio N.V. v Montenegro, ICSID Case No. ARB(AF)/12/8, Award, 4 May 2016. 295 HB/G/016/1222-1404: Alpha Projektholding GmbH v Ukraine, ICSID Case No. ARB/07/16, Award, 8 November 2010. 296 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, paras. 374-375. 297 HB/A/002/035-143: Claimant’s Memorial, paras. 374-378.

Page 80: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

73

including Fedax v Venezuela,298 MNSS v Montenegro299 and Abaclat v Argentina300 to support

this contention.301

In its Reply, the Claimant refers to the decision in African Holding v DRC302 to say that an

assignment does not change the nature of the original investment and that once an

investment has been acquired there is no further investment needed to be made to retain its

nature. The Claimant submits that the assignment of a loan is an assignment of economic

value of the work done and not paid, and the status of a loan as an investment is constant.303

It disagrees with the Respondent’s suggestion that a mere transfer of a lender would deprive

it of its status as an investment, despite the expressed provision in the Implementation

Agreement recognising such transfer or assignment.304

The Respondent counters that the essence of the Claimant’s claim is a claim for the repayment

of the debt owed by IPTL, which the Claimant has dressed up as a frivolous discrimination

and expropriation claim under the Implementation Agreement. Such a claim does not arise

out of the Facility as investment because ultimately it is based on the Loan Facility Agreement

between IPTL and the consortium of Malaysian banks which was acquired by the Claimant.

Thus, it submits that the link to the Facility is too remote and irrelevant and could not clothe

the Claimant as having been exposed to the risks attendant to the Facility.305

Further, the Respondent submits that the form and nature of the Claimant’s activity does not

constitute an investment under Article 25(1) of the ICSID Convention. The Respondent

contends that, in a memorandum of July 1996,306 Mr Patrick Rutabanzibwa (as Commissioner

for Energy and Petroleum Affairs) wrote that the Facility itself did not contribute to the

298 HB/G/002/021-033: Fedax N.V. v Republic of Venezuela, ICSID Case No. ARB/96/3, Decision of the Tribunal on Objections to Jurisdiction, 11 July 1997. 299 HB/G/014/898-1027: MNSS B.V. and Recupero Credito Acciaio N.V. v Montenegro, ICSID Case No. ARB(AF)/12/8, Award, 4 May 2016. 300 HB/G/017/1405-1688: Abaclat and Others v Argentine Republic, ICSID Case No. ARB/07/5, Decision on Jurisdiction and Admissibility, 4 August 2011. 301 HB/A/002/035-143: Claimant’s Memorial, paras. 381-385. 302 HB/G/013/852-897: African Holding Company of America, Inc. and Société Africaine de Construction au Congo S.A.R.L. v Democratic Republic of the Congo, ICSID Case No. ARB/05/21, Decision on Jurisdiction and Admissibility, 29 July 2008. 303 HB/A/004/371-603: Claimant’s Reply, paras. 424-433; HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, para. 378. 304 HB/A/006/828-939: Claimant’s Rejoinder on Jurisdiction, para. 382. 305 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 214; HB/A/005/604-827: Respondent’s Rejoinder, paras. 212-217. 306 HB/H/011/027-267: Memorandum on the IPTL Power Project by Patrick Rutabanzibwa,1 July 1996.

Page 81: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

74

economic development of Tanzania and it also argues that what was needed in Tanzania at

the time the Facility was contracted for, financed and built, was an emergency power project

and not an onerous medium-term project.307

The Respondent argues that: first, the cases referred to by the Claimant in paragraph 204

above are not related to Article 25(1) ICSID Convention, but to the definition of “investment”

in the relevant bilateral investment treaty applicable in each case; and second, that the cases

relied upon by the Claimant recognize that a loan in itself is not an investment under the ICSID

Convention if it is not linked to a process of value creation, or if it does not contribute

substantially to the development of the host State. According to the Respondent, the

Claimant’s purported acquisition of Term Loans 1 and 2 is not a loan that would constitute

an “investment”, because it is not linked to a process of value creation as it is purely a

commercial operation not different to those made by financial institutions.308

The Respondent says that any alleged admission or statement that was made in the BIT

Arbitration was in the context of analysis concerning the bilateral investment treaty between

Tanzania and the United Kingdom, and therefore it is not relevant to the present case.309

Further, the Respondent submits that the PPA Tribunal did not engage in analysis of the

specific characteristics of an investment and therefore is not useful for the present case.310

The Respondent contends that all the cases cited by the Claimant are inapposite to the facts

of the present case.311 Further the Respondent asserts that the Claimant relies upon the

expansive definitions of investment following the approach of Fedax v Venezuela, which has

since been criticised by other tribunals and commentators.312

Tribunal’s Analysis

As a starting point, the Tribunal takes the view that the construction and operation of an

infrastructure project,313 such as the Facility in Tanzania, is an investment, notwithstanding

307 HB/A/005/604-827: Respondent’s Rejoinder, para. 214. 308 HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 225-226. 309 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 232. 310HB/A/003/144-370: Respondent’s Counter-Memorial, para. 233. 311 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 234. 312 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 228. 313 The Respondent’s reference to Mihaly v Sri Lanka to suggest that even in a power plant project may not always be an “investment” is inappropriate. In that case, the parties were merely in the negotiation stages and no agreement was eventually entered into. HB/G/094/9597-9615: Mihaly International Corporation v Democratic Socialist Republic of Sri Lanka, ICSID Case No. ARB/00/2, Award, 15 March 2002.

Page 82: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

75

that a senior member of the Tanzanian Government thought at one stage that the Facility did

not contribute to the economic development of Tanzania. The provision of electricity from

the Facility in the face of power shortages qualifies as an investment. Whether, in hindsight,

that investment was optimal or could have been structured differently cannot alter its

qualification as an investment.

The main thrust of the Respondent’s arguments lies on the fact that:

i. the Claimant was not the original Lender under the Financing Documents and the

Implementation Agreement;

ii. the purchase of the Loan by the Claimant was not an investment; and therefore

iii. the assignment of any security created, including the rights under the

Implementation Agreement could not be pursued by an ICSID arbitration.

The most critical issue that requires consideration is whether the purchase of the Loan by the

Claimant in the circumstances of the case is in the nature of an “investment.” This then

requires an examination of whether there exists in this transaction, the various elements of

risk, substantial contribution, minimum duration and arguably, economic development of

Tanzania.

Risk

Parties’ Submissions

The Respondent suggests that the Claimant had assumed no “operational risk”314 for when

they took over the Loans, the Facility was already constructed and operating. In the

Respondent’s view, any risks attendant on the Loans were borne by the original lenders, as

they were then exposed to the uncertainty as to whether the Facility would be completed

before any income stream could flow. What the Claimant had assumed, according to the

Respondent, was merely a “commercial risk” which exists in any transaction, and which in

this case would be further ameliorated by the security which it enjoyed over the Facility and

revenues of IPTL, giving the Claimant an ascertainable return. In its view, the Claimant’s best

outcome in taking over the loan “did not go beyond the prospect of receiving an economic

314 HB/A/005/604-827: Respondent’s Rejoinder, para. 224.

Page 83: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

76

return through the repayment of the money loaned with interest”315 and was nothing more

than an exchange, with no value creation for the Facility.316

The Claimant, on the other hand, argues that under the PPA, TANESCO agreed to pay IPTL the

tariff stipulated in the PPA. It was envisaged that the loan would be repaid from the cash flows

generated by IPTL under the PPA. The economic success of the Project was dependent upon

IPTL receiving regular payments from TANESCO, and the support and non-interference of the

Respondent. The Claimant therefore assumed not just the risk of non-payment of the debt,

but also the risk of the success or failure of the Facility.317

Tribunal’s Analysis

The concept of “commercial risk” has been distinguished from “investment risk” by the

tribunal in Romak v Uzbekistan318 in the following way –

229. All economic activity entails a certain degree of risk. As such, all contracts – including contracts that do not constitute an investment – carry the risk of non-performance. However, this kind of risk is pure commercial, counterparty risk, or, otherwise stated, the risk of doing business generally. It is therefore not an element that is useful for the purpose of distinguishing between an investment and a commercial transaction.

230. An “investment risk” entails a different kind of alea, a situation in which the investor cannot be sure of a return on his investment, and may not know the amount he will end up spending, even if all relevant counterparties discharge their contractual obligations. Where there is “risk” of this sort, the investor simply cannot predict the outcome of the transaction.

These remarks were adopted by an ICSID tribunal in Poštová Banka v Greece319 which re-

stated the term “investment risk” as “operational risk” and added that such is “not a

315 HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 226-227. 316 HB/A/005/604-827: Respondent’s Rejoinder, para. 224; HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 226-227. 317 HB/A/004/371-603 at pgs. 510-511: Claimant’s Reply, para. 411. 318 HB/G/095/9616-9680: Romak S.A. (Switzerland) v Republic of Uzbekistan, PCA Case No. AA280, Award, 26 November 2009, paras. 229-230 (emphasis added). 319 HB/G/058/6120-6237: Poštová Banka a.s. and ISTROKAPITAL SE v Hellenic Republic, ICSID Case No. ARB/13/8, Award, 9 April 2015, paras. 367-370.

Page 84: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

77

commercial risk or a sovereign risk”320 and expressed the view that its distinction is that an

“operational risk” means that “profits are not ascertained but depend on the success or failure

of the economic venture concerned […].”321 In that case, the tribunal had found that the “Greek

Government Bonds” were issued for economically unproductive activity viz. for financing

government operations, to meet general budgetary purposes and repaying government debts

and no “operational risk” was present.

The Tribunal accepts that loans and financial instruments standing alone without any link to

some economic venture intended to provide for the improvement of the State’s development

would not be considered an “investment.” It follows that an assignment of loans merely as an

income stream unconnected to any investment is not an “investment” in international

investment law.322

Arbitral tribunals have on several occasions held that loans and financial facilities (whether

in the form of direct loans, bonds or notes) issued by or undertaken in the context of financing

an investment would qualify as investments under Article 25 of the ICSID Convention.323

There is no doubt in the Tribunal’s mind that there were clearly investment risks when the

original Lenders extended the Loan to IPTL to finance the construction and operation of the

Facility and that they had accepted those risks. What the Respondent contends is that the

Claimant not being the original Lender, is not in a position to say that it carried any risk akin

to that of the original Lenders.

On first principles, the Respondent’s suggestion ignores the fact that the Claimant has staked

its claim as the assignee of the Loan and the lawful assignee under the Implementation

Agreement (which the Tribunal has found in its favour – see paragraph 172 above). As

assignee, the Claimant stepped into the shoes of the original Lenders. And as assignee the

320 HB/G/058/6120-6237: Poštová Banka a.s. and ISTROKAPITAL SE v Hellenic Republic, ICSID Case No. ARB/13/8, Award, 9 April 2015, para. 369. 321 HB/G/058/6120-6237: Poštová Banka a.s. and ISTROKAPITAL SE v Hellenic Republic, ICSID Case No. ARB/13/8, Award, 9 April 2015, para. 370. 322 HB/G/082/8364-8452: Alps Finance and Trade AG v Slovak Republic, UNCITRAL, Award, 5 March 2011, paras 242-243. 323 See: HB/G/002/021-033: Fedax N.V. v Republic of Venezuela, ICSID Case No. ARB/96/3, Decision of the Tribunal on Objections to Jurisdiction (case of promissory notes), 11 July 1997; HB/G/008/441-473: Ceskoslovenska Obchodni Banka, A.S. v Slovak Republic, ICSID Case No. ARB/97/4, Decision of the Tribunal on Objections to Jurisdiction, 24 May 1999 (a case on assignment of non-performing loans); HB/G/014/898-1027: MNSS B.V. and Recupero Credito Acciaio N.V. v Montenegro, ICSID Case No. ARB(AF)/12/8, Award, 4 May 2016 (a case of the acquisition of shares and loans in the entities that had undertaken to extend loans).

Page 85: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

78

Claimant became entitled to the rights of the original lenders, it also assumed the risks of the

original Lenders. Much like the assignment of the loan in MNSS B.V. v Montenegro,324 the

assignment of the loan changed the creditor under the Loan Agreement and the beneficiary

under the Implementation Agreement but not the nature of the transaction. The substance of

the Facility remains the same. The link between the Loan and the Implementation Agreement

to the Facility and its continuing operations has not been broken. The risks undertaken by

the original Lenders are now borne by the Claimant because the original Lender could not or

would not be in a position to do so. Although the construction of the Facility was completed,

the Claimant carries the continuing risks of the operation. There was no certainty that the

Facility would run smoothly, or that the power generated would yield the projected revenue

that could repay the outstanding loans. The risk of TANESCO not paying the tariffs and IPTL

not being able to make the Power Plant available; and the political risk of interference by the

Respondent with the Project, are not “ordinary commercial risk.” These risks subsequent to

the assignment were clearly borne by the Claimant.

The Tribunal recognises that it is possible that the right of investment protection could be

abused by a speculative debt hunter. An illustration of such an abuse can be seen in Phoenix

Action Ltd v Czech Republic325 where the claimant purchased two insolvent companies that

were embroiled in litigation not for any economic activity but for the sole purpose of bringing

international litigation against the Czech Republic. The tribunal rightly declined jurisdiction

as it found that “the whole ‘investment’ was an artificial transaction to gain access to ICSID.”326

The Tribunal does not accept the Respondent’s characterisation of the Claimant. The

Claimant acquired the Loans from the original Malaysian banks following a re-structuring

initiated by the Malaysian banking authority. The Claimant was the sole bidder willing to take

over the Term Loan 1 (USD 92.547 million)327 and Term Loan 2 (8.236 million)328 and paid

324 HB/G/014/898-1027: MNSS B.V. and Recupero Credito Acciaio N.V. v Montenegro, ICSID Case No. ARB(AF)/12/8, Award, 4 May 2016. 325 HB/G/057/6058-6119: Phoenix v Czech Republic, ICSID Case No. ARB/06/5, Award, 15 April 2009. 326 HB/G/057/6058-6119 at pg. 6115: Phoenix v Czech Republic, ICSID Case No. ARB/06/5, Award, 15 April 2009, para. 143. 327 HB/C/013/535-551 at pg. 548: Sale and Purchase Agreement for Loan Account – IPTL between Danaharta Managers and SCB, 4 August 2005. 328 HB/C/013/535-551 at pg. 548: Sale and Purchase Agreement for Loan Account – IPTL between Danaharta Managers and SCB, 4 August 2005.

Page 86: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

79

USD 76.1 million329 on terms that it provided no recourse against the original Lender or the

vendor. The fact that the Claimant had paid less than the principal outstanding due is in itself

no basis to suggest that it was a “no risk” venture. The original loans were in fact re-structured

in the hands of Danaharta to give the borrower more time to make repayment and a forgiving

of part of the accrued interest, as well enabling the repayment of the outstanding due by IPTL

to the Engineering Procurement and Construction (“EPC”) contractor, Wartsila NSD

Nederland B.V.330

The Respondent’s suggestion that the Claimant’s expectation of receiving an economic return

through the repayment of the money loaned with interest is indicative that it is a normal

commercial transaction with usual commercial risks and nothing more, fails to account for

the risks assumed in granting, maintaining and restructuring the loans in relation to the

establishment and maintenance of the Facility.

The fact that the sale assets were described by the purchaser as “distressed” in fact indicates

that the Claimant would be exposed to a higher risk than the original Lender. With no

recourse to the original Lender,331 the Claimant assumed all the attendant risks and

obligations from the original Lender associated with the Facility as spelt out in the Sale and

Purchase Agreement thus:

5. Assumption of Obligations To the extent that the Vendor shall have obligations remaining to be performed under the Asset Documentation after the Closing Date as disclosed in writing by the Vendor or as contained and disclosed in the Accounts Information relating to the Sale Asset and/or to the extent there are any claims against and/or liabilities on the part of the Vendor in respect of or in connection with the Sale Assets on or after the Closing Date, the Purchaser hereby agrees to perform all such obligations and will indemnify the Vendor and each of their officers, directors, employees and advisors ("a Vendor Party") and hold each of them harmless from and against any liability to or claim of liability by any third party on account of the failure of such obligations to be performed.332

329 The amount paid by the Claimant for was close to the asset valuation made by Danaharta’s financial advisors of USD 77.4 million. See HB/H/059/ 851-866 at pgs. 862-863: CIMB Ltd Credit Report, 30 August 2004; HB/C/013/535-551 at pg. 550: Sale and Purchase Agreement for Loan Account – IPTL between Danaharta Managers and SCB, 4 August 2005. 330 HB/H/032/621-628: Loan Management Paper for Approval; Ref: DMLL/LM/J3/2001/268, 11 October 2001. 331 HB/C/013/535-551 at pg. 542: Sale and Purchase Agreement for Loan Account – IPTL between Danaharta Managers and SCB, 4 August 2005, Clause 10. 332 HB/C/013/535-551 at pg. 539: Sale and Purchase Agreement for Loan Account – IPTL between Danaharta Managers and SCB, 4 August 2005, Clause 5 (emphasis in original).

Page 87: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

80

Unlike the claimant in Phoenix Action Ltd v Czech Republic, who did nothing other than initiate

ICSID arbitration shortly after it made the “investment”, the Claimant here was obliged and

was fully engaged in undertaking the obligations as the Lender to IPTL by honouring its

obligations to IPTL and the Facility. IPTL continued to make principal and interest

repayments until April 2007 when it went into default.333 During that same period, GoT

engaged the Claimant through its Tanzanian branch officers for the possibility of GoT taking

over the loans from the Claimant334 and a “pretrade agreement” was said to have been signed

off with GoT.335

In doing so, the Claimant carried the burden of the original Lender and it would be incorrect

to term it as speculative debt. The original loans were required to build and maintain the

Facility. The Facility provided a necessary public good. These loans entailed risk. That risk

was borne by the original Lender and assumed by the Claimant. That suffices to establish that

the Claimant’s acquisition of the loans qualifies as an investment.

The Tribunal is therefore satisfied that the Claimant was fully exposed to the investment risk

inherent in this transaction.

Substantial Contribution

The Respondent says that there is no substantial contribution element as that requires

contribution of technical know-how, equipment and services, which are absent in the present

case.336

The Tribunal notes that the Claimant’s involvement in taking over the loans from Danaharta

was made known to GoT more than one year before it occurred. In his report to the PS MEM

reported that he was approached by SCB HK and informed of the Malaysian Government’s

intention to close Danaharta’s operations and to find a taker for the loan accounts of IPTL. He

reported that he had agreed to give support for such a move by SCB HK in exchange for a

reduction in IPTL’s capacity charge following the re-financing. SCB HK then subsequently

reported that a USD 200,000 per month reduction would be possible for a few years.

According to the report, GoT intended to approach the Malaysian Government for assistance.

333 HB/H/488/7196-7215: SCB HK Loan Calculations. 334 HB/H/065/884: Email from Hemen Shah of SCB Tanzania to Andrew Hardacre of SCB HK and others, 17 August 2005; HB/H/067/886: Email from Hemen Shah of SCB Tanzania to Paul Jurie of SCB HK and others, 23 August 2005. 335 HB/H/069/889: Email from Paul Jurie of SCB HK to Sherazam Mazari of SCB UK and others, 17 October 2005. 336 Respondent’s PHB, para. 81.

Page 88: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

81

GoT itself was also looking at ways to take over the Facility and had broached the possibility

of funding from the World Bank:

20. During the negotiations for the Emergency Power Supply Project which were held with the World Bank in April-May, 2004, the Tanzania delegation to those negotiations formally requested the World Bank's assistance in buying out or otherwise dealing with IPTL's lenders and shareholders so that the burden of the project's capacity charges can be reduced. The World Bank ruled out the possibility of providing funds with which the Government could purchase the IPTL plant, but undertook to look into whether it could identify risk mitigation arrangements and funding sources which could help address the problem. The World Bank undertook to discuss with its affiliates MIGA and IFC to this end, and revert to the Government.337

The report recommended that GoT support SCB’s bid to take over the Loan –

19. Standard Bank has suggested that the Government allows the re-financing of IPTL’s debt to proceed as a first step. After a few years, when (i) TANESCO’s ability to pay both IPTL and Songas has been demonstrated and (ii) the IPTL shareholders’ respective rights have been confirmed by the courts, perceived risks about IPTL will diminish and it may be possible to do another re-financing as a second step which would result in a more significant reduction in the capacity charge. It is evident that the perceived risks currently surrounding IPTL are a hindrance to negotiating a meaningful reduction in the capacity charge.

[…]

26. […] (ii) The Ministry should respond positively to Standard Bank's proposals for re-financing IPTL in two phases (as described in paragraph 19 above) but (a) seek more time to contact the Malaysian government and (b) require the re-financing arrangements to anticipate a second phase which may involve the purchase of the IPTL plant and the possible participation of other financiers including the World Bank or its affiliates.338

There is no doubt that GoT viewed SCB HK’s involvement as positive and necessary. There

was need for more power generation. GoT wanted a reduction in the capacity charge, but at

a reduced cost and IPTL was under-capitalised. GoT had hoped to take control of the Facility

or for someone to take over the role of the Lenders. While it is true that the money paid by

337 HB/H/055/835-844 at pg. 840: Brief on IPTL issues from Patrick Rutabanzibwa to Minister of Energy, 6 July 2004, para. 20. 338 HB/H/055/835-844 at pgs. 840, 842: Brief on IPTL issues from Patrick Rutabanzibwa to Minister of Energy, 6 July 2004, paras. 19, 26.

Page 89: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

82

SCB HK did not go directly into the Facility, but to Danaharta, SCB HK’s involvement brought

stability and enabled the Facility to continue operating. All this occurred at a time when

TANESCO had disputes with IPTL, had delayed, withheld or threatened to withhold payment

to IPTL, thereby triggering possible default.339 Danaharta could have recalled the loan or

refused to re-structure the same. GoT saw the need for SCB HK to take over the loan to enable

it to gain time to consider other possible options including funding from the World Bank to

take over thereafter.

Unlike the case of Phoenix Action Ltd v Czech Republic, the Claimant here had paid a

discounted but nevertheless substantial sum (USD 76 million) to take over the loans from

Danaharta. By doing so, IPTL did not need to seek alternative funding and could continue to

operate the Facility. In the Tribunal’s view, these facts indicate that the Claimant made a

substantial contribution to the Project and to the Respondent.

Minimum Duration

The Tribunal notes that the Claimant had taken over a commitment to maintain the Loans for

a period of up to 10 years. The Facility was intended to be operational for more than 20 years.

Such duration is not short by any measure. The Respondent argues however that the Claimant

“could have sold its debt through a financial transaction” and that the Claimant had admitted

through its witness Mr Casson that it had attempted to do so, albeit unsuccessfully. The

Respondent submits that the Claimant’s commitment fails the “non-transitory commitment”

to the host State.

The Tribunal finds such a criticism quite misplaced. The nature of the Project and the long-

term financing arrangement speak for themselves. Mr Casson indeed said that he was in

discussion with Mr Sethi and had signed a Memorandum of Agreement on 25 November 2011

for an exit from the loan for a discounted sum of USD 75 million (when the amount

outstanding then was USD 128 million). It was however clear from his witness statement340

and oral testimony341 that Mr Casson had decided to exit when he felt frustrated by the

discriminatory treatment meted out to SCB HK rather than executing what SCB HK had

always planned to do so. In his report seeking approval for this arrangement, he stated:

339 HB/H/056/845-846: Letter from Minister of Energy and Minerals to TANESCO, 8 July 2004. 340 HB/F/004/052-125 at pgs. 91-93: Witness Statement of Joseph Wesley Casson, 15 November 2017, (“Casson WS”), paras. 156-162. 341 Tr. Day 4 [820:12-823:11].

Page 90: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

83

From the negotiation with Sethi, SCB has signed a Memorandum of Agreement (MOA) on 24 November, on a non-binding basis and subject to credit approval to pencil down a proposal for a one-off payment of US$75m for the Bank to exit the loan […]. SCB will then withdraw international arbitrations against GOT and TANESCO. The Bank has been advised the MOA has shown to GOT and the Attorney General by Sethi to request time for finalizing settlement, instead of liquidating IPTL.

[…]

Regarding to settlement risk, it is uncertain to access the availability of the escrow amount of US$85m, otherwise, how GOT secure sufficient funding for settlement. Local contacts advise TANESCO may inject more to top up escrow funds for a global settlement.342

Quite clearly this was an attempt to resolve the disputes with the other parties globally so

that the Claimant could get out of the difficulties they found themselves in over the years

(from 2005 to 2011), and not an indication that the Claimant had only intended a transitory

holding of the loan portfolio.

The Tribunal is satisfied that the Claimant’s commitment was non-transitory.

Contribution to the Economic Development of Host State

This factor is one of the more controversial of the elements suggested by the Salini tribunal.

As expressed earlier, the Tribunal shares the view articulated by tribunals in recent cases that

this element is not a strict requirement but will nevertheless consider this feature as

presented by the Respondent.

Contribution to the host State’s economic development is of course the desired outcome of

any foreign investment and the basis for the promotion of foreign investment underlying of

the ICSID Convention. As one author reasoned –

Hence, investments not devoted to productive purposes, such as those undertaken for speculative purposes and those that do not develop the productive resources of the host State without positive impact on the productivity or increase the standards of living or labor conditions, could be considered to be beyond the outer limits of ICSID.343

342 HB/H/203/2622-2624 at pg. 2623: Memorandum from Joe Casson to Joe Stevens, Ivo Philipps and Jake Williams entitled "Divestment of Senior Loan to Independent Power Tanzania Limited (IPTL) Approval Request", 29 November 2011. 343 HB/G/122/10647-10672 at pg. 10658: Omar E. García-Bolívar, Protected Investments and Protected Investors: The Outer Limits of ICSID’s Reach, 2(1) TRADE LAW & DEVELOPMENT 145 (2010).

Page 91: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

84

The Respondent submits that what is required to be shown is not whether the Facility or the

original loan that funded the facility contributed to the economic development of the host

State, but rather whether the Claimant’s purported acquisition of the Term Loans 1 and 2

made such contribution and added to Tanzania’s economic development.

The Respondent sets out the circumstances under which the Claimant made the acquisition

from Danaharta, a Malaysian Government owned asset management company created to

remove non-performing loans. It contends that the purchase provided no benefit to the

Respondent State. Rather it was a simple commercial transaction with only the recovery of

money in mind. The Respondent points out that there was not a single drawdown by IPTL

after the Claimant became the sole lender to underscore the point that SCB HK brought with

it no economic benefit to Tanzania.344

The Respondent has repeatedly described the Claimant as “nothing more than a speculative

and bad faith endeavour which did not contribute to the economic development of

Tanzania[…].”345 It submits that had SCB HK not bought the loans from Danaharta it “would

not have entailed a disruption of the Facility” as at the time of acquiring the loan the Facility

“had already been financed and built and was already operating”,346 it therefore reasoned

that the Claimant did not “primarily and directly” contribute to the economic development of

Tanzania.347 The Respondent has also pleaded that the Claimant’s acquisition of the loan

outside Tanzania was evidence of the speculative nature of the Claimant’s activities.348

As stated earlier, the Tribunal notes that the original loans were re-structured when IPTL had

difficulty meeting repayments, due to TANESCO’s challenging the calculation of the capacity

charges and in delaying or withholding making such payments to IPTL. The acquisition of the

loan by SCB HK from Danaharta assured IPTL, TANESCO and GoT of the continuing

availability of financial support for the operation of the Facility. The support of GoT for SCB

HK’s taking over of the loans from Danaharta is in the Tribunal’s view the acceptance by GoT

that SCB HK’s involvement would contribute to the economic development of Tanzania. SCB

344 HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 25, 139, 206. 345 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 9(ii). 346 Respondent’s PHB, para. 83; In its submission, the Respondent attributed this suggestion to a member of the Tribunal in Tr. Day 4 [839-840]. A reading of the portion of the transcript referred to (Tr. Day 4 [839:6-840:10]), shows this to be incorrect. No member of the Tribunal made any such suggestion. 347 Respondent’s PHB, para. 83. 348 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 237.

Page 92: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

85

HK’s support in taking over and maintaining the availability of the loans was even more

critical when GoT realized that its hope of World Bank funding was not forthcoming.

The Tribunal is satisfied that far from being a speculative transaction, SCB HK stepped in

when no others would. If the element of contribution to economic development is required

to be shown, the Claimant has satisfied the same.

c. Alternative Arbitral Forum in the Implementation Agreement

(i) Parties’ Submissions

The Respondent in its Counter-Memorial adds to its challenge that the presence of the ICC

arbitration clause in Article 21.2 of the Implementation Agreement reinforces the notion that

the Tribunal does not have jurisdiction under the ICSID Convention in this case.349

Article 21.2 of the Implementation Agreement provides after the reference to ICSID

arbitration that –

… If for any reason the Dispute cannot be settled in accordance with the ICSID Rules, whether if the GOT fails to implement the Convention, or if the Company should not be agreed to be a foreign controlled entity, or if the request for arbitration proceedings is not registered by the Centre, or if the Centre fails or refuses to take jurisdiction over such Dispute, or otherwise, any Dispute shall be finally settled by arbitration under the Rules of Arbitration of the International Chamber of Commerce (the "ICC Rules") by one or more arbitrators appointed in accordance with the ICC Rules.

The Respondent submits that the provision of such an alternative arbitral forum was included

because the Parties had doubts as to whether their transaction would qualify as an

investment, especially in view of the possibility that the rights could be assigned, upon

approval of the Respondent, to other entities.350 The Claimant responds that there is a

hierarchy established in Article 21.2 of the Implementation Agreement between the “ICSID

arbitration clause and the ICC arbitration clause” wherein the former applies to any dispute

349 HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 242-245. 350 HB/A/005/604-827: Respondent’s Rejoinder, paras. 231-232; Respondent’s PHB, para. 82; HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 243-244 - The Respondent cited a passage from HB/G/118/10560-10569 at pg. 10569: Christoph H. Schreuer, Loretta Malintoppi, August Reinisch and Anthony Sinclair, THE ICSID CONVENTION: A COMMENTARY (2nd ed., Cambridge University Press 2009) (excerpts).

Page 93: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

86

or difference between the Parties and the latter is “subsidiary” and applicable only when for

any reason the Dispute cannot be settled by ICSID Rules.351

(ii) Tribunal’s Analysis

The Tribunal agrees that parties have made this proviso in anticipation that certain disputes

may not fall within the general jurisdiction of ICSID and, if that should happen, those should

then be referred to ICC arbitration. The text of the proviso sets out the various scenarios

contemplated by the parties namely, viz. Tanzania fails to implement the ICSID Convention,

or if IPTL is not a foreign-controlled entity, or if ICSID fails to register the dispute or a tribunal

refuses to take jurisdiction. There is, however, no room to infer by reverse reasoning that the

parties have by making such a proviso accepted or anticipated that an assignment of rights

would trigger a reference to the alternative arbitral forum. The Tribunal’s reading is simple,

the proviso is an expression of the parties’ intention to have their disputes referred to

institutional arbitration and not to a national court such that if for any reason this Tribunal

declined jurisdiction, the Claimant would be at liberty to seek relief from the alternative

forum. The proviso in Article 21.2 of the Implementation Agreement does not therefore add

support the Respondent’s argument in any manner.

(3) Tribunal’s Decision on Jurisdiction under Article 25 of the ICSID Convention

Following the Tribunal’s consideration of the various elements of the Claimant’s undertaking,

including maintaining the loans for the benefit of IPTL and the Facility, the Tribunal finds that

this is a legal dispute arising out of an investment and that it has jurisdiction under Article 25

of the ICSID Convention. Neither the Project, nor its individual elements, ceased to be an

investment merely because the identity of the Lender under the Facility Agreement has

changed or that no further drawdown of funds were made following the transfer. The fact is

that the Facility continued to enjoy the use of the funds earlier disbursed following the change

of the Lender. The Tribunal is also satisfied that the Claimant is the rightful party to maintain

such claim as an absolute assignee who is entitled to enforce the rights thereunder in its own

name. Being a Chinese entity, it is indisputably a “National of another Contracting State.”

In these circumstances, the Tribunal therefore holds that the ratione personae and ratione

materiae jurisdiction elements under Article 25 of the Convention are fully satisfied.

351 HB/A/004/371-603: Claimant’s Reply, paras. 402-403.

Page 94: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

87

VI. LIABILITY

A. EXPROPRIATION CLAIM UNDER ARTICLE 16 OF THE IMPLEMENTATION AGREEMENT

The Claimant’s claim for expropriation hinges on the undertaking given by GoT in Article 16

of the Implementation Agreement.

Under Article 16.1 of the Implementation Agreement, GoT is expressly prohibited from

certain specific actions, namely:

16.1 Assurance Against Discriminatory Action

The GOT shall not take any discriminatory action which materially and adversely affects the Project or the performance of the Company's obligations or the enjoyment of its rights or the interests of the Investors under the Security Package or expropriate or, except as hereinafter provided, acquire the Facility or the Company, whether in whole or in part. Nothing in the foregoing shall apply to any actions taken by the GOT, TANESCO, or any Governmental Authority pursuant to their respective rights and obligations arising under this Agreement, the Power Purchase Agreement and the other documents comprising the Security Package.352

Under Article 16.2 of the Implementation Agreement, GoT undertook not to expropriate or

nationalise the assets of the IPTL:

16.2 Acquisition of Shares or Assets

Subject to Article 20. 1, the GOT undertakes to the Company that neither it nor TANESCO or any Governmental Authority will expropriate, compulsorily acquire, nationalise, or otherwise compulsorily procure any Ordinary Share Capital or assets of the Company […].353

(1) Scope of Expropriation Under Article 16.2 of the Implementation Agreement

a. Parties’ Submissions

The Claimant submits that the term “expropriate” in Article 16.2 of the Implementation

Agreement should be given the meaning as understood under international investment law.

According to the Claimant, the term must be read in the context of the factual background,

including that: (i) the Implementation Agreement was part of a suite of agreements entered

352 HB/C/005/192-267 at pg. 219: Unsigned copy of Implementation Agreement (including Schedules), 8 June 1995, para 16.1(emphasis added). 353 HB/C/005/192-267 at pg. 219: Unsigned copy of Implementation Agreement (including Schedules), 8 June 1995, para 16.2 (emphasis added).

Page 95: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

88

into to support a significant foreign investment in Tanzanian infrastructure; (ii) the purpose

of the Implementation Agreement was to provide investment protection to IPTL and its debt

and equity investors; (iii) the language of Article 16.2 of the Implementation Agreement is

broad and there is no definition of “expropriation”, albeit there is a prohibition of the same by

any “Governmental Authority”, which is defined by Article 1.1. of the PPA, and could include

executive, legislative, administrative or judicial acts; and (iv) as there is an ICSID arbitration

clause, there was an intent that the term “expropriate” would have the meaning attributed to

it by ICSID tribunals.354

The Claimant similarly submits that the Parties’ agreement on the meaning of “expropriate”

under the Implementation Agreement is not prohibited by Tanzanian Law, and expropriation

can have a meaning independent of the statutory protection in Section 22 of The Tanzanian

Investment Act, 1997. Furthermore, according to the Claimant, claims for indirect, creeping

expropriation and measures tantamount to expropriation are contemplated by The

Tanzanian Investment Act, 1997 and the National Investment (Promotion and Protection) Act,

1990, as they reference investment treaties, which commonly encompass such broad notions

of expropriation.355 Moreover, the Claimant underscores that it is not bringing a claim under

domestic legislation, so the only matter that the Tribunal needs to determine is the meaning

of “expropriation” under the Implementation Agreement.356

The Claimant submits, in the alternative, that even if Article 16.2 is construed to give the term

“expropriate” a narrow meaning, the Tribunal should nonetheless consider international

investment law protections against expropriation, which the Claimant contends cannot be

disregarded.357 As support for this premise, the Claimant cites Caratube v Kazakhstan, for

example, where the tribunal concluded that protections under international investment law

could not be ignored even when parties have chosen domestic law to apply.358

354 HB/A/004/371-603: Claimant’s Reply, paras. 537-539; Claimant’s PHB, para. 119. 355 Claimant’s PHB, paras. 123-126. 356 Claimant’s PHB, para. 127. 357 HB/A/004/371-603: Claimant’s Reply, paras. 544-545. 358 HB/A/004/371-603: Claimant’s Reply, paras. 546-547.

Page 96: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

89

With respect to the elements of expropriation, citing prior ICSID cases,359 the Claimant

submits that expropriation does not require a benefit to accrue to the State.360 Moreover, the

Claimant contends that judicial acts may constitute expropriation. The Claimant submits that

Article 16.2 of the Implementation Agreement anticipates expropriation through judicial acts

as it explicitly prohibits expropriation by any “Government Authority”, which, according to

Article 1.1 of the PPA, includes any “court, judicial or administrative body.”361

In the Claimant’s view, the test for judicial expropriation is the same as any other form of

expropriation: expropriation occurs when the act complained of results in a substantial

deprivation of a property right or benefit of a property right.362 The Claimant underscores

that the expropriation standard is distinct from a denial of justice and that there is

consequently no requirement for judicial acts to be “tainted by a denial of justice.”363 Similarly,

the Claimant contends that there is no requirement to exhaust local remedies before pursuing

a claim for expropriation by the judiciary.364

With regard to the Respondent’s argument that the Claimant did not possess property rights

that could be subject to expropriation, the Claimant explains that the Implementation

Agreement is different from a bilateral investment treaty and that its claims are not for any

property rights which it or Mechmar holds. Rather the Claimant is claiming a breach of the

contractual undertaking not to expropriate the Ordinary Share Capital and assets of IPTL as

listed in Article 16.2 of the Implementation Agreement.365

GoT submits that Article 16.2 of the Implementation Agreement is subject to Tanzanian law,

and it must therefore be interpreted and construed in accordance with Tanzanian law.366

Under the Law of Tanzania, the concept of “expropriation” is limited to a form of “lawful

expropriation, enacted through a legislative act, entailing a dispossession of the expropriated

359 HB/G/003/034-068: Metalclad Corporation v United Mexican States, ICSID Case No. ARB(AF)/97/1, Award, 30 August 2000, para. 103; HB/G/004/069-149: Técnicas Medioambientales Tecmed, S.A. v United Mexican States, ICSID Case No. ARB (AF)/00/2, Award, 29 May 2003, para. 113; HB/G/005/150-328: CME Czech Republic B.V. v Czech Republic, UNCITRAL, Partial Award, 13 September 2001, para. 604. 360 HB/A/004/371-603: Claimant’s Reply, paras. 554-562. 361 HB/A/004/371-603: Claimant’s Reply, paras. 563-571. 362 Claimant’s PHB, para. 134. 363 Claimant’s PHB, paras. 136-138. 364 Claimant’s PHB, paras. 139-142; HB/A/004/371-603: Claimant’s Reply, paras. 572-577. 365 Claimant’s PHB, paras. 116-118. 366 Respondent’s PHB, para. 114.

Page 97: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

90

party and a correspondent taking of the property by the State against compensation of the

expropriated party”.367 Moreover, although the Claimant argues that the definition of

“Governmental Authority” in the Implementation Agreement includes any “court, judicial or

administrative body”, this definition must still be interpreted in light of Tanzanian law, which

does not recognize judicial expropriation.368

GoT says that the Constitution of Tanzania protects personal rights to property, and that

special Tanzanian laws in particular Section 22 of The Tanzania Investment Act, 1997 and

Section 28 of the National Investment (Promotion and Protection) Act, 1990 speak only to this

form of legal expropriation and no other form such as “indirect, judicial or creeping

expropriation to the benefit of third private parties and with no benefit whatsoever accruing to

the State.”369

The provisions relied upon by the Respondent are:

i. National Investment (Promotion and Protection) Act, 1990, Section 28:

28.-(I) No approved enterprise, or any property belonging to any person shall be compulsorily taken Possession of, and no interest in a right over such enterprise or property shall be compulsorily acquired except for public interest and after due process of the law.370

ii. The Tanzania Investment Act, 1997, Section 22:371

22(1) […] (a) no business enterprise shall be nationalised or expropriated by the Government, and

(b) no person who owns, whether wholly or in part, the capital of any business enterprise shall be compelled by law to cede his interest in the capital to any other person.

(2) There shall not be any acquisition, whether wholly or in part of a business enterprise to which this Act applies by the State unless the

367 Respondent’s PHB, para. 115. 368 HB/A/005/604-827: Respondent’s Rejoinder, para. 268. 369 Respondent’s PHB, para. 115. 370HB/G/182/13157-13193 at pg. 13178: The National Investment (Promotion and Protection Act) (Tanzania), Part V, 19 June 1990. 371 HB/G/176/12866-12886 at pg. 12881: The Tanzania Investment Act 1997, Official Gazette No. 40, Vol. 78, Acts Supplement No.7, 3 October 1997.

Page 98: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

91

acquisition is under the due process of law which makes provision for - (a) payment of fair adequate and prompt compensation […]

The Respondent further refutes the Claimant’s submission that Section 23 of The Tanzania

Investment Act, 1997, which references bilateral investment treaties, was meant to

incorporate the wider concept of expropriation under those instruments as that provision

merely states the obvious: that investors with bilateral investment treaties have access to

arbitration; but Section 23 does not purport to incorporate the bilateral investment treaties

definition of expropriation.372

The Respondent submits that Article 16.2, read with Article 20.1 of the Implementation

Agreement, presupposes a direct taking of the Facility by GoT373 and that in all such cases,

compensation would be payable by GoT in accordance with the formulae set out in Schedule

2 thereof, which corresponds with the value of the Facility taken over. GoT concedes that

there is no specific reference to a “transfer of the Facility” to GoT specified under Article

20.1(d) of the Implementation Agreement (“expropriation”), but says that it would be unfair

to GoT to have to pay compensation for the value of the Facility without the transfer of the

Facility to GoT and therefore it must be inferred that GoT must have already acquired the

Facility. It therefore concludes that in all situations, GoT must have directly acquired

possession of the Facility, viz. that GoT has taken over the Facility or acquired shares in IPTL,

neither of which have in fact occurred as the Facility remains owned by IPTL, a private legal

entity.374

The Respondent also submits that because the compensation for expropriation, which is

under row 4 of Schedule 2 of the Implementation Agreement, is less than compensation for

contractual breaches under Row 2 of Schedule 2, the remedy contemplated under Article

20.1(d) of the Implementation Agreement must be a reference to “lawful expropriation”

otherwise “it would make no sense for the Government to escape the obligation to pay a higher

compensation as ordinarily due in case of breaches of the Implementation Agreement.”375

372 Respondent’s PHB, para. 115. 373 Respondent’s PHB, para. 117. Except in the situation under Article 20.1(d), Implementation Agreement. 374 Respondent’s PHB, paras. 113, 117. 375 Respondent’s PHB, para. 118.

Page 99: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

92

The Respondent objects to the Claimant’s attempt to incorporate international law, ignoring

the specific applicable law clause that designates Tanzanian law. The Respondent counters

that scholars have confirmed international law cannot be imported where there is a specific

municipal law in the contract. Moreover, the Respondent points out that in addition to the

ICSID clause, there is also an ICC clause in the contract.376 The Respondent similarly rejects

the Claimant’s argument based on Article 42 of the ICSID Convention to take into account

international law, as this provision only applies where there is no party agreement, and in

this case the Parties agreed to the application of Tanzanian law.377 The Respondent argues

that not taking Tanzanian law into account would be a ground for annulment.378

In addition, the Respondent contends that even under an international law standard, the

Claimant’s case fails as the State has not received either a direct or indirect benefit from the

alleged expropriation. The Respondent further argues that another flawed aspect of the

Claimant’s case is that the Claimant only holds security rights, which do not constitute

property rights that can be expropriated.379

The Respondent submits that even if international investment law were applicable, the

Claimant’s case on judicial expropriation would fail as its case relates only to a few judicial

decisions, not to the judiciary as a whole.380 In the Respondent’s view, under international

law, for a judicial act to constitute expropriation it “cannot simply be illegal but the

proceedings leading up to said act must amount to denial of justice”, which necessitates the

exhaustion of local remedies.381 Moreover, the Respondent asserts that there can be no

judicial expropriation when the “frustrations suffered by the investors in local courts were due

to their own procedural errors”, which the Respondent submits is the case here.382

376 Respondent’s PHB, paras. 120-121. 377 Respondent’s PHB, para. 122. 378 HB/A/005/604-827: Respondent’s Rejoinder, para. 262. 379 HB/A/005/604-827: Respondent’s Rejoinder, paras. 264-265. 380 HB/A/005/604-827: Respondent’s Rejoinder, para. 267; HB/A/003/144-370: Respondent’s Counter-Memorial, para. 307. 381 HB/A/005/604-827: Respondent’s Rejoinder, para. 270; HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 306-307. 382 HB/A/003/144-370: Respondent’s Counter- Memorial, para. 307.

Page 100: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

93

b. Tribunal’s Analysis

The term “expropriate” was used twice in Article 16 of the Implementation Agreement, but it

has not been specifically defined. As the Implementation Agreement is expressly subject to

Tanzanian law,383 the Tribunal has some difficulty accepting the logic of GoT’s argument, that

Tanzanian law recognises only legal expropriation with compensation and therefore what

was allegedly done by GoT could not be “expropriation” as contemplated in Article 16 of the

Implementation Agreement. In other words, GoT appears to contend that Article 16 of the

Implementation Agreement is an undertaking by GoT not to expropriate legally and not a

prohibition against expropriating illegally. Perhaps, realising the strained logic in its

submission, the Respondent subsequently accepted that “[t]his does not mean that cases of

unlawful expropriation would be unable to give rise to the Government’s liability but simply that

IPTL or its valid assignees would have no action under the Implementation Agreement for any

event of unlawful expropriation […].”384

The Tribunal does not consider it plausible that the parties would have entered into the

Implementation Agreement with protections for IPTL that went no further than lawful

expropriation under Tanzanian law. In the Tribunal’s view, this argument is obviously flawed

and must be rejected.

The Constitution of Tanzania provides in Article 24 that –

(1) Every person is entitled to own property, and has a right to the protection of his property held in accordance with the law.

(2) Subject to the provisions of subarticle (1), it shall be unlawful for any person to be deprived of his property for the purposes of nationalization or any other purposes without the authority of law which makes provision for fair and adequate compensation. 385

The Constitutional position is that to deprive someone of its property, whether for purposes

of “nationalization or any other purposes”, “fair and adequate compensation” must be provided

to the person so deprived. This overarching protection is extended to foreign businesses

under specific Tanzanian legislation (viz. The Tanzania Investment Act, 1997 and National

383 HB/C/005/192-267 at pg. 251: Unsigned copy of Implementation Agreement (including Schedules), 8 June 1995, Article 24.8. 384 Respondent’s PHB, para. 118. 385 HB/G/175/12775-12865 at pg. 12794: The Constitution of the United Republic of Tanzania, 1977, Article 24.

Page 101: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

94

Investment (Promotion and Protection) Act, 1990), which provide that “no interest in a right

over such […] property shall be compulsorily acquired […]” and any acquisition of a “business”

[…] “whether wholly or in part”, of a foreigner by GoT is permitted386 only after due process

of law and with adequate compensation being given. The law also expressly provides

protection for an investor against being “compelled by law to cede his interest in the capital to

any other person.”387 This means that any form of interference with the rights of foreign

investors, whether by dispossessing or disempowering them of their lawful exercise over the

investment or related security, would be unlawful expropriation and expressly prohibited.

The granting of protection to foreign investment is in the interest of Tanzania. GoT’s

acceptance of the prohibition against expropriation (which it is in any event legally bound

not to do under Tanzanian law) under Article 16.1 of the Implementation Agreement and its

undertaking not to expropriate under Article 16.2 of the Implementation Agreement, do not

violate and is in fact fully consistent and compliant with the Tanzanian Constitution and the

investment laws.

The Preamble in the Implementation Agreement sets out clearly that it was given to

encourage the public-private sectors’ cooperation to build the Facility for generating

electricity for the national grid. The Implementation Agreement speaks of foreign investors,

lenders, foreign currency, etc. The reference by GoT, to the use of the notion of “expropriation”

in The Tanzania Investment Act, 1997 and the National Investment (Promotion and Protection)

Act, 1990 shows that the term is intended as a protection against compulsory acquisition

given in relation to foreign investments in Tanzania. Both pieces of legislation make specific

reference to ICSID. In the Tribunal’s view, both Tanzanian legislations are clearly intended to

reflect what is usually understood and accepted in international law, in particular in the

application of the ICSID Convention and investment treaties, which was the context in which

these laws on foreign investment were enacted. Similarly, the term “expropriate” as used in

the text of Article 16, not being qualified in any manner must be given it ordinary meaning

viz. it includes both direct and indirect expropriation as understood in international law.

386 This requirement under the National Investment (Promotion and Protection) Act 1990, Section 28 was omitted under the later The Tanzania Investment Act 1997, Section 22; HB/G/182/13157-13193 at pgs. 13178-13179: The National Investment (Promotion and Protection Act) (Tanzania), Part V, 19 June 1990; HB/G/176/12866-12886 at pg. 12881: The Tanzania Investment Act 1997, Official Gazette No. 40, Vol. 78, Acts Supplement No.7, 3 October 1997, Section 22. 387 HB/G/176/12866-12886 at pg. 12881: The Tanzania Investment Act 1997, Official Gazette No. 40, Vol. 78, Acts Supplement No.7, 3 October 1997, Section 22.

Page 102: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

95

The right to be protected against expropriation in the international context is a right given by

host States to ensure foreign investors enjoy protection against involuntary deprivation or

dispossession of an investor’s property or property rights. Expropriation may be expressly

permitted and thereby lawful if it is made pursuant to Tanzanian law, for public purposes,

and subject to due process and adequate compensation. The clearest example of a direct

expropriation is when a host State takes over the project, the facility, or its management

directly and runs it as a State enterprise; or when the host State compulsorily acquires the

controlling shares of the investor company. Expropriation can also be achieved indirectly,

where no actual outright seizure or taking of property by the State occurs but actions

attributable to a host State (whether directly or indirectly) result in the investor being

deprived of the “economic value of the investment or deprive the owner of its ability to manage,

use or control its property in a meaningful way.”388

There is a body of decisions both in ICSID and non-ICSID investor-State arbitrations relating

to claims for indirect expropriation. Many of these arose from a change to the regulatory

regime of the host State that negatively impacted the investment at issue.389 In essence, to

establish expropriation, the Claimant needs only show that the rights that it would otherwise

enjoy have been substantially impacted or that it has been deprived of control over or access

to the economic use of its investment. There is also no requirement that GoT must have

directly acquired possession of the Facility, by itself taking over the Facility or the shares in

IPTL. Tanzanian law recognises that “expropriation” could be founded upon the actions of

GoT which lead to the acquisition by “any other person.”390

The Respondent, in its argument against indirect expropriation, takes the view that

expropriation must only mean expropriation by GoT executed by way of an act of the

legislature and that therefore the actions or omissions of all other arms of the State, whether

the judiciary or government linked entities could never be attributable to the GoT. In the first

place, nothing in the Tanzanian Constitution supports the suggestion that expropriation

388 HB/G/108/10292-10472 at pg. 10312: UNCTAD Series on Issues in International Investment Agreements II, “Expropriation”, UN Doc (UNCTAD/DIAE/IA/2011/7), 2012. 389 These may be in form of change in areas of taxation, local shareholding, licensing, etc. See HB/G/003/034-068: Metalclad Corporation v United Mexican States, ICSID Case No. ARB(AF)/97/1, Award, 30 August 2000; HB/G/004/069-149: Técnicas Medioambientales Tecmed, S.A. v United Mexican States, ICSID Case No. ARB (AF)/00/2, Award, 29 May 2003; HB/G/012/809-851: El Paso Energy International Company v Argentine Republic, ICSID Case No. ARB/03/15, Decision on Jurisdiction,27 April 2006. 390 HB/G/176/12866-12886 at pg. 12881: The Tanzania Investment Act 1997, Official Gazette No. 40, Vol. 78, Acts Supplement No.7, 3 October 1997, Section 22(1)(b).

Page 103: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

96

could only take place by way of a Tanzanian legislation. In the Tribunal’s view, there is no

justification for this limitation. The State is compendious and may act through different

agencies which actions are nevertheless attributable to the State because these actions carry

out State functions. The acts of the State must necessarily include the acts of organs of State,

the executive and judicial arms of the State and any entity given public powers to act on behalf

of the State. The Tanzanian Constitution also does not exclude any specific arm of government

the judiciary as a possible player in the act of expropriation.

The Tribunal does not disagree with the Respondent that the judiciary should not be

implicated, or its acts be described as “judicial expropriation” simply because judicial

decisions were taken in error or may be considered aberrant. However, judicial decisions that

permit the actions or inactions of other branches of the State and which deprive the investor

of its, property or property rights, can still amount to expropriation. While denial of justice

could in some case result in expropriation, it does not follow that judicial expropriation could

only occur if there is denial of justice.

As for other possible actors in the alleged expropriation, the Respondent has pointed out that

the Administrator General and Official Receiver’s office when acting in its capacity as

liquidator (provisional or otherwise) or receiver was acting as an agent of the company in or

pending liquidation. That is indeed the proper role. However, the office of the Administrator

General and Official Receiver remains an arm of GoT; it is at all times a part of the Ministry of

Justice and Constitutional Affairs. Insofar as discharging its duties in the interest of the

company in liquidation, it is expected to hold a high standard of integrity and impartiality. If

the office of the Administrator General and Official Receiver acts beyond the boundaries

granted by the law, such improper acts could not be attributable to the Company as its

principal. The Administrator General and Official Receiver must be liable for its own actions

and not that of the Company. This is all the more so if it acted in a manner that favoured the

GoT to the detriment of other persons with an interest in the company in liquidation. The

Respondent cannot hide behind the argument that the Administrator General and Official

Receiver was merely acting as an agent of the company.

In this context, the Tribunal notes that the undertaking given against expropriation under

Article 16.2 of the Implementation Agreement is made in respect of the actions of “GOT”,

Page 104: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

97

“TANESCO”, or “any Governmental Authority”, The term “Governmental Authority”391 is defined

as –

Any state, municipal or local government or regulatory department, body, political subdivision, commission, instrumentality, agency, ministry, court, judicial or administrative body, taxing authority or other relevant authority having jurisdiction over either Party, the Facility.

There is no question that the office of the Administrator General and Official Receiver is a

Government Authority, which could exercise authority over the parties. Its action or inaction

beyond that permitted by law must therefore be attributable to GoT.

The Respondent’s submission that the Claimant has no property interest but merely security

rights is also quite misplaced. Firstly, the Claimant is not claiming a breach of the Constitution

where the term “property” is used. The Claimant’s claim is based on the contractual terms of

Article 16 under which GoT, is prohibited from expropriating or acquiring the Facility or IPTL,

and undertook that it (and TANESCO, and any Government Authority) would not

“expropriate, compulsorily acquire, nationalise, or otherwise compulsorily procure any

Ordinary Share Capital or assets of the Company.” The Claimant’s interest in the Facility and

shares of the IPTL may have come through the Security Package. That itself does not mean

the Claimant’s interest are merely security rights and not property rights. The Claimant as

absolute assignee has all the rights in and of IPTL and IPTL’s assets for which the Respondent

undertook not to expropriate or compulsorily acquire or otherwise procure. There is no

question that these are property rights and not mere security rights.

The Tribunal therefore holds that the contractual prohibition in Article 16 of the

Implementation Agreement against expropriation and the undertaking not to expropriate

given by GoT are compliant and consonant with the Tanzanian Constitution. The Respondent

is therefore bound by its terms not to do anything which would deprive the Claimant’s

interest in IPTL and the assets of IPTL. Whether the Respondent through its various

“instrumentality, agency, ministry, court, judicial or administrative body” acted in a manner

that amount to a breach of Article 16 is a matter of fact that the Tribunal needs to hereafter

examine.

391 HB/C/005/192-267 at pg. 196: Unsigned copy of Implementation Agreement (including Schedules), 8 June 1995; HB/C/002/013-128 at pg. 024: PPA, 26 May 1995.

Page 105: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

98

(2) Claimant’s Expropriation Allegations

In the discussion that follows, the Tribunal will consider the allegations made against GoT

that the Claimant asserts are steps which either individually or collectively violate the

prohibition against expropriation.

The principal actors identified by the Claimant that had roles in this regard were:

i. TANESCO;

ii. the Tanzanian courts (particularly the actions of Utamwa J in handing down the

Utamwa J Order);

iii. the provisional liquidators appointed over IPTL and the Administrator General;

iv. BRELA;

v. the Minister of Energy and Minerals and the PS MEM;

vi. the Attorney General; and

vii. the Bank of Tanzania.

The Respondent on the other hand says that the real parties involved in the entire affair were

several different entities, mostly private ones, such as IPTL, VIP, Mechmar, PAP and others,

but not the Government.392 Additionally, the Respondent submits that as a factual matter

neither IPTL nor SCB HK was ever nationalised or expropriated by the Government. IPTL has

always been a private company and its rights and assets have remained with its shareholders,

albeit they have changed. In addition, the Respondent submits that the Tariff Dispute was

eventually negotiated between TANESCO and IPTL, the Escrow Account was released upon

IPTL’s instructions, the top up payments were paid to IPTL, and the Facility remained in

IPTL’s possession.393

The Claimant lists the following actions as constituting expropriation of the Facility, IPTL's

other assets and IPTL's Ordinary Share Capital by the GoT, TANESCO and Governmental

Authorities in breach of Articles 16.1 and 16.2 of the Implementation Agreement:394

i. TANESCO's failure to make payments to IPTL or SCB HK under the PPA;

ii. the steps taken to frustrate the Interpretation Proceedings by TANESCO, the

Tanzanian courts and the First PL;

392 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 10. 393 Respondent’s PHB, paras. 113,126. 394 HB/A/002/035-143: Claimant’s Memorial, para. 194; Claimant’s PHB, para. 130.

Page 106: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

99

iii. the First PL's failure, in breach of his duty to preserve and protect IPTL's assets, to

take any steps to enforce TANESCO’s obligation to pay the tariff under the PPA;

iv. the steps taken by TANESCO, the Second PL and the Tanzanian courts to frustrate the

PPA Arbitration;

v. the Second PL and Administrator General's countersignature of the VIP-PAP-SPA

which purported, wrongly, to recognise PAP as owner of Mechmar's shares in IPTL;

vi. the Utamwa J Order;395

vii. the actions of TANESCO, the Minister of Energy, the PS MEM, the Attorney General

and the Bank of Tanzania in the period September to December 2013 facilitating the

release of the Escrow Account funds to PAP; and

viii. the Minister of Energy and the PS MEM's refusal to consider the evidence submitted

by SCB HK, following the Utamwa J Order, concerning its rights over IPTL's Ordinary

Share Capital. This was followed by BRELA's subsequent registration of PAP as the

owner of all of the shares in IPTL, which constitutes an expropriation of IPTL's

Ordinary Share Capital.

The Respondent submits that there was no breach of Article 16.2 of the Implementation

Agreement. In summary, the Respondent disputes the Claimant’s expropriation claims as

follows:

IPTL’s rights under the PPA: payments under the PPA were delayed by TANESCO’s decision to dispute invoices issued by IPTL. This decision was justified by IPTL overcharging TANESCO, as eventually recognised by the PPA Tribunal. In not pursuing the Interpretation Proceedings (which were eventually withdrawn by Mechmar) the first provisional liquidator of IPTL, Mr Rugonzibwa (even assuming that he may be considered a Government official in his function as provisional liquidator, which is denied), exercised his discretion as granted to him by the law. In any case, TANESCO and IPTL eventually reached an agreement to end the Tariff Dispute and restore payments to IPTL, which now renders Claimant’s complaint in this respect moot and untimely.

The Ordinary Share Capital of IPTL: This was transferred by Mechmar and VIP, the original shareholders of IPTL, to PAP. To the extent that said transfers violated SCB HK’s rights as a secured creditor, VIP and Mechmar are the entities responsible for said violation. To the extent that the Utamwa J Order recognised said transfers, SCB HK did not take the necessary actions to counter said finding or to have its rights otherwise judicially recognised in Tanzania and is thus now barred from

395 See para. 39 above.

Page 107: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

100

bringing a claim of expropriation by the judiciary. Furthermore, Claimant cannot complain about Mr Saliboko, the second provisional liquidator of IPTL (assuming that he may be considered a Government official in his function as provisional liquidator, which is denied) countersigning the VIP/PAP SPA as Mr Saliboko was entitled to have doubts on SCB HK’s standing as a secured creditor, given that the PwC Report noted that the Security Deed had not been registered or stamped at BRELA. In any case, as provisional liquidator, Mr Saliboko’s actions were subject to the scrutiny of the High Court of Tanzania, before which Claimant failed to adequately challenge them. Finally, Claimant can neither complain about Government officials or BRELA recognising the transfer of the Ordinary Share Capital of IPTL as they could not reverse the findings of the judiciary made through the Utamwa J Order.

The Facility: The same considerations made with respect to the Utamwa J Order in relation to the transfer of the Ordinary Share Capital of IPTL apply to the transfer of the Facility to PAP.

IPTL’s interest in the Escrow Account and top-up payments: further to the Utamwa J Order transferring the affairs of IPTL to PAP and to TANESCO and IPTL reaching an agreement for the release of the Escrow Account funds, the Government could not refuse to transfer said funds to IPTL. While the Escrow Agreement expressly prohibits payments being made to creditors of IPTL (such as SCB HK) – and contains no such prohibition with respect to shareholders or managers of IPTL – the Government released the funds on the basis of IPTL’s instructions. The Government played no role with respect to the top-up payments, which were agreed exclusively between TANESCO and IPTL in October 2013 and were directly paid by TANESCO to IPTL in the years thereafter.396

The Tribunal analyses the Claimant’s expropriation allegations, in turn, below.

a. TANESCO's Failure to Make Payments under the PPA, and the Interpretation Proceedings frustrated by the Tanzanian Courts, TANESCO and GoT officials

(i) Tribunal’s Analysis

The ICSID 1 Award397 resolved some of the initial disputes between IPTL and TANESCO by

incorporating a new financial model agreed to by TANESCO and IPTL, which would be used

by the parties to calculate the capacity and energy tariffs after the start of commercial

operation. The ICSID 1 Tribunal also trimmed down certain costs incurred and ordered them

to be borne by IPTL.

396 Respondent’s Reply PHB, para. 60 (emphasis in original). 397 HB/D/002/066-299: ICSID 1 Award, 12 July 2001.

Page 108: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

101

Differences between Mechmar and VIP thereafter arose when VIP took the position that

Mechmar should bear the additional expenses disallowed to be recoverable by the ICSID 1

Tribunal, instead of accounting for them as expenses to be borne by IPTL. This led to VIP

petitioning for the liquidation of IPTL in the Tanzanian High Court398 on 25 February 2002.

Against this background, Mechmar commenced the LCIA Arbitration based on the PSA of 28

September 1994, and eventually obtained the LCIA Award399 directing VIP to discontinue its

Petition for Winding Up and application for appointment of a provisional liquidator in Misc.

Civil Cause No. 49 of 2002 before the Tanzanian courts.

Meanwhile, TANESCO began payment of the tariffs following the commencement of

commercial operations of the Facility in 2001. But in 2004, TANESCO started raising issue

over certain tariff payments. TANESCO continued paying IPTL on the urging of GoT.400 These

payments flowed down to enable repayments of the loan by IPTL (first to Danaharta and later

to SCB HK). TANESCO stopped doing so in May 2007.

In May 2007, TANESCO raised the issue of Mechmar's contribution to the capital of IPTL

which was made principally by way of a shareholder loan rather than paid-up share capital.

TANESCO argued that this was inconsistent with the PPA and the ICSID 1 Award. TANESCO

however made payments to the Escrow Account.

The differences between IPTL and TANESCO relating to the tariff payment led IPTL (the

majority shareholders Mechmar were supported by SCB HK) in June 2008, to commence the

Interpretation Proceedings under Article 50 of the ICSID Convention in relation to the ICSID

1 Award. IPTL’s action was challenged by TANESCO as lacking a valid corporate act on the

basis that VIP had not authorised the commencement of the Interpretation Proceedings.

Mechmar sought to rely on its LCIA Award to assert its authority to maintain the

Interpretation Proceedings. The LCIA Award was never given effect, and, although an

application for setting aside was made in September 2003 and an application for enforcement

was made in November 2004, they were not heard until 31 October 2008 when the LCIA

398 HB/H/037/709-725: Winding Up Petition, 25 February 2002. 399 HB/D/007/616-639 at pgs. 626-628: LCIA Award, 26 August 2003, paras. 54-59. 400 HB/H/056/845-846: Letter from Ministry of Energy and Minerals to Tanesco, 8 July 2004.

Page 109: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

102

Award was eventually refused enforcement by Oriyo J401 on the basis that Mechmar had not

complied with the court’s direction to serve submissions as directed earlier.

In November 2008, to establish IPTL’s position to pursue the Interpretation Proceedings, SCB

HK applied to the Tanzanian courts to restrain VIP from continuing the Winding Up

proceedings against IPTL.402 This application was never heard.

On 15 December 2008, in the exercise of its power granted to it under the Charge of Shares,

SCB HK appointed a receiver over VIP's shares in IPTL to order use of those shares to vote in

favour of continuation of the Interpretation Proceedings.403

On 16 December 2008, the Receiver appointed for the VIP Shares applied to the High Court

of Tanzania in the same Misc. Civil Cause No. 49 of 2002 asking that “the petition for the

winding up, and the application for the appointment of a provisional liquidator […be]

withdrawn and/or abandoned.”404

On that same day, 16 December 2008, which was also the day the tribunal in the

Interpretation Proceedings was set to sit to hear the Parties in London, the High Court of

Tanzania (Oriyo J)405 dismissed IPTL’s application for a stay, granted VIP’s application for the

appointment of a provisional liquidator and appointed the Administrator General/Official

Receiver as First PL. The written decision of Oriyo J does not suggest any hearing was held

before the matters were decided. In relation to the stay application, the Learned Judge, while

accepting that the application for appointment of a provisional liquidator should not be

decided before considering IPTL’s application for stay of the proceedings, went on to dismiss

the application for stay saying it “does not serve any useful purpose”:406

[...] It will be unfair to determine the petition to wind up IPTL before its applications for stay is determined. However, due to intervening factors since March, 2002 to date, a decisions on application for stay may not serve any useful purpose […] And as correctly stated by the applicant the application for stay of proceedings has been overtaken by events and is now redundant. It has become obsolete; it does not serve any useful

401 HB/H/097/1020-1030 at pgs. 1026-1028: Judgment of Oriyo J in the Tanzanian Court, 31 October 2008. 402 HB/H/098/1013-1048: Application by SCB HK before the High Court of Tanzania, 21 November 2008. 403 HB/H/102/1076-1100 at pgs. 1097-1098: Letter from RHB Bank Berhad to ICSID, 15 December 2008. 404 HB/H/105/1139-1146 at pg. 1140: Application by Share Receiver before the High Court of Tanzania, 16 December 2008. 405 HB/H/104/1122-1138: High Court of Tanzania's Appointment of PL, 16 December 2008. 406 HB/H/104/1122-1138 at pgs. 1127-1128: High Court of Tanzania's Appointment of PL, 16 December 2008.

Page 110: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

103

purpose. In the circumstances, the application for stay of proceedings pending arbitration is accordingly dismissed. […].

It is unclear what circumstances convinced Oriyo J that the stay application could serve no

useful purpose. What is clear is that the LCIA Award though not enforced remains a valid

arbitral award, unless it had been set aside by the court of the seat of arbitration (viz. the

English courts). It should be noted that in her decision of October 2008, Oriyo J did not in fact

set aside the award, because she took the view that “[h]aving dismissed the Petition to Enforce

Award, the application to set aside the Award is rendered obsolete.”407

In relation to VIP’s application for a provisional liquidator, Oriyo J stressed that Mechmar and

IPTL’s written submissions were “limited to points of law” and “have not countered the

affidavits in the petition by the applicant; those averments stand uncontroverted and are

accordingly adopted by the court.” Relying on that, the court ruling appeared to have accepted

that:

On the degree of urgency; its relevancy here cannot be overstated because the oppressive acts, fraud, etc of Mechmar against VIP has been in a continuous process since 2001; that is, for a period of over seven years […]

The need for the appointment of a Provisional Liquidator pending winding up has in no doubt been adequately established by VIP through the affidavits of James Burchard Rugemalira filed on 25.2.2002 and 24.9.2003. […].408

The court also remarked that the appointment of a provisional liquidator is justified in the

public interest in that:

It is intended to serve interests of groups like those doing business with IPTL including TANESCO and the government of Tanzania.409

Urgency, potential detriment and public interest are of course sound factors that should be

considered by a court to appoint a provisional liquidator. It is curious that Oriyo J did not in

her written decision explain what had informed her of the sudden urgency that prompted her

to revive an application made in 2002 and relying on affidavits made some five years ago to

407 HB/H/097/1020-1030 at pg. 1029: Judgment of Oriyo J in the Tanzanian Court, 31 October 2008. 408 HB/H/104/1122-1138 at pg. 1132: High Court of Tanzania's Appointment of PL, 16 December 2008. 409 HB/H/104/1122-1138 at pg. 1133: High Court of Tanzania's Appointment of PL, 16 December 2008.

Page 111: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

104

hold that an immediate appointment would be necessary and in the public interest without

calling upon the parties involved to be heard substantively.410 In making this observation, the

Tribunal is assuming that the application411 by the VIP Share Receiver made on the same day

was received by the court after the release of the Learned Judge’s decision. If the situation

was, otherwise, a further question arises as to why the Learned Judge did not consider the

application for the withdrawal of the provisional liquidator application and the abandonment

of the liquidation petition.

The appointment of the First PL halted the Interpretation Proceedings scheduled for 16

December 2008, as the authority to maintain any action on behalf of IPTL rested with the

First PL. As provisional liquidator, the First PL’s duty is to gather in and safeguard the assets

of IPTL. On this understanding, SCB HK wrote to the First PL seeking his consent to continue

the Interpretation Proceedings, as well as an undertaking to bear the costs incurred in doing

so and only seeking to recover them from IPTL in the event a favourable decision be made in

IPTL’s favour.412 This was followed up on 8 January 2009 by SCB HK’s lawyers413 repeating

the same request and offering similar costs outlay. No response was forthcoming from the

First PL.

On the application of SCB HK on 23 January 2009, the Tanzanian High Court made an order

for the appointment of an Administrator for IPTL on 27 January 2009.414 Unlike a provisional

liquidator, whose role is to preserve assets for creditors in anticipation of liquidation, the role

of an Administrator is to attempt a possible rescue of the company. Mihayo J saw a “new

ground” in Tanzanian company law through an Administrator, in that it would give IPTL an

opportunity to navigate on a new and firm direction. The Learned Judge was conscious that

such an order would dislodge the order made by Oriyo J appointing the First PL –

But what has taxed my mind a great deal is whether my granting of the prayer for appointing an administrator has the effect of torpedoing, cancel[l]ing or over ruling my sister Judge which powers I do not have. I am aware that Oriyo, J. was seeking to protect the assets of the Company without more. An application like the present one was not before the court then. After giving the question serious thought, in my considered

410 HB/H/106/1147-1149: Email from Joe Casson to Wilman Leung, 16 December 2008 – It appears that Oriyo J did ask for parties to attend on 16 December 2008 (based on the Claimant’s understanding, it was to schedule a hearing of the applications, but the judge instead delivered her decision). 411 HB/H/105/1139-1146: Application by Share Receiver before the High Court of Tanzania, 16 December 2008. 412 HB/H/108/1152-1154 at pg. 1153: Letter from SCB HK to the Provisional Liquidator of IPTL, 22 December 2008. 413 HB/H/109/1155-1157: Letter from Ringo & Associates to the Provisional Liquidator of IPTL, 8 January 2009. 414 HB/A/004/371-603: Claimant’s Reply, paras. 132-136.

Page 112: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

105

opinion, this court has if it grants the application, an opportunity to take matters further in a positive way, by rescuing the company. Under the provisions of section 250 of the Act, an administration order protects a company from its creditors and also protects the creditors. […]

I am persuaded that the powers as provided are far more than those of a provisional liquidator and are capable of rescuing the company and protecting the creditors. This means the 100mw the company is capable of generating, and was actually generating, will not go down the drain.415

Mihayo J made his order without hearing the First PL, a procedural error that led to the First

PL’s complaint to the Chief Justice and placed the matter suo motu on revision to the Court of

Appeal, which heard the same on 19 March 2009.

On 24 March 2009, the Administrator confirmed his instruction for the Interpretation

Proceedings to proceed.416 The tribunal in the Interpretation Proceedings decided then to

proceed. However, on 9 April 2009, the Court of Appeal made its ruling revoking the

appointment of the Administrator. In doing so, it roundly condemned Mihayo J for failing to

hear the First PL and IPTL before making the order appointing the Administrator: “[…] there

can be no equal justice when one, for no compulsive reason, is condemned unheard.”417

On 15 April 2009, the First PL informed the tribunal in the Interpretation Proceedings to stay

the proceedings.418

On 17 September 2009, SCB HK re-applied419 for the appointment of an administrator. This

matter remained unheard and was eventually withdrawn in 2013.

In December 2009, SCB HK sought to intervene directly in the Interpretation Proceedings,

exercising its rights as assignee of the PPA pursuant to the Security Deed. The Interpretation

Proceedings did not proceed much further save for the challenge brought against Judge

415 HB/H/112/1185-1195 at pgs. 1193-1194: Order of the High Court of Tanzania, 27 January 2009. 416 HB/H/116/1201-1204: Letter from the Interpretation Tribunal, 3 April 2009. 417 HB/H/117/1205-1231 at pg. 1230: Ruling of the Court of Appeal of Tanzania, 9 April 2009. 418 HB/H/119/1234-1236 at pg. 1235: Letter from the Provisional Liquidator to the ICSID 1 Tribunal, 15 April 2009. 419 HB/H/122/1242-1252: Petition by SCB HK in Misc. Civil Cause No. 112 of 2009 before the High Court of Tanzania, 17 September 2009.

Page 113: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

106

Brower, who resigned and was replaced by Mr Makhdoom Ali Khan on 23 April 2010.420 Mr

Rokison, the president of the tribunal was also challenged on 25 June 2010 and the

proceedings were thereby suspended.

The ICSID public case record421 shows that IPTL requested the discontinuance of the

Interpretation Proceedings on 7 July 2010,422 to which TANESCO agreed on 13 July 2010.423

The ICSID 1 Interpretation Proceeding finally ended on 19 August 2010 by the discontinuance

order of the tribunal.

SCB HK relies upon this sequence of litigation to show that TANESCO, GoT officials and the

Tanzanian courts acted to frustrate IPTL’s efforts to progress the Interpretation

Proceedings.424 The Tribunal will consider whether these interventions sought to deprive

IPTL or SCB HK of their investment or their rights in the investment.

Although TANESCO failed to terminate the PPA in the ICSID 1 arbitration, it succeeded in

reducing the cost of the project from USD 163.5 million to USD 127.2 million, with a senior

debt of USD 89 million (further reduced to USD 85.3 million) and the remainder

(approximately USD 38 million) in equity.425 This impacts the calculation of the tariff. The

ICSID 1 Award also disallowed certain EPC costs, thereby reducing the EPC costs from USD

114 million to USD 98 million.426 This had the impact of reducing the capacity charges payable

by TANESCO. The ICSID 1 Award was based on a financial model of 70% debt and 30%

shareholders’ equity. Upon realising that IPTL’s shareholding had been financed largely by

shareholders’ loans, TANESCO took the position that it could not be bound by the formula for

the calculation of the capacity charges as agreed.

In the Tribunal’s view, whatever the merits of TANESCO’s position, TANESCO did appear to

have a concern that permitting a review of the ICSID 1 Award in the Interpretation

Proceedings risked weakening its bargaining position to insist on a reduction of capacity

420 HB/H/144/2089-2090 at pg. 2090: Letter from the ICSID Interpretation Proceedings Tribunal to IPTL and Tanesco, 26 May 2010. 421See: https://icsid.worldbank.org/en/Pages/cases/casedetail.aspx?CaseNo=ARB/98/8 (as last accessed on 27 June 2019). 422 HB/H/145/2091-2093 at pg. 2093: Letter from ICSID to IPTL and Tanesco, 8 July 2010. 423 HB/H/146/2094: Letter from Hunton & Williams to ICSID, 13 July 2010. 424 HB/A/002/035-143: Claimant’s Memorial, paras. 73-90. 425 HB/D/002/066-299 at pg. 271: ICSID 1 Award, 12 July 2001. 426 HB/D/002/066-299 at pgs. 217, 219: ICSID 1 Award, 12 July 2001.

Page 114: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

107

charges. Adopting a litigation or negotiation strategy to protect one’s economic financial or

commercial interest is the right of any party. The various challenges launched by TANESCO

to the Interpretation Proceedings against IPTL’s standing, refusing SCB HK’s participation as

intervener and disqualification challenges against members of the tribunal may seem

unhelpful and obstructionist, nevertheless they were part of their litigation strategy. This

alone, does not deprive IPTL of the benefits of its investment.

The only government official implicated in this scenario was the First PL. SCB HK’s complaint

is that he did nothing to progress the Interpretation Proceedings and had frustrated attempts

to move the Interpretation Proceedings even when SCB HK had offered to fund the

proceedings on a cost-recovery basis should IPTL succeed against TANESCO. No explanation

was forthcoming from the First PL to explain the position he had taken. It is the duty of the

provisional liquidator, to gather in and preserve the assets of IPTL. Why then the inaction?

Counsel for GoT suggested that the First PL must have considered that the potential benefits

to be gained in the Interpretation Proceedings were outweighed by the costs of continuing

them and the risk that they could be unsuccessful. SCB HK’s offer that it would bear the costs

and seek costs recovery only upon successful recovery from TANESCO would appear to have

taken away much of the risk. Arguably, if IPTL failed in the Interpretation Proceedings, there

could be cost exposure, but failing to take up SCB HK’s invitation to discuss funding would

appear to be imprudent. It is unexplained why no steps were taken to protect the interests of

IPTL.

Unlike TANESCO which was protecting its own financial interest, the First PL has the primary

responsibility of preserving the assets of IPTL. SCB HK, as a substantial creditor and successor

lender, is an investor protected under the Implementation Agreement. The First PL’s inaction

could well have put the investor at risk. However, it is uncertain and somewhat speculative

to suggest that had the First PL decided to proceed with the Interpretation Proceedings, the

outcome would be one that favours the IPTL. As such, the Tribunal is not prepared to hold

that this lapse by the First PL is sufficient to meet the threshold of expropriation.

Looking then at the role of the courts, the Tribunal does find Oriyo J’s refusal of the stay of

the liquidation proceeding and the application for the appointment of the provisional

liquidator, troubling. Oriyo J came to a view that was not explained and perhaps inexplicable:

that the stay application no longer served any purpose and was obsolete; that the

appointment of a provisional liquidator was urgent; and that it would be in the public interest

Page 115: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

108

(with specific mention of TANESCO and the Government) to appoint a provisional liquidator.

She did so without calling upon any of the parties concerned to address her. In doing so, Oriyo

J did exactly (if not more) than what the Court of Appeal said in its judgment of 9 April 2009427

with regard to Mihayo J’s order appointing the administrator. Oriyo J was fully aware that the

interested parties were all represented and yet did not call upon them to address her. Instead

she chose to make a decision on the same day that she had scheduled a meeting for directions.

It appears too coincidental that the judge decided to deliver her decision on the day (16

December 2008) the share receivers appointed over VIP (the petitioner for liquidation and

for appointment of a provisional liquidator) applied to withdraw the Petition and application,

which was also the same day the Interpretation Proceedings were scheduled to begin in

London.

Oriyo J’s primary justification for the order appointing the provisional liquidator lacked

substance and was flawed in procedure and the appointment of a provisional liquidator had

a direct impact on IPTL as a going concern.

The Court of Appeal was of course correct to have set aside Mihayo J’s order appointing the

Administrator for breach of due process. The Court of Appeal however declined to consider

the merits of the application to appoint the administrator, and simply said that there were

“no compelling reasons to discuss the remaining issues” relating to the appointment of an

administrator, suggesting that if parties still wished to pursue such an appointment, they

could do so in the High Court. SCB HK then filed a new application428 on 17 September 2009

in Misc. Cause 112 of 2009 for the appointment of an administrator, serving it on the

Provisional Liquidator of IPTL, VIP, IPTL and the creditors of IPTL. This application was noted

by the court on several occasions (e.g. Kaijage J on 6 November 2009,429 9 February 2011,430

Mwaikugile J on 11 August 2011,431 and again by Kaijage J on 24 August 2011,432 19 January

427 HB/H/117/1205-1231: Ruling of the Court of Appeal of Tanzania, 9 April 2009. 428 HB/H/122/1242-1252: Petition by SCB HK in Misc. Civil Cause No. 112 of 2009 before the High Court of Tanzania, 17 September 2009; An application for the removal of the provisional liquidator was also filed on the same day: HB/H/123/1253-1254: Application to remove Provisional Liquidator, 17 September 2009. 429 According to SCB HK, this was adjourned “by consent” by Kaijage J on 6 November 2009 “pending the position of parties becoming known in regard to IPTL” in Winding-up Petition No. 5 of 2002. SCB HK’s lawyers wrote in to clarify that no such consent was given, HB/H/133/1294-1295: Letter from Ringo & Associates Advocates to the High Court of Tanzania, 11 November 2009. 430 HB/H/175/2304-2306: DLA Piper attendance note of hearing (redacted), 9 February 2011. 431 HB/H/188/2556-2558: Order of Mwaikugile J in the High Court of Tanzania, 11 August 2011. 432 HB/H/190/ 2562-2565: DLA Piper attendance note of hearing, 24 August 2011.

Page 116: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

109

2012 and on 16 March 2012.433 The Court of Appeal noted this lapse in its decision of 17

December 2012.434

The Tribunal accepts that divergence of views by the courts is to be expected and is very much

part of the legal system in many jurisdictions. Poor decisions or decisions without proper

justifications do not rise to the standard of expropriation. With regard to the actions and

inaction of the Tanzanian courts in relation to attempts by the Claimant to revive the ICSID 1

Award by the Interpretation Proceedings, the Tribunal finds that the Tanzanian judiciary as

a whole, had not acted to deprive IPTL or SCB HK of the economic value of their investments.

b. PPA Arbitration: TANESCO, the Second PL and the Tanzanian courts; VIP, Mechmar Share transfers and control of IPTL; and Utamwa J Order

(i) PPA Arbitration

SCB HK’s inability to proceed with the Interpretation Proceedings to resolve IPTL’s

differences with the capacity charges and tariff payments as set out in paragraphs 293 to 312

above, led SCB HK (as IPTL’s assignee) to commence the PPA Arbitration in September 2010.

The PPA Arbitration was concerned with issues of IPTL’s actual “equity” participation, the

tariff calculations and the amount outstanding due to the IPTL. These were finally disposed

by the PPA Decision in February 2014,435 the PPA Award in September 2016436 and confirmed

by the ad hoc Annulment Committee in 2018.437

Numerous adverse findings were made by the tribunal in the PPA Decision438 and in the PPA

Award, and TANESCO was eventually found liable for not making payments of the tariff to

IPTL and SCB HK.

The Tribunal has considered the PPA Decision and the PPA Award and noted that while there

were allegations and suggestions that through some improper dealings GoT “took over

433 HB/H/207/2794-2805: Standard Chartered Bank (Hong Kong) Limited v Independent Power Tanzania Limited and others, High Court of Tanzania, Misc. Civil Cause No. 112 of 2009, Orders (Kaijage J), 19 January 2012 and 16 March 2012. 434 HB/H/258/3725-3752 at pgs. 3748-3749: Decision of the Court of Appeal of Tanzania, 17 December 2012. 435 HB/D/004/367-479: PPA Decision, 12 February 2014. 436 HB/D/005/480-586: PPA Award,12 September 2016. 437 Exhibit CL-216: Standard Chartered Bank (Hong Kong) Limited v Tanzania Electric Supply Company Limited, ICSID Case No. ARB/10/20, Decision on Annulment, 22 August 2018. 438 HB/D/004/367-479: PPA Decision, 12 February 2014.

Page 117: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

110

control” of the Facility,439 the disputes were essentially contractual in nature and, in fact, the

PPA Tribunal was rightly conscious that an expropriation claim would not be within its

jurisdiction.440 The case that TANESCO offered as the basis of its refusal to make payment to

IPTL and SCB HK was found by the PPA Tribunal to be wrong and not sufficient to absolve it

from its liability to SCB HK. Standing alone, the factual background that gave rise to those

disputes and the findings441 of liability in respect of payments due under the PPA could not,

in the Tribunal’s view, sustain a claim for expropriation or discrimination against SCB HK by

GoT. The fact that TANESCO had not honoured the PPA Award, on its own would also not

constitute an expropriatory act as they were but mere commercial disputes and/or non-

compliance with obligations under the contract or award.

(ii) Sale of Mechmar Shares and control of IPTL

At a meeting on 8 June 2010442 with the PS MEM of Tanzania, Mr David Kitundu Jairo at his

office, SCB HK's legal counsel, Mr Charles Morrison, and Mr Joseph Wesley Casson were

informed that Mechmar had approached GoT to sell its majority shareholding in IPTL, and

that GoT had decided to buy the shares. Mr Jairo requested that Mr Morrison and Mr Casson

439 HB/D/004/367-479: PPA Decision,12 February 2014, para. 72: “Around October 2009, according to the Claimant, the GoT took control of the power plant, and the PL and TANESCO entered into an interim PPA on February 5, 2010 (the “Interim PPA”). According to the Claimant, “[t]he PL has not properly accounted for monies received pursuant to the interim operation of the Plant. Despite repeated requests by SCB HK, the PL has failed to disclose detailed accounts reflecting the current state of IPTL’s finances.” 440 HB/D/004/367-479: PPA Decision, 12 February 2014, paras. 247-248 –

“247. The issue of expropriation is a matter between SCB HK and the GoT, not between SCB HK and TANESCO, and it has been the subject of a separate ICSID arbitration between SCB and the Government of Tanzania. The GoT is not a party to the present arbitration nor has the question of expropriation been placed before this Tribunal. Thus, the Tribunal is not in a position to determine whether and at what date any expropriation might have taken place or fix a date for the determination of loss relying on an expropriation date as the effective date for limiting any damages claim for breach of the PPA. 248. In sum, the Tribunal is able to determine whether there has been a breach of the PPA and what loss flows from that breach. And, the loss it can determine includes all losses resulting from that breach. It cannot fix a limit on those losses on the basis of an expropriation claim that has not been placed before it and it is not in a position to decide. Any claim that the acts of a third party have the effect of suspending either IPTL or TANESCO’s obligation to perform the PPA would have to be made on the basis of the PPA itself; in other words, it would have to be pleaded on the basis of an express contractual term (such as a force majeure clause) or an equivalent doctrine under the applicable law of the PPA. No such claim has been made by the Respondent.”

441 HB/D/005/480-586 at pgs. 584-585: PPA Award, 12 September 2016, para. 414 – The Tribunal ordered payment to and release of the Escrow Account did not discharge TANESCO’s liability under the PPA; payments to PAP-controlled IPTL after August 2013 did not discharge amount due; adjudged that TANESCO was to pay USD 148.4 million plus interest to SCB HK under the PPA. 442 HB/F/004/052-125: Casson WS, 15 November 2017, para. 67.

Page 118: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

111

attend a meeting with himself and Datuk Baharuden Bin Abd Majid, representing Mechmar,

to discuss the Charge of Shares and determine who had the right to sell the 70% of shares in

IPTL held by Mechmar to the GoT. A meeting with Datuk Baharuden was held the next day in

which Mr Nimrod Mkono and Mr Karel Daele, lawyers for the GoT,443 were also present. Mr

Casson and Mr Morrison reminded all that Mechmar Shares in IPTL were charged to SCB HK

and that a receiver had been appointed, and it was acknowledged in Mechmar’s Annual

Report that:

On 3rd February, 2009, SCBHK exercised its lien over the Company’s shares in IPTL and appointed a Receiver & Manager over these said shares. As such, the Company also lost control to govern the on-going legal proceedings against TANESCO and the Government of Tanzania in the capacity of a shareholder of IPTL.444

Meanwhile on 7 July 2010, Datuk Baharuden wrote to ICSID withdrawing the Interpretation

Proceedings on behalf of IPTL.445 On 13 July 2010, TANESCO confirmed that it had no

objection to the discontinuance.446

On 19 July 2010, SCB HK wrote to Mr Jairo, setting out SCB HK’s security interest in the

Mechmar Shares, reiterating its position that sale of the Mechmar Shares could not be made

by Mechmar but by the Receiver.447 On that same day, ICSID informed SCB HK of the

withdrawal of the Interpretation Proceedings by IPTL and invited comments to be received

by 23 July 2010.448 It is SCB HK’s case that it was unaware that Mechmar had initiated the

withdrawal of the Interpretation Proceedings. Mr Casson said that he thought it was the First

PL who had instigated the withdrawal.449 The communication from ICSID to SCB HK indeed

made no mention of who initiated the “discontinuation” of the proceedings. The

Interpretation Proceedings came to an end on 19 August 2010.

The fact that GoT was in discussions to purchase the Mechmar Shares in or around July 2010

cannot be denied. In its letter of 11 August 2010 to the PS MEM, Mechmar referred to the

443 HB/F/004/052-125 at pgs. 070-071: Casson WS, 15 November 2017, para. 69. 444 HB/H/143/1975-2088 at pg. 2076: 2009 Annual Report of Mechmar, 29 April 2010. 445 HB/H/145/2091-2093: Letter from ICSID to IPTL and Tanesco, 8 July 2010. 446 HB/H/146/2094: Letter from Hunton & Williams to ICSID, 13 July 2010. 447 HB/H/150/2100-2101: Letter from SCB HK to the Permanent Secretary of the Ministry of Energy and Minerals, 19 July 2010. 448 HB/H/149/2099: Email from ICSID to Herbert Smith LLP, 19 July 2010. 449 HB/F/004/052-125: Casson WS, 15 November 2017, para. 77.

Page 119: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

112

earlier discussions and stating “as desired by you” (Mr Jairo), submitted its proposal to sell its

stake of 70 % shares together with an assignment of its loan under its Shareholders Loan

Agreement to IPTL to GoT and promising that:

Mechmar Corp will take such steps and execute such documents or may be required to assuage the concerns of the Government of Tanzania in relation to claims of other parties. Mechmar Corp will also give an irrevocable undertaking to co-operate and assist the Government of Tanzania as well as TANESCO in resisting and defending against any such claims and to assert its own claims.450

Mr Jairo then wrote to the Attorney-General and, referring to the specific undertaking made

by Mechmar set out in paragraph 327 above, sought advice to –

draw up a negotiation strategy for GOT's approval to be used in the negotiations with Mechmar Corp for the final buying of the shares.451

GoT was therefore on full notice452 and aware of the interests of SCB HK in the Mechmar

Shares and was clearly intent on acquiring the Mechmar Shares.

With no assurance from Mechmar that it would not proceed with the intended sale, SCB HK

commenced court proceedings in Malaysia on 9 August 2010, to enforce its charge over the

Mechmar Shares. SCB HK’s application for an interim injunction to prevent Mechmar from

selling the Mechmar Shares was granted on 4 October 2010.453 The court also ordered that

the share certificates be delivered to SCB HK within 7 days from date of the order. However,

on 12 October 2010, Mechmar’s solicitors informed SCB HK that Mechmar had sold its shares

in IPTL on 9 September 2010 and delivered the share certificates to the (undisclosed)

purchaser i.e., while the injunction application was pending.454

Following another order of the Malaysian Court (High Court of Malaya) on 19 October

2010,455 Mechmar disclosed that the Mechmar Shares were sold to Piper Link Investments

450 HB/H/154/2220: Letter from Mechmar to the Permanent Secretary of the Ministry of Energy and Minerals, 11 August 2010 (emphasis added). 451 HB/H/155/2221-2222 at pg. 2221: Letter from the Permanent Secretary of the Ministry of Energy and Minerals to the Attorney-General, 1 September 2010. 452 HB/H/150/2100-2101: Letter from SCB HK to the Permanent Secretary of the Ministry of Energy and Minerals, 19 July 2010. 453 HB/D/008/640-642: Interlocutory Injunction Order of the High Court of Malaya in SCB HK v Mechmar, 4 October 2010. 454 HB/H/159/2232: Letter from Teh & Associates to M/s SK Yeoh & Partners, 12 October 2010. 455 HB/D/010/647-654: Ex parte Injunction Order of the High Court of Malaya in SCB HK v Mechmar, 19 October 2010.

Page 120: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

113

Ltd,456 a BVI company that was incorporated only on 2 September 2010. The sale price was

USD 6 million, with USD 1.2 million paid as a deposit.

By letter dated 2 November 2010, Mechmar’s solicitors disclosed a letter from a Mr Issa

Mohamed Al Rawahy, who was said to be the “owner” of Piper Link explaining that the sum

of USD 1.2 million supposed to have been paid as deposit by Piper Link was “paid to my good

friend Mr. Omar Mohamed AlBusaidy of Dubai for introducing us […].”457

SCB HK obtained an order from the High Court of Malaya on 8 November 2010458 appointing

“Receivers” of Mechmar. On the same day, Ms Renju commenced action as Share Receiver of

IPTL in the BVI Court and obtained an ex-parte freezing order459 against Piper Link to deliver

the share certificates to the BVI Court and to take no steps to dispose of the shares pending a

trial of the action. The shares were eventually delivered to the BVI Court by Piper Link.460

Martha Renju obtained a final summary judgment from the BVI Court on 11 April 2011461 and

the court ordered the release of the share certificates to Martha Renju forthwith. On 20 April

2011, Mr Casson informed the PS MEM of the outcome in the BVI Court (enclosing a copy of

the judgement) and copied the same to the Minister for Energy and Minerals and sought an

audience with the PS MEM.462 From these events, the Mechmar Shares reached the hands of

SCB HK in April 2011 and PS MEM and the Minister were so informed.

On 18 May 2012, the Malaysian Court (High Court of Malaya) made a winding up order in

respect of Mechmar to be wound up463 and the receivers earlier appointed were appointed as

liquidators. There could be no doubt that the proper persons to represent Mechmar in any

456 HB/H/165/2249-2258 at pgs. 2251-2258: Letter from Teh & Associates to SK Yeoh & Partners (enclosing the Share Sale Agreement between Mechmar and Piper Link Investment Ltd dated 9 September 2010), 28 October 2010. 457 HB/H/167/2261-2263 at pg. 2262: Letter from Teh & Associates to SK Yeoh & Partners (enclosing Letter from Issa Mohamed Al Rawahy dated 10 September 2010), 2 November 2010. 458 HB/H/168/2264.1-2264.6: Ex parte application to appoint a receiver in SCB HK v Mechmar before the High Court of Malaya, 4 November 2010; HB/D/011/655-659: Ex parte Order appointing a receiver in SCB HK v Mechmar before the High Court of Malaya, 8 November 2010. 459 HB/D/014/665-671: Freezing and Custody Order of the High Court of British Virgin Islands in Renju v Piper Link, 8 November 2010. 460 HB/H/174/2303: Letter from Issa Mohamed Al Rawahy to Mechmar, 1 December 2010. 461 HB/D/015/672-674: BVI proceedings (Renju v Piper Link) Order for Summary Judgment, 11 April 2011. 462 HB/H/181/2317-2320: Letter from SCB HK to the Permanent Secretary of the Ministry of Energy and Minerals, 20 April 2011. 463 HB/D/012/660-661: Order of the High Court of Malaya, 18 May 2012.

Page 121: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

114

transaction relating to the assets of Mechmar would be the Mechmar’s liquidators or persons

authorised by them and no other.464

It should also be recalled that the holder of the other 30% of the shareholding in IPTL was

VIP, who had executed by deed under seal a Charge of Shares over the same to the Security

Agent for the benefit of the secured creditors on 28 June 1997.465 The Security Agent, RHB

Bank, for and on behalf of the successor lender, SCB HK, had on 15 December 2008 appointed

a receiver over the shares pursuant to its power under the Charge of Shares and the

appointment was notified in the register of VIP on 19 December 2008.466

By the VIP-PAP-SPA dated 15 August 2013, VIP purported to have sold to PAP its 30% shares

in IPTL for USD 75 million.467 The VIP-PAP-SPA in its preamble cited a litany of events relating

to VIP’s claim that “SCB”468 had interfered in VIP’s winding-up proceedings which it said had

caused VIP loss and damage amounting to USD 465 million and that both VIP and PAP had

reached “the conclusion that SCB is not a Creditor of IPTL”469 and had therefore decided to

resolve their differences by VIP selling its 30% stake in IPTL to PAP without prejudice to VIP’s

claim against SCB for more than USD 485 million.470

The VIP-PAP- SPA also mentioned that–

(t) PAP has represented and warranted to VIP that it indirectly bought MECHM[A]R's Shares in IPTL from PIPER LINKS INVESTMENTS LIMITED as a bonafide purchaser since the year 2011 and that transaction was not only sanctioned but validated by MECHMAR; and SCBHK being cognizant of that fact, several times signed Agreements with PAP (copies of which PAP exhibited to VIP) attempting to sell to

464 This was also later directed by the High Court of Malaya: HB/D/013/662-664: Directions from the High Court of Malaya, 16 April 2013. 465 HB/C/010/458-473: Charge of Shares between (1) Mechmar Corporation (Malaysia) Berhad, (2) VIP engineering and Marketing Limited and (3) Sime Bank Berhad, 28 June 1997. 466 HB/H/107/1150-1151: (Amended) Notice of appointment of receiver or manager Pursuant to Section 106(1) of the Companies Act 2002, 19 December 2008. 467 HB/H/283/4422-4445: VIP-PAP-SPA dated 15 August 2013 but signed on 19 August 2013. 468 HB/H/283/4422-4445 at pg. 4424 et seq: VIP-PAP-SPA, 15 August 2013. The VIP-PAP SPA defines the term “SCB” in its preamble at para. (g) as – “[…] Standard Chartered Bank Plc., a public company incorporated under the laws of England and Wales, and with its corporate seat in London (UK) and branches located, inter alia, in New York (USA), claimed to have entered into an agreement, through its subsidiary and agent Standard Chartered Bank (Hong Kong) Limited, a company incorporated under the laws of Hong Kong, China, (hereinafter: SCB) […]”. 469 HB/H/283/4422-4445 at pg. 4428: VIP-PAP-SPA, 15 August 2013, preamble para. (u). 470 HB/H/283/4422-4445 at pg. 4428: VIP-PAP-SPA, 15 August 2013, preamble para. (v).

Page 122: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

115

PAP for US$ 75.0million the debt which SCBHK purports that it is owed by IPTL. 471

The VIP-PAP-SPA however seems to acknowledge that the “rightful owner of MECHMAR’S

70% Shares in IPTL” still required to be resolved.472 The VIP-PAP-SPA was signed on behalf

of PAP by Harbinder Singh Sethi as its Managing Director and Manraj Singh Bharya as its

Director. The VIP-PAP-SPA was “[w]itnessed and [e]ndorsed” by the Mr Philip Saliboko, the

Official Receiver and Provisional Liquidator of IPTL. 473

From the documents disclosed, the Tribunal notes that there were two documents that have

traced PAP’s claim to the Mechmar Shares viz:

i. Agreement for Sale of Shares between Piper Link and Mr Sethi dated 21 October

2010;474 and

ii. Deed of Assignment of Shares between Piper Link and PAP dated 21 October 2011.475

Mr Issa Al Rawahy signed both these documents on behalf of Piper Link even though an

injunction against the sale by Mechmar of its IPTL shares to Piper Link was issued on 4

October 2010 by the Malaysian Court (High Court of Malaya)476 and the share certificates

were said to have already been surrendered to the BVI Court and subsequently into the hands

of SCB HK in April 2011 (see paragraphs 332 to 334 above) following the judgment having

been granted against Mechmar.

On any interpretation of these documents and the factual scenario surrounding their

execution, Piper Link could have no title to the Mechmar Shares sold, transferred or assigned

to PAP or Mr Sethi. That said, it could not be suggested that GoT was working in concert with

Mr Sethi or PAP in the VIP-PAP-SPA. Standing alone, this transaction did not directly involve

the GoT and could not be said to have committed any breach of Article 16 of the

Implementation Agreement.

471 HB/H/283/4422-4445 at pg. 4427: VIP-PAP-SPA, 15 August 2013, preamble para. (t) (emphasis in original). 472 HB/H/283/4422-4445 at pg. 4429: VIP-PAP-SPA, 15 August 2013, preamble para. (z) (emphasis in original). 473 HB/H/283/4422-4445 at pgs. 4444-4445: VIP-PAP-SPA, 15 August 2013. 474 HB/H/164/2240-2248: Agreement for Sale of Shares between Piper Links Investments Ltd and Harbinder Singh Sethi, 21 October 2010. 475 HB/H/193/2571-2573: Deed of Assignment between Piper Link and PAP, 21 October 2011. 476 HB/D/008/640-642: Interlocutory Injunction Order of the High Court of Malaya in SCB HK v Mechmar, 4 October 2010.

Page 123: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

116

(iii) The Utamwa J Order477

The Winding up Petition, Misc. Civil Cause No. 49 of 2002 brought by VIP against IPTL, came

before Utamwa J on 3 and 5 September 2013 on the application made by VIP applying for a

withdrawal of the petition seeking winding-up of IPTL in the following terms:

1. That this court marks the petition as duly withdrawn with no order as to costs.

2. That the appointment of the Provisional Liquidator be terminated.

3. That the Provisional Liquidator shall hand over all the affairs of IPTL including the IPTL Power Plant (the plant) to PAP, which has committed to pay off all legitimate Creditors of IPTL and to expand the plant capacity to about 500 MW and sale power to TANESCO at a Tariff of between Us Cents 6 and 8/Unit in the shortest possible time after taking over in the public interests.

4. That parties are free to commence new independent claims in any court with competent jurisdiction against any party should they fail to reach amicable settlement out of court on any issue which arose in IPTL.

5. That the court has taken judicial notice of the agreement between VIP and PAP.478

The application was supported by the provisional liquidator and “Mechmar” as understood

by the court (represented by Mr Lutema, “Lutema/Mechmar”). It should be noted that prior

to this application, the provisional liquidator had made arrangements to pay off some

creditors mostly the lawyers (including those who were representing or represented VIP,

IPTL and Lutema/Mechmar) and other service providers,479 but excluded SCB HK from the

arrangement. The payments were expected to be made from the monies being released from

the Escrow Account held at the BoT.

Based on the written ruling made by Utamwa J, there was general consensus that the

withdrawal of the winding-up petition should be permitted, except that an objection was

raised by Law Associates who said that the release/discharge of the Second PL should be

allowed only after all their fees are paid in full from the Escrow Account and for other

477 HB/H/311/4733-4748: Utamwa J Order, 5 September 2013. 478 HB/H/311/4733-4748 at pg. 4736: Utamwa J Order, 5 September 2013. 479 HB/H/285/4452-4468: Compromise Agreement between the Provisional Liquidator and Uncontested Creditors of IPTL, 20 August 2013.

Page 124: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

117

restraining orders. The court recorded Mechmar’s liquidators as not opposing the

withdrawal but objecting to the other prayers sought, as VIP and PAP had no mandate to

execute the agreement and prayed for the orders.

Utamwa J in his ruling dealt primarily with the objections raised by Law Associates about the

outstanding legal fees owed and the prayer for injunction against BoT, until these fees were

paid, and that the Second PL be restrained from handing over IPTL to PAP. The judge disposed

of the objection on the procedural footing that the application was made under the wrong

rule, was fatal and could not be cured. The court added that the creditors would, in any event,

not be prejudiced as the withdrawal of the winding up would not mean that creditors have

no recourse as on the contrary, the arrangement permitted parties to take action to pursue

their claims.

In relation to the Mechmar’s liquidators’ objection, the court ruled that they lacked locus

standi as their application to intervene was not before the court, and even if it was, no order

having been made permitting their intervention, they could not be heard in relation to

objections to any of the prayers sought.

Having understood the underlying history that led to this application to withdraw the

petition, the Tribunal has sympathy for granting the withdrawal. With the winding-up

petition out of the way, the long-standing matters relating to IPTL would come to an end and

the Facility would then be able to operate. But the real issue lies not with the withdrawal of

the winding-up petition of IPTL. The most disturbing aspect of the decision is that the court

had sanctioned the share transfer and allowed the Facility to be transferred to PAP.

Utamwa J’s decision that the Mechmar’s liquidators had no standing and could not be heard

is inexplicable. There is no clearer principle common to all corporate insolvency law than that

when a company is in liquidation, the liquidator stands in the shoes of the company in

liquidation. This was the law applied to IPTL when it was in liquidation, hence the First PL,

the Liquidator and lastly the Second PL were heard as the voice of IPTL. Yet, Utamwa J seemed

to have ignored Mechmar’s liquidators who had been expressly given the direction by the

Malaysian Court to represent the interest of Mechmar in Tanzania.

Utamwa J was given a copy of the draft order of the prayers sought in advance and

presumably the supporting documents which included the VIP-PAP SPA. He would have

noted that that very document pointed to a dispute as to 70% of the ownership of the shares

Page 125: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

118

in IPTL (see the preamble (s) and (z )) , yet he took “judicial notice” of the same and ordered

that “all the affairs of IPTL including the IPTL Power Plant (the plant) be handed over to PAP”.

By doing so, the court sanctioned the handing over of IPTL and the Facility to PAP. This order

was subsequently interpreted as including the monies held in the Escrow Account, which

were also to be released to PAP.

Quite clearly Utamwa J either failed to read or simply chose to ignore the contents or consider

the implications of such an order. Even a cursory glance at the VIP-PAP-SPA would have

shown that there was another interest that the court ought to have been concerned about,

that is the interests of SCB HK, the successor lenders of the Facility as well as the majority

shareholders, Mechmar’s liquidators.

Unfortunately, Utamwa J denied SCB HK and Mechmar’s liquidators any speaking rights; and

instead purportedly taking “judicial notice” of the VIP-PAP-SPA arrangement and proceeded

to adopt the draft order crafted by the Second PL, VIP, Lutema/Mechmar to open wide the

door for PAP to enter IPTL without restrictions to do whatever PAP had planned. In doing so,

the court effectively shut out all of SCB HK’s rights and interest in the Facility and deprived it

of its right to control IPTL, and its interest in the investment.

In the Tribunal’s view, the Utamwa J Order was quite a thoughtless and reckless act made

without regard to the consequences that would follow. This had the immediate effect of

imperilling SCB HK’s economic rights and control over the Facility and assets assigned to it

by IPTL. SCB HK and Mechmar’s liquidators were left out as if they had no interest and no

contribution to the Facility, save only to witness the subsequent emptying of the Escrow

Account. The Utamwa J Order had gone beyond merely being a wrong judicial decision, rather

it is an egregious error amounting to abject failure of justice.

c. Release of the Escrow Account Funds

The Respondent does not dispute the facts relied upon by the Claimant and how the funds

from the Escrow Account were released and eventually dissipated. It nevertheless relies on

the following to deny any responsibility for the losses allegedly suffered by SCB HK by stating

that:

the decision to settle the Tariff Dispute was triggered by the Utamwa J Order;

Page 126: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

119

once the Tariff Dispute was settled, the relevant Governmental Authorities could not

resist the release of the funds in the Escrow Account;480

the Escrow funds were released to IPTL and it was for IPTL to repay creditors;481

IPTL’s non-payment of SCB HK was beyond GoT’s control;482

it had been advised to satisfy itself that PAP had acquired Mechmar’s shares and was

given an indemnity by IPTL against adverse claims;483

the Attorney-General’s advice that “Any decision to release the Tegeta Escrow Account

is safeguarded, protected and cushioned by the decision of the High Court (Utamwa,

J)”; 484

the funds from the Escrow Account were released to IPTL and therefore there could

not be any expropriation; and

the responsibility for the losses allegedly suffered by the Claimant lies with Mr Sethi

who after receiving the funds failed to settle with SCB HK. Further, that Mr Sethi was

not an agent of the GoT.485

As the Tribunal has earlier remarked, the Utamwa J Order opened the door wide for PAP (and

Mr Sethi its Managing Director) to do whatever it liked, and PAP/Mr Sethi moved in very

quickly.

Mr Sethi convened a “first board [of directors] meeting” on 6 September 2013 and confirmed

himself and a Dr Magesvaran Subramaniam and Mr Manraj Singh Bharya as directors. Mrs

Leong Oi Mooi was removed as the company secretary and replaced with Mr Joseph

Makandege. The minutes also sought to confirm that the transfers of VIP’s 3 shares and

Mechmar’s 7 shares in IPTL be confirmed. In relation to the Mechmar Shares, the minutes

recorded that the transfer was from Mechmar to Piper Link and then on to PAP. The minutes

declared that the effect of the Utamwa J Order was that “The IPTL Power Plant and all other

IPTL properties and assets legally became vested to NOBODY ELSE but PAP.”486

480 Respondent’s PHB, para. 103. 481 Respondent’s PHB, para. 106. 482 Respondent’s PHB, para. 106. 483 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 99; Respondent’s PHB, para. 104. 484 HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 96-98; HB/H/331/4850-4851: Memo from the Attorney General of Tanzania, 2 October 2013 (emphasis in original). 485 Respondent’s PHB, para. 110. 486 HB/H/313/4758-4760 at pg. 4759: Minutes of IPTL Board Meeting, 6 September 2013.

Page 127: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

120

Mr Saliboko (Official Receiver/Provisional Liquidator of IPTL) handed control of IPTL to

PAP/Sethi on 10 September 2013.487

On 13 September 2013,488 IPTL (Mr Sethi) wrote to TANESCO demanding payment of all

outstanding monies owed to IPTL and the release of the funds in the Escrow Account.

On 16 September 2013, PS MEM (then Mr E. C. Maswi) sought advice from the Attorney -

General on PAP’s request “to release the money in the […] Escrow Account to PAP”489 and

received a reply on the same day that as the Utamwa J Order was not appealed against and

there was no injunction against compliance, the Escrow Account should be handed over

subject to resolving the “Invoice Notice” dispute. The Attorney-General also advised that

GoT’s “Guarantee under the PPA should be re-negotiated given the changed circumstances and

the risks that it potentially expose the Government.”490

On 20 September 2013, PS MEM (then Mr E. C. Maswi), informed Mr Sethi that the Escrow

Account would be released subject to “Submission of evidence that you have legally purchased

70% shares of Mechmar in IPTL [..].”491

On 18 September 2013, IPTL (Mr Sethi) wrote to TANESCO appealing for release of the funds

from the Escrow Account and to pend any claims until later.492

On 19 September 2013, the TANESCO board discussed the release and decided to hold the

release until the claims due to TANESCO had been sorted out.493

GoT did indeed set up a team of officials from Ministry of Minerals and Energy, Ministry of

Finance (“MOF”), Attorney General Chambers, TANESCO and the BoT (the “GoT team”). They

487 HB/H/312A/4757.1-4757.51 at pg. 4757.3: Handing over report by the Provisional Liquidator of IPTL, Mr Phillip G. Saliboko: 16.12.2008 to 05.09.2013, 5 September 2013. 488 HB/H/321/4811-4813: Letter from Mr Sethi to Tanesco (attachment 6 to the PAC Report), 13 September 2013. 489 HB/H/323A/4819.1-4819.2 at pg. 4819.1: Letter from the Permanent Secretary of the Ministry of Energy and Minerals to the Attorney General of Tanzania,16 September 2013. 490 HB/H/324/4820-4821: Letter from the Attorney General to the Permanent Secretary of the Ministry of Energy and Minerals, 16 September 2013. 491 HB/H/328/4840-4841: Letter from Mr Maswi to Mr Sethi (attachment 19 to the PAC Report), 20 September 2013. 492 HB/H/325/4822-4833: Letter from IPTL to TANESCO (copied to the Ministry of Energy and Minerals), 18 September 2013. 493 HB/H/326/4834-4835: Minutes of Board of Directors of Tanesco, 19 September 2013.

Page 128: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

121

met for 5 days and submitted a report on 30 September 2013 to the Permanent Secretary

Treasury.494 In its report the team observed that:

PAP had yet to register its ownership of the VIP shares with BRELA, because PAP had

yet to pay for the same in full;

there was a potential claim by SCB HK;

SCB HK was not a party to the “Compromise Agreement”;495

there were pending actions commenced by IPTL Administrator Receiver, Martha

Renju in Commercial Case No. 123 of 2013496 seeking declaration of SCB HK’s interest

and injunction restraining releasing assets in the Escrow Account and seeking control

of the IPTL Power plant;

SCB HK had no plausible claims;

Martha Renju’s documents were executed outside Tanzania and would be

inadmissible as evidence; and

IPTL (Mr Sethi) had agreed to consider a 10-15% discount off TANESCO’s outstanding

debts.

Based on these observations, the GoT team took the view that the SCB HK and Martha Renju’s

claims were unlikely to succeed. The GoT team’s concerns were focused only on any possible

exposure to GoT when the monies were released to PAP-controlled IPTL. They concluded

with the recommendation that GoT, BoT and TANESCO be freed from any obligation after the

release of the Escrow Account and to re-negotiate the PPA on “PAP’s commitment in terms [of]

generation and pricing […].”497

The GoT team that was tasked to consider the validity of the sale of the Mechmar’s 70%

shares to PAP, simply stated that the “Share Purchase Agreement of [the] IPTL Shares, (30 per

cent of the VIP and 70 per cent of Mechmar) has been executed.”498 Attached to the report was

494 HB/H/330/4849-4849.167: Letter from Mr Likwelile to the Permanent Secretary of the Ministry of Energy and Minerals attaching Report on the Delivery of Funds in the Tegeta Escrow Account (with annexes) (“Letter enclosing Delivery of Funds Report”), 30 September 2013. 495 HB/H/285/4452-4468: Compromise Agreement between the Provisional Liquidator and Uncontested Creditors of IPTL, 20 August 2013. 496 HB/H/315/4775-4785: Plaint by Martha Renju in Commercial Case 123 of 2013, 6 September 2013. 497 HB/H/330/4849-4849.167 at pg. 4849.24: Letter enclosing Delivery of Funds Report, 30 September 2013. 498 HB/H/330/4849-4849.167 at pg. 4849.22: Letter enclosing Delivery of Funds Report, 30 September 2013.

Page 129: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

122

a copy of the Deed of Assignment of Shares dated 21 October 2011.499 The report made no

mention of the fact that the Malaysian Court had prior to that date issued several orders

relating to Mechmar, particularly against the disposal of its 70% shares in IPTL. These orders

included an injunction500 (which SCB HK had forwarded to PS MEM on 14 October 2010)501

and an order appointing “Receivers” made on 8 November 2010.502 It was also well known

that Mechmar was eventually ordered to be wound up and liquidators were appointed by the

Malaysian Court. The orders and court actions in the BVI Court were not mentioned despite

the fact that on 20 April 2011,503 PS MEM was informed of the BVI Court judgment of 11 April

2011 that had ordered the Mechmar Shares be returned to SCB HK.

The GoT team had no reason to disregard the orders made by the Malaysian Court in relation

to Mechmar, a Malaysian company, but instead took the view that they were inadmissible in

Tanzania. This is an incomprehensible position to take. The ability of Mechmar (in

liquidation) to execute a sale of its assets must necessarily be dependent upon its ability

under Malaysian law and the directions of the Malaysian courts. As regards the BVI Court

ruling, the GoT team’s silence is indeed baffling.

The team’s confidence that SCB HK had no plausible claim is clearly misplaced. Unfortunately,

the GoT team was not alone. The Attorney-General504 too took a similarly disdaining view in

much stronger terms:

On the issue of indemnity against futuristic claims against the Government, I do earnestly think, that is farfetched and illusory. Talking about on-going wrangles, none of them will negate what has already been decided by the High Court (Utamwa J). I am thus of the firm view that the only issue of substance relates only to funds in ’permitted investment.’ This is the issue given that TANESCO invoices and other claims are out of the way.

499 HB/H/330/4849-4849.167 at pg. 4849.147: Letter enclosing Delivery of Funds Report, (Refer the Annexed Deed of Assignment of Shares dated 21 October 2011), 30 September 2013. 500 HB/D/008/640-642: Interlocutory Injunction Order of the High Court of Malaya in SCB HK v Mechmar, 4 October 2010. 501 HB/H/161/2234-2237 at pg. 2234: Letter from SCB HK to the Permanent Secretary of the Ministry of Energy and Minerals, 14 October 2010. 502 HB/D/011/655-659: Ex parte Order appointing a receiver in SCB HK v Mechmar before the High Court of Malaya, 8 November 2010. 503 HB/H/181/2317-2320: Letter from SCB HK to the Permanent Secretary of the Ministry of Energy and Minerals, 20 April 2011. 504 HB/H/331/4850-4851: Memo from the Attorney General of Tanzania, 2 October 2013 (emphasis in original).

Page 130: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

123

Strangely, the final push to release the Escrow Account seems to have come from the

Attorney-General, who saw this as an opportunity to negotiate out of its guarantee or take

unilateral action. In his words “[t]he soonest this is done the best” since–

The government should not be seen to be waffling in implementing what the court decided. This decision saves wider public interests that the never-ending wrangles over funds in escrow account. Any decision to release the Tegeta Escrow Account is safeguarded, protected and cushioned by the decision of the High Court (Utamwa, J). There is no obstruction or injunction to deal with the account as of now.

[…]

The Government should use this golden opportunity to disentangle herself from unwarranted litigation. The High Court has given us a summons of relief. We should act now instead of acting as a devil's Advocate. Time is of essence.

The Attorney-General’s advice taken on its face urged the immediate “[t]ime is of essence”

direction for the release of the Escrow Account, dismissing SCB HK’s interest as totally

“illusory”. He also ignored the question of whether PAP owned Mechmar’s 70% shares in

IPTL. He was content to hide under the cover of the Utamwa J Order and to do so before

anything that changed this situation occurred.

The Tribunal could understand why GoT saw the “golden opportunity” to extricate itself from

what they perceived as a difficult situation and a problematic project which it had guaranteed

and committed to but doing so by ignoring the rights of SCB HK and imperilling its investment

must necessarily entail consequences. With Utamwa J’s Order opening the door, and the

Attorney-General pointing the way that it could hide behind that door, there was no longer

any impediment against the PAP-controlled IPTL from putting its hands on the funds.

The Attorney-General had also assured GoT that the “corporate veil” of IPTL could justify its

action. In this regard, the Attorney-General probably thought that so long as the escrow funds

were released to “IPTL”, regardless who was in control, GoT would be free from any adverse

claims by other creditors, in particular SCB HK. This same line was followed by GoT’s counsel

in this arbitration.

The Attorney-General’s advice and view was unfortunate and had emboldened the other GoT

officials to hasten the release of the funds, despite a pending application for stay of execution

Page 131: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

124

of the Utamwa J Order by SCB HK,505 for order against preventing Martha Renju from taking

possession of IPTL assets in Commercial Case No 100 of 2013506 and for an order not to

release funds from the Escrow Account in Commercial Case 123 of 2013 by Martha Renju.507

Following further negotiations, TANESCO, IPTL (PAP controlled) and GoT (through PS MEM)

agreed to release the full sum in the Escrow Account and to pay a negotiated discounted top-

up amount of USD 45,485,719.97 or US$ 79,049,724.50.508

In the Tribunal’s view, the steps which GoT took, as set out in paragraphs 358 to 373 above,

were taken to minimise its exposure to possible adverse claims. None of them could justify

depriving SCB HK of its investment. The actions of GoT officials facilitated the transfer of

control in IPTL to PAP, viz. by the Second PL entering into the Compromise Agreement,

endorsing the VIP-PAP-SPA, and appearing before Utamwa J to consent to the adoption of the

draft order presented by VIP and PAP. The Attorney-General then, relying on Utamwa J’s

“judicial notice” of the VIP-PAP-SPA, saw the “golden opportunity” to extricate itself from the

guarantees and assurances given to the Project and directed that the Escrow Account be

released “soonest.” The end result is that the Escrow Account was emptied in haste and paid

to PAP-controlled IPTL.

GoT having facilitated the taking-over of IPTL by PAP cannot now be permitted to say that

the release of the funds to IPTL discharges GoT and TANESCO’s responsibility. GoT knew well

that the funds did not go into IPTL but into the account of PAP. This is evidenced by the very

terms of the “AGREEMENT FOR DELIVERY OF FUNDS TO INDEPENDENT POWER TANZANIA

LIMITED,”509 where the funds were directed to be sent to PAP’s bank account and not to IPTL:

Beneficiary Name: INDEPENDENT POWER TANZANIA LIMITED C/O PAN AFRICA POWER SOLUTIONS (T) LIMITED

Bank Name: UBL BANK (TANZANIA) LTD […]

Account Number: TZS-010-0016-6 Account Number: USD-060-0016-1

505 This was indicated in the GoT team’s Report at – HB/H/330/4849-4849.167 at pg. 4849.15: Letter enclosing Delivery of Funds Report, para. 4.1.2. 506 HB/H/317/4789-4799: Application by Ms Martha Renju in Miscellaneous Commercial Case No. 100 of 2013, 11 September 2013. 507 HB/H/315/4775-4785: Plaint by Martha Renju in Commercial Case 123 of 2013, 6 September 2013. 508 HB/H/338/4877-4882: Agreement between GoT and IPTL for delivery of escrow funds, 21 October 2013. 509 HB/H/338/4877-4882 at pg. 4878: Agreement between GoT and IPTL for delivery of escrow funds, 21 October 2013.

Page 132: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

125

Swift Code: UNILTZTZ

Mr Sethi eventually directed BoT on 28 November 2013510 to transfer the monies from the

Escrow Account directly to the PAP Account in Stanbic Bank–

Account Name: Pan Africa Power Solutions (T) Ltd TZS account number: 9120000125294 USD account number: 9120000125324 Swift Code SBICTZTX

In that same letter, he asked that all the Treasury Bills held in the BoT Escrow Account be

transferred to “PAN AFRICA POWER SOLUTIONS (T) LTD c/o IPTL”.

The fact that GoT was fully mindful that by recognising that paying to a PAP-controlled IPTL

GoT would be subject to the potential exposure to SCB HK is reflected in the Deed of

Indemnity executed by PAP-controlled IPTL in favour of GoT as condition precedent for the

release, which in part started unequivocally in its preamble that –

The Government and the Escrow Agent being cautious of the pending and potential disputes against IPTL in connection with the escrow monies including the remnants of the Standard Chartered Hong Kong's claims pending in Courts, are minded to have the Government and the Escrow Agent indemnified by IPTL against all present and future claims, charges, actions, proceedings that may arise against or may be submitted to the Government consequent upon the release and payment of the funds in the Tegeta Escrow Account to IPTL.511

Having accepted this risk and the mitigation thereof offered by the PAP-controlled IPTL

indemnity, GoT should not now be heard to say that that it has no responsibility, merely by

saying that the monies were paid to IPTL and not PAP. The transfer to PAP’s account was

done with the full knowledge of GoT, TANESCO and the BoT. GoT cannot deny that it knew

that the monies did not reach IPTL, but PAP’s account. To suggest that GoT did not obtain

direct or indirect benefit from the arrangement ignores the fact that GoT had, through this

scheme, extricated itself (or so it believed) from its obligations under the Implementation

Agreement and, at the same time, its national electricity grid managed by TANESCO was then

able to deal with the PAP-controlled IPTL to resolve their claims to its advantage.

510 Exhibit C-414: Letter from Mr. Sethi to the Bank of Tanzania, 28 November 2013 (submitted at the Hearing). 511 HB/H/340/4884-4887 at pg. 4886: Letter from IPTL to the Permanent Secretary of the Ministry of Energy and Minerals and to the Governor of the Bank of Tanzania, attaching a “Deed of Indemnity”, 28 October 2013.

Page 133: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

126

(3) Tribunal’s Decision on Expropriation

The Tribunal therefore finds that GoT, through MEM, TANESCO, Utamwa J, the Attorney-

General and BoT, facilitated the improper transfer of control of IPTL to PAP and/or Mr Sethi,

without due regard to the interests of IPTL and SCB HK as successor lender and assignee

pursuant to the Implementation Agreement. Utamwa J most injudiciously decided to “take

judicial notice” of the illicit and fictitious sale of Mechmar Shares in IPTL and recklessly

ordered IPTL and the Power Plant to be handed to PAP. GoT through its agencies, as stated

above, further aided and abetted the improper release of the Escrow Account, disregarding

the legitimate interest of IPTL and SCB HK as successor lender and assignee, by enabling PAP

and Sethi to receive the full release of the monies and assets in the Escrow Account thereby

depriving IPTL and SCB HK of the right to properly exercise their rights of control and

economic benefits of their investment. Such acts are clear acts of expropriation expressly

prohibited, and to which GoT had solemnly promised to abide by under Article 16 of the

Implementation Agreement. The Tribunal therefore find that GoT is in breach of Article 16.2

of the Implementation Agreement.

B. DISCRIMINATION CLAIM UNDER ARTICLE 16.1 OF THE IMPLEMENTATION AGREEMENT

The basis of the Claimant’s discrimination claim is Article 16.1 of the Implementation

Agreement, which provides as follows:

The GOT shall not take any discriminatory action which materially and adversely affects the Project or the performance of [IPTL's] obligations or the enjoyment of its rights or the interests of the Investors under the Security Package or expropriate or, except as hereinafter provided, acquire the Facility or [IPTL], whether in whole or in part. Nothing in the foregoing shall apply to any actions taken by the GOT, TANESCO, or any Governmental Authority pursuant to their respective rights and obligations arising under this Agreement, the Power Purchase Agreement and the other documents comprising the Security Package.512

The Claimant claims that the Respondent breached Article 16.1 of the Implementation

Agreement in:

512 HB/C/005/192-267: Unsigned copy of Implementation Agreement (including Schedules), 8 June 1995.

Page 134: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

127

“favouring PAP and VIP (IPTL's minority shareholder)”, which are “two Tanzanian

entities […] over Mechmar (IPTL's majority shareholder)” and the Claimant which was

“(IPTL's lender and secured creditor)”;513 and

“favouring IPTL when it wrongly came into Tanzanian hands, while mistreating IPTL

when it was legitimately owned/controlled by foreign entities”.514

The Claimant argues that the Respondent’s discriminatory actions materially and adversely

affected the Project and performance of IPTL’s obligations, the enjoyment of IPTL’s rights and

the Investor’s interests under the Security Package. Further, that those actions of the

Respondent led to IPTL’s inability to discharge the PPA Award and IPTL could not

consequently earn and apply income that would otherwise be earned pursuant to the PPA

from September 2013, which in turn could then be applied to reduce its loan outstanding

under the Facility Agreement which, as of August 2018, stood at over USD 187 million.515

The Respondent asserts that the Claimant’s claim is devoid of merit. It submits that the

Claimant’s case does not meet the requirements of Article 16.1516 arguing that:

only IPTL can bring a claim under Article 16.1;

any purported discriminatory action must be between companies with similar

projects;

the discriminatory action must issue from the “Government” and not any other

“Governmental Authority”; 517

a discriminatory intent is required, which is absent in the present case;518 and

there was no evidence that any of the alleged acts caused material and adverse effects

on IPTL.

513 Claimant’s PHB, para. 174. 514 Claimant’s PHB, para. 174. 515 Claimant’s PHB, para. 175. 516 Respondent’s PHB, paras. 131-133. 517 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 255. 518 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 256.

Page 135: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

128

(1) Is SCB HK Entitled to Bring a Discrimination Claim under Article 16.1 of the Implementation Agreement?

a. Parties’ Submissions

The Respondent maintains that the undertaking against discrimination given under Article

16.1 is addressed to IPTL, and IPTL is, as such, the only party that can benefit from the

protection given. The Respondent argues that this position is confirmed by Article 24.6 of the

Implementation Agreement, which excludes third party beneficiaries, and Article 16.1 is not

among the exceptions stated in the provision.519

Article 24.6 of the Implementation Agreement reads:

24.6 No Third Party Beneficiaries

This Agreement shall not confer any right of suit or action whatsoever on any third party, except for the specific rights granted to the Lenders pursuant to Articles 15.2, 18.2 and 19.4. 520

The Respondent states that the Claimant cannot rely on the second part of Article 16.1 of the

Implementation Agreement, including the wording “Investors under the Security Package”, as

only IPTL could bring an action and investors cannot bring an action in their own name. Any

other approach would be an excessively wide interpretation of the meaning of discrimination

in this provision. Furthermore, even if investors could bring an action based on this wording,

the Claimant could still not bring an action as it is not an investor or shareholder of IPTL and

does not have standing to bring an action on behalf of IPTL. The Respondent submits that

only IPTL can bring a claim for breaches under Article 16.1 of the Implementation Agreement

related to the Project which are contended for by the Claimant, including the performance of

IPTL’s obligations, the enjoyment of IPTL’s rights or the investors interests under the Security

Package.521

b. Tribunal’s Analysis

Consistent with the Tribunal’s finding that the Claimant is the lawful assignee under Article

15.2 of the Implementation Agreement and has title and interest to pursue its claims against

GoT for any breach of the Implementation Agreement in its own name [see paragraph 172

519 Respondent’s PHB, para. 132. 520 HB/C/005/192-267 at pg. 250: Unsigned copy of Implementation Agreement (including Schedules), 8 June 1995 (emphasis in original). 521 Respondent’s PHB, para. 133.

Page 136: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

129

above], the Respondent’s argument that the Claimant cannot claim protection against

discrimination must fail.

The Respondent’s argument reads into Article 16.1 of the Implementation Agreement that

any discriminatory action must be directed against IPTL. Article 16.1 of the Implementation

Agreement is not limited in this way. The prohibition concerns actions of the GoT that could

affect or impact “the Project or the performance of [IPTL's] obligations or […] the interests of

the Investors under the Security Package.” This must therefore mean that persons apart from

IPTL, viz. IPTL’s actual shareholders, lenders and investors under the Security Package whose

interests are materially and adversely affected by GoT’s actions, are included.

In any event, Article 24.6 of the Implementation Agreement itself specifically creates the

exception for “specific rights granted to the Lenders pursuant to Articles 15.2, […]” which

means that Lenders are not the “third party” intended under it and as such are not prohibited

from exercising their specific security rights created under the Implementation Agreement,

of which Article 16.1 of the Implementation Agreement is one. The Tribunal therefore finds

that the Claimant as assignee and lender, is entitled to seek the benefit of GoT’s undertaking

against discrimination specifically created under Article 16.1 of the Implementation

Agreement.

(2) Does the Discriminatory Action Require a Comparator?

a. Parties’ Submissions

The Respondent’s argument is that to sustain an action for discrimination, a comparison with

an entity discriminated against is necessary and that this approach is confirmed by

contractual interpretation and international law, which provides that such comparison must

be done with other similar projects or categories or companies in “like circumstances.”522 The

Respondent submits that on a plain analysis of the ordinary meaning of Article 16.1 of the

Implementation Agreement, the discriminatory action intended is not to cover discrimination

that as between shareholders, lenders or investors, but rather between companies with

similar projects or similar circumstances.523

522 Respondent’s PHB, para. 134; Respondent’s Reply PHB, para. 88; HB/A/003/144-370 at pgs. 291-297: Respondent’s Counter-Memorial; HB/A/005/604-827 at pgs. 767-771: Respondent’s Rejoinder. 523 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 253.

Page 137: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

130

The Respondent says that the Claimant’s theory that the Respondent favoured VIP and PAP

over Mechmar and the Claimant, and favoured IPTL when under PAP’s control compared to

IPTL under Mechmar’ s control, is not within the scope of the discrimination contemplated in

Article 16.1 of the Implementation Agreement.

Further, the Respondent contends, such discrimination must mean the imposition of

obligations, conditions or standards that are unduly and materially more onerous than those

persons in like circumstances. In support of this, the Respondent refers to (i) the World

Bank’s Model Implementation Agreement which contains a similar clause to Article 16.1 of

the Implementation Agreement; (ii) other implementation agreements; and (iii)

international investment case law generally, including LG&E Energy Corp and others v

Argentina,524 wherein the tribunal decided that for a measure to be discriminatory it must be

inter alia “that is not taken under similar circumstances against another national”.525

The Claimant’s position is that there is no such qualification in Article 16.1 of the

Implementation Agreement that the discriminatory action must be directed against IPTL

itself or that it must be between similar projects, and that there is no requirement that

discrimination must relate to IPTL vis-à-vis competitors. It submits that the only qualification

is that the discriminatory action must materially and adversely affect certain matters relating

to IPTL and the Project, which shows that the objective of the provision is to protect IPTL.526

Further, the Claimant argues that the description of “discrimination” in other implementation

agreements or the World Bank’s Model Implementation Agreement is not relevant to the

inquiry of what discrimination means in the Implementation Agreement, as both contain

inclusive, rather than exhaustive descriptions of discriminatory action.

b. Tribunal’s Analysis

The Tribunal agrees with the Respondent that in order for conduct to be considered

discriminatory, there must be a comparator that permits comparison against which the

suspect conduct can be measured. The conduct that is discriminatory is a separate matter

from the consequences of such conduct. Thus, discrimination ordinarily requires that another

524 HB/G/062/6556-6641: LG&E Energy Corp and others v Argentine Republic, ICSID Case No. ARB/02/1, Decision on Liability, 3 October 2006. 525 HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 253-254. 526 Claimant’s PHB, para. 179.

Page 138: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

131

person, in like circumstances, has been given more favourable treatment. If IPTL as a

company was treated less favourably than other companies in like circumstances during that

same period, such would generally constitute discrimination. In LG&E Energy Corp and others

v Argentina,527 a dispute arose out of a bilateral investment treaty between the United States

and Argentina, which provided that "[n]either Party shall in any way impair by arbitrary or

discriminatory measures the management, operation, maintenance, use, enjoyment, acquisition,

expansion, or disposal of investments."528 The claimants in that case had complained that they

“received treatment different from that accorded to similarly situated public utilities, including

electricity and water distribution companies.”529

The Tribunal does not agree with the Claimant’s suggestion that “discrimination” in the

context of this Implementation Agreement, requires only the qualification that the

discriminatory action “materially and adversely affects the Project or the performance of the

Company's obligations or the enjoyment of its rights or the interests of the Investors under the

Security Package”. In other words, according to the Claimant, there need not be a comparative

disadvantage, so long as it could be shown that GoT had taken action which could cause IPTL

(viz. its assigns as we have so found) to suffer “materially and adversely”. This would collapse

the discriminatory conduct and its effects and is not warranted on a reading of the provision.

In the Tribunal’s view, the requirement for “material and adverse” effect is a separate

requirement of liability. The action taken by GoT must first be discriminatory, and only if such

discriminatory action gives rise to material and adverse effect could it sustain a cause for

breach of the undertaking.

As observed earlier, Article 16.1 of the Implementation Agreement extends its application to

all persons who might be affected by actions of GoT in their enjoyment of the rights and

interest in the Project or IPTL or the Security Package. The Tribunal does not therefore accept

the Respondent’s argument that the discrimination under Article 16.1 of the Implementation

Agreement is limited to IPTL alone. In any event, the manner of treatment meted out by GoT

to IPTL when it was under the control of foreign entities (IPTL’s shareholders and the

527 HB/G/062/6556-6641: LG&E Energy Corp and others v Argentine Republic, ICSID Case No. ARB/02/1, Decision on Liability, 3 October 2006. 528 HB/G/062/6556-6641: LG&E Energy Corp and others v Argentine Republic, ICSID Case No. ARB/02/1, Decision on Liability, 3 October 2006, para. 140. 529 HB/G/062/6556-6641: LG&E Energy Corp and others v Argentine Republic, ICSID Case No. ARB/02/1, Decision on Liability, 3 October 2006, para. 141.

Page 139: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

132

Claimant) and when it became a PAP-controlled IPTL also needs to be considered.530 The

primary purpose of GoT giving the undertaking against discrimination was to assure the

Investor (including the Lenders) that their interest would not be affected by any

discriminatory action taken by GoT. How GoT treated IPTL before and after the change of

control, are the best signs of whether GoT had complied with its undertaking not to take

discriminatory action which could adversely affect the interests of the Project, the

performance of the Company, the Investor and the Lenders.

(3) Meaning of the Reference to “GOT” in Article 16.1 of the Implementation Agreement

a. Parties’ Submissions

The Respondent argues that Article 16.1 of the Implementation Agreement contemplates

only acts of the Respondent as it refers to “GOT” and not the actions of any other

“Governmental Authority.”531

The Implementation Agreement at Article 1 provides:

“Governmental Authority" bears the meaning attributable thereto in the Power Purchase Agreement.

The PPA provides the definition of “Governmental Authority” at Article 1.1 as: 532

“Governmental Authority": Any state, municipal or local government or regulatory department, body, political subdivision, commission, instrumentality, agency, ministry, court, judicial or administrative body, taxing authority or other relevant authority having jurisdiction over either Party, the Facility.

The Respondent therefore argues that the Claimant’s complaint against the acts of the

Tanzanian Courts and First PL and Second PL cannot be attributed to the GoT.533

The Claimant’s response to this is that the definition of “Government of Tanzania” is narrower

than “Governmental Authority” as defined in Article 1.1 of the PPA and the issue is which

530 See paras. 412, 423 and 427 to 429 below. 531 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 255. 532 HB/C/002/013-128 at pg. 024: Power Purchase Agreement, 26 May 1995 (emphasis in original). 533 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 255.

Page 140: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

133

elements of “Governmental Authority” fall within the meaning of “GOT”.534 It says that the

ordinary meaning of the term “government’” would include acts by the judicial, executive and

legislative branches of the Respondent, including acts by the Tanzanian Courts, First PL,

Second PL, other government officials involved in the release of the funds in the Escrow

Account.535 Alternatively, the Claimant submits that even if the words “Government of the

United Republic of Tanzania” do not include the judicial branch, they should at the minimum

cover the executive branch of the national government and this is clear from the references

in the Implementation Agreement to the “GOT” such as Article XI536 (granting immigration

approvals), Article XII537 (controlling and directing security forces), Article 18.4538

(confirming the grant of tax exemptions) and Article 24.7539 (waiving sovereign immunity).

The Claimant submits that this is relevant as the key discriminatory actions were carried out

by executive authorities.540

b. Tribunal’s Analysis

The Tribunal has little hesitation in disagreeing with the position taken on behalf of the

Respondent. The term “Government” is not specifically defined in the Implementation

Agreement, and it is generally understood that the term is the embodiment of the entire

administration of a State and has generally the authority to act on behalf of the State and not

limited to constitutional arms of government, viz. the legislature, the executive and the

judiciary (see discussion earlier in paragraphs 280 to 281). The Implementation Agreement

was in fact signed by the GoT “acting through its Ministry of Water, Energy and Minerals”. It

was then signed on its behalf by the Principal Secretary of the “Ministry of Water, Energy and

Minerals”. By using the term “Governmental Authority” and ascribing to it the specific meaning

given to it in the PPA, the Government has expressly intended to act through the

Governmental Authority so defined, which include the actions of the Office of the

Administrator General and Official Receiver, “court”, and “judicial” arms of the Government.

Their actions or inactions must be attributable to the GoT.

534 HB/A/004/371-603: Claimant’s Reply, para. 512. 535 HB/A/004/371-603: Claimant’s Reply, paras. 511-514. 536 HB/C/005/192-267 at pg. 212: Unsigned copy of Implementation Agreement (including Schedules), 8 June 1995. 537 HB/C/005/192-267 at pg. 213: Unsigned copy of Implementation Agreement (including Schedules), 8 June 1995. 538 HB/C/005/192-267 at pg. 232: Unsigned copy of Implementation Agreement (including Schedules), 8 June 1995. 539 HB/C/005/192-267 at pg. 250: Unsigned copy of Implementation Agreement (including Schedules), 8 June 1995. 540 HB/A/004/371-603: Claimant’s Reply, paras. 515-516.

Page 141: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

134

(4) Intention to Discriminate

a. Parties’ Submissions

The Respondent has also suggested that for GoT’s actions to be considered discriminatory, it

must be shown to have been done with such intent. It referred to the LG&E Energy Corp and

Others v Argentina541 where the tribunal stated at paragraph 146: 542

[I]n order to establish when a measure is discriminatory, there must be (i) an intentional treatment (ii) in favor of a national (iii) against a foreign investor, and (iv) that is not taken under similar circumstances against another national.

The Claimant, on the other hand, submits that Article 16.1 of the Implementation Agreement

does not require subjective intent to discriminate. It only requires that the action be

discriminatory. It points out that the element of intent was held by some other tribunals as

not to be essential.543 As to the Respondent’s reliance on LG&E Energy Corp and others v

Argentina, the Claimant points out that the tribunal there had preceded the portion quoted

by the Respondent, at paragraph 146, by stating that discriminatory effect may also

constitute a discriminatory measure viz.:

146. In the context of investment treaties, and the obligation thereunder not to discriminate against foreign investors, a measure is considered discriminatory if the intent of the measure is to discriminate or if the measure has a discriminatory effect.544

The Claimant nevertheless asserts that GoT’s actions were in fact intentional as it knew that

the Claimant was a secured lender and that the Escrow Account should have been used to pay

the PPA Award and reduce IPTL’s debt, but wrongfully preferred PAP and VIP’s interests.545

541 HB/G/062/6556-6641: LG&E Energy Corp and others v Argentine Republic, ICSID Case No. ARB/02/1, Decision on Liability, 3 October 2006, para. 146. 542 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 256 (Referring to LG&E Energy Corp and others v Argentine Republic, ICSID Case No. ARB/02/1, Decision on Liability, 3 October 2006, para. 146 in footnote - emphasis in original). 543 HB/A/004/371-603: Claimant’s Reply, para. 524; HB/G/035/3377-3453: Occidental Exploration and Production Company v Republic of Ecuador, LCIA Case No. UN3467 (Award), 1 July 2014, para. 177; (cited but not exhibited) Siemens A.G. v Argentine Republic, ICSID Case No. ARB/02/8, Award, 17 January 2007, para. 321; HB/G/038/3732-3803: Eastern Sugar B.V. (Netherlands) v Czech Republic, SCC Case No. 088/2004 (Partial Award), 27 March 2007, para. 338. 544 HB/G/062/6556-6641: LG&E Energy Corp and others v Argentine Republic, ICSID Case No. ARB/02/1, Decision on Liability, 3 October 2006, para. 146. 545 HB/A/004/371-603: Claimant’s Reply, paras. 523-527.

Page 142: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

135

b. Tribunal’s Analysis

There appears weak support from other tribunals for the proposition that intention to

disfavour or discriminate is an essential element to establish less favourable treatment or

discrimination. The tribunal in LG&E Energy Corp and others v Argentina, as correctly pointed

out by the Claimant, did not take the position that intention is an essential element to

discriminate. Other cases, suggest that “intent is not necessarily decisive”546 and in one case,

the absence of intention to disfavour a party but “to favor newcomers and preserve [their]

jobs[…], the result is still […] a violation […] [if] the effect […] was a discriminatory and

unreasonable measure ”.547 In another case, an act done not “with the intent of discriminating

against” another is discriminatory so long the party seeking such redress has “received less

favourable treatment” than that accorded to another.548

The Tribunal takes the view that Article 16.1 of the Implementation Agreement does not

support a requirement of intent; what is addressed is the discriminatory action and its

consequences. Intent is a distinct element and one that is burdensome to prove and should

not be readily implied since it would reduce the scope of protection without explicit mention.

The question of whether it is a breach of the Respondent’s undertaking requires a

consideration of the impact each of the alleged discriminatory actions. This requires a factual

inquiry of the four specific complaints raised by the Claimant which it says are discriminatory

actions by applying the aforesaid tests. The Tribunal will consider each of these complaints

and see if any of these are discriminatory actions, and, if so, consider whether they “materially

and adversely affects the Project or the performance of the Company's obligations or the

enjoyment of its rights or the interests of the Investors under the Security Package.”

(5) The Factual Basis of the Discrimination Claim: Alleged Discriminatory Actions

The Claimant alleges four categories of discriminatory actions. The facts of each of them have

been narrated in the earlier discussion on the Claimant’s claim for expropriation. The

Tribunal will in this section make brief reference to the same for the purpose of considering

546 HB/G/074/7626-7708: S. D. Myers, Inc v Government of Canada, NAFTA/UNCITRAL, Partial Award, 13 November 2000, para. 254. 547 HB/G/038/3732-3803: Eastern Sugar B.V. (Netherlands) v Czech Republic, SCC Case No. 088/2004 (Partial Award), 27 March 2007, para. 338. 548 HB/G/035/3377-3453: Occidental Exploration and Production Company v Republic of Ecuador, LCIA Case No. UN3467 (Award), 1 July 2004, para. 177.

Page 143: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

136

this issue of whether they amount to discriminatory actions and if so, the material impact on

the Project, IPTL and the Claimant.

a. The Respondent Frustrated the Pursuit by IPTL of the Interpretation Proceedings549

(i) Parties’ Submissions

The Claimant alleges that Oriyo J and the First PL discriminated against the Claimant and

Mechmar in favour of VIP (which is a Tanzanian entity) by taking steps which frustrated the

continuation of the Interpretation Proceedings. More specifically, this relates to Oriyo J’s

decision of 16 December 2008 to dismiss IPTL’s stay application as being “[…] redundant”

and stated that “[i]t has become obsolete; it does not serve any useful purpose.”550

The Claimant says that the Interpretation Proceedings were supported by Mechmar but

opposed by VIP. By the order refusing the stay application and appointing the First PL, Oriyo

J discriminated against Mechmar as she vested the power over IPTL to the First PL, who acted

in accordance with VIP’s wishes and declined to continue the Interpretation Proceedings.

According to the Claimant, the inability to continue the Interpretation Proceedings materially

and adversely affected IPTL's enjoyment of its rights under the PPA as they prevented the

Tariff Dispute from being resolved, which consequently prevented payments to be made

under the PPA and thus preventing IPTL's debts from being reduced.551

The Respondent however argues that the First PL acted in his capacity as provisional

liquidator of the company and as such his actions cannot be attributed to the Respondent.

Furthermore, the withdrawal of the Interpretation Proceedings was initiated by Mechmar.

The Respondent adds that the Interpretation Proceedings were not “easy straightforward”

proceedings and would not have “quickly resolved” the Tariff Dispute and as such no material

and adverse effect could be derived from the discontinuation of the Interpretation

Proceedings. In its view, the First PL had taken a rational decision by balancing the cost of the

proceedings and the risks of an unsuccessful outcome.552

549 See paras. 292 to 308 above. 550 HB/H/104/1122-1138 at pgs. 1127-1128: High Court of Tanzania's Appointment of PL, 16 December 2008. 551 Claimant’s PHB, para. 187. 552 Respondent’s Reply PHB, para. 92.

Page 144: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

137

(ii) Tribunal’s Analysis

The Tribunal recalls its discussion on Oriyo J’s decision [see paragraphs 299 to 303 above]

and its observations that the judge’s decision was unclear as to what had convinced her that

the stay application could serve no useful purpose, and she could have on a date fixed for the

hearing of an application for a stay of those proceedings; instead, she proceeded to make a

substantive order appointing a provisional liquidator, relying on affidavits filed by VIP some

five years earlier, and to hold that an immediate appointment would be necessary and in the

public interest without calling upon the parties involved to be heard substantively. Oriyo J

tried to justify her reliance on those affidavits by saying that -

For reasons not on record it is apparent that the first and second respondents did not file any counter affidavits to oppose the petition for winding up IPTL. […]

As stated earlier, the 1st and 2nd respondents do not have much by way of affidavits in reply/opposition; so their written submissions are limited to points of law. Otherwise they are mere statements from the bar. Since the respondents have not countered the affidavits in the petition by the applicant; those averments stand uncontroverted and are accordingly adopted by the court.553

On the merits of the application, Oriyo J also appeared to have taken the view that fraud had

been committed by Mechmar and continuing viz. -

On the degree of urgency; its relevancy here cannot be overstated because the oppressive acts, fraud, etc of Mechmar against VIP has been in a continuous process since 2001; that is, for a period of over seven years. […]

The need for the appointment of a Provisional Liquidator pending winding up has in no doubt been adequately established by VIP through the affidavits of James Burchard Rugemalira filed on 25.2.2002 and 24.9.2003. And on the basis of the said affidavits, both VIP and IPTL (the company) stand to suffer irretrievably if a Provisional Liquidator is not appointed. But for Mechmar; if the appointment of a Provisional Liquidator is not immediately made; it does not stand to suffer or lose anything except prolong the period of corporate waste, diversion of funds, conversion of ass[e]ts, fraud, deadlock etc.554

553 HB/H/104/1122-1138 at pgs. 1125-1126: High Court of Tanzania's Appointment of PL, 16 December 2008. 554 HB/H/104/1122-1138 at pgs. 1132-1133: High Court of Tanzania's Appointment of PL, 16 December 2008.

Page 145: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

138

Even more unintelligible was Oriyo J’s observation that the appointment of a provisional

liquidator would serve the interests of some others including TANESCO viz. –

On the issue of public interest considerations; it calls for urgent action towards appointment of a Provisional Liquidator. It is intended to serve interests of groups like those doing business with IPTL including TANESCO and the government of Tanzania.555

Bearing in mind that IPTL’s application for a stay of the petition was to enable IPTL to proceed

in the Interpretation Proceedings in an attempt to seek further compensation from TANESCO

under the PPA, Oriyo J’s reasoning is indeed difficult to comprehend.

Taking a generous view of the thinking behind Oriyo J’s decision, the Tribunal would say that

the decision of 16 December 2008 is both puzzling and inexplicable. Her actions suggested

that she was distracted by other unexplained considerations.

The immediate consequence of Oriyo J’s decision was that the Interpretation Proceedings did

not proceed on the day it was set for hearing. The First PL decided not to proceed further

despite SCB HK’s repeated offers to undertake to bear the costs incurred in doing so and only

to seek recovery from IPTL in the event a favourable decision be made in IPTL’s favour.556

As for the complaint made against the First PL’s decision not to proceed with the

Interpretation Proceedings, the Tribunal finds it curious that the First PL did not respond to

the Claimant’s offer to fund the Interpretation Proceedings. To the extent that there is a

possibility (whatever may be the probability) of recovery of more compensation for IPTL,

and its creditors from TANESCO, it would appear that the First PL should have considered the

offer.

The Tribunal notes, however, that it could not be said that if the Interpretation Proceedings

had proceeded, the outcome would have been a favourable one for IPTL. There is every

possibility that the PPA Tribunal might have made an interpretative ruling in favour of IPTL,

or for TANESCO or made “no order”. In other words, there is nothing before this Tribunal to

enable it to foresee the likely outcome of the Interpretation Proceedings. There is no evidence

to support any suggestion that the Claimant or Mechmar or IPTL had suffered any loss or had

555 HB/H/104/1122-1138 at pg. 1133: High Court of Tanzania's Appointment of PL, 16 December 2008. 556 HB/H/108/1152-1154 at pg. 1153: Letter from SCB HK to the Provisional Liquidator of IPTL, 22 December 2008; HB/H/109/1155-1157 at pg. 1155: Letter from Ringo & Associates to the Provisional Liquidator of IPTL, 8 January 2009.

Page 146: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

139

been “materially and adversely affected”. With this burden undischarged by the Claimant, the

Tribunal cannot find that consequences of the actions complained of were detrimental within

the meaning of Article 16.1 of the Implementation Agreement.

b. The Respondent Procured the Power Plant to be Operated by the First PL under the Interim PPA

(i) Parties’ Submissions

The Claimant alleges that the First PL had through various actions favoured VIP over the

Claimant and Mechmar. These actions include resuming operations of the power plant under

the Interim PPA in July 2009 under the directions of the Respondent, as well as entering the

Interim PPA, which covered only running costs and prejudiced IPTL’s ability to maintain the

Facility at its highest standards, and prevented IPTL from having means to provide a return

to Mechmar (which was the majority shareholder) and repay the debt owed to the

Claimant.557

The Claimant argues that these actions materially and adversely affected the ownership,

operation of the Power Plant, and therefore the Project, IPTL’s enjoyment of its rights to full

payment under the PPA, and the Claimant’s and Mechmar’s interests under the Security

Package.558

The Respondent’s response is that the emergency measures to restore operations in the

Facility taken by the First PL were within his authority and were made in order to preserve

IPTL’s assets, and that none of the measures operated in favour of VIP but rather were taken

solely in the interest of IPTL.559

(ii) Tribunal’s Analysis

The Tribunal sees little basis for the Claimant’s complaint. Entering into an arrangement to

operate the plant to generate power for TANESCO could not of itself be favouring any party.

IPTL was under an obligation to operate the Plant to generate power. Even without the

imposition of the First PL, and even when the parties were in disagreement over how the

tariffs and expenses had to be calculated, IPTL, whether under the control of the original

shareholders or the Claimant, would have the duty to operate it, whether to generate positive

557 Claimant’s PHB, para. 187. 558 Claimant’s PHB, para. 187. 559 Respondent’s Reply PHB, para. 92.

Page 147: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

140

revenue or mitigate losses. In any case, VIP as a shareholder of IPTL stands in the same

position as Mechmar and would suffer the same detriment had the arrangement by the First

PL increased liability for IPTL.

The Tribunal therefore finds that the actions of the First PL in this regard are not

discriminatory and no breach of the undertaking under Article 16.1 of Implementation

Agreement could arise.

c. Transfers of IPTL and the Power Plant, and Payment Out of the Escrow Account

The factual narration relating to this issue is set out in the Tribunal’s discussion on

“Expropriation” in paragraphs 324 to 373 above.

(i) Parties’ Submissions

The Claimant argues that the Second PL, Utamwa J, BRELA, the Minister for Energy and

Minerals, and the PS MEM acted in favour of VIP and PAP, disregarding the interests of the

Claimant in IPTL through its ownership of the Mechmar shares. The discriminatory actions

included: (i) the Second PL’s recognition of the purported sale of Mechmar’s shares and

planned sale of VIP’s shares to PAP by countersigning the VIP-PAP-SPA and supporting VIP’s

application for PAP to take over IPTL’s affairs; (ii) Utamwa J’s refusal to hear the Claimant’s

submissions or the Share Receiver, and instead taking “judicial notice” of the purported sale

of Mechmar’s shares in IPTL and handing over affairs to PAP despite the knowledge of the

Claimant’s rights; (iii) BRELA’s registration of the transfer of shares to PAP despite having

seen documents that put PAP’s ownership of Mechmar’s shares in doubt; and (iv) the

Permanent Secretary Maswi’s signing of the agreement to release the Escrow funds despite

being aware of the Claimant’s rights and that PAP could not have purchased Mechmar’s

shares.560

The Claimant asserts that these actions materially and adversely affected the ownership and

operation of the Power Plant, and therefore the Project; IPTL’s enjoyment of its rights to full

payment under the PPA; and the Claimant’s and Mechmar’s interests under the Security

Package.561

560 Claimant’s PHB, para. 187. 561 Claimant’s PHB, para. 187.

Page 148: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

141

In relation to the actions of the Second PL, the Respondent says that the Administrator

General and Official Receiver’s office when acting in his capacity as liquidator (provisional or

otherwise) or receiver was acting as an agent of the company in or pending liquidation. He

was therefore not acting as a government official and therefore his actions could not be

attributable to the Respondent.562 As the provisional liquidator, he had the right to hold

doubts over the Claimant’s standing, especially when viewed in the light of the PwC Report,

which referred to the Claimant as an “unsecured creditor”.563 In any case, as provisional

liquidator, the Second PL’s actions were subject to the High Court’s scrutiny and the Claimant

failed to adequately challenge them.564

As regards Utamwa J’s Order of 5 September 2013, directing that the affairs of IPTL be vested

on PAP, the Respondent relies on the principle of separation of powers set out in Articles

107A and 107B of the Constitution of the United Republic of Tanzania,565 that executive

officials could not take account of documents submitted by private parties (such as the

Claimant) conflicting with the findings of a court (Utamwa J Order) and were bound to follow

the Utamwa J Order.566 In other words, GoT was merely complying with the orders given by

the court and could do little more.

As to the subsequent release of the Escrow Account, the Respondent says that this was a

consequence of the agreement between TANESCO and IPTL to end the Tariff Dispute and

their agreement acknowledged that the proceeds in the Escrow Account would be released

to enable it to pay off its legitimate creditors. The Respondent relies heavily on the Utamwa J

Order.

The Respondent also submits that it released the proceeds of the Escrow Account upon IPTL’s

instructions567 to IPTL and not to IPTL’s creditors, and the fact that IPTL indicated different

bank accounts for the money to be released to does not change the fact that payment was

made to IPTL.568

562 Respondent’s PHB, para. 107. 563 HB/H/220/3140-3213 at pg. 3180: Price Waterhouse Cooper's Report entitled "IPTL Creditor Claim Assessment", 29 April 2012. 564 Respondent’s Reply PHB, para. 92. 565 HB/G/175/12775-12865 at pg. 12836: The Constitution of the United Republic of Tanzania, 1977. 566 Respondent’s Reply PHB, para. 92. 567 Respondent’s Reply PHB, para. 92. 568 Respondent’s Reply PHB, para. 92; HB/H/338/4877-4882 at pg. 4878: Agreement between GoT and IPTL for delivery of escrow funds, 21 October 2013; Exhibit C-414: Letter from Mr. Sethi to the Bank of Tanzania, 28 November 2013.

Page 149: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

142

(ii) Tribunal’s Analysis

The Tribunal accepts the Respondent’s argument that the Administrator General and Official

Receiver’s office when acting in his capacity as liquidator (provisional or otherwise) or

receiver was acting as an agent of the company. However, this does not negate the fact that

the Administrator General and Official Receiver’s office remain a Governmental Authority

within the definition given in the Implementation Agreement read with the PPA. It has the

public duty to act fairly and abide by the obligations required under the Implementation

Agreement not to discriminate against IPTL and its lawful shareholders when discharging its

responsibility as Second PL. The Second PL had in his Compromise Agreement dated 20

August 2013569 agreed to pay some USD 14.6 million to “uncontested creditors” including fees

of ASYLA ATTORNEYS for USD 500,000 being the legal services “supplied to […] PAP” in

relation to the “Agreement for the Sale and Purchase of VIP Shares in IPTL dated 15th August

2013 between VIP and PAP”.570

As regards the role of BRELA in registering the transfer of shares in favour of PAP despite

knowledge of the possible discrepancy in the chain of transfer, the Tribunal accepts that

BRELA was merely complying with the Utamwa J Order and its acts were purely

administrative and could not of themselves be considered as discriminating against the

Claimant, Mechmar or IPTL.

As for the Utamwa J Order, the Tribunal is conscious that its role is not that of an appellate

body to review Utamwa J’s decision. It has no jurisdiction to do so and is not doing so. The

Tribunal is nevertheless bound to consider whether Utamwa J acted judiciously, and not

capriciously in the discharge of his functions. As observed in paragraphs 347 to 352 above,

Utamwa J had acted without regard to the interest of Mechmar and the Claimant in IPTL,

made no inquiry as to whether PAP’s purported transfer was a genuine transaction and

blessed it with “judicial notice” and directed that IPTL and the Power Plant be handed over to

PAP’s control. The court attendance extracts show that these were made in the absence of

SCB HK’s counsel.571 Counsel representing the Malaysian liquidators of Mechmar (in

569 HB/H/285/4452-4468: Compromise Agreement between the Provisional Liquidator and Uncontested Creditors of IPTL, 20 August 2013. 570 HB/H/285/4452-4468 at pg. 4459: Compromise Agreement between the Provisional Liquidator and Uncontested Creditors of IPTL, 20 August 2013, para. 2.7 (emphasis added). 571 HB/H/302/4631-4659 at pg. 4658: Court record of hearing before Utamwa J, 30 August 2013-5 September 2013.

Page 150: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

143

liquidation) (the majority shareholders of IPTL) who objected was also not heard after the

court ruled that he had no locus standi.572

The Utamwa J Order deprived the Claimant as lender, secured creditor and shareholders of

IPTL (through its control of Mechmar) of its assets. The Order was then relied upon by MEM,

who wished to get out of its obligations in the Project; by the Attorney General who advised

the this provided a “golden opportunity”573 for GoT to extricate itself from its involvement in

the Project; by TANESCO to settle its claims with the PAP-Controlled IPTL and enable BoT to

release payment out of the Escrow Account. The cumulative force of Utamwa J’s Order, the

MEM action, the Attorney General’s advice, TANESCO’s settlement agreement with PAP and

BoT’s cooperation clearly discriminated against IPTL, Mechmar and the Claimant in favour of

PAP. IPTL, Mechmar and the Claimant were materially and adversely affected in their

“performance of the Company's obligations or the enjoyment of its rights or the interests of the

Investors under the Security Package” and GoT is accordingly in breach of its obligation not to

discriminate under Article 16.1 of the Implementation Agreement.

The Respondent has argued that the Claimant could have appealed and sought recourse

against Utamwa J Order as it was aware of the course of action to take as it did so in relation

to the challenging the winding-up order of IPTL in 2012.574 To this the Tribunal needs to

firstly point out that as the Claimant (SCB HK) was not a party to that action, it could not be

in any position to appeal against the order. The Tribunal notes that following the Utamwa J

Order the Claimant did by itself and through IPTL’s receivers (and later its liquidators)

attempt to intervene by taking the following steps:

The Administrative Receiver of IPTL filed a plaint against IPTL before the High Court

(Commercial Division) at Dar Es Salaam on 11 September 2013 in Original

Commercial Case No. 124 of 2013 seeking inter alia a “perpetual injunction order

restraining the Defendant [IPTL] […] from preventing the Plaintiff [Administrative

Receiver] from entering the Plant and exercising the lawful right to take possession and

control of IPTL and its assets; […]”.575

572 HB/H/302/4631-4659 at pg. 4656-4657: Court record of hearing before Utamwa J, 30 August 2013-5 September 2013. 573 HB/H/331/4850-4851 at pg. 4851: Memo from Attorney General of Tanzania, 2 October 2013. 574 Respondent’s PHB, paras. 98-100. 575 HB/H/318/4800-4806 at pg. 4803: Plaint by Martha Renju in Commercial Case 124 of 2013, 11 September 2013.

Page 151: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

144

On 11 September 2013, the Administrative Receiver of IPTL filed for an ex parte

interim injunction to restrain IPTL from “committing breach of contract by preventing

the Applicant [Administrative Receiver] from taking possession of the power plant”,

pending determination of the permanent injunction application on an inter partes

basis.576

On 12 September 2013, the Claimant’s application for a Revision from the

Proceedings, Ruling and Orders of Utamwa J’s earlier order of 24 April 2013, came up

for hearing before the Court of Appeal. SCB HK attempted to bring to the court’s

attention Utamwa J’s order of 5 September 2013 transferring the affairs of IPTL to

Pan Africa Power Solutions (T) Limited. The Court of Appeal declined to consider the

matter adding that:

[The] Court cannot on the basis of the Notice of Motion journey into what the applicant anticipates from subsequent decisions of the High Court […] At any rate, we were not availed with any copy of the proceedings to see for ourselves what Utamwa, J. ordered in September, 2013.577

On 6 September 2013, the Administrative Receiver of IPTL (Ms Martha Renju) filed a

plaint against PAP, VIP and BoT before the High Court (Commercial Division) at Dar

Es Salaam in Commercial Case No. 123 of 2013 seeking “inter alia a perpetual

injunction order restraining the Defendants or any person under or acting pursuant to

the Defendants order, control, or instructions whether as employee, agent or trustee

from taking possession of, releasing, transferring or dealing with all or any of the

proceeds of the Escrow Account […]”.578

On 6 September 2013, the Administrative Receiver of IPTL also filed a plaint against

PAP, VIP and BoT before the High Court (Commercial Division) at Dar Es Salaam in

Misc. Commercial Case No. 98 of 2013 (originating from Civil Case No. 123 of 2013)

seeking inter alia an interim injunction to maintain ‘status quo’ and restrain VIP and

576 HB/H/317/4789-4799 at pgs. 4791-4792: Application by Ms Martha Renju in Miscellaneous Commercial Case No. 100 of 2013, 11 September 2013. 577 HB/H/337/4866-4876 at pg. 4874: Standard Chartered Bank (Hong Kong) Limited v VIP Engineering and Marketing Ltd and others, Court of Appeal (Tanzania), Civil Application No. 130 of 2013, Ruling, 18 October 2013. 578 HB/H/315/4775-4785 at pg. 4781: Plaint by Martha Renju in Commercial Case 123 of 2013, 6 September 2013.

Page 152: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

145

PAP or any other person from taking possession or exercising control on the proceeds

in the Escrow Account until the “hearing and final determination of the main suit”.579

On 4 November 2013, the liquidators of Mechmar applied to the Court of Appeal to

quash Utamwa J’s order of 5 September 2013.580 This application was filed before the

funds in the Escrow Account were transferred out. The appeal remains unheard.

The Tribunal notes that it is quite evident from these steps that the Claimant and Mechmar

had made several attempts to seek recourse against the Utamwa J Order but to little avail.

The Respondent has also submitted that there could never be any discrimination by its

decision to release the funds in the Escrow Account to IPTL as the funds were paid to IPTL

and as IPTL had directed it.581 Such an argument ignores the reality that the control of IPTL

was wrested from Mechmar and the Claimant pursuant to the purported Agreement for the

Sale of Shares made between Piper Link and PAP dated 21 October 2010582 when the

Mechmar Shares in IPTL had already been surrendered by Mechmar and deposited with the

BVI Court and subsequently released to SCB HK, making such a sale impossible. The release

of the funds to PAP-controlled IPTL is clearly not a release of funds to IPTL. This argument is

artificial and contrived.

(6) Tribunal’s Decision on Discrimination

By giving credence to the transaction and relying solely on the Utamwa J Order, GoT, through

MEM, TANESCO, the Attorney-General and BoT, acted in a manner that consciously ignored

the interest of the Claimant and IPTL in favour of PAP, aiding and abetting the release of the

funds in the Escrow Account to PAP. In the Tribunal’s view, these are discriminatory actions

which materially and adversely affected the enjoyment of the rights and interests of SCB HK

and IPTL and were thereby in breach of Article 16.1 of the Implementation Agreement.

579 HB/H/314/4761-4774 at pg. 4764: Application by Ms Martha Renju in Miscellaneous Commercial Case No. 98 of 2013, 6 September 2013. 580 HB/H/343/4983-4910: Civil Application No. 190 of 2013 in the Tanzanian Court of Appeal brought by Mechmar against VIP, IPTL, the Administrator General and PAP, 4 November 2013. 581 Respondent’s Reply PHB, para. 92. 582 HB/H/164/2240-2248: Agreement for Sale of Shares between Piper Links Investments Ltd and Harbinder Singh Sethi, 21 October 2010.

Page 153: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

146

C. CLAIM UNDER ARTICLE 15.3 OF THE IMPLEMENTATION AGREEMENT: FAILURE TO PROVIDE SECURITY

(1) Parties’ Submissions

The Claimant argues that the Respondent is in breach of Article 15.3 of the Implementation

Agreement which provides that:

In the event TANESCO fails to provide the security for payment required by Article 6.6 of the Power Purchase Agreement, the GOT shall within 10 Days after receipt of a notice from the Company to GOT, that states that TANESCO have [sic] failed to provide the security for payment required by Article 6.6 of the Power Purchase Agreement, provide directly to the Company [IPTL] the security for payment on the same terms and conditions as required under the Power Purchase Agreement[…].

The Claimant submits that Article 6.6 of the PPA requires TANESCO to provide security, either

in the form of a letter of credit or funds paid into an Escrow Account, equal to an aggregate of

two months of capacity payments and energy payments, and in the event the security was

drawn, TANESCO was required to reinstate the full required amount within 30 days. Further,

that Article 15.3 of the Implementation Agreement requires the Respondent to provide this

security if TANESCO fails to do so.583

The Claimant submits that on 5 February 2014, the Claimant wrote to the Respondent

referring to Article 15.3 and stating that following the dissipation of the monies that were in

the Escrow Account with Bank of Tanzania, TANESCO has failed to provide security for its

payment obligations as required by Article 6.6 of the PPA and demanding that the

Respondent provide such security within 10 days from receipt of the notice.584 The Claimant

contends that the Respondent failed to provide such security and so it breached Article 15.3

of the Implementation Agreement.585

The Respondent’s pleaded case is that it is unclear whether the alleged breach of Article 15.3

of the Implementation Agreement arises from TANESCO or the Government not having

established the security referred to in Article 6.6 of the PPA in the form of a letter of credit or

Escrow Account for the “required amount” under that Agreement (i.e. two months of capacity

payments and energy payments) or whether the breach of Article 15.3 is caused by the

583 HB/A/002/035-143: Claimant’s Memorial, paras. 204-207. 584 HB/A/002/035-143: Claimant’s Memorial, paras. 206-207. 585 HB/A/002/035-143: Claimant’s Memorial, paras. 206-207.

Page 154: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

147

Government not having reinstated the amount formerly held in the Escrow Account after its

contents were paid to IPTL in 2013.586 Furthermore, the Respondent states that funds were

withdrawn from the Escrow under Article 6.8 of the PPA in relation to the Tariff Dispute and

not Article 6.6 of the PPA. It submits that consequently there is no obligation to reinstate any

money into the Escrow, as they were only there due to the Tariff Dispute.587

Finally, the Respondent submits that in any event, even if the Claimant is correct, it would

only be entitled to a declaratory judgment as it suffered no loss for the alleged violation of

Article 15.3 of the Implementation Agreement. Alternatively, the Claimant would be entitled

the equivalent to the security required to be as per Article 6.6 of the PPA. 588

(2) Tribunal’s Analysis

The Tribunal notes that the Parties did not in their Post-Hearing Briefs address this claim in

any detail. The Claimant only mentioned it as part of its prayer for relief that a declaration be

made on GoT’s breach of Article 15.3589 and the Respondent criticises it as being “brought by

SCB HK with the sole intent of unduly multiplying its chances of recovery.”590

It is clear to the Tribunal that this claim was made on the basis that the dissipation of the

monies formerly held in escrow by the BoT meant that there was no security in place for

TANESCO’s payment obligations required by Article 6.6 of the PPA. Relying on that, the

Claimant then made a demand on 3 December 2013 and 5 February 2014591 that the security

be replenished as a remedy to prevent an Event of Default under Article 19.1(b)(vii) of the

Implementation Agreement. Based on the Tribunal’s findings that the dissipation of the

Escrow Account was an act of expropriation as well as the consequence of the discriminatory

action by GoT, the Claimant’s demand for its remedy is justified. The Tribunal therefore finds

that Article 15.3 of the Implementation Agreement was breached by the Respondent.

586 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 322. 587 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 324. 588 HB/A/005/604-827: Respondent’s Rejoinder, paras. 288 -289. 589 Claimant’s PHB, para. 227. 590 Respondent’s PHB, para. 137. 591 HB/H/360/5116-5118 at pg. 5118: Letter from SCB HK to Principal Secretary, Ministry of Water, Energy and Minerals, 5 February 2014.

Page 155: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

148

D. TERMINATION

The Claimant asserts that the Respondent’s actions amount to “GOT Event[s] of Default” as set

out in Article 19.1(b) of the Implementation Agreement, which entitle the Claimant as an

assignee of IPTL to terminate the Implementation Agreement.592 It argues that pursuant to

Article 20.1(b), if IPTL elects to terminate the Implementation Agreement due to a “GOT Event

of Default”, it may elect to transfer the Facility to the Respondent, and the Respondent must

pay compensation calculated in accordance with the formula in Row 2 of Schedule 2 of the

Implementation Agreement.593

The Claimant states in its Memorial that by the time of filing its Memorial, it had notified the

Respondent of seven Events of Default committed by GoT many of which gave it the right to

terminate the Implementation Agreement, which right it had expressly reserved and that it

intended to terminate the Implementation Agreement by the time of the hearing which was

scheduled to be heard in April 2018.594 It also states in its Memorial, that there were two

other GoT Events of Default that entitled it to terminate the Implementation Agreement, but

it had not at the time of filing the Memorial notified the Respondent regarding the same.

During the Hearing, the Claimant stated that it had terminated the Implementation

Agreement through a (“Termination Notice”) dated 6 July 2018,595 following the expiration

of the time for remedy.

The Termination Notice, which was presented to the Tribunal during the Hearing,

summarised the notice process followed for each of the eight Events of Default that formed

the basis of the termination.596 The Claimant says that if it succeeds on any one of the Events

of Default it has relied upon it will be entitled to terminate the Implementation Agreement.597

The Respondent’s case is that: (i) first, the Claimant is not a party to the Implementation

Agreement or a valid assignee of IPTL, so its intention to terminate the Implementation

Agreement does not carry any material substance;598 (ii) second, its acts do not constitute

592 Claimant’s PHB, para. 188. 593 HB/A/002/035-143: Claimant’s Memorial, para. 209. 594 HB/A/002/035-143: Claimant’s Memorial, paras. 210-212. 595 HB/J/Tab 1. 596 Claimant’s PHB, para. 189; Tr. Day 2 [487:5-495:19]. 597 Claimant’s PHB, para. 194. 598 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 328.

Page 156: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

149

“GOT Event[s] of Default” under the Implementation Agreement; 599 (iii) third, that the

Claimant has not met the necessary steps required to terminate the Implementation

Agreement including the notice provisions;600 and (iv) fourth, even in case the Tribunal

decides that the Claimant has satisfied the necessary notice requirements, the Claimant

cannot claim compensation upon termination without satisfying the pre-condition of

transferring the Facility to the Respondent, as compensation is calculated as being the

consideration for the acquisition of the Facility by the Respondent.601

(1) GoT Events of Default and Notice Requirements

a. Parties’ Submissions

In its claim for termination under the Implementation Agreement, the Claimant relies on

Article XIX and XX of the IMA, specifically Articles 19.1(b), 19.2 and 20.1(b), which are

reproduced below:602

19.1 Termination for Default […]

(b) Termination by the Company

Each of the following events shall be an event of default by the GOT (each a "GOT Event of Default"), which, if not cured within the time period permitted (if any) to cure shall give rise to the right on the part of the Company to terminate this Agreement pursuant to Article 19.2; provided, however, that no such event shall be an Event of Default by the GOT (aa) if it results from a breach by the Company of the Power Agreement or this Agreement or; (bb) if it occurs as a result of a Force Majeure Event during the period provided pursuant to Article 17.4:

(i) The expropriation, compulsory acquisition, or nationalization by the GOT or any Governmental Authority of (i) any Ordinary Share Capital, or (ii) any material asset or right of the Company (except as contemplated by the Security Package);

[…]

(vi) Any material breach by the GOT of this Agreement that is not remedied within ninety (90) Days after notice from the Company to the GOT stating that a material breach of the Agreement has occurred that

599 HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 328, 329-333. 600 HB/A/005/604-827: Respondent’s Rejoinder, paras. 296-298. 601 Respondent’s PHB, para. 137. 602 HB/C/005/192-267 at pg. 235 et seq: Unsigned copy of Implementation Agreement (including Schedules), 8 June 1995.

Page 157: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

150

could result in the termination of this Agreement, identifying the material breach in reasonable detail, and demanding remedy thereof;

(vii) Any material breach by TANESCO of the Power Purchase Agreement including but not limited to the failure by TANESCO to provide the security for payment required by Article 6.6 of the Power Purchase Agreement, that is not remedied within thirty (30) Days after the receipt of a notice from the Company to TANESCO that states that a material breach of the applicable. agreement has occurred that could result in the termination of that agreement., identifies the breach in reasonable detail, and demands remedy thereof or the failure of the GOT to provide the security for payment required under Article 15.3 […].

19.2 Termination Notices

(a) Upon the occurrence of a GOT Event of Default or a Company Event of Default, as the case may be, that is not cured within the applicable period (if any) for cure, the non-defaulting Party may, at its option, initiate termination of this Agreement by delivering a notice (a "Notice of Intent to Terminate”) of its intent to terminate this Agreement to the defaulting Party: The Notice of Intent to Terminate shall specify in reasonable detail the Company Event of Default or the GOT Event of Default, as the case may be, giving rise to such notice.

(b) Following the delivery of a Notice of Intent to Terminate, the Parties shall consult for a period of up to thirty (30) Days in case of a failure by either Party to make payments when due, and up -to sixty (60) Days with respect to any other Event of Default (or such longer period as the Parties may mutually agree), as to what steps shall be taken with a view to mitigating the consequences of the relevant Event of Default taking into account all the circumstances. During the period following the delivery of the Notice of the Intent to Terminate, the Party in default may continue to undertake efforts to cure the default, and if the default is cured at any time prior to the delivery of a Termination Notice in accordance with Article 19.2(c), then the non-defaulting Party shall have no right to terminate this Agreement in respect of such cured default.

(c) Upon expiration of the consultation period described in Article 19.2(b) and unless the Parties shall have otherwise agreed or unless the Event of Default giving rise to the Notice of Intent to Terminate shall have been remedied, the Party having given the Notice of Intent to Terminate may terminate this Agreement by delivering a Termination Notice to the other Party, whereupon this Agreement shall immediately terminate and Article XX shall apply.

[…]

Page 158: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

151

20.1 Compensation Upon Termination […]

b) GOT Event of Default

In the event the Company terminates this Agreement pursuant to Article 19.1(b) as a result of GOT Event of Default, the Company may elect to transfer the Facility to the GOT or its designee and, upon such transfer, the GOT or its designee shall pay the Company the compensation amount set forth in Row 2 of Schedule 2. […]”

The Respondent in its Counter-Memorial contends that at the time of the filing of its Counter-

Memorial, the Claimant had not met the notice requirements; had not yet terminated the

Implementation Agreement; and did not have the right to do so, and as such Article 20.1 and

Schedule 2 of the Implementation Agreement could not be triggered.603

The Respondent also contends that the different steps required in Article 19.2 of the

Implementation Agreement show that there has to be a “sufficient connection in content and

time” between the Notice of Intent to Terminate and the Termination Notice in order to

terminate the Implementation Agreement. It refers to decisions in Architectural Installation

Services Ltd v James Gibbons Windows Ltd and Mvita Construction Co Ltd v Tanzania Harbours

Authority604 to support its proposition that in contracts of this nature with complex notice

requirements, “the validity of those notices depends on the precise observance of the specified

conditions” and that there “has to be a necessary sufficient connection between the various

notices for them to be valid.”605

The Respondent submits that due to the fact that many of the Claimant’s Notices of Intent to

Terminate606 were issued more than four years from April 2018, they lack sufficient

connection with the Termination Notice that the Claimant intended to issue at the time of the

Hearing and the Notices of Intention to Terminate did not convey certainty of intent to

terminate.607

603 HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 334-339. 604 HB/G/284/14781-14787 at pgs. 14784-14786: Architectural Installation Services Ltd v James Gibbons Windows Ltd, 16 ConLR 68, Judgment, 14 June 1989; HB/G/285/14788-14809 at pgs. 14804-14805: Mvita Construction Co Ltd v Tanzania Harbours Authority, Court of Appeal (Tanzania), 46 BLR 19, Judgment, 26 February 1988. 605 HB/A/005/604-827: Respondent’s Rejoinder, para. 297. 606 HB/H/477/7112-7113, Letter from SCB HK to TANESCO, 13 October 2017. 607 HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 337-341.

Page 159: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

152

The Claimant summarised the various steps leading to its Termination Notice608 as follows:

Event A:609

Expropriation of the Facility and of IPTL's shares by Governmental Authorities (Article19.1(b)(i))

• On 3 December 2013, the Claimant served a notice on the Respondent notifying it that the expropriation of the Facility and Mechmar's shareholding in IPTL amounted to a GoT Event of Default.610

• On 5 February 2014, the Claimant served a notice on GoT notifying it that the 60-day consultation and remedy period had elapsed without the Respondent remedying the Event of Default and that the Claimant reserved its right to terminate the Implementation Agreement without further consultation.611

• As there is no cure period under Article 19.1(b)(i), the Claimant immediately issued Notice of Intention to Terminate under Article 19.2(a) of the Implementation Agreement, triggering a 60-day consolation and remedy period and reserved its right to terminate the Implementation Agreement should the Respondent not remedy its default within the 60 days.

• The Claimant in its Termination Notice gave notice of the exercise of its termination right pursuant to Article 19.2(c) based on this GoT Event of Default.612

Event B:

Material breach of the PPA by TANESCO in failing to pay undisputed sums (Article 19.1(b)(vii))

• On 3 December 2013, the Claimant notified the Respondent of the Event of Default that TANESCO had failed, despite the Claimant’s demands, to pay undisputed sums under the PPA, and of its failure to remedy the breach within 30 days of being notified. It also triggered a 60-day consolation period to remedy the Default pursuant to Article 16.2(b) of the Implementation Agreement.613

• On 5 February 2014, the Claimant noted that the Respondent had failed to remedy its Event of Default and gave notice of Intent to Terminate under Article

608 HB/J (Bundle J was submitted by the Claimant at the Hearing). 609 Numbering of the Events of Default adopted here are the same as in the Termination Notice at HB/J. 610 HB/J Tab 2/pg. 5; HB/H/352/4948-4953: Letter from SCB HK to Principal Secretary, Ministry of Water, Energy and Minerals, 3 December 2013. 611 HB/H/360/5116-5118: Letter from SCB HK to Principal Secretary, Ministry of Water, Energy and Minerals, 5 February 2014. 612HB/ J/Tab 1, para. 6. 613 HB/H/352/4948-4953: Letter from SCB HK to Principal Secretary, Ministry of Water, Energy and Minerals, 3 December 2013.

Page 160: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

153

19.2(a) of the Implementation Agreement based on the default.614

• On 9 April 2014, the Claimant notified the Respondent that the 60-day consultation and remedy period initiated by the Notice of Intention to Terminate was over.615

• The Claimant in its Termination Notice gave notice of the exercise of its termination right pursuant to Article 19.2(c) based on this GoT Event of Default.616

Event C:

Expropriation of the Facility and of Ordinary Share Capital of IPTL in material breach of Articles 16.1 and 16.2 of the Implementation Agreement by the GoT (Article 19.1(b)(vi))

• On 3 December 2013, the Claimant notified the GoT regarding this event of default.617

• On 10 March 2014, the Claimant served a notice on the Respondent informing it that the material breaches of Article 16.1 and 16.2 had not been remedied within the 90-day period and gave Notice of Intention to Terminate triggering a 60-day consultation and remedy period.618

• On 1 June 2018, the Claimant notified the Respondent that the 60-day consultation and remedy period initiated by the Notice of Intention to Terminate was over and that it was entitled to terminate the Implementation Agreement under Article 19.2(c) and reserved its right to do so without further consultation.619

• The Claimant in its Termination Notice gave notice of the exercise of its termination right pursuant to Article 19.2(c) based on this GoT Event of Default.620

Event D: • On 5 February 2014, the Claimant served a notice on the GoT notifying it that given the dissipation of the

614 HB/H/360/5116-5118: Letter from SCB HK to Principal Secretary, Ministry of Water, Energy and Minerals, 5 February 2014. 615 HB/J/Tab 2/pgs. 15-16: Schedule to Termination Notice titled “SCHEDULE - NOTICES IN RELATION TO IMPLEMENTATION AGREEMENT” (“Schedule”), paras. 4-6; HB/H/370/5304-5305: Letter from SCB HK to Principal Secretary, Ministry of Water, Energy and Minerals, 9 April 2014. 616 HB/J/ Tab 1, para. 10. 617 HB/H/352/4948-4953: Letter from SCB HK to Principal Secretary, Ministry of Water, Energy and Minerals, 3 December 2013. 618 HB/H/365/5125-5126: Letter from SCB HK to Principal Secretary, Ministry of Energy and Minerals, 10 March 2014. 619 HB/J/Tab 2/pgs. 24-25: Schedule, enclosing letter dated 1 June 2018. 620 HB/ J/Tab 1, para. 14.

Page 161: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

154

Failure of GoT to provide security for TANESCO's payment obligations (Article 19.1(b)(vii))

Escrow Account monies, TANESCO had failed to provide a security in accordance with Article 6.6 of the PPA.621

• On 25 February 2014, the Claimant served a notice on the Respondent notifying it that it had failed to provide the “replacement security” under Article 15.3 of the Implementation Agreement, and that this constituted a GoT Event of Default, and gave Notice of Intention to Terminate under Article 19.2 (a) of the Implementation Agreement.622

• On 1 June 2018, the Claimant notified the Respondent that the 60-day consultation and remedy period initiated by the Notice of Intent to Terminate was over and that it was entitled to terminate the Implementation Agreement under Article 19.2(c) and reserved its right to do so without further consultation. 623

• The Claimant in its Termination Notice gave notice of the exercise of its termination right pursuant to Article 19.2 (c) based on this GoT Event of Default.624

Event E:

Expropriation in relation to the Escrow Account (Article 19.1(b)(i))

• On 5 February 2014 the Claimant notified the Respondent that it had failed to remedy this Event of Default due to expropriation relating to the Escrow Account. It also noted that there is no cure period under Article 19.1(b)(i) and gave Notice of Intention to Terminate under Article 19(2)(a) of the Implementation Agreement.625

• On 9 April 2014, the Claimant notified the GoT that the 60-day consultation and remedy period initiated by the Notice of Intention to Terminate was over and that the Claimant was entitled to terminate the Implementation Agreement and expressly reserved the right to do so without further consultation.

621 HB/H/360/5116-5118: Letter from SCB HK to Principal Secretary, Ministry of Water, Energy and Minerals, 5 February 2014. 622 HB/J/Tab 2/pg. 12: Schedule, enclosing letter dated 25 February 2014. 623 HB/J/Tab 2/pg. 25: Schedule, enclosing letter dated 1 June 2018. 624 HB/ J/Tab 1, para. 18. 625 HB/H/360/5116-5118: Letter from SCB HK to Principal Secretary, Ministry of Water, Energy and Minerals, 5 February 2014.

Page 162: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

155

• The Claimant in its Termination Notice gave notice of the exercise of its termination right pursuant to Article 19.2 (c) based on this GoT Event of Default.626

Event F:

Dissipation of Escrow Account in material breach of Articles 16.1 and 16.2 of the Implementation Agreement by the GoT (Article 19.1(b)(vi))

• On 5 February 2014, the Claimant gave notice of an Event of Default under Article 19.1(b)(vi) of the Implementation Agreement due to the escrow monies being dissipated and demanded that the Respondent remedy the same within 90 days.

• On 29 January 2018, the Claimant noted that the Respondent had failed to remedy its Event of Default and gave Notice of Intention to Terminate under Article 19.2(a) of the Implementation Agreement.627

• On 1 June 2018, the Claimant notified the Respondent that the 60-day consultation and remedy period intimated by the Notice of Intent to Terminate was over and that the default had not been remedied so the Claimant had the right to terminate the Implementation Agreement pursuant to Article 19.2(c) and expressly reserved the right to terminate the Implementation Agreement without further consultation.628

• The Claimant in its Termination Notice gave notice of the exercise of its termination right pursuant to Article 19.2(c) based on this GoT Event of Default.629

Event G:

Failure by TANESCO to provide replacement security in material breach of the PPA (Article 19.1(b)(vii))

• On 7 February 2014, the Claimant’s legal representatives wrote to the Respondent’s legal representatives noting the release of funds in the Escrow Account and asking TANESCO to provide replacement security within 30 days in accordance with Article 6.6 of the PPA. A copy was given to the Respondent.630

• On 10 March 2014, the Claimant notified the Respondent of its the failure to replace the security in material breach of Article 6.6. and 6.8 of the PPA and that the default had not been remedied within 30 days

626 HB/J/Tab 1, para. 21. 627 HB/J/Tab 2/pg. 21: Schedule, enclosing letter dated 29 January 2018. 628 HB/J/Tab 2/pg. 25: Schedule, enclosing letter dated 1 June 2018. 629 HB/J/Tab 1, para. 25. 630 HB/J/Tab 2/pgs. 10-11: Schedule, enclosing letter dated 7 February 2014.

Page 163: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

156

of being notified of the same. The Claimant demanded that the respondent remedy the default within the 90-day cure period given to TANESCO under Article 16.2(c) of the PPA.631

• On 29 January 2018 the Claimant noted in its letter that the Respondent had not remedied the Event of Default and gave Notice of Intent to Terminate under Article 19.2(a) of the Implementation Agreement.632

• On 1 June 2018, the Claimant notified the Respondent that the 60-day consultation and remedy period initiated by the Notice of Intention to terminate was over and that the Respondent had not remedied the Event of Default, so the Claimant would be entitled to terminate the Implementation Agreement under Article 19.2(c) and expressly reserved its right to terminate the Implementation Agreement without further consultation.633

• The Claimant in its Termination Notice gave notice of the exercise of its termination right pursuant to Article 19.2(c) based on this GoT Event of Default.634

Event H:

Material breach of the PPA by TANESCO in failing to pay the amount under the PPA Award (Article 19.1(b)(vii))

• On 13 October 2017, the Claimant informed TANESCO that it had failed to pay the sums owed under the PPA (USD 163,384,358.40), thereby materially breaching the PPA, and asked TANESCO to remedy the same in 30 days. A copy was given to the Respondent.635

• On 20 November 2017, the Claimant notified Respondent of this Event of Default due to TANESCO’s failure to pay the sums owed under the PPA in material breach of the PPA, and its failure to remedy this within 30 day of being notified, and gave a Notice of Intention to Terminate pursuant to Article 19.2(a) of the Implementation Agreement.636

• On 29 January 2018, the Claimant noted that the Respondent had not remedied the default and it also

631 HB/J/Tab 2/pgs. 13-14: Schedule, enclosing letter dated 10 March 2014. 632 HB/J/Tab 2/pg. 22: Schedule, enclosing letter dated 29 January 2018. 633 HB/J/Tab 2/pgs. 25-26: Schedule, enclosing letter dated 1 June 2018. 634 HB/J/Tab 1, para. 30. 635 HB/J/Tab 2/pgs. 17-18: Schedule, enclosing letter dated 13 October 2017. 636 HB/J/Tab 2/pgs. 19-20: Schedule, enclosing letter dated 20 November 2017.

Page 164: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

157

gave a Notice of Intention to Terminate under Article 19.2(a).637

• On 1 June 2018, the Claimant notified the Respondent that the 60-day consultation and remedy intimated by the Notice of Intention to Terminate was over and the default was not remedied so the Claimant would be entitled to terminate the Implementation Agreement under Article 19.2(c) and expressly reserved its right to terminate the Implementation Agreement without further consultation.638

• The Claimant in its Termination Notice gave notice of the exercise of its termination right pursuant to Article 19.2 (c) based on this GoT Event of Default.639

The Respondent categorises all of the Claimant’s alleged “GOT Event[s] of Default” into 3

categories as, according to it, they are based on the same underlying facts viz.: (i) first, “alleged

expropriation of the Facility and of IPTL’s assets” which include Events A, C, E and F listed

above; (ii) second, alleged “failure of GoT to provide security for TANESCO’s payment

obligations” which include Events D and G; and (iii) third, alleged “material breach of the PPA

by TANESCO by failing to pay undisputed sums” which is Event B (and the Respondent submits

that Event H falls in this category).640

In relation to the first category, the Respondent submits that there has been no expropriation,

compulsory acquisition or nationalisation by the Respondent or any Governmental Authority

of the Facility or IPTL’s shares and that the dissipation of the Escrow Funds was not a material

breach of the Implementation Agreement as the account was established under Articles 6.6

and 6.8(b) of the PPA to deposit disputed sums in relation to the Tariff Dispute with IPTL and

the money was released once the dispute was settled in October 2013.641

In relation to the second category, the Respondent argues that the Claimant confuses the

scope of Articles 6.6 and 6.8 of the PPA as the Claimant alleges a violation of Article 15.3 of

the Implementation Agreement by failing to provide security for TANESCO’s payment

637 HB/J/Tab 2/pg. 22: Schedule, enclosing letter dated 29 January 2018. 638 HB/J/Tab 2/pg. 26: Schedule, enclosing letter dated 1 June 2018. 639 HB/J/Tab 1, para. 35. 640 HB/A/003/144-370: Respondent’s Counter-Memorial, paras. 329-333; HB/A/005/604-827: Respondent’s Rejoinder, para. 294. 641 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 330.

Page 165: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

158

obligations as per Article 6.6, whereas the monies in the Escrow Account were deposited

pursuant to the Tariff Dispute and thus fell under Article 6.8(b) of the PPA. Further it submits

that IPTL did not need to withdraw monies from the Escrow Account because TANESCO had

paid Tariff since October 2013.642

Regarding the third category and related Event H, the Respondent argues that this cannot be

an Event of Default as TANESCO’s failure to make payments under the PPA was justified on

the ground that IPTL had breached the PPA and the Implementation Agreement.643 Again, the

Claimant’s response is that the PPA Award had determined that TANESCO owed USD 148.4

million as at 30 September 2015 along with interest.644

The Respondent also argues that the compensation payable under Schedule 2 would be

invalid for some GoT Events of Default, as it would constitute a penalty clause and not a

genuine pre-estimate of the damages of the breach for damages of the Implementation

Agreement. The Claimant maintains that Schedule 2 is not a liquidated damages clause, but a

formula calculated to provide compensation when the Implementation Agreement is

terminated, and the elements are appropriate pre-estimate of loss.645

b. Tribunal’s Analysis

In the Tribunal’s view, to entitle the Claimant (as assignee of IPTL) to terminate the

Implementation Agreement, the Claimant needs only to show that an Event of Default had

occurred. As the GoT had committed clear and direct acts of expropriation [see paragraph

380 above] and discrimination [see paragraph 441 above] expressly prohibited under Article

16 of the Implementation Agreement, the right of Termination has accrued in favour of the

Claimant in respect of events A, C, E and F as described above, which the Respondent terms

as the first category [see paragraph 458 above]. These Events of Default require no cure

period.

The Tribunal is satisfied that the Claimant has adhered faithfully to the procedural steps to

terminate the Implementation Agreement. These are matters of facts and of the record and

require no further discussion.

642 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 330. 643 HB/A/003/144-370: Respondent’s Counter-Memorial, para. 330. 644 HB/A/004/371-603: Claimant’s Reply, para. 622. 645 Claimant’s PHB, para. 198; HB/A/005/604-827: Respondent’s Rejoinder, paras. 293, 302.

Page 166: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

159

With regards to the second category,646 Article 6.6 of the PPA requires that TANESCO or GoT

provides security for payments due to IPTL by way of a letter of credit or payment into an

Escrow Account. Any amount drawn down from the account must then be reinstated within

30 days. The intent behind this arrangement was to provide assurance of payment by

TANESCO of any amounts due to IPTL under the PPA. The Respondent’s criticism that the

Claimant was wrong to have relied on Article 6.6 of the PPA and should instead be relying on

Article 6.8 of the PPA, would make little difference. Article 6.8 merely provides for a situation

where there is a dispute as to whether such sums are due to IPTL, it nevertheless refers to

the same Escrow Account mentioned in Article 6.6 of the PPA and withdrawal must be made

only when the amount is undisputed with disputed sums remaining in account. There was no

error or confusion that the GoT has the joint responsibility under Article 6.6 of the PPA to

reinstate the amounts so withdrawn from the Escrow Account. The Tribunal therefore

reaffirms that the failure to do so is an Event of Default as it is a “material breach” specifically

identified in Article 19.1(b)(vii) of the Implementation Agreement and for which GoT is

obliged to provide security under Article 15.3 of the Implementation Agreement.

The Respondent’s criticism of the third category647 also lacks merit. The Claimant has since

obtained the PPA Award in its favour, but TANESCO has failed to make payment and the

Claimant remains unable to recover any sum under the PPA Award. Any suggestion that the

PPA Award was subject to appeal has since been put to rest when the ICSID ad hoc Annulment

Committee rendered its final decision in August 2018.648 There is no doubt in the Tribunal’s

mind that TANESCO’s breach of the PPA in failing to make payments that were due and failing

to abide by the PPA Award constitute a “material breach by TANESCO” under Article

19.1(b)(vii) of the Implementation Agreement, entitling the Claimant the terminate the

Implementation Agreement.

646 As defined in para. 458 above. 647 As defined in para. 463 above. 648 Exhibit CL-216: Standard Chartered Bank (Hong Kong) Limited v Tanzania Electric Supply Company Limited, ICSID Case No. ARB/10/20, Decision on Annulment, 22 August 2018.

Page 167: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

160

(2) Whether the Claimant is Entitled to Claim Compensation under Row 2 of Schedule 2 of the Implementation Agreement without Transferring the Facility to the Respondent?

a. Parties’ Submissions

The Claimant claims that upon Termination it is entitled to be compensated in accordance

with Schedule 2 of the Implementation Agreement as provided in Article 20.1(b) of the

Implementation Agreement.

The Respondent rejects the Claimant’s claims, maintaining that compensation upon

termination by the IPTL (the Company) requires as a pre-condition, a transfer of the Facility

to the Government.

Article 20.1(b) of the Implementation Agreement reads:

In the event the Company terminates this Agreement pursuant to Article I9.1(b) as a result of GOT Event of Default, the Company may elect to transfer the Facility to the GOT or its designee and, upon such transfer, the GOT or its designee shall pay the Company the compensation amount set forth in Row 2 of Schedule 2.

The Claimant’s position is: (i) first, that the proper reading of Article 20.1(b) of the

Implementation Agreement is that the requirement that the Facility be transferred to the

Respondent is not applicable in case the Facility has been expropriated and this is apparent

as the first Event of Default as listed in Article 19.1(b) includes expropriation of a material

asset of IPTL; and (ii) second, that in general the Claimant’s inability to transfer the Facility

to the Respondent is due to the Respondent’s wrongful conduct i.e. expropriation of the

Facility and IPTL’s shares and thus violates the principle that a party cannot benefit from its

own wrong.649

b. Tribunal’s Analysis

It is difficult to see how this provision could be interpreted otherwise than that it provides

for the Company (viz. IPTL or the Claimant in this instance) to “elect to transfer the Facility to

the GOT.” Admittedly, SCB HK is in no position to, and has not suggested it could, effectively

do so. The Tribunal therefore agrees with the Respondent that the Claimant is not entitled to

compensation under Row 2 of the Second Schedule to the Implementation Agreement. This,

649 HB/A/004/371-603: Claimant’s Reply, paras. 653-654; Claimant’s PHB, para. 197.

Page 168: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

161

however, does not mean that the Claimant is left with no remedy upon termination. The

Tribunal therefore considers that the Respondent’s discriminatory actions (in breach of

Article 16.1) and the Respondent’s failure to provide security (in breach of Article 6.6 of the

PPA and Article 15.3 of the Implementation Agreement), the actions of Oriyo J, Utamwa J,

MEM and PAP all culminated in the expropriation of the shares in IPTL and depletion of the

Escrow Account. It is this ultimate event of expropriation that the Claimant should get proper

compensation upon termination.

The Implementation Agreement provides specifically for such an event in Article 20.1(d) viz:

In the event the GOT or TANESCO expropriate, compulsorily acquire, nationalise, or otherwise compulsorily procure any Ordinary Share capital or assets of the Company, the GOT shall pay the Company the compensation account set forth in Row 4 of the Compensation Table in schedule 2.

Article 20.1(d) of the Implementation Agreement requires no transfer of the Facility. The

situation the Claimant is found in fits squarely into this category of compensation and should

in principle be entitled to compensation according to Row 4 of Schedule 2 of the

Implementation Agreement and not Row 2 of Schedule 2.

VII. QUANTUM

The Claimant submits that as a statutory assignee it is entitled to recover all damages and

compensation payable under the Implementation Agreement and is not limited to the amount

of loans, subject to the excess being accounted. It relies on the Chivers and Zervos Expert

Reports650 to substantiate this proposition.651

The Claimant asserts that as an assignee of IPTL it is entitled to recover damages for the

following loss and damages resulting from the breaches of Implementation Agreement. The

Claimant claims a total of USD 352,514,258 in damages which comprise of:652

650 HB/E/004/149-198: Expert Report of David Chivers QC, 8 November 2017; HB/E/002/022-062: Second Expert Report of Nicholas Zervos, 10 November 2017. 651 Claimant’s PHB, para. 202; Claimant’s Reply PHB, para. 122. 652 Claimant’s PHB, paras. 207-216.

Page 169: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

162

Damages of USD 176,291,811 for breach of the Implementation Agreement relating

to the PPA tariff for the period up to September 2013: dissipation of the Escrow and

failure to use the top-up payment to discharge IPTL’s debts.653

Damages of USD 176,227,447 for breach of the Implementation Agreement in relation

to losses arising from the transfer of IPTL’s affairs to PAP and relating to the period

after September 2013 which includes:

a) Damages of USD 120,733,915 for October 2013 to 31 August 2018;654 and

b) Damages of USD 55,488,533 for 31 August 2018 to January 2022.655

The Respondent’s primary case is that the Claimant should not be awarded any damages or

compensation. It argues that this is because it would be against the principle of multiple

recovery to do so as the Claimant has already been awarded substantial amounts by the 2016

Flaux J Judgement and the PPA Award. Alternatively, it submits that should the Tribunal find

that the Claimant is entitled to terminate the Implementation Agreement and seek

compensation under Schedule 2 of the Implementation Agreement, it should not be allowed

to be awarded both compensation and damages. In its PHB, the Respondent has also provided

alternative calculations to the Claimant’s expert’s calculations of compensation.656

The Tribunal notes that the Claimant has succeeded on its claim for expropriation for which

it is entitled to termination and compensation under Article 20.1(d) of the Implementation

Agreement.657 The Claimant as assignee of IPTL had also suffered loss and damage during the

period leading up to the expropriation. It is quite incorrect therefore to suggest that the

Claimant should only be limited to a claim for compensation under the Implementation

Agreement and no claim for damages. They are distinct heads of claim, and the Claimant

should be entitled to the damages it can prove.

The Tribunal’s finding against GoT on discriminatory action and breach of Article 16.1

however has no impact on the damages that the Claimant could seek. This is because these

653 Updated Expert Report of Mr Colin Johnson updated at 7 September 2018 (“Updated Johnson Expert Report”), para. 8.3; Claimant’s PHB, paras. 207-210, 216(i). 654 Updated Johnson Expert Report, para. 5.18; Claimant’s PHB, paras. 211-213, 216(ii)(a). 655 Updated Johnson Expert Report, paras. 5.22-5.23; Claimant’s PHB, paras. 211-212, 214. 656 Respondent’s PHB, paras. 189-191. 657 See paras. 471 to 473 above.

Page 170: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

163

same actions have also been earlier found to be acts of expropriation for which damages will

be awarded and quantified below.

A. CALCULATION OF DAMAGES

The Claimant seeks damages for breach of the Implementation Agreement under the

following heads:658

Damage related to the amounts covered by the PPA Award (tariff payments for the

period up to September 2013)-

a) by calculating the amount, including any interest earned, that would have

been available in the Escrow Account as at September 2016 (PPA Award) and

therefore available to satisfy the PPA Award and in turn reduce IPTL's debt to

SCB HK, had the Escrow Account not been paid out to PAP in late 2013;

b) alternatively, on the assumption that the funds withdrawn from the Escrow

Account in November and December 2013 (plus the top-up sum paid by

TANESCO) should, having been withdrawn, have been paid to SCB HK in USD,

and should have been used to reduce the amount outstanding under the SCB

HK loan, to calculate the damage to IPTL as at 31 August 2018 resulting from

the non-payment of these sums to SCB HK; and

c) alternatively, and assuming no payments before September 2016, to calculate

the damage to IPTL as at 31 August 2018 from TANESCO's failure to pay the

PPA Award as at September 2016.

Damages incurred for the period October 2013 to January 2022-

a) Loss of capacity payments between October 2013 and 31 August 2018; and

b) Loss of capacity payments between 31 August 2018 and January 2022.

The Claimant submitted, together with its PHB, an updated Expert Report by Mr Johnson.659

There is no issue raised as regard the amount in the Escrow Account when converted to USD

in December 2013, it was USD 125,719,064. Reference to the Johnson Expert Report hereafter

is a reference to the latest updated version.

658 Claimant’s PHB, paras. 207-216. 659 Updated Johnson Expert Report.

Page 171: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

164

The substance of Mr Johnson’s Report remained the same as when it was first submitted, but

it updates the calculation of damages and compensation up to 31 August 2018. The Updated

Report uses an updated loan balance under the Facility Agreement rather than a projected

loan balance; updates the calculations for the effects of hypothetical payments on IPTL’s

indebtedness; updates the applicable interest to the past hypothetical payments; updates the

discounting in case of future hypothetical payments; applies a discount rate of 17.96% rather

than 19.73%; uses the actual date rather than projected figures for the United States

Consumer Price Index (“CPI”), LIBOR and exchange rates of the period of October 2016 to

August 2018; and calculates compensation under the Implementation Agreement based on

the contract termination on 6 July 2018.660

Using these figures, Mr Johnson shows how, if the payment from the Escrow Account had

been made in December 2013 together with the top-ups between March 2015 and July 2015,

it would reduce IPTL’s indebtedness in December 2013 to 2015 by USD 176,291,811.661

Alternatively, without taking into consideration the top-up payment, if the Escrow Account

was used to pay the loan following the PPA Award in September 2016, IPTL’s debt would

have been reduced by USD 144,868,181 and if used to repay the loan in December 2013

IPTL’s debt would have been reduced by USD 147,039,707.662

The Respondent asserts that its primary case is that the Claimant is not entitled to any

compensation or damages. In the event that the Tribunal finds in favour of the Claimant, the

Respondent’s position is that the Claimant should not succeed beyond USD 41.33 million as

compensation for the undertaking against expropriation or up to USD 95.55 million as

compensation should the Tribunal find in the Claimant’s favour on its other claims for breach

justifying termination.663 The Respondent takes the position that the Claimant should not be

awarded both compensation and damages. If, however, the Tribunal were to award damages

alone and were to find in Claimant’s favour on issues relating to the release of the Escrow

Account, these damages should not exceed USD 144.87 million664 as quantified by the

Claimant in it PHB.665 Further, should the Tribunal find the Respondent to be fully liable of all

660 Claimant’s PHB, para. 200. 661 Updated Johnson Expert Report, para. 4.23. 662 Claimant’s PHB, para. 131. 663 Respondent’s Reply PHB, para. 118. 664 Respondent’s Reply PHB, para. 119. 665 Claimant’s PHB, para. 209.

Page 172: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

165

the Claimant’s claims the aggregate sum should not exceed USD 156.62 million or USD 187.27

million depending on whether enforcement costs of USD 30.65 million incurred by the

Claimant ought to be deducted as unrecoverable.666

In the following sections, the Tribunal will discuss the quantification of each of these claims.

(1) Damage Related to the Amounts covered by the PPA Award (Tariff Payments for the Period up to September 2013)

a. Parties’ Submissions

The Claimant claims to be entitled to damages in relation to losses during the period up to

September 2013, arising from the improper release of funds from the Escrow Account and

the making of the top-up payment to PAP-controlled IPTL, which funds should have been

used to reduce IPTL’s indebtedness under the Facility Agreement. It submits that the loss

suffered under this head is the difference between the outstanding loan balance under the

Facility Agreement as of 31 August 2018 and the outstanding loan balance had the Escrow

Account funds, which were released in November – December 2013, been used to reduce

IPTL’s indebtedness, or alternatively, if the Escrow Account had been used to pay the PPA

Award issued in September 2016.667

The Respondent argues that the Claimant in its PHB claims for the amount based on the

estimated reduction of IPTL’s indebtedness in case Escrow funds would have been used to

pay the PPA Award in September 2016, and the Respondent submits that the amount of USD

176.29 million, which is the Claimant’s proposed amount, is inappropriate, because had IPTL

and TANESCO not reached an agreement for the release of the Escrow Account, they would

also not have agreed on top-up payments. The Respondent also argues that it is inappropriate

to consider IPTL’s indebtedness as being reduced by the payment of the Escrow Account in

December 2013 as the Claimant was not entitled to the Escrow Account funds until the PPA

Award was issued.668

b. Tribunal’s Analysis

The Tribunal accepts that IPTL had suffered loss of revenue that could have been used to

assist it to pay down the outstanding loans, and the fact that the Claimant only obtained the

666 Respondent’s Reply PHB, para. 120. 667 Claimant’s PHB, paras. 207-210; Claimant’s Reply PHB paras. 129-131. 668 Respondent’s Reply PHB, para. 119.

Page 173: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

166

PPA Award in September 2016 does not mean that its entitlement to payment became due

and payable only thereafter. The purpose of the Escrow Account was to pay IPTL who in turn

had financial obligations to the Claimant. The Tribunal also accepts the Respondent’s

argument that, had there not been agreement for the release of funds from the Escrow,

TANESCO would not have agreed to make any top-up of the funds and, as such, it would not

be reasonable to add the top-up amount in reckoning the loss.

The loss of these funds to pay down the loan is best ascertained by the difference between

the outstanding loan balance under the Facility Agreement as at 31 August 2018 and what

the outstanding loan balance would have been had the Escrow Account been used to reduce

IPTL's indebtedness upon its release in November and December 2013. No account should,

however, be taken of the top-up amount for if there was no such agreement to release the

funds in the Escrow Account, no top-up payment would have been made by TANESCO. The

Tribunal finds that based on Mr Johnson’s calculations as at 31 August 2018 (without taking

into account the top-up sum) IPTL's indebtedness would have been reduced by

USD 144,868,181. The Respondent has in its Reply PHB also accepted this as the more

proper quantification of the Claimant’s loss under this head.669

(2) Damages Relating to the PPA tariff for the Period after September 2013: October 2013 to January 2022

a. Parties’ Submissions

The Claimant submits that the transfer of IPTL to PAP in breach of the Implementation

Agreement deprived IPTL of the ability to earn and apply income under the PPA from

September 2013, which would have reduced its debt to the Claimant and other creditors. The

loss suffered in relation to this is calculated based on the loss of capacity payments and

bonuses that IPTL would have expected to receive from TANESCO during the continuing

operation of the Facility under the PPA.670 The figures provided in Mr Johnson’s calculations

amount to USD 176.22 million, as summarised in the table below:

Period Description Claimant’s Amount October 2013 to 31 August 2018

Net Capacity Charges that IPTL would have earned under the PPA (taking into account the costs of earning those charges).

USD 105,974,522671

669 Respondent’s Reply PHB, para. 119. 670 Claimant’s Reply PHB, paras. 132-138. 671 Updated Johnson Expert Report, paras. 5.7-5.8.

Page 174: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

167

Bonus Payments that IPTL might reasonably have expected to earn.

USD 2,891,983672

Had these proceeds been properly applied so as to reduce IPTL's indebtedness under the Facility Agreement, IPTL would have avoided interest and penalties.

USD 11,867,410673

As at 31 August 2018, the overall loss suffered by IPTL for this period.

USD 120,733,915674

31 August 2018 to January 2022

The net Capacity Charges that IPTL would have earned under the PPA (taking into account the costs of earning those charges)

USD 71,847,199675

Bonus Payments that IPTL might reasonably have expected to earn.

USD 3,254,711676

Applying a discount rate of 17.96% to these amounts, the overall loss suffered by IPTL for the period

USD 55,488,533677

The Respondent criticised Mr Johnson’s calculation of bonus payments, the exclusion of

applicable taxes, and improper interest rate selection for bringing forward historical

damages calculated between October 2013 and 31 March 2018.678 It provides an alternative

calculation by removing the bonus payments from 2013 onwards, takes into account

corporate income taxes and applies a risk-free interest rate to cash flows from October 2013

to August 2018 which it submits should reduce the Claimant’s claimed damages under this

head to USD 142.39 million. The Respondent prepared the following comparative table of this

calculation viz:679

Claimant’s Calculations (USD mil)

Respondent’s Calculations (USD mil)

Loss of capacity payments between October 2013 and August 2018

120.73 99.26

Loss of capacity payments between August 2018 and January 2022

55.49 43.13

Total 176.22 142.39

672 Updated Johnson Expert Report, paras. 5.11-5.13. 673 Updated Johnson Expert Report, para. 5.16. 674 Updated Johnson Expert Report, para. 5.18. 675 Updated Johnson Expert Report, para. 5.20. 676 Updated Johnson Expert Report, para. 5.21. 677 Updated Johnson Expert Report, paras. 5.22-5.23. 678 Respondent’s PHB, paras. 171-181; Respondent’s Reply PHB, paras. 113-116. 679 Respondent’s Reply PHB, pg. 37 Table 7.

Page 175: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

168

b. Tribunal’s Analysis

The Tribunal agrees that providing for bonus payments may be speculative as the same are

subject to agreement to be reached between IPTL and TANESCO based on previous year

transactions.680 Mr Johnson had calculated bonus payment based on Equivalent Availability

Factor (“EAF”) being greater than the threshold of 0.90. His calculation of lost cashflows from

2013 thereafter assumes that EAF would be achieved beyond 0.90 and had therefore worked

out bonus payments as annually payable from 2013. Mr Johnson had in fact used the EAF of

2007 of 0.93 to support his theory that EAF would be achieved from 2013 at the same rate.

In this regard, the Tribunal agrees that this would indeed be speculative and should be

disallowed. The element of bonus payments should therefore be disregarded in the

calculations together with the VAT thereon of 18%. By removing all bonus payments from

October 2013 to January 2022, using Mr Johnson’s model, would reduce the damages sought

from USD 176.22 million to USD 170.71 million.

The Respondent also points out that Mr Johnson had made several other errors in his

computation viz. the exclusion of applicable taxes and the improper interest rate selection for

bringing forward historical damages calculated between October 2013 and 31 March 2018.

On taxes, Mr Johnson had used “EBITDA” (Earnings Before Interest, Taxes, Depreciation and

Amortization) to quantify the cashflow loss. The omission of corporate tax would have

reduced the damages by 21.9%.

It was also pointed out by the Respondent that the interest rate used by Mr Johnson was

LIBOR +2% plus, and additional 1% as penalty interest, when the Loan Facility Agreement

stipulated USD – 6 month LIBOR +2.5% which was later reduced to LIBOR +2%681 after the

restructuring.682

The Respondent has in its Reply PHB adjusted these using Johnson’s native Excel spreadsheet

submitted as directed by the Tribunal and arrived with the following results:683

Claimant’s Calculations (USD mil)

Respondent’s Calculations (USD mil)

Loss of capacity payments between 120.73 99.26

680 HB/C/002/013-128 at pg. 37: PPA, 26 May 1995, Article 6.5(b). 681 HB/C/008/280-365 at pgs. 293, 306, 333-334: Facility Agreement, 28 June 1997. 682 Respondent’s PHB, para. 179; HB/H/034/631-637 at pg. 633: Letter from Danaharta to IPTL, 29 October 2001. 683 Respondent’s Reply PHB, pg. 37 Table 7.

Page 176: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

169

October 2013 and August 2018 Loss of capacity payments between August 2018 and January 2022

55.49 43.13

Total 176.22 142.39

The Tribunal agrees with the observations made by the Respondent with regard to Mr

Johnson’s omission of corporate taxes and the application of default penalty interest in the

reckoning of future cashflows. The Tribunal therefore accepts the Respondent’s

quantification as a better and proper approach under this head of claim and fixes the

Claimant’s loss of capacity payments at USD 142,387,737 only.

The loss and damage that the Claimant and IPTL would have suffered works out to

USD 287,255,918 (being USD 144,868,181 [paragraph 488 above] + USD 142,387,737

[paragraph 495 above]) .

B. COMPENSATION FOR TERMINATION

The Claimant contends that it has terminated the Implementation Agreement on 6 July 2018

and is thus also entitled to recover compensation as provided in Row 2 of Schedule 2,

pursuant to Article 20.1(b) of the Implementation Agreement. In accordance with the

Tribunal’s ruling that the Claimant is entitled only to compensation for termination based on

expropriation,684 the relevant computation formula is Row 4 of Schedule 2 of the

Implementation Agreement, which incorporates only elements (a) + (b) + (e).

These elements are defined under Part 2 of Schedule 2 of the Implementation Agreement

as:685

a= Sum of (i) the total amount outstanding to the Lenders under the Financing Documents (including interest during the original construction period through the earlier of the date of termination of this Agreement or the Scheduled Commercial Operations Date) plus (ii) the total amount outstanding under any loan agreements for capital improvements to the Facility that are required under the Power Purchase Agreement, as approved by the GOT, plus (iii) the total amount of any other outstanding debt incurred by the Company that was approved by the GOT, less any insurance proceeds available to the Company following a Force Majeure Event and not spent for Restoration.

684 See paras. 471 to 473 above. 685 HB/C/005/192-267 at pg. 266: Unsigned copy of Implementation Agreement (including Schedules), 8 June 1995.

Page 177: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

170

b= The initial equity investment by the shareholders of the Company multiplied by a fraction, the numerator of which is the number of years remaining in the initial term of the Power Purchase Agreement and the denominator of which is the initial term of the Power Purchase Agreement.

[…]

e= The summation of the products of (i) any additional equity amounts that are contributed by the shareholders of the Company for any of the events that are described under Article 17.5 plus any such equity contributions approved by the GOT, times (ii) a fraction, the numerator of which is the number of years remaining in the initial term of the Power Purchase Agreement and the denominator of which is the number of years remaining in the initial term of the Power Purchase Agreement at the time of such contribution or approval for each such additional equity amount.

Both Parties agree that there was no additional equity contribution and as such the value for

element (e) is zero.686 The Tribunal therefore needs only to consider the values of elements

(a) and (b).

(1) Element (a) – Outstanding Loan

Mr Johnson performed calculations under three scenarios based on the Scheduled

Commercial Operations Date (“SCOD”) which was 28 October 1999 as the Financing

Documents were signed on 28 June 1997 and SCOD is defined as 28 months following

Financial Closing.687

In Scenario 1, Mr Johnson took “the loan principal and interest outstanding at SCOD plus

interest and penalties that accrued to July 2018 (i.e. date of termination) less payments made

by IPTL against the outstanding amounts during this period. This is the actual amount

outstanding under SCB HK's loan to IPTL.”.688 In Scenario 2, he adjusted Scenario 1 by capping

it at “the lowest of the amount of the loan principal and interest outstanding at SCOD or any

lower level of principal and interest outstanding that is achieved at any time (which happens

686 Claimant’s PHB, para. 219; HB/A/002/035-143: Claimant’s Memorial, para. 285; HB/A/003/144-370: Respondent’s Counter-Memorial, para. 387; HB/A/004/371-603: Claimant’s Reply, para. 736. 687 See HB/C/002/013-128 at pg. 027: PPA, 26 May 1995, Article 1.1 provides: “Scheduled Commercial Operations Date: The date that is 28 months after Financial Closing, as such date is extended for Force Majeure Events in accordance with provisions of Article XV.” (emphasis in original); Updated Johnson Expert Report, para. 7.4. 688 Updated Johnson Expert Report, para. 7.5.

Page 178: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

171

in the period immediately prior to 31 January 2007)”.689 In Scenario 3, the amount of “the

loan principal and interest that was outstanding at SCOD less payments made by IPTL against

the outstanding amounts through to 31 January 2007.”. Under Scenario 3, he ignored the

“additional interest that in fact accrued under the loan after SCOD, and for the purposes of

the compensation formula assume that all payments made by IPTL to its lenders are applied

against the principal and interest outstanding at SCOD.”.690

These calculations yield amounts of USD 182,782,152 (Scenario 1), USD 88,290,092 (Scenario

2) and USD 41,325,329 (Scenario 3).691 Mr Johnson did not include capital improvements to

the Facility, or any other outstanding debt incurred by the Company that was approved by

the GoT.692

The Parties are both in agreement that Scenario 2 is not appropriate.693

The Claimant insists that Scenario 1 is most appropriate as “it is closest to the language of the

contract (which is inclusive) and according to Mr Johnson "is typical in terms of project

financing".694 The Respondent disagrees, maintaining that the approach in Scenario 1 violates

the definition given to element (a) of Schedule 2.695 According to the Respondent, Mr Johnson

had used the amount outstanding to the lenders as the theoretical balance of the SCB HK loan

as of 31 March 2018, based on a principal equivalent to the sum of the drawdowns made by

IPTL before October 1999, the Scheduled Commercial Operations Date, i.e., USD 84 million.696

The Respondent submits that, in doing so, Mr Johnson excluded the last drawdown of USD

1.86 million made by IPTL in January 2000697 and calculated the interest and penalty on the

basis of the principal as of SCOD of USD 84 million. Interest and penalties post-SCOD were

added together with insurance costs and enforcement costs, which were all incurred after the

SCOD.698

689 Updated Johnson Expert Report, para. 7.5. 690 Updated Johnson Expert Report, para. 7.5. 691 Updated Johnson Expert Report, para. 7.12. 692 Updated Johnson Expert Report, paras. 7.7-7.8. 693 Claimant’s PHB, para. 220; Respondent’s PHB, para. 152. 694 Claimant’s PHB, para. 220 695 Respondent’s PHB, paras. 147-149. 696 Respondent’s PHB, para. 148; HB/E/003/063-148: Expert Report of Colin Johnson, 16 December 2016, Appendix 21, “Loan amounts” tab, column B. 697 Respondent’s PHB, para. 148. 698 Respondent’s PHB, para. 148.

Page 179: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

172

The Tribunal sees the force of the Respondent’s criticisms. Indeed, element (a) speaks only

of “the total amount outstanding to the Lenders under the Financing Documents (including

interest during the original construction period through the earlier of the date of termination

of this Agreement or the Scheduled Commercial Operations Date)”. On a plain and simple

reading, this limits the amount of principal and interest outstanding as at the date of SCOD

and requires that any payments made by IPTL be applied to reduce this loan, disregarding

interest accruing after the SCOD. The Tribunal therefore agrees that Mr Johnson’s Scenario 3

is the maximum that can be awarded under element (a) and finds that this is the correct and

appropriate approach for calculating element (a), which amounts to USD 41.33 million.

(2) Element (b) – Initial Capital

For element (b) Mr Johnson considered 2 scenarios –

Scenario A - the actual initial equity investment of USD 60 million is used. This is on

the basis that a shareholder's loan represents equity because the shareholder was

taking equity risk and calculated this amount as USD 10,594,521.

Scenario B – an initial equity investment of USD 41.4 million is used, which was the

deemed amount of equity for the purposes of calculating the tariff in the ICSID 1

Award. Mr Johnson had calculated this amount as USD 7,310,219. 699

The Respondent does not agree to either of the positions suggested. The Respondent argues

that the original shareholders did not put in equity (save for USD 100) as required but had

instead extended a Shareholder’s Loan of USD 60 million, which was eventually partially paid

down to Mechmar. It suggests that this element is a simple zero.700

The Claimant disagrees with the suggestion that a shareholder loan could not constitute its

equity contribution. The Claimant submits that by extending a loan, Mechmar was taking an

equity risk. It also observed that the tribunal in the PPA Award made no such finding that

Mechmar’s funding was not "equity" for the purposes of the project documents. It argues that,

in any event, even if this funding was not "equity" within the meaning of element (b), it would

fall instead within outstanding debt advanced by lenders under element (a).701

699Claimant’s PHB, para. 220(ii); Updated Johnson Expert Report, paras. 7.9, 7.12-7.13. 700 Respondent’s PHB, paras. 155-157. 701 Claimant’s PHB, paras. 220-221; Claimant’s Reply PHB, paras. 150-151.

Page 180: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

173

The Tribunal agrees with the Respondent that while Mechmar may have extended loans to

IPTL, it is nevertheless not equity as generally understood. Whereas equity remains the asset

of the company, a loan is a liability of the company and an asset of the lender. As lender, there

is a right to demand repayment, and in fact there was repayment. The Claimant’s suggestion

that as lender, the amount could then be considered under element (a) is also flawed as the

“Lender” referred to in element (a) refers only to the Lender as defined in the Implementation

Agreement, which would not include shareholders.

The Tribunal therefore finds that the compensation available to the Claimant under Article

20.1(d) of the Implementation Agreement is element (a) only, which the Tribunal determined

to be USD 41.33 million.

C. POTENTIAL OVERLAP BETWEEN DAMAGES AND COMPENSATION

The Tribunal’s finding against GoT on discriminatory action and breach of Article 16.1 of the

Implementation Agreement, however, has no impact on the damages that it could seek. This

is because these same actions have also been earlier found to be acts of expropriation for

which the Tribunal is awarding compensation and damages.

The Respondent states that there is an overlap between Claimant’s claim for damages

calculated under breach of the Implementation Agreement and compensation arising from

the termination of the Implementation Agreement.702 During the Hearing, Mr Johnson agreed

that there were two elements of overlap703 and this was agreed to by the Claimant in its

Closing presentations. They are:

Element (a) in the compensation formula which is the amount outstanding to the

lenders may overlap with the damages for breach of the Implementation Agreement

because the damages reflect the loss suffered by IPTL due to its indebtedness not

being reduced. The Claimant proposes that in case the Tribunal goes against its

primary case then the amount awarded under element (a) could be deducted from

the damages award; and

Element (d) of the compensation formula which is the net cash flows following

termination could overlap with damages in relation to Net Capacity Charges and

bonuses earned after 31 August 2018 and the Claimant proposes that should the

702 Respondent’s PHB, paras. 184-186. 703 Tr. Day 5 [1043: 15 – 1049:10].

Page 181: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

174

Tribunal decided against its primary case, the amount awarded under element (d)

could be deducted from the damages in relation to the net Capacity Charges and

bonuses for the aforementioned period.704

As the Tribunal has found that element (d) is not relevant in reckoning computation of

compensation under Row 4 of Schedule 2 of the Implementation Agreement, there is no

overlap with the damages awarded as net cash flow loss quantified based on the Net Capacity

Charges projected for after 31 August 2018.

The Tribunal notes that as for element (a), which the Tribunal has fixed at USD 41.33 million,

this should be deducted from the final reconciling of damages and compensation due to the

Claimant.

Additionally, the Claimant notes that such overlap will not take place in the case where the

Tribunal decides to award only termination or compensation (but not both), or alternatively

agrees to the Claimant’s proposal at paragraph 517 below. The Respondent further states

that there is an additional area of double counting in between the initial equity contribution

i.e. element “b” and the discounted net cash flows as calculated by Mr Johnson under breach

of the Implementation Agreement from October 2013 onwards. However, as the Tribunal has

given a zero factor for element (b), this overlap would not in fact feature.

The Tribunal summarises below the quantification of the claims amounting to USD 287.26

million which it has reached, as follows:

Calculations (USD mil)

Overlap (USD mil)

Tariff payments for the period up to September 2013

144.87

Loss of capacity payments between October 2013 and August 2018

99.26

Loss of capacity payments between August 2018 and January 2022

43.13

Compensation under Article 20.1(d) 41.33 Total 287.26

During the Hearing and in its PHB, the Claimant stated that it was amenable to the Tribunal

making the following order in relation to the sum in excess of the outstanding bank loan

amount and restricting its recovery to amount due under the Facility Agreement:

704Claimant’s PHB, para. 225.

Page 182: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

175

i. making a declaration as to the total amount of damages and compensation due under the Implementation Agreement (or a declaration that this is greater than the sum due under the Facility Agreement, if this is the case); and

ii. ordering that the GoT pay to SCB HK the full amount due under the Facility Agreement, comprising:

(a) US$187,269,605, being the current amount due under the Facility Agreement; plus

(b) additional interest and other sums due in relation to the period after August 2018, as calculated by the Facility Agent; less

(c) any amounts recovered by SCB HK or SCB Malaysia from IPTL or Tanesco prior to the Tribunal’s award.705

The Claimant submits that the loan balance under the Facility Agreement as at 31 August

2018 stood at USD 187,269,605 and that this includes additional interest, penalties and

enforcement costs, since 16 November 2016 when USD 168,800,063.87 was found

outstanding by Flaux J.706 The breakdown of the outstanding loan balance as per the Updated

Loan Model at Appendix 8 of the Updated Johnson Expert Report is given in tabular form in

the Johnson Expert Report at paragraph 4.13 and reproduced below:

Projected Balance At 31 August2018 USD Enforcement Costs 30,652,893 Insurance 5,637,070 Penalties 14,022,940 Interest 49,899,729 Principal 87,056,972 Total 187,269,605

The rationale behind the Claimant’s proposal is that it had originally proposed in its Opening

that it would account to IPTL for any sum in excess of its stake in the Project. It then realised

that this would be cumbersome and perhaps unworkable and therefore withdrew the

original proposal.

The Tribunal is conscious that while SCB HK has stepped into the shoes of IPTL and claiming

rights as an assignee, it should nevertheless not be entitled to enjoy a windfall. For GoT, the

possibility of being exposed to a claim by the very same PAP-controlled IPTL for the amount

705 Claimant’s PHB, para. 203. 706 Claimant’s PHB, para. 201.

Page 183: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

176

so adjudged or declared is an unhappy one. Unfortunately, as the Tribunal has found that it

had committed discriminatory actions against the Claimant/Mechmar and wrongly

expropriated IPTL’s assets, and imperilled SCB HK’s security interest, this is a consequence it

has to face. In fact, if the Tribunal declines to make such a declaration as proposed by the

Claimant, GoT could well have to bear and make full and immediate payment of the adjudged

amount to SCB HK. Making the declaration as sought by the Claimant would ring-fence or

limit GoT’s current exposure. Should PAP-controlled IPTL attempt to rely on this Award, the

Tribunal is confident that GoT would be more than able to raise a strong defence.

In relation to the final amount to be adjudged as payable to the Claimant, the Respondent has

suggested that the costs of enforcement should be deducted from the loan outstanding

because GoT should not pay for “Claimant’s abusive and convoluted litigation strategy over the

years, including for other claims that were unsuccessfully brought against the Government such

as the BIT Arbitration.”707

The Claimant’s response to this is that the enforcement costs incurred by it were sums due

as damages under the Implementation Agreement because GoT's breaches of the

Implementation Agreement have prevented the sums under the Facility Agreement from

being repaid. The Claimant says it is entitled to add enforcement costs to the sum due

pursuant to Clause 24(C) of the Facility Agreement, which provides that IPTL shall pay "on

demand, all costs and expenses (including Taxes thereon and legal fees) incurred […] in

protecting or enforcing any rights under the Financing Documents".708 In the proceedings

before the English court, Faux J had in his judgment ruled that the loan outstanding as USD

168,800,063.87 which included enforcement costs of USD 24.19 million.709 Further, the

Claimant states that the enforcement costs were also incurred in attempts at recovery in

courts in Malaysia, BVI, New York, English, and Tanzanian proceedings, and four ICSID

arbitrations.710

While the Tribunal takes note of GoT’s observation that the Claimant should not be allowed

to recover costs for its “convoluted and abusive” litigation strategy,711 the Tribunal is

707 Respondent PHB, para. 140. 708 HB/C/008/280-365: Facility Agreement, 28 June 1997, Clause 24(C). 709 HB/D/018/755-793 at pg. 792: Flaux J Judgment, 16 November 2016, para. 152. 710 Claimant’s Reply PHB, para. 125. 711 Respondent’s PHB, para. 140.

Page 184: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

177

nevertheless conscious that but for the discriminatory actions and expropriation, none of

these costs would ever have been incurred. In the Tribunal’s view, all of these are proper

heads of losses and should be allowed, save and except the Claimant’s costs incurred for the

BIT Arbitration which was dismissed for want of jurisdiction. The Tribunal will deduct from

the amount finally adjudged the sum of USD 1,820,164.95.712

Taking all these into consideration the Tribunal will make the declaration sought and limit

the recovery of the Claimant in this award to USD 187,269,605 less USD 1,820,164.96, i.e. USD

185,449,440.04 being the amount suffered to discharge the indebtedness due to the

Claimant under the Facility Agreement.

The Tribunal notes that the sum of USD 185,449,440.04 included interest accrued up to end

August 2018. The Claimant in its Post-Hearing Brief713 sought “additional interest and other

sums due in relation to the period after August 2018, as calculated by the Facility Agent”. Until

the sum of USD 185,449,440.04 is fully paid, the Claimant should be compensated for the loss

of use of such funds and be entitled to interest thereon at the same rate as that provided for

in the Facility Agreement viz. 6-month LIBOR +2%714 and payable as from 1 September 2018

until full and final payment.

The Tribunal is also urged by the Respondent to order a set-off of whatever amount that

Tribunal is awarding to the Claimant in this arbitration against the claims they had succeeded

in the 2016 Flaux J judgment715 (USD168.8 million) and the PPA Award716 (USD148.4

million). It should be noted that there is no identity of parties in this matter with those other

proceedings; the respondent in the PPA Arbitration was TANESCO and the respondents in

the Flaux J’s judgment were IPTL, VIP and PAP. Further, as neither the award nor the

judgment has been satisfied in whole or in part, there is no basis to suggest that the Claimant

has obtained double recovery or has such intention to do so. An enforcement court will in the

normal course require disclosure of parallel enforcement proceedings. An award-debtor

could easily bring this to the attention of the relevant forum to resist any enforcement action

712 HB/D/003/300-366: Final Award ICSID Case No. ARB/10/12 (BIT Award), 2 November 2012, paras. 192, 278. 713 Claimant’s PHB, para. 203 714 HB/C/008/280-365 at pgs. 293, 306, 333-334: Facility Agreement, 28 June 1997; HB/H/034/631-637 at pg. 633: Letter from Danaharta to IPTL, 29 October 2001; HB/C/014/552-557 at pg. 557: Form of Deed of Assignment made between Danaharta Managers (L) Ltd and SCB HK, 17 August 2005. 715 HB/D/018/755-793 at pg. 792: Flaux J Judgment, 16 November 2016. 716 HB/D/005/480-586: PPA Award, 12 September 2016.

Page 185: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

178

which could lead to double recovery. In this regard, the Claimant shall not seek recovery

beyond the amount adjudged in this Award. In all attempts at enforcing this Award, the

Claimant shall make full and proper account of the aggregate sums recovered and the balance

still remaining due.

VIII. COSTS

A. PARTIES’ SUBMISSIONS

The Claimant submits that the Tribunal has power to award costs as it deems appropriate

and is not bound to follow decisions of previous ICSID Tribunals.717 The Claimant relies upon

the following provisions:

Article 61(2) of the ICSID Convention which provides:

(2) In the case of arbitration proceedings the Tribunal shall, except as the parties otherwise agree, assess the expenses incurred by the parties in connection with the proceedings, and shall decide how and by whom those expenses, the fees of the members of the Tribunal and the charges for the use of the facilities of the Centre shall be paid. Such decision shall form part of the award.

ICSID Arbitration Rule 47(1) (j) which provides:

(j) any decision of the Tribunal regarding the cost of the proceeding.

The Claimant submits that the Tribunal should award costs on the principle “costs follow the

event” and should take into consideration conduct of the parties and nature of the case they

advanced. It relies on the decision in Caratube v Kazakhstan718 to support this position.719 It

asserts that the “cost follow the event” rule should be followed as it is common practice in

international arbitration and a norm in investment arbitration. It also submits that the rule

is desirable from a policy perspective as well.720 The Claimant asserts that there are various

reasons which justify an award of costs against the Respondent.

717 Claimant’s Cost Submissions, paras. 4-6. 718 HB/G/39/3804-4215 at pg. 4199: Caratube International Oil Company LLP and Devinci Salah Hourani v Republic of Kazakhstan, ICSID Case No. Arb/13/13, Award, 27 September 2017, para. 1253. 719 Claimant’s Cost Submissions, paras. 7-11. 720 Claimant’s Cost Submissions, paras. 7-11.

Page 186: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

179

First, the Claimant submits that the Respondent’s procedural conduct has caused delay,

inefficiency and increased costs, and points out three instances, which include: (i) the

Respondent’s delay in filing its Rejoinder; (ii) the Respondent’s defective document

production and delay in complying with the Tribunal’s orders concerning the Respondent’s

document production; and (iii) the Respondent’s non-attendance at the first procedural

hearing.721

Second, the Claimant contends that the Respondent raised several factual allegations, which

were without merit, and the Claimant had to present a large amount of witness and

documentary evidence to demonstrate why these allegations were incorrect.722

Additionally, the Claimant also submits that due to unequal payments by the Respondent and

the Claimant towards the advance on costs of arbitration (i.e. USD 87,500 paid by the

Claimant towards the Respondent’s half of the first advance and USD 150,000 towards the

Respondent’s half of USD 300,000 that the Parties were asked to pay on 5 June 2018 by

ICSID). The Claimant submits that it has paid a total of USD 712,764.33 to ICSID and the

Respondent has paid USD 150,000.00. Thus, if the Tribunal decides to order that costs of

arbitration be shared equally, it should order a balance payment of USD 268,882.16 to be paid

by the Respondent to the Claimant.723

The Claimant also submits that in case the Tribunal orders the Respondent to pay the

Claimant damages and/or compensation sufficient to pay off the sum due under the Facility

Agreement, then it does not separately require costs for this arbitration from the Respondent

as those costs would already have been paid off by the Claimant under the Facility Agreement.

Thus, the Claimant is seeking payment of its costs only to the extent that damages and/or

compensation which the Tribunal orders to be paid to the Claimant are “insufficient to pay off

the amount due under the Facility Agreement, as updated by [Claimant] at the date of the

Award.”724

The Claimant claims its costs for this arbitration as incurred up to 19 September 2018 and

any additional costs incurred in connection the arbitration arising after that date. It provides

721 Claimant’s Cost Submissions, paras. 13-14. 722 Claimant’s Cost Submissions, paras. 15-16. 723 Claimant’s Cost Submissions, paras. 17-22. 724 Claimant’s Cost Submissions, paras. 23-25.

Page 187: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

180

the breakdown of its costs in Annexures to its Costs Submissions and summarises its costs in

a table which is reproduced below:725

Description Total incurred Herbert Smith Freehills LLP – legal services and disbursements

£2,145,668.15

Linklaters LLP – legal services and disbursements

£142,835.15

Payments to ICSID US$712,764.33 Witness costs US$41,876.44;

HK$66,784.49; TZS30,627,410

Expert costs £249,925.58; and US$37,170

Other costs £1,716.00 Total costs (to 19 September 2018): £2,540,144.88;

US$791,810.77; HK$66,784.49; TZS30,627,410

At current exchange rate, the Claimant’s costs incurred amounts to about USD 4,130,000.

The Respondent submits that it seeks costs pursuant to Article 61(2) of the ICSID Convention

(see paragraph 527(i) above) and Rule 28 of the ICSID Arbitration Rules.

The Respondent submits that the “loser pays” principle is not followed strictly by ICSID

tribunals and rather a variety of factors are considered including the relative success of the

parties’ claims and the good faith of the unsuccessful party in making those claims. It relies

on the decision Noble Ventures, Inc v Romania726 to support this submission.727

The Respondent characterises the Claimant’s litigation strategy as abusive and cites various

circumstances which include:

that the Claimant’s parent company started the BIT Arbitration, and, even though

claims were rejected for lack of jurisdiction, the tribunal, ordered each party to bear

their own costs and half the ICSID fees each. The Respondent adds that the Claimant

is now attempting to recover its part of the BIT Arbitration costs by including them

in the calculation as enforcement costs in the claimed outstanding loan amount;

725 Claimant’s Cost Submissions, para. 28, Annexure 1- 3. 726 Exhibit RL-163: Noble Ventures, Inc. v Romania, ICSID Case No. ARB/01/11, Award, 12 October 2005, paras. 234-235 (submitted as additional legal authorities along with Respondent’s Reply PHB). 727 Respondent’s Reply PHB, para. 125.

Page 188: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

181

that various procedural errors were made by the Claimant before the Tanzanian

Courts which included missing relevant deadlines;

that the Claimant’s withdrawal from the Tanzanian court proceedings and its failure

to properly challenge Utamwa J Order shows that its litigation strategy was not

genuine;

the fact that the Claimant bringing this arbitration after obtaining the PPA Award and

2016 Flaux J Judgment, which shows that its intention is to pressurise the

Respondent; and

finally, that the Claimant has inflated its relief which was reflected: (a) in its own

admission that there many areas of overlap in the Claimant’s calculations; (b)

Claimant originally claiming a payment order under the Loan Facility Agreement

which was changed once challenged by the Respondent on the illogical nature of such

an order; and (c) the claim for declaratory relief on behalf of IPTL for amounts which

IPTL would not be entitled is irrational.728

Thus, the Respondent submits that in line with the reasons stated above, the Tribunal should

award costs to the Respondent or if it finds in favour of the Claimant’s case then to apportion

costs in a manner that does not “unfairly overburden” the Respondent.729

The Respondent claims the following as costs:730

Item No. Category Amount 1 Fees and Expenses of the Tribunal and the

Charges of ICSID USD 175,000

2 Counsel Fees (Legal fees paid to Curtis, Mallet-Prevost, Colt & Mosle LLP)

USD 4,000,000

3 Counsel Expenses (total) USD 529,607.94 3.1 Expenses incurred by Curtis, Mallet-

Prevost, Colt & Mosle LLP USD 429,877.70

3.2 Expenses incurred by Crax Law Partners in Association with RK Rweyongeza and Co. Advocates

TZS 227,686,000 (approximately USD 99,730.24)

Total USD 4,704,607.94

728 Respondent’s Reply PHB, para. 126. 729 Respondent’s Reply PHB, para. 126. 730 Respondent’s Reply PHB, paras. 128-131.

Page 189: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

182

B. TRIBUNAL’S ANALYSIS

The Tribunal accepts that in ICSID arbitration, the principle of “loser pays” is not followed

strictly. The Tribunal is also aware that in many cases where the merits of each party’s case

are mixed, determining who is the successful party may be difficult. In this case, the Tribunal

has found that the Respondent committed acts of expropriation and taken discriminatory

actions against the Claimant. The clear conclusion is that the Claimant has succeeded

substantially in its claims, albeit its monetary awards have been moderated. The Tribunal

does not see how the actions taken by the Claimant were abusive when they were genuinely

attempting to legally assert their rights through whatever available legal course but had thus

far not been successful in doing so. The Tribunal therefore takes the view that the Respondent

must bear its own costs, the cost of this arbitration (i.e. the costs paid or payable to ICSID’s

administration, and the Tribunal’s fees and expenses) and the costs incurred by the Claimant

in prosecuting this matter.

The amount sought by the Claimant is approximately USD 4.13 million as compared to the

Respondent’s costs claim of USD 4.7 million. Given the work that had to be undertaken, the

Claimant’s costs appear to be fair and reasonable and would in normal circumstances be

recoverable.

The costs of the arbitration, including the fees and expenses of the Tribunal, ICSID’s

administrative fees and direct expenses, amount to (in USD):

Arbitrators’ fees and expenses

Prof Lawrence Boo (President)

Justice David Unterhalter SC (Co-arbitrator)

Dr Kamal Hossain (Co-arbitrator)

251,812.18

254,164.53

216,718.04

Mr Stanley Burnton (Co-Arbitrator) 3937.50

ICSID’s administrative fees 148,000.00

Direct expenses (estimated) 128,243.56

Total 1,002,875.81

As of the date of this Award, the Claimant had paid as advances towards the cost of ICSID and

the fees and expenses of the Tribunal, amounting to USD 937,764.33, including a portion of

the Respondent’s advances, whereas the Respondent has paid USD 175,000.00. As the

Claimant has stated in its Submission of Costs (see paragraph 532 above), it would not be

Page 190: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

183

seeking any order for cost of arbitration should the damages and compensation awarded

herein be sufficient to discharge the Respondent’s indebtedness under the Facility

Agreement, the Tribunal will make no order on the costs of arbitration or reimbursement of

any advances made.

IX. AWARD

For the reasons set out above,

The Tribunal hereby Declares –

I. That the Tribunal has jurisdiction over the Parties and the dispute:

a. The Claimant is the lawful assignee under Article 15.2 of the Implementation

Agreement and has the title and interest to pursue its claims against the

Respondent for any breach of the Implementation Agreement in its own

name; and

b. under Article 25 of the ICSID Convention.

II. that the United Republic of Tanzania has breached Articles 15.3, 16.1 and 16.2 of the

Implementation Agreement;

III. the Implementation Agreement was terminated on 6 July 2018 in accordance with

the Claimant’s Termination Notice; and

IV. the Claimant is entitled to compensation pursuant to termination under Article

20.1(d) of the Implementation Agreement and damages for the Respondent’s

breaches of the Implementation Agreement.

And the Tribunal therefore, Adjudges, Awards, Orders and Directs that–

The United Republic of Tanzania shall:

V. Pay to the Claimant the sum of USD 185,449,440.04 together with interest thereon

at the rate of LIBOR (6-month) +2% from the 1 September 2018 until the date of full

and final payment; and

VI. Bear its own legal costs and expenses.

Page 191: STANDARD CHARTERED BANK (HONG KONG IMITED...30 September 2015 The Secretary-General of ICSID registered the Request in accordance with Article 36(3) of the ICSID Convention and notified

David Unterhalter

Arbitrator

2, 5 SEP. ZD�

awrence G S Boo

President of the Tribunal

Date: 0 8 OCl. 2019

3 0 SEP. 2019

184

[signed] [signed]

[signed]