SQXF 25 m Cable Practice Winding at LBNL Miao Yu Dan Cheng 10/31/2013.
-
Upload
jayson-berry -
Category
Documents
-
view
220 -
download
2
Transcript of SQXF 25 m Cable Practice Winding at LBNL Miao Yu Dan Cheng 10/31/2013.
SQXF 25 m Cable Practice Winding at LBNL
Miao Yu
Dan Cheng
10/31/2013
Practice Winding Goal
• Wind inner layer of SQXF short version coil to – Test L1 end parts designed by BEND– Experience the cable windability
• Use the HQ winding mandrel as a baseline– FNAL-supplied mandrel spacer (120 mm -> 150 mm)
eliminates need for significant tooling fabrication• Some tooling was modified or adjusted
– All the parts were epoxy printed (SLA) through rapid prototyping machine.
2
Practice Winding Model
3
Need to modify clamping rig mount positions and hole locations
FNAL supplied spacer to fill space from 120mm to 150mm dia needs modification for mounting to HQ mandrel
4
Winding setup and procedure
• Use HQ winding traveler as the guidance• 30 lbs winding tension
5
Cable
• 25 m long QXF Cable wrapped with E-glass tape, the average insulation thickness is 0.15 mm
• Winding with the tool, no popped strands
6
Layer Jump Cable
Layer jump cable exit L1 LE Pole
SQXF Design at FNAL
7
End parts fitting
8
Fluffy Coil
• Low winding tension• Short coil has bigger end effect.
Off mid-plane by 10 mm
9
L1 LE
After compression very hard on LE, we can install the saddle and all the end parts fit better.
10
4~5 mm Gap
11
12
~3 mm gap
13
L1 RE
14
15
Experience from the winding
• The insulated cable (1045Z-13) was stable• Coil is very fluffy, although it is due to low winding
tension and short coil end effect, the flexible end parts are needed.
• Some of the parameter may need to be adjusted during 2nd iteration of the end parts. We will try 4 IL parts with different angle during 1 m SQXF coil.