SRI NARASIMHARAYA SAGAR PROJECT (G.B.R)

3
SRI NARASIMHARAYA SAGAR PROJECT (G.B.R) 1 PROJECT PROFILE: Construction of Sri Narasimharaya Sagar Reservoir (Gorakallu BR) with a live storage of 10.29 TMC at F.R.L. (+261 m). 2 Admn. Sanction : G.O.Ms.No. 145, Dt: 27-12- 2004 for Rs. 617.00 Crores 3 No. of Packages : 1 4 Agreement value of package : Rs. 448.2 Crs. 5 Expenditure of the project 2004-05 : Rs. 22.40 Crs. 2005-06 : Rs. 9.09 Crs. Cum. Exp. : Rs. 31.49 Crs. 6 Ayacut Stabilization(SRBC) : 1,90,000 Acers 7 Land Acquisition Required : 1898.13 Acres

description

SRI NARASIMHARAYA SAGAR PROJECT (G.B.R). SRI NARASIMHARAYA SAGAR PROJECT (G.B.R). SRI NARASIMHARAYA SAGAR (GORAKALLU BALANCING RESERVOIR). SRBC construction of Sri Narasimharaya Sagar Reservoir with a live storage of 10.29 TMC at F.R.L. (+261 m). - PowerPoint PPT Presentation

Transcript of SRI NARASIMHARAYA SAGAR PROJECT (G.B.R)

Page 1: SRI  NARASIMHARAYA  SAGAR  PROJECT (G.B.R)

SRI NARASIMHARAYA SAGAR PROJECT (G.B.R)

1 PROJECT PROFILE: Construction of Sri Narasimharaya Sagar Reservoir

(Gorakallu BR) with a live storage of 10.29 TMC at F.R.L. (+261 m). 2 Admn. Sanction : G.O.Ms.No. 145, Dt: 27-12-

2004 for Rs. 617.00 Crores

3 No. of Packages : 1

4Agreement value of package

: Rs. 448.2 Crs.

5 Expenditure of the project

2004-05 : Rs. 22.40 Crs.

2005-06 : Rs. 9.09 Crs.

Cum. Exp. : Rs. 31.49 Crs.

6Ayacut Stabilization(SRBC)

: 1,90,000 Acers

7 Land Acquisition

Required : 1898.13 Acres

Acquired : 1820.98 Acres

Balance to be acquired : 77.15 Acres

Page 2: SRI  NARASIMHARAYA  SAGAR  PROJECT (G.B.R)

10 Estimate cost of R & R : R & R Est. for Rs.2.35 Crores prepared and submitted to Govt. for Sugali thanda (V)

11 Storage capacity : 10.29 TMC12 Mobilisation Advance 2004-05 :

2005-06 : Rs. 22.40 Crores

Total : Rs. 22.40 Crores

13 Target Date : 3/2008

SRI NARASIMHARAYA SAGAR PROJECT (G.B.R)

9 Forest Land : 1923 Acres (Land process completed

& Acquired)

Present Status : Rs.4.60Crs. Paid towards afforestation Final clearance awaited from Forest authorities.

Page 3: SRI  NARASIMHARAYA  SAGAR  PROJECT (G.B.R)

i. SRBC construction of Sri Narasimharaya

Sagar Reservoir with a live storage of

10.29 TMC at F.R.L. (+261 m).

SRI NARASIMHARAYA SAGAR (GORAKALLU BALANCING RESERVOIR)

Name of the Contractor : M/s SABIR, SEW & PRASAD (JV)

Agreement Amount : Rs. 448.20 Crs.

Agreement Date : 31-3-2005

Period of Completion : 36 Months

Target date of Completion : 3/2008 Investigation : Completed

Designs : Approved

Execution : Earth work is in progress

Qty. of earth work done : 8.141 lakh cum against 124.00 lakh cum.

Machinery deployed : 102 Nos.

EXPENDITURE : Rs. 31.49 Crs. (inc. Mob. Adv. Rs. 22.4 Crs.) against 448.20 Crs.

2004-05 : Rs. 22.4 Crs. (Mob. Adv.)

2005-06 : Rs. 9.09 Crs.

Capacity of Reservoir : 10.29 TMC

Land Acquisition : Required – 1898.13 Acres; Acquired – 1820.98 Ac.

Balance to be acquired: 77.15 Acres

Forest Land : 1923 Acres process completed and Rs.4.60 Crores paid towards afforestation

R & R : Est. prepared for Rs.2.35 Crs and submitted to Govt.