SRIPADASAGAR PROJECT (YELLAMPALLY PROJECT) AYACUT MAP.

15
SRIPADASAGAR PROJECT (YELLAMPALLY PROJECT) AYACUT MAP

Transcript of SRIPADASAGAR PROJECT (YELLAMPALLY PROJECT) AYACUT MAP.

SRIPADASAGAR PROJECT (YELLAMPALLY PROJECT)

AYACUT MAP

PKG No.

Description AwardedBid AmountRs. in Crs.

1

Construction of Sripada Sagar Project acress Godavari river at Yellampally (V), Ramagundam(M), Karimnagar Dt.

(Stage-I)

SCANSKA Cementation Ltd. 408.85

2

Excavation of approach channel Construction of pump house, Supply and commissioning of pumping machinery to lift 8.5 TMC, Transformers, sub-stations, Pressure mains Supply and layers of pipelines from Barrage to NTPC Balancing Reservoir.

M/s.Subhash

Projects &

Marketing(P) Ltd.

98.92

3

Stage-II, Phase-I of Sripada Sagar Project- supply,

installation and commissioning of pumping

machinery, transformers, sub-stations, pressure

mains including construction of pump house all civil

structures to irrigate 2.00 Lakh acres in upland areas

of Karimnagar (Dist.)

M/s. IVRCL-SEW-

Navayuga (JV)1737

TOTAL 2244.77

SRIPADA SAGAR PROJECT

1 Project Profile : i) Construction of Sri Padasagar Project across river Godavari (St-I) Ph-I

ii) Supply of 8.5 TMC of water to NTPC (St-I, Ph-II)

iii) Lifting 12 TMC to irrigate 2 Lakh Acres (St-II, Ph-I)

2 Administrative Sanction :G. O. Ms. No. 71, I & CAD (PW) GVI, Dt: 16-7-2004 for Rs. 900 Crores

3 No. of EPC Packages : 3 Nos.4 Agt. Value of 3 Pkgs : Rs. 2244.77Crs.

5 Budget Provision for 2006-07 (For GWUA) : Rs. 1240 Crs.

6 Expenditure of the Project

2004-05 : Rs. 20.44 Crs.

2005-06 : Rs. 202.07 Crs.

TOTAL : Rs. 222.51 Crs.

7 Utilisation ( Stg-I, Ph-I, Ph-II & Stg-II,Ph-I) : 20.5 TMC

Ultimate : 180.50 TMC8 Ayacut New Ayacut : 2,00,000 acres

SRIPADASAGAR L. I. SCHEME

9 Lift-I Lift Height : 96 M

No. of Pumps : 4 Nos.

Total pumps capacity : 10.8 MW

10 Lift-II

Lift Height : 120 M

No. of Pumps : 4 Nos.

Total pumps capacity : 13 MW

11 Lift-III Lift Height : 80 M

No. of Pumps : 4 Nos.

Total pumps capacity : 5,25 MW x 2, 8.26 MW x 2

12 Lift-IV

Lift Height : 50 M

No. of Pumps : 2 Nos.

Total pumps capacity : 0.50 MW

13 Power required (Stg-I, Ph-II) – water supply to NTPC : 9 MW

14 Power required (Stg-II, Ph-I) – Irrigation 2L Acs : 137 MW

SRIPADASAGAR L. I. SCHEME

15 Land Acquisition

Required : 15,981 acres

Acquired : 430 acres

Requisitioned : 15,981 acres

16 Est. Cost for LA : Rs. 222.00 Crores

17 Est. Cost for R & R : Rs. 500.00 Crores

18 Mobilisation Advance : PaidRecovered

2004-05 : Rs. 20.44 Crs.

2005-06 : Rs.106.05 Crs. 3.31 Crs.

Total : Rs. 126.49 Crs. 3.31 Crs.

19 Target date for completion : 10/2007

SRIPADASAGAR L. I. SCHEME

Package No. 1 : (Stg-I Ph-I)

Construction of Sripada Sagar Project across Godavari river at Yellampally (V), Ramagundam(M), Karimnagar Dt. to store 20 TMC at FRL + 148M.

Name of the Contractor : ITD Cementation India Ltd.

Agreement Amount : Rs. 408.85Crs.

Agreement Date : 07-11-2004/17-2-2005

Period of Completion : 36 Months(10 milestones)

Date of completion : 06-11-2008

SRIPADASAGAR PROJECT

Survey work : Completed Designs : Alignment of barrage - FINALISED

Earth bunds approved by CE/CDO; Spillway under approval in CE/CDO

Execution : Drilling of exploratory bore holes

in river for spill way & earth bund : Completed Excavation of Cutoff trenches for

right side & left side earthen

bunds : Completed Exc. of Cutoff trenches for spillway : In progress Qty. of Earthwork done : 2.43 L Cum against 3.062 L Cum. Expenditure : Rs. 63.59 Crores. (including Mob.

Advance Rs.36.04Crs.) against Rs. 408.85 Crores.

Land Acquisition : Required = 8745 Acres; Acquired=225 Acres Requisitioned = 8456 Acs.

Package No.2 : (Stg-I Ph-II)

i) Excavation of approach channel

ii) Construction of pump house

iii) Supply and commissioning of pumping machinery to lift 8.5 TMC, Transformers, sub-stations

iv) Pressure mains

v) Supply and laying of pipelines to NTPC Reservoir

Name of the Contractor : M/s.Subhash Projects &

Marketing(P) Ltd.

Agreement Amount : Rs. 98.92 Crs.

Agreement Date : 07-04-2005

Period of Completion : 18 Months (6

milestones)

Date of completion : 06-10-2006

SRIPADASAGAR PROJECT Water Supply to NTPC

Survey work : Completed

Designs : Designs for pressure mains submitted to CE/CDO & are under scrutiny

: Designs for pump houses, pumps etc. to be submitted by Agency

Designs of pipelines : Yet to be furnished by the Agency.

Execution : Fabrication Unit erected at site for manufacture of pipes

Alignment of pressure mains, location

of approach channel and intake well : under approval by CE/CDO

Expenditure : Rs.12.48Crs. (incl. Mob. Adv.) against Rs.98.92Crs.

Land acquisition : Required 70 Acres,

SRIPADASAGAR PROJECT (Stg-I, Ph-II) Water Supply to NTPC

1 Expenditure

2005-06 Works : Rs. 7.53 Crs.

Mob. Adv. : Rs.4.95 Crs.

Total : Rs. 12.48 Crs.

2 Land Acquisition

Total Required : 55 acres

Acquired : Nil

Requisitioned : 15 Acres

3Utilization

: 8.5 TMC

4 Lift-I

Lift Height : 50 M

No. of Pumps : 4

Total pumps capacity : 3300 HPs.

5 Power required : 9 MW

SRIPADASAGAR PROJECT STAGE-II, PHASE-I (Irrigation)

SALIENT FEATURES :

1 PROJECT PROFILE Installation and commissioning of pumping machinery, transformers, sub-stations, pressure mains including construction of pump house all civil structures to irrigate 2.00 Lakh acres in upland areas of Karimnagar (Dist.)

2 Admn. Sanction:

G. O. Ms. No. 149, I & CAD, Dt: 16-8-2005 for Rs. 1688.86 Crores

3 Expenditure

2005-06 : Rs.146.44 Crs.

4 Land Acquisition

Total Required : 15,000 acres

Acquired : Nil

Requisitioned : 407 Acres

5 Forest Land : 285 Acres

6Utilisation

: 12 TMC

7 Ayacut New Ayacut : 2 Lakhs acres

Stabilisation :

8 Lift-I

Lift Height : 96 M

No. of Pumps : 4 Nos.

Total pumps capacity : 10.8 MW

9 Lift-II

Lift Height : 120 M

No. of Pumps : 4 Nos.

Total pumps capacity : 13 MW

10 Lift-III

Lift Height : 80 M

No. of Pumps : 4 Nos.

Total pumps capacity :5,25 MW x 2, 8.26 MW x 2

SRIPADASAGAR PROJECT STAGE-II, PHASE-I

11 Lift-IV

Lift Height : 50 M

No. of Pumps : 2 Nos.

Total pumps capacity : 0.50 MW

12 Power required : 137 MW

13 Mobilisation Advance 2005-06 :PaidRecovered

Rs. 85.50Crs Rs. 3.31Crs.

SRIPADASAGAR PROJECT STAGE-II, PHASE-I

Package No.3 : Stage-II, Phase-I of

Sripada Sagar Project- supply,

installation and commissioning of

pumping machinery, transformers, sub-

stations, pressure mains including

construction of pump house all civil

structures to irrigate 2.00 Lakh acres in

upland areas of Karimnagar (Dist.)

Name of the Contractor : M/s. IVRCL-SEW-

Navayuga (JV)

Agreement Amount : Rs. 1737Crs.

Agreement Date : 03-04-2005

Period of Completion : 30 Months(10 milestones)

Date of completion : 02-10-2007

SRIPADASAGAR PROJECT

Utilization : 12 TMC (Lifting)

Power Required : 137 MW

Investigation : Pressure mains completed

: Pump house & gravity canal under progress

Designs : Designs of pressure mains and alignment submitted to CE/CDO for approval

Mobilization Advance paid : 85.50 Crores

Mob. Advance recovered : Rs. 3.31 Crs.

Land Acquisition : Required : 2000 Acres; Requisitioned : 437 Acres.

(Rs. 5.00 Crores deposited with Revenue Authorities)