    Construction of Major Bridge with approaches across Vynatheya branch of River

    Godavari at Km 105.00 on NH-214, Kathipudi - Pamarru, NH division, Kakinada,

    A.P.

    Stage of work as on 31.08.2010

    Major Bridge:(2 Abutments & 12 piers Completed upto Substructure. 6 Piers completed upto

    Well cap & Substructure is in

    Progress.6 Piers Foundation is in progress.)

    A1 Bed Block & Dirt wall completed.

    P1 Bed block completed.

    P2 Bed block completed.

    P3 Bed block completed.

    P4 Casting of well Steining completed up to 38.58 m & arrangement for

    Kentledge is in progress for rectification of the shift of well.

    P5 Bed block completed.

    P6 Bed block completed.

    P7 Bed block completed.

    P8 Bed Block Completed. P9 Bed Block Completed.

    P10 Bed block completed.

    P11 Bed block completed.

    P12 Bed block completed.

    P13 Casting of well steining completed up to 35.46m against 35.46m and

    sinking is in progress.

    P14 Pier cap Completed.

    P15 Pier cap Completed.

    P16 Pier cap Completed.

    P17 Pier cap Completed.

    P18 Well Cap completed.

    P19 Casting of well steining completed up to 29.13m against 34.46m and

    sinking is in progress.

    P20 Casting of well steining completed up to 31.28m against 34.46m and

    sinking is in progress.

    P21 Casting of well steining completed up to 29.13m against 34.46m and

    sinking is in progress.

    P22 Casting of well steining completed up to 28.73m against 32.46m and

    sinking is in progress.

    P23 Well cap Completed.

    P24 Bed Block completed.

    A2 Dirt wall completed upto 2.70 m against 3.65 m.

    Benda Canal Bridge:

    Abutment1 Dirt wall& wing walls completed. P2-A2 Deck slab completed.

    Abutment2 Dirt wall& wing walls completed. P1-P2 Deck slab completed.

    Pier 1 Bed Block completed. A1-P1 Deck slab

    completed

    Pier 2 Bed Block completed.

    Box culvert on Manepalli Channel:

    Structure completed.

    Approaches:

  • 8/8/2019 Stage of Work as on 28.08.10

    2/2

    On Bodasakurru side (A1 side) Earth work excavation for top soil removal completed onA1 side from Ch.270.0 to Ch.552.0 (Abutment 1) and Embankment formation wascompleted above ground level to an average height of 2.0 mts & stopped due to thestoppage of embankment material by the Revenue Dept., for want of permit from MinesDept., since 28.04.2010. So far, 38,760 Cum. completed for Embankment Formation fromCh. 270 to Ch. 552. Now as the problem was solved, Contractor has restarted theconveyance of Embankment material since 08.07.10 and heaping the material near theAbutment1 & again stopped since 26.7.10.

    On Pasarlapudi side (A2 side) Top soil removal completed from Ch. 1640 to ch.1800.

    Cumulative value of work done is 47.160 % (` 2681.573Lakhs)