SR 9/I-95 Interchange at 45 th Street Project Development and Environment (PD&E) Study Palm Beach County, Florida FPID No.: 436519-1-22-01 | FAP No.: 0951-682-1 | ETDM No.: 14225 Public Kick-Off Meeting September 13, 2016

Transcript of SR 9/I-95 Interchange at 45 th Street45Street_Public Kick... · 2016-09-14 · • SR 9/I-95...

SR 9/I-95 Interchange at 45th StreetProject Development and Environment (PD&E) Study

Palm Beach County, FloridaFPID No.: 436519-1-22-01 | FAP No.: 0951-682-1 | ETDM No.: 14225

Public Kick-Off MeetingSeptember 13, 2016

FPID No.: 436519-1-22-01 | FAP No.: 0951-682-1 | ETDM No.: 14225

SR 9/I-95 Interchange at 45th Street PD&E Study

Today’s Agenda

• Introduction

• Project Development & Environment (PD&E) Study Process

• Project Description

• Key Project Issues

Engineering Issues

Environmental Issues

• Summary Schedule

• Closing

2

FPID No.: 436519-1-22-01 | FAP No.: 0951-682-1 | ETDM No.: 14225

SR 9/I-95 Interchange at 45th Street PD&E Study

Introduction • What is a Project Development and Environment

(PD&E) Study?

o A process followed by FDOT to evaluate:

Engineering Alternatives

Environmental Impacts

Social, Cultural and Economic impacts associated with a planned transportation project

o Mandatory by the National Environmental Policy Act (NEPA)

o Required when Federal Funds are Involved

3

PLANNING

FINAL DESIGN &ENGINEERING

RIGHT-OF-WAYACQUISITION

PROJECT DEVELOPMENT& ENVIRONMENT

(PD&E) STUDY

CONSTRUCTION

MAINTENANCE

Phase 1

Phase 2

Phase 3

Phase 4

Phase 5

Phase 6

PUBL

IC IN

VOLV

EMEN

T

FPID No.: 436519-1-22-01 | FAP No.: 0951-682-1 | ETDM No.: 14225

SR 9/I-95 Interchange at 45th Street PD&E Study

PD&E Study Process

4

Phase 1

DATACOLLECTION

PRELIMINARYCONCEPTANALYSIS

ENGINEERING ANALYSIS &

DESIGNENVIRONMENTAL

ANALYSISFINAL

DOCUMENTS

Engineering Data Needs Analysis Engineering Analysis

Environmental Studies

Preliminary Engineering Report

Environmental Data Initial Concept Developments

Preliminary Engineering Screening

EnvironmentalDocuments Categorical

Exclusion Type II

Other Information Preliminary Concept

Screening

FHWA Issues Location and

Design Concept Acceptance

(LDCA)

FHWA Review ofFinal Documents

Phase 2 – PD&E Study

Value Engineering

PLANNING

FINAL DESIGN &ENGINEERING

RIGHT-OF-WAYACQUISITION

PROJECT DEVELOPMENT& ENVIRONMENT

(PD&E) STUDY

CONSTRUCTION

MAINTENANCE

Phase 2

Phase 3

Phase 4

Phase 5

Phase 6

PUBL

IC IN

VOLV

EMEN

T

FPID No.: 436519-1-22-01 | FAP No.: 0951-682-1 | ETDM No.: 14225

SR 9/I-95 Interchange at 45th Street PD&E Study

Project Description• SR 9/I-95 – from S of 45th Street to N of 45th Street• 45th Street – From Village Boulevard to Congress Avenue

5

FPID No.: 436519-1-22-01 | FAP No.: 0951-682-1 | ETDM No.: 14225

SR 9/I-95 Interchange at 45th Street PD&E Study

Background• SR 9/I-95 Interchange at 45th Street

Interchange Concept Development ReportFlorida Department of Transportation – District FourAugust 2014

• I-95 Master Plan StudyFlorida Department of Transportation – District Four2003

6

FPID No.: 436519-1-22-01 | FAP No.: 0951-682-1 | ETDM No.: 14225

SR 9/I-95 Interchange at 45th Street PD&E Study

Purpose and Need • Project Purpose: The purpose of the study is to identify the short-term

and long term needs of I-95 and develop design concepts to address traffic spillback onto I-95, improve interchange operations, reduce congestion, and increase safety at the study interchange. This study will also consider Strategic Intermodal System (SIS) connector improvements needed within the project area and is consistent with plans for the I-95 mainline, including the potential extension of I-95 Express lanes through Palm Beach County.

• Project Need: Capacity Transportation Demand Safety Planning Consistency Social Demands/Economic Development Modal Interrelationships System Linkage

7

FPID No.: 436519-1-22-01 | FAP No.: 0951-682-1 | ETDM No.: 14225

SR 9/I-95 Interchange at 45th Street PD&E Study

5 Year Crash History • Crash data from January 2010 to December 2014• 6 Fatal Crashes• Predominant crash types: Along I-95: Rear End: 40% Along 45th Street: Rear End: 33% and Head On: 33%

8

0

20

40

60

80

100

120

140

Villa

ge B

lvd

Nor

thpo

int B

lvd

I-95

SB R

amps

I-95

NB

Ram

ps

Corp

orat

e W

ay

Cong

ress

Ave

Crash Summary along 45th Street1 1

0

50

100

150

200

250

300

SB O

ff Ra

mp

SB O

n Ra

mp

I-95

at 4

5thSt

NB

Off

Ram

p

NB

On

Ram

p

Crash Summary along I-95

1

3

2010 2011 2012 2013 2014FATAL CRASHES

FPID No.: 436519-1-22-01 | FAP No.: 0951-682-1 | ETDM No.: 14225

SR 9/I-95 Interchange at 45th Street PD&E Study

What is Level of Service? • Level of Service (LOS)

A standard measurement, based on vehicle delay and speed, which reflects the relative ease of traffic flow on a scale of A to F

• LOS “A”: free-flow traffic

• LOS “F”: highly congested traffic conditions

9

ABCDEF

Optimal

Acceptable

Below Standard

FPID No.: 436519-1-22-01 | FAP No.: 0951-682-1 | ETDM No.: 14225

SR 9/I-95 Interchange at 45th Street PD&E Study

Existing ConditionsExisting 2015 Traffic Conditions

10

I-95

SB R

amps

Villa

ge B

lvd

Nor

thpo

int

Blvd

I-95

NB

Ram

ps

Cong

ress

Ave

Corp

orat

e W

ay

45th StreetD (E) D (D) C (B) C (C) B (B) C (C)

C (C)

AM Peak Hour LOSPM Peak Hour LOS

Source: I-95 (SR 9) Interchange at 45th Street Palm BeachInterchange Concept Development ReportHCM 2000 LOS

FPID No.: 436519-1-22-01 | FAP No.: 0951-682-1 | ETDM No.: 14225

SR 9/I-95 Interchange at 45th Street PD&E Study

Future No-Build ConditionsOpening Year 2025 No-Build

11

I-95

SB R

amps

Villa

ge B

lvd

Nor

thpo

int

Blvd

I-95

NB

Ram

ps

Cong

ress

Ave

Corp

orat

e W

ay

45th StreetD (E) D (D) D (C) C (D) C (D) D (E)

C (C)

AM Peak Hour LOSPM Peak Hour LOS

Source: I-95 (SR 9) Interchange at 45th Street Palm BeachInterchange Concept Development ReportHCM 2000 LOS

FPID No.: 436519-1-22-01 | FAP No.: 0951-682-1 | ETDM No.: 14225

SR 9/I-95 Interchange at 45th Street PD&E Study

Future No-Build ConditionsDesign Year 2045 No-Build

12

I-95

SB R

amps

Villa

ge B

lvd

Nor

thpo

int

Blvd

I-95

NB

Ram

ps

Cong

ress

Ave

Corp

orat

e W

ay

45th StreetE (E) F (F) F (E) E (E) D (F) F (F)

C (C)

AM Peak Hour LOSPM Peak Hour LOS

Source: I-95 (SR 9) Interchange at 45th Street Palm BeachInterchange Concept Development ReportHCM 2000 LOS

FPID No.: 436519-1-22-01 | FAP No.: 0951-682-1 | ETDM No.: 14225

SR 9/I-95 Interchange at 45th Street PD&E Study

Environmental Analysis • Efficient Transportation Decision Making (ETDM) #14225

• Effective/timely decision making without compromising environmental quality

• Enables agencies and public to provide early input about the potential effects of proposed transportation projects

• Anticipated Class of Action – Categorical Exclusion Type II

• For more ETDM information regarding this project please visit: https://etdmpub.fla-etat.org

13

N/A No InvolvementEnhancedMinimal to NoneModerateSubstantialDispute Resolution

N/A

2345

1

FPID No.: 436519-1-22-01 | FAP No.: 0951-682-1 | ETDM No.: 14225

SR 9/I-95 Interchange at 45th Street PD&E Study

Environmental Analysis

14

Land Use Changes Social Relocation Potential Farmlands Aesthetic Effect Economic Mobility

Section 4(f) potential Historic and Archeological Sites Recreation Areas

Social and Economic Effects

Cultural Effects

FPID No.: 436519-1-22-01 | FAP No.: 0951-682-1 | ETDM No.: 14225

SR 9/I-95 Interchange at 45th Street PD&E Study

Wetlands Water Quality and Quantity Floodplains Wildlife and Habitat Coastal and Marine

Noise Air Quality Contamination Infrastructure

Natural Resources

Physical Effects

Environmental Analysis

15

FPID No.: 436519-1-22-01 | FAP No.: 0951-682-1 | ETDM No.: 14225

SR 9/I-95 Interchange at 45th Street PD&E Study

Alternatives to be Considered • No-Build

• Transportation System Management & Operations (TSM&O)

• Build Alternatives

Improvements to the I-95 and 45th

Street Interchange

Improvements to Arterial Street Intersections along 45th Street

16

Alternatives Evaluation Process

NB

No Build Build Alternatives

1 2 3

ALTERNATIVES SCREENING

EVALUATION MATRIX

Traffic OperationsSafetyFreightAccess ManagementUtilitiesCanal ImpactsConstructabilityMOT

Historic & ArcheologicalWetlandsNoise ImpactsPermittingR/W ImpactsAesthetic FeaturesCommunity Services

AlternativesPublic Workshop

Recommended Alternative

A

TSM&O

FPID No.: 436519-1-22-01 | FAP No.: 0951-682-1 | ETDM No.: 14225

SR 9/I-95 Interchange at 45th Street PD&E Study

Agency Coordination Coordination

• Palm Beach Metropolitan Planning Association (MPO)• Palm Beach County Engineering and Public Works• Palm Tran • Florida Department of Environmental Protection (FDEP)• Florida Department of State Historical Resources • South Florida Water Management District (SFWMD)• US Fish and Wildlife Service • Federal Highway Administration • City of West Palm Beach• Town of Mangonia Park• City of Riviera Beach

17

FPID No.: 436519-1-22-01 | FAP No.: 0951-682-1 | ETDM No.: 14225

SR 9/I-95 Interchange at 45th Street PD&E Study

Summary Schedule Project Kick-Off Meeting: September 13th, 2016Alternatives Workshop: Spring 2017Public Hearing: Fall 2017

18

ACTIVITY2016 2017 2018

J F M A M J J A S O N D J F M A M J J A S O N D J F M A M JNotice to ProceedFact Sheet/NewsletterElected Officials/Agency Kick-Off MeetingPublic Kick-Off MeetingEngineering Data CollectionEngineering AnalysisEnvironmental Data CollectionEnvironmental AnalysisDevelop and Evaluate AlternativesAlternatives Public WorkshopEngineering ReportsEnvironmental ReportsPublic HearingFederal Highway Administration (FHWA) ReviewLocation and Design Concept Acceptance (LDCA)Continuous Public Involvement

FPID No.: 436519-1-22-01 | FAP No.: 0951-682-1 | ETDM No.: 14225

SR 9/I-95 Interchange at 45th Street PD&E Study

Public Involvement • 2 Public Meetings

• Public Hearing

• Coordination with local communities

• Coordination with major stakeholders

• Many opportunities for public comments:

Complete a Comment Form today

Mail, e-mail, or fax your comments

Visit the project’s website: www.95at45Street.com

19

FPID No.: 436519-1-22-01 | FAP No.: 0951-682-1 | ETDM No.: 14225

SR 9/I-95 Interchange at 45th Street PD&E Study

20

For more information, please call, email or write to:

Robert Lopes, PEProject Manager Florida Department of Transportation – District Four 3400 West Commercial BoulevardFort Lauderdale, FL 33309 Phone: (954) 777- 4425 Toll free: (866) 336-8435, ext. 4425E-mail: [email protected]