Single Site Verification Overview

• Hardware Check (for each sector)

• Network Check (for each sector)

• Service Static Test (for each sector)

• Service Dynamic Test (Clockwise and Anticlockwise)

Cluster Verification Overview

• 2G Cluster Drive Test

• 3G Cluster Drive Test

Page 3: SSV and CV Process_NEW

3www.huawei.com

3

Single Site Verification

Hardware Checking 1. For each cell, choose one location close the BTS. The target Cell

should be in the Light of Sight.2. The following items should be checked approximately:

Antenna Azimuth (Compass needed) Antenna Tilt (Visual)

Note: This test should be repeated for each Sector

If notice Big Configuration Problem such as big antenna deviation on azimuth or tilt, inform Huawei Interface and continue SSV in Another site (Report this in all your reports). Include pictures of site positions and surrounding environment (Two pictures for each sector 0°and 180°) .

Page 4: SSV and CV Process_NEW

4www.huawei.com

4

Single Site Verification

Network Checking 1. For 2G Network Check, collect the information below using an

IDLE UE locked in 2G mode : Frequency BCCH BSIC Cell ID LAC/RAC

2. For 3G Network Check, collect the information below using an IDLE UE locked in 3G mode : Frequency Primary Scrambling Code Cell ID LAC/RAC

3. Test 2G -> 3G reselection

Page 5: SSV and CV Process_NEW

5www.huawei.com

5

Single Site Verification

Hardware and Network Checking 1. Hardware and Network checking should be made together sector

by sector.2. If the 3 sectors are well configured from the Hardware and

Network information aspects, Test team can start Static Service test.

3. If Test team detects mistakes in the network configuration such as Frequency, BCCH, Scrambling code, Test team should process as follow:i. Contact with Huawei Interface to check if the problem could

be recovered immediately.ii. In case the problem can be solved immediately, Test team

should wait until the problem is recovered by Huawei team. Huawei will notice the test team about the problem recovery.

iii. In case the problem cannot be controlled immediately and will make some delay. Test team should move to another BTS for SSV.

Page 6: SSV and CV Process_NEW

6www.huawei.com

6

Single Site Verification

Page 7: SSV and CV Process_NEW

7www.huawei.com

7

Single Site Verification

Service Static Checking

1. For 2G Service Check, do the following tests using a UE locked in 2G mode : Mobile originated calls (3 times) Mobile terminated calls (3 times) EDGE FTP Download (3 times) (1Mbyte)

2. For 3G Service Check, do the following tests using a UE locked in 3G mode : AMR originated call (3 times). AMR terminated call (3 times). Video originated call (3 times). Video terminated call (3 times). R99 FTP download (3 times) (1Mbyte) HSDPA FTP download (3 times) (10Mbyte) HSUPA FTP Upload (3 times) (3Mbyte)

Page 8: SSV and CV Process_NEW

8www.huawei.com

8

Single Site Verification

2G Service Static Checking1. For 2G Service Check:

UE1: Mobile originated calls (3 times) Call by Call , Dial UE2 number, call duration 20 seconds and Test interval 15 seconds

UE2: Mobile terminated calls (3 times) called by UE1 UE1: FTP download from the server 10.12.4.5 with UE1 and download

the file 3 times (file size is 1Mbyte) :

2. Test is considered successful if all the voice tests are made successfully. If not, Contact with Huawei Interface in order to find arrangement.

3. Throughput status should be checked carefully, any abnormal event or instable throughput should be reported immediately and noted on the report. During tests, choose a place with good coverage (RxLev>-75, RxQual=0 and CI>18) and make sure that you can get 4 RTSL and MCS9;

4. Test is considered successful is all the data attempts are made successfully and maximum throughput reaches around 200kbps and stays stable around this value. If not, Contact with Huawei Interface in order to find arrangement.

5. Logfile should be saved and transferred to post processing engineer and Huawei team. The Logfile title should follow this format: Date_BTS name_CELLID_2G_Static_number

Page 9: SSV and CV Process_NEW

9www.huawei.com

9

Single Site Verification

3G Service Static Checking (1/2)1. For 3G Service Check:

UE1: AMR originated call (3 times): Call by Call , Dial UE2 number, call duration 20 seconds and Test interval 15 seconds.

UE2: AMR terminated call (3 times) UE1: Video originated call (3 times): Call by Call , Dial UE2 number,

call duration 30 seconds and Test interval 15 seconds. UE2: Video terminated call (3 times) UE1: FTP download from server 10.12.4.5 ; file is 1Mbyte

2. Test is considered successful if all the voice and the video tests are made successfully. If not, Contact with Huawei Interface in order to find arrangement.

3. Logfile should be saved and transferred to post processing engineer and Huawei team. The Logfile title should follow this format: Date_NodeB name_CELLID_R99_Static_number

Page 10: SSV and CV Process_NEW

10www.huawei.com

10

Single Site Verification

3G Service Static Checking (2/2)For HSPA Data service static check: HSPA datacard 1: download the file 3 times from the server 10.12.4.5 ;

file size is 10 Mbytes HSPA datacard 1: Upload the file 3 times to the server 10.12.4.5 ; file

size is 3 Mbytes

1. Logfile should be saved and transferred to post processing engineer and Huawei team. The Logfile title should follow this format: Date_NodeB name_CELLID_HSPA_Static_number

2. All PS throughput and statistics MUST be monitored during the test. If throughput is lower than threshold (R99=300kbps, HSDPA=2Mbps, HSUPA=1Mbps) you need to report that to report that to Huawei support team.

3. Test is considered successful is all the data attempts are made successfully. If not, Contact with Huawei Interface in order to find arrangement.

Page 11: SSV and CV Process_NEW

11www.huawei.com

11

Single Site Verification

Page 12: SSV and CV Process_NEW

12www.huawei.com

12

Single Site Verification

Service Dynamic Checking

1. For 2G Service Check, Use 3 UEs and one GPS in order to execute the following tests : Long call Short call FTP Download. (file size 3 Mbytes) Note: the test should be made Clockwise and anti clockwise

2. For 3G Service Check, Use 4 UEs and one GPS in order to execute the following tests : AMR Long call AMR Short call HSDPA download (file size 40 Mbytes) Note: the test should be made Clockwise and Anti Clockwise

Page 13: SSV and CV Process_NEW

13www.huawei.com

13

Single Site Verification

2G Service Dynamic Checking

1. For 2G Service Dynamic Check, Use 2 UEs and one GPS : UE1 locked in 2G mode: continuous call AutoReply Number

(1152) UE2 locked in 2G Short call: call by call Orange AutoReply

Number (1152), call duration 20 seconds and test interval 15 seconds

FTP download from Huawei FTP server 10.12.4.5. File size is 3 Mbytes.

Note: the test should be made Clockwise and anti clockwise

2. Logfile should be saved and transferred to post processing engineer and Huawei team. The Logfile title should follow this format: Date_BTS name_2G_Dynamic_number

3. If UE battery problem or UE or GPS disconnect with Proble, test team should stop the test recording, solve the tools problem and than start a new test recording. Different logfiles could be combined during troubleshooting phase.

Page 14: SSV and CV Process_NEW

14www.huawei.com

14

Single Site Verification

2G Service Dynamic Checking

Page 15: SSV and CV Process_NEW

15www.huawei.com

15

Single Site Verification

3G Service Dynamic Checking

1. For 3G Service Dynamic Check, UE1: AMR Long call : Continous call 1152 UE2: AMR Short call: call by call 20 s and Test interval 15

seconds to 1152. FTP download for HSDPA file size is 40 Mbytes.

2. The monitoring windows will be displayed automatically when the project will be opened

3. Logfile should be saved and transferred to post processing engineer and Huawei team. The Logfile title should follow this format: Date_NodeB name_3G_Dynamic_number

4. If UE battery problem or UE or GPS disconnect with Proble, test team should stop the test recording, solve the tools problem and than start a new test recording. Different logfiles could be combined during troubleshooting phase.

Page 16: SSV and CV Process_NEW

16www.huawei.com

16

Single Site Verification

3G Service Dynamic Checking

Page 17: SSV and CV Process_NEW

17www.huawei.com

17

Contents

Single Site Verification Overview

• Hardware Check (for each sector)

• Network Check (for each sector)

• Service Static Test (for each sector)

• Service Dynamic Test

Cluster Verification Overview

• 2G Cluster Drive Test

• 3G Cluster Drive Test

Page 18: SSV and CV Process_NEW

18www.huawei.com

18

Cluster VerificationDrive Test items

1. For 2G Service Check, the following tests will be considered: Idle (2G). 2G Only Long call. 2G Only Short call. Automatic Long call (2G and 3G). EDGE PS attach + PDP activation EDGE FTP Download (Dynamic) (2Mbyte). EDGE FTP Download (Static) (2Mbyte).

2. For 3G Service Check, the following tests will be considered: Scanner Idle automatic (Auto mode). 3G only short call. 3G only Long call . PS attach and PDP activation R99. PS attach and PDP activation HSDPA. PS attach and PDP activation HSUPA. R99 FTP download (Dynamic) (2 Mbytes). HSDPA FTP download (Dynamic) (33 Mbytes). HSUPA FTP download (Dynamic) (13 Mbytes).

Page 19: SSV and CV Process_NEW

19www.huawei.com

19

Cluster Verification

2G Cluster Verification (First Run)

1. For 2G First run : UE1 locked in 2G mode: Long call Orange AutoReply Number

1152 (Continuous call) UE2 locked in 2G mode: Short call Orange AutoReply Number

1152 (30s and test interval is 15s) HSPA datacard1: FTP download from Huawei Server 10.12.4.5

(file size is 33 Mbytes)

2. Logfile should be saved and transferred to post processing engineer and Huawei team. The Logfile title should follow this format: Date_Region_Cluster_name_2GFirstRun_Number

3. If UE battery problem or UE or GPS disconnect with Proble, test team should stop the test recording, solve the tools problem and than start a new test recording. Different logfiles could be combined during troubleshooting phase.

Page 20: SSV and CV Process_NEW

20www.huawei.com

20

Cluster Verification

2G Cluster Verification (Second Run)

1. For 2G second run: UE1 blocked in 2G: Idle UE2 automatic network selection: idle UE3 EDGE PS: Download from Orange FTP server (2 Mbytes)

2. Logfile should be saved and transferred to post processing engineer and Huawei team. The Logfile title should follow this format: Date_Region_Cluster_Name_2GSecondRun_Number

3. If UE battery problem or UE or GPS disconnect with Proble, test team should stop the test recording, solve the tools problem and than start a new test recording. Different logfiles could be combined during troubleshooting phase.

Page 21: SSV and CV Process_NEW

21www.huawei.com

21

Cluster Verification

3G Cluster Verification (First Run)

1. For 3G First run: Scanner: Scan FDD1 and FDD2 UE1 locked in 3G mode: Continous call Orange AutoReply

Number 1152 UE2 locked in 3G mode: Short call Orange AutoReply Number

1152 (30 seconds period and 15s test interval) UE3 locked in 3G mode: R99 FTP download from Orange Server

(2 Mbytes)

2. Logfile should be saved and transferred to post processing engineer and Huawei team. The Logfile title should follow this format: Date_Region_Cluster_Name_3GFirstRun_Number

3. If UE battery problem or UE or GPS disconnect with Proble, test team should stop the test recording, solve the tools problem and than start a new test recording. Different logfiles could be combined during troubleshooting phase.

Page 22: SSV and CV Process_NEW

22www.huawei.com

22

Cluster Verification

3G Cluster Verification (Second Run)

1. For 3G Second run, Use 2 UEs, 1 HSPA dongle and one scanner ; open the project named CV_3G_SecondRun_Test and start the test plan which includes the following tests : UE1 : Continuous call during to Orange auto reply number 1152

with Auto mode (2G+3G). As soon as a HHO happens, stop manually the call, wait until going back to 3G (reselection) then start manually the call again.

UE2 : HSUPA FTP upload to Orange Server (13 Mbytes)

2. Logfile should be saved and transferred to post processing engineer and Huawei team. The Logfile title should follow this format: Date_Region_Cluster_Name_3GSecondRun_Number

3. If UE battery problem or UE or GPS disconnect with Proble, test team should stop the test recording, solve the tools problem and than start a new test recording. Different logfiles could be combined during troubleshooting phase.

Page 23: SSV and CV Process_NEW

23www.huawei.com

23

Cluster Verification

General view on main problems to avoid• DO NOT stop recording log file before stopping the test. This will

lead to wrong call drops, wrong session drops, …• MUST put mobile phones and data cards near to the front

window of the car. Special attention to the U6100 which antenna is down and behind, so this mobile must be placed keyboard down.

• MUST include all the problem met during the DT or SSV in the report, this will allow quick and more accurate optimization.

• MUST follow general radio information on probe (radio condition, throughput, delay for reselection, …) report them to Huawei support team, and report them on your reports.

• SSV Reports must be provided, fully completed (including problem encountred during SSV), by 24 hours.

• CV Reports must be provided, fully completed (including problem encountred during CV), by 48 hours.