ID Task Name Duration Start Finish 0 IMPROVEMENT TO SION PANVEL SPECIAL STATE HIGHWAY (UNDER B.O.T.) FROM B.A.R.C. JUNCTION(CH 140/690) TO KALAMBOLI JUNCTION (CH 115/800) - SECTION A,C AND D 441.25 days 29 Dec '11 29 Jun '13 1 LEFT HAND SIDE CARRIAGEWAY CONSTRUCTION 429.25 days 29 Dec '11 14 Jun '13 2 SECTION A: CH 126.140 - CH 128.200(APPROX 2.060KM) START OF SECTION 2 TO NEW SHIRVANE VEHICULAR UNDERPASS APPROACH THANE END 419 days 09 Jan '12 12 Jun '13 3 NEW CROSS DRAINAGE STRUCTURES 114 days 16 Jan '12 05 Jun '12 4 BOX CULVERT AT CH 126.310 84 days 16 Jan '12 28 Apr '12 5 BOX CULVERT AT CH 126.510 84 days 24 Jan '12 07 May '12 6 BOX CULVERT AT CH 126.700 84 days 01 Feb '12 16 May '12 7 BOX CULVERT AT CH 126.800 84 days 01 Feb '12 16 May '12 8 BOX CULVERT AT CH 127.015 84 days 21 Feb '12 05 Jun '12 9 NEW SLIP ROAD 180 days 16 Jan '12 25 Aug '12 10 ADJACENT TO EXISTING NERUL FLYOVER - CH 127.100 TO CH 127.800( 2LANE X 700MTR RIGID PAVEMENT) 180 days 16 Jan '12 25 Aug '12 11 NEW PEDESTRIAN UNDERPASS 282 days 01 Feb '12 17 Jan '13 12 PEDESTRIAN UNDERPASS AT CH 126.400 130 days 01 Feb '12 12 Jul '12 13 PEDESTRIAN UNDERPASS AT CH 127.270(BELOW EXISTING NERUL FLYOVER) 130 days 12 Jul '12 20 Dec '12 14 PEDESTRIAN UNDERPASS AT CH 127.400(BELOW EXISTING NERUL FLYOVER) 131 days 07 Aug '12 17 Jan '13 15 NEW VEHICULAR UNDERPASS 205 days 01 Oct '12 12 Jun '13 16 SHIRAVNE VEHICULAR UNDERPASS FROM CH 127.860 TO CH 128.195(335MTR WITH 2 CELL BOX FOR UNDERPASS TRAFFIC) 205 days 01 Oct '12 12 Jun '13

description

ddsfgdf

Transcript of Sptpl Jkil Program 24th Dec 11

Page 1: Sptpl Jkil Program 24th Dec 11

ID Task Name Duration Start Finish

0 IMPROVEMENT TO SION PANVEL SPECIAL STATE HIGHWAY (UNDERB.O.T.) FROM B.A.R.C. JUNCTION(CH 140/690) TO KALAMBOLIJUNCTION (CH 115/800) - SECTION A,C AND D

441.25days

29 Dec '11 29 Jun '13

1 LEFT HAND SIDE CARRIAGEWAY CONSTRUCTION 429.25days

29 Dec '11 14 Jun '13

2 SECTION A: CH 126.140 - CH 128.200(APPROX 2.060KM)START OF SECTION 2 TO NEW SHIRVANE VEHICULARUNDERPASS APPROACH THANE END

419 days 09 Jan '12 12 Jun '13

3 NEW CROSS DRAINAGE STRUCTURES 114 days 16 Jan '12 05 Jun '12

4 BOX CULVERT AT CH 126.310 84 days 16 Jan '12 28 Apr '12

5 BOX CULVERT AT CH 126.510 84 days 24 Jan '12 07 May '12

6 BOX CULVERT AT CH 126.700 84 days 01 Feb '12 16 May '12

7 BOX CULVERT AT CH 126.800 84 days 01 Feb '12 16 May '12

8 BOX CULVERT AT CH 127.015 84 days 21 Feb '12 05 Jun '12

9 NEW SLIP ROAD 180 days 16 Jan '12 25 Aug '12

10 ADJACENT TO EXISTING NERUL FLYOVER - CH 127.100TO CH 127.800( 2LANE X 700MTR RIGID PAVEMENT)

180 days 16 Jan '12 25 Aug '12

11 NEW PEDESTRIAN UNDERPASS 282 days 01 Feb '12 17 Jan '13

12 PEDESTRIAN UNDERPASS AT CH 126.400 130 days 01 Feb '12 12 Jul '12

13 PEDESTRIAN UNDERPASS AT CH 127.270(BELOWEXISTING NERUL FLYOVER)

130 days 12 Jul '12 20 Dec '12

14 PEDESTRIAN UNDERPASS AT CH 127.400(BELOWEXISTING NERUL FLYOVER)

131 days 07 Aug '12 17 Jan '13

15 NEW VEHICULAR UNDERPASS 205 days 01 Oct '12 12 Jun '13

16 SHIRAVNE VEHICULAR UNDERPASS FROM CH 127.860TO CH 128.195(335MTR WITH 2 CELL BOX FORUNDERPASS TRAFFIC)

205 days 01 Oct '12 12 Jun '13

-1

Page 2: Sptpl Jkil Program 24th Dec 11

ID Task Name Duration Start Finish

17 CONSTRUCTION OF FLEXIBLE PAVEMENT IN LANE 4 & 5FOR TRAFFIC DIVERSION BEFORE TAKING UP CCPAVEMENT WORKS IN MAIN CARRIAGEWAY LANE 1,2& 3

91 days 09 Jan '12 30 Apr '12

18

19 C.C. PAVEMENT WORKS - ALL FIVE LANES 208 days 01 Mar '12 15 Nov '12

20 NEW FOOT OVER BRIDGES 205 days 01 Oct '12 12 Jun '13

21 FOOT OVER BRIDGE AT CH 126.800 205 days 01 Oct '12 12 Jun '13

22 NEW STORM WATER DRAIN & FOOTPATH 144 days 15 Nov '12 14 May '13

23 MEDIAN REINSTATEMENT 237 days 08 Jun '12 30 Mar '13

24 SIGNAGES, LANDSCAPING & FINISHING WORKS 91 days 19 Feb '13 12 Jun '13

25 SECTION C: CH 130.450 - CH 133.900(APPROX 3.45KM)SANPADA FLOVER TO VASHI TOLL PLAZA EXCL. CCPAVEMENT

394 days 29 Dec '11 02 May '13

26 NEW SLIP ROAD FOR PROPOSED SANDAPA FLYOVERCONSTRUCTION

73 days 29 Dec '11 28 Mar '12

27 SLIP ROAD ADJACENT TO PROPOSED SANPADAFLYOVER ON LHS (APPROX 850MTR)

73 days 29 Dec '11 28 Mar '12

28 CONSTRUCTION OF LHS SIDE OF SANPADA FLYOVERBETWEEN CH 130.450 - CH 131.080

366 days 01 Feb '12 02 May '13

29 FOUNDATION(18 NOS, AVG 3 PILES EACH,18 PILECAPS)

186 days 01 Feb '12 20 Sep '12

30 SUBSTRUCTURE(18 NOS PIERS & CAPS) 210 days 02 Mar '12 19 Nov '12

31 SUPERSTRUCTURE(16 STANDARD SPANS, 1OBLIGATORY SPAN)

242 days 16 Apr '12 11 Feb '13

32 REINFORCED EARTHWORK STRUCTURE INAPPROACH - TURBHE END

90 days 20 Nov '12 12 Mar '13

33 REINFORCED EARTHWORK STRUCTURE INAPPROACH - SION END

90 days 20 Nov '12 12 Mar '13

34 FINISHING ITEMS(ANTI CRASH BARRIERS, EXPANSIONJOINTS, WEARING COAT)

156 days 12 Sep '12 26 Mar '13

-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18D J F M A M J J A S O N D J F M A M J

Task

Critical Task

Split

Milestone

Summary

Critical Summary

Project Summary

CLIENTPWD(SPECIAL PROJECT CELL)GOVT. OF MAHARASHTRA

IMPROVEMENT TO SION PANVEL SPECIAL STATE HIGHWAY (UNDER B.O.T.) FROM B.A.R.C. JUNCTION( CH 140/690) TO KALAMBOLI JUNCTION (CH115/800)

SECTION 2: CH 126.140 TO CH 140.700SECTION A,C AND D BOTH CARRIAGEWAY(LEFT+RIGHT) PART1 - REV R.1(DETAIL PROGRAM)

CONCESSIONAIRESION PANVEL TOLLWAY PVT LTD

EPC CONTRACTORJ.KUMAR INFRAPROJECTS LTD

Page 2 OF 7

Project: SPTPL-BOT PROJECT-SECTION 2Date: R.1 24TH DEC 11 - VLA

Create PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)

Page 3: Sptpl Jkil Program 24th Dec 11

ID Task Name Duration Start Finish

35 MISCELLANEOUS ITEMS(PAINTING, ELECTRICALS,SIGNAGES ETC)

136 days 14 Nov '12 02 May '13

36 SECTION D: CH 136.350 - CH 139.250(APPROX 2.90KM) VASHIJAKAT NAKA(BMC) TO MANKHURD VEHICULAR UNDERPASS

420 days 10 Jan '12 14 Jun '13

37 NEW CROSS DRAINAGE STRUCTURES 104 days 10 Jan '12 17 May '12

38 BOX CULVERT AT CH 137.380 84 days 10 Jan '12 23 Apr '12

39 BOX CULVERT AT CH 137.610 84 days 18 Jan '12 01 May '12

40 BOX CULVERT AT CH 138.040 84 days 26 Jan '12 10 May '12

41 BOX CULVERT AT CH 138.820 83 days 04 Feb '12 17 May '12

42 BOX CULVERT AT CH 139.190 83 days 04 Feb '12 17 May '12

43 NEW SLIP ROAD FOR PROPOSED CMLR DUPLICATIONFLYOVER

66 days 10 Jan '12 31 Mar '12

44 SLIP ROAD ADJACENT TO PROPOSED CMLRDUPLICATION FLYOVER - APPROX 700MTR

66 days 10 Jan '12 31 Mar '12

45 CONSTRUCTION OF DUPLICATION FLYOVER AT CMLRJUNCTION

332 days 27 Feb '12 15 Apr '13

46 FOUNDATION(22 NOS, AVG 3 PILES EACH,22 PILECAPS)

175 days 27 Feb '12 02 Oct '12

47 SUBSTRUCTURE(22 NOS PIERS & CAPS) 210 days 28 Mar '12 13 Dec '12

48 SUPERSTRUCTURE(20 STANDARD SPANS, 1OBLIGATORY SPAN)

210 days 10 May '12 26 Jan '13

49 REINFORCED EARTHWORK STRUCTURE INAPPROACH - VASHI END

90 days 15 Dec '12 05 Apr '13

50 REINFORCED EARTHWORK STRUCTURE INAPPROACH - SION END

90 days 15 Dec '12 05 Apr '13

51 FINISHING ITEMS(ANTI CRASH BARRIERS, EXPANSIONJOINTS, WEARING COAT)

182 days 25 Jul '12 08 Mar '13

52 MISCELLANEOUS ITEMS(PAINTING, ELECTRICALS,SIGNAGES ETC)

162 days 25 Sep '12 15 Apr '13

-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18D J F M A M J J A S O N D J F M A M J

Task

Critical Task

Split

Milestone

Summary

Critical Summary

Project Summary

CLIENTPWD(SPECIAL PROJECT CELL)GOVT. OF MAHARASHTRA

IMPROVEMENT TO SION PANVEL SPECIAL STATE HIGHWAY (UNDER B.O.T.) FROM B.A.R.C. JUNCTION( CH 140/690) TO KALAMBOLI JUNCTION (CH115/800)

SECTION 2: CH 126.140 TO CH 140.700SECTION A,C AND D BOTH CARRIAGEWAY(LEFT+RIGHT) PART1 - REV R.1(DETAIL PROGRAM)

CONCESSIONAIRESION PANVEL TOLLWAY PVT LTD

EPC CONTRACTORJ.KUMAR INFRAPROJECTS LTD

Page 3 OF 7

Project: SPTPL-BOT PROJECT-SECTION 2Date: R.1 24TH DEC 11 - VLA

Create PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)

Page 4: Sptpl Jkil Program 24th Dec 11

ID Task Name Duration Start Finish

53 NEW PEDESTRIAN UNDERPASS 121 days 01 Oct '12 27 Feb '13

54 PEDESTRIAN UNDERPASS AT CH 138.950 121 days 01 Oct '12 27 Feb '13

55 CONSTRUCTION OF FLEXIBLE PAVEMENT IN LANE 4 & 5FOR TRAFFIC DIVERSION BEFORE TAKING UP CCPAVEMENT WORKS IN MAIN CARRIAGEWAY LANE 1,2& 3

66 days 10 Jan '12 31 Mar '12

56

57 C.C. PAVEMENT WORKS - ALL FIVE LANES 210 days 22 Mar '12 08 Dec '12

58 NEW STORM WATER DRAIN & FOOTPATH 147 days 10 Dec '12 10 Jun '13

59 NEW FOOT OVER BRIDGES 207 days 01 Oct '12 14 Jun '13

60 FOOT OVER BRIDGE AT CH 136.710 195 days 01 Oct '12 30 May '13

61 FOOT OVER BRIDGE AT CH 139.250 193 days 17 Oct '12 14 Jun '13

62 MEDIAN REINSTATEMENT 181 days 20 Aug '12 01 Apr '13

63 SIGNAGES, LANDSCAPING & FINISHING WORKS 179 days 05 Nov '12 14 Jun '13

64

65 RIGHT HAND SIDE CARRIAGEWAY CONSTRUCTION 433days

09 Jan '12 29 Jun '13

66 SECTION A: CH 126.140 - CH 128.200(APPROX 2.060KM)START OF SECTION 2 TO NEW SHIRVANE VEHICULARUNDERPASS APPROACH THANE END

433 days 09 Jan '12 29 Jun '13

67 NEW CROSS DRAINAGE STRUCTURES 114 days 16 Jan '12 05 Jun '12

68 BOX CULVERT AT CH 126.310 84 days 16 Jan '12 28 Apr '12

69 BOX CULVERT AT CH 126.510 84 days 24 Jan '12 07 May '12

70 BOX CULVERT AT CH 126.700 84 days 01 Feb '12 16 May '12

-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18D J F M A M J J A S O N D J F M A M J

Task

Critical Task

Split

Milestone

Summary

Critical Summary

Project Summary

CLIENTPWD(SPECIAL PROJECT CELL)GOVT. OF MAHARASHTRA

IMPROVEMENT TO SION PANVEL SPECIAL STATE HIGHWAY (UNDER B.O.T.) FROM B.A.R.C. JUNCTION( CH 140/690) TO KALAMBOLI JUNCTION (CH115/800)

SECTION 2: CH 126.140 TO CH 140.700SECTION A,C AND D BOTH CARRIAGEWAY(LEFT+RIGHT) PART1 - REV R.1(DETAIL PROGRAM)

CONCESSIONAIRESION PANVEL TOLLWAY PVT LTD

EPC CONTRACTORJ.KUMAR INFRAPROJECTS LTD

Page 4 OF 7

Project: SPTPL-BOT PROJECT-SECTION 2Date: R.1 24TH DEC 11 - VLA

Create PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)

Page 5: Sptpl Jkil Program 24th Dec 11

ID Task Name Duration Start Finish

71 BOX CULVERT AT CH 126.800 84 days 01 Feb '12 16 May '12

72 BOX CULVERT AT CH 127.015 84 days 21 Feb '12 05 Jun '12

73 NEW SLIP ROAD 180 days 16 Feb '12 27 Sep '12

74 ADJACENT TO EXISTING NERUL FLYOVER - CH 127.100TO CH 127.800( 2LANE X 700MTR RIGID PAVEMENT)

180 days 16 Feb '12 27 Sep '12

75 NEW PEDESTRIAN UNDERPASS 282 days 18 Feb '12 04 Feb '13

76 PEDESTRIAN UNDERPASS AT CH 126.400 130 days 18 Feb '12 30 Jul '12

77 PEDESTRIAN UNDERPASS AT CH 127.270(BELOWEXISTING NERUL FLYOVER)

130 days 30 Jul '12 08 Jan '13

78 PEDESTRIAN UNDERPASS AT CH 127.400(BELOWEXISTING NERUL FLYOVER)

131 days 24 Aug '12 04 Feb '13

79 NEW VEHICULAR UNDERPASS 205 days 01 Oct '12 12 Jun '13

80 SHIRAVNE VEHICULAR UNDERPASS FROM CH 127.860TO CH 128.195(335MTR WITH 2 CELL BOX FORUNDERPASS TRAFFIC)

205 days 01 Oct '12 12 Jun '13

81 CONSTRUCTION OF FLEXIBLE PAVEMENT IN LANE 4 & 5FOR TRAFFIC DIVERSION BEFORE TAKING UP CCPAVEMENT WORKS IN MAIN CARRIAGEWAY LANE 1,2& 3

91 days 09 Jan '12 30 Apr '12

82

83 C.C. PAVEMENT WORKS - ALL FIVE LANES 208 days 19 Mar '12 03 Dec '12

84 NEW FOOT OVER BRIDGES 205 days 01 Oct '12 12 Jun '13

85 FOOT OVER BRIDGE AT CH 126.800 205 days 01 Oct '12 12 Jun '13

86 NEW STORM WATER DRAIN & FOOTPATH 144 days 03 Dec '12 30 May '13

87 MEDIAN REINSTATEMENT 237 days 27 Jun '12 17 Apr '13

-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18D J F M A M J J A S O N D J F M A M J

Task

Critical Task

Split

Milestone

Summary

Critical Summary

Project Summary

CLIENTPWD(SPECIAL PROJECT CELL)GOVT. OF MAHARASHTRA

IMPROVEMENT TO SION PANVEL SPECIAL STATE HIGHWAY (UNDER B.O.T.) FROM B.A.R.C. JUNCTION( CH 140/690) TO KALAMBOLI JUNCTION (CH115/800)

SECTION 2: CH 126.140 TO CH 140.700SECTION A,C AND D BOTH CARRIAGEWAY(LEFT+RIGHT) PART1 - REV R.1(DETAIL PROGRAM)

CONCESSIONAIRESION PANVEL TOLLWAY PVT LTD

EPC CONTRACTORJ.KUMAR INFRAPROJECTS LTD

Page 5 OF 7

Project: SPTPL-BOT PROJECT-SECTION 2Date: R.1 24TH DEC 11 - VLA

Create PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)

Page 6: Sptpl Jkil Program 24th Dec 11

ID Task Name Duration Start Finish

88 SIGNAGES, LANDSCAPING & FINISHING WORKS 91 days 08 Mar '13 29 Jun '13

89 SECTION C: CH 130.450 - CH 133.900(APPROX 3.45KM)SANPADA FLOVER TO VASHI TOLL PLAZA EXCL. CCPAVEMENT

416 days 16 Jan '12 15 Jun '13

90 NEW SLIP ROAD FOR PROPOSED SANDAPA FLYOVERCONSTRUCTION

73 days 16 Jan '12 14 Apr '12

91 SLIP ROAD ADJACENT TO PROPOSED SANPADAFLYOVER ON LHS (APPROX 850MTR)

73 days 16 Jan '12 14 Apr '12

92 CONSTRUCTION OF RHS SIDE OF SANPADA FLYOVERBETWEEN CH 130.450 - CH 131.080

384 days 24 Feb '12 15 Jun '13

93 FOUNDATION(18 NOS, AVG 3 PILES EACH,18 PILECAPS)

196 days 24 Feb '12 25 Oct '12

94 SUBSTRUCTURE(18 NOS PIERS & CAPS) 221 days 24 Mar '12 25 Dec '12

95 SUPERSTRUCTURE(16 STANDARD SPANS, 1OBLIGATORY SPAN)

260 days 08 May '12 27 Mar '13

96 REINFORCED EARTHWORK STRUCTURE INAPPROACH - TURBHE END

90 days 26 Dec '12 17 Apr '13

97 REINFORCED EARTHWORK STRUCTURE INAPPROACH - SION END

90 days 26 Dec '12 17 Apr '13

98 FINISHING ITEMS(ANTI CRASH BARRIERS, EXPANSIONJOINTS, WEARING COAT)

156 days 27 Oct '12 09 May '13

99 MISCELLANEOUS ITEMS(PAINTING, ELECTRICALS,SIGNAGES ETC)

136 days 28 Dec '12 15 Jun '13

100 SECTION D: CH 136.350 - CH 138.650(APPROX 2.30KM) VASHIJAKAT NAKA(BMC) TO MANKHURD VEHICULAR UNDERPASS

432 days 10 Jan '12 29 Jun '13

101 NEW CROSS DRAINAGE STRUCTURES 104 days 10 Jan '12 17 May '12

102 BOX CULVERT AT CH 137.380 84 days 10 Jan '12 23 Apr '12

103 BOX CULVERT AT CH 137.610 84 days 18 Jan '12 01 May '12

104 BOX CULVERT AT CH 138.040 84 days 26 Jan '12 10 May '12

105 BOX CULVERT AT CH 138.820 83 days 04 Feb '12 17 May '12

-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18D J F M A M J J A S O N D J F M A M J

Task

Critical Task

Split

Milestone

Summary

Critical Summary

Project Summary

CLIENTPWD(SPECIAL PROJECT CELL)GOVT. OF MAHARASHTRA

IMPROVEMENT TO SION PANVEL SPECIAL STATE HIGHWAY (UNDER B.O.T.) FROM B.A.R.C. JUNCTION( CH 140/690) TO KALAMBOLI JUNCTION (CH115/800)

SECTION 2: CH 126.140 TO CH 140.700SECTION A,C AND D BOTH CARRIAGEWAY(LEFT+RIGHT) PART1 - REV R.1(DETAIL PROGRAM)

CONCESSIONAIRESION PANVEL TOLLWAY PVT LTD

EPC CONTRACTORJ.KUMAR INFRAPROJECTS LTD

Page 6 OF 7

Project: SPTPL-BOT PROJECT-SECTION 2Date: R.1 24TH DEC 11 - VLA

Create PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)

Page 7: Sptpl Jkil Program 24th Dec 11

ID Task Name Duration Start Finish

106 BOX CULVERT AT CH 139.190 83 days 04 Feb '12 17 May '12

107 NEW PEDESTRIAN UNDERPASS 121 days 01 Oct '12 27 Feb '13

108 PEDESTRIAN UNDERPASS AT CH 138.950 121 days 01 Oct '12 27 Feb '13

109 CONSTRUCTION OF FLEXIBLE PAVEMENT IN LANE 4 & 5FOR TRAFFIC DIVERSION BEFORE TAKING UP CCPAVEMENT WORKS IN MAIN CARRIAGEWAY LANE 1,2& 3

66 days 10 Jan '12 31 Mar '12

110

111 C.C. PAVEMENT WORKS - ALL FIVE LANES 210 days 09 Apr '12 26 Dec '12

112 NEW STORM WATER DRAIN & FOOTPATH 147 days 26 Dec '12 27 Jun '13

113 NEW FOOT OVER BRIDGES 207 days 01 Oct '12 14 Jun '13

114 FOOT OVER BRIDGE AT CH 136.710 195 days 01 Oct '12 30 May '13

115 FOOT OVER BRIDGE AT CH 139.250 193 days 17 Oct '12 14 Jun '13

116 MEDIAN REINSTATEMENT 181 days 05 Sep '12 18 Apr '13

117 SIGNAGES, LANDSCAPING & FINISHING WORKS 179 days 19 Nov '12 29 Jun '13

PWD(SPECIAL PROJECT CELL)GOVT. OF MAHARASHTRAFROM B.A.R.C. JUNCTION( CH 140/690) TO KALAMBOLI JUNCTION (CH115/800)SECTION 2: CH 126.140 TO CH 140.700SECTION A,C AND D BOTH CARRIAGEWAY(LEFT+RIGHT) PART1 - REV R.1(DETAIL PROGRAM)SION PANVEL TOLLWAY PVT LTDEPC CONTRACTORJ.KUMAR INFRAPROJECTS LTDProject: SPTPL-BOT PROJECT-SECTION 2Date: R.1 24TH DEC 11 - VLA