Spring Proposal 1-14-10 - Pennsylvania State University · Spring Thesis Proposal Revision January...
Transcript of Spring Proposal 1-14-10 - Pennsylvania State University · Spring Thesis Proposal Revision January...
Neonatal Intensive Care Unit (NICU)
3030 W. Dr. Martin Luther King, Jr. Blvd.
Tampa, FL 33607
Spring Thesis Proposal Revision
January 14, 2011
Dennis Gibson
Construction Management
Dr. Robert Leicht
December 10, 2010 ST. JOSEPH’S WOMEN’S HOSPITAL – NICU EXPANSION
Dennis Gibson - CM | Final Thesis Proposal 2
Executive Summary
After a full semester of analyzing the current construction means and methods, costs, scheduling, contracts, and issues, this document has been drafted to propose potential opportunities to improve upon these current procedures. Unexplored areas that may pose potential benefits for the construction processes are going to be explored, covering various topics such as constructability, value engineering, critical industry issues and trends, and schedule acceleration scenarios. These analyses have been organized into four construction depth analyses, which will be supplemented with a structural redesign breadth analysis and a mechanical redesign breadth analysis.
The first analysis entails redesigning the façade to include more prefabrication, which is a currently increasing industry trend. The idea will be to include the glazing in a manufacturing environment so as to reduce cost, increase quality, and save time in the field. This will be the primary analysis, covering all four points mentioned above, and constituting the majority of the report.
Currently the structural slab system is 12” thick with double matted rebar. In a hospital where above ceiling MEP space is at a premium, and in an economy where material costs have succumbed to inflation, it would be beneficial to explore other floor system options. A comparative matrix will be created to help the owner, engineers, and contractors visually and numerically assess their decision on which floor system would best benefit them. From there the chosen slab type will be designed at a basic level to manifest a general working knowledge of structural design methods.
The current schedule is aggressive and entails some phased turnover along with a difficult demolition phase. Different opportunities for phased turnover and sequencing will be explored in hopes to accelerate the overall project schedule, or better distribute float to tasks with ambiguous durations.
Finally an energy study will be conducted on the current design and then suggestions for engineered improvement will be made. The building is set to achieve LEED Certified. Possibly with more energy reduction provisions, Silver will be possible. Once an energy reduction system is chosen, it will be schematically designed and analyzed for return on investment in addition to initial costs. This analysis will also comprise the mechanical breadth.
These topics may be subject to change pending a site visit over the winter break, and feedback early next semester from industry professionals and faculty advisors.
December 10, 2010 ST. JOSEPH’S WOMEN’S HOSPITAL – NICU EXPANSION
Dennis Gibson - CM | Final Thesis Proposal 3
Contents
Executive Summary ................................................................................................................................... 2
Project Information .................................................................................................................................... 4
Construction Analysis Topics .................................................................................................................. 5
Analysis #1: Façade Redesign and Prefabrication ............................................................................. 5
Analysis #2: Change of Structural Slab Design .................................................................................. 6
Analysis #3: Phased Turnover & Resequencing of Construction .................................................... 7
Analysis #4: Energy Assessment and Reduction ............................................................................... 8
Analysis Weight Matrix .......................................................................................................................... 11
Conclusion ................................................................................................................................................ 11
Appendix A: Breadth Analysis Topics .................................................................................................. 12
Breadth Requirements ............................................................................................................................. 13
Structural Breadth ................................................................................................................................ 13
Mechanical Design Breadth ................................................................................................................ 13
Appendix B: Schedule for Development of Analyses, Spring 2011 .................................................. 14
Appendix C – Slab Comparison Analysis Matrix ............................................................................... 16
Deecember 1
Projec
In April 20Women’stwice as mprivacy. Ioperatingfacility wi
Constructtight deadfive story the demoorange. Foutlined isensitive cprocesses
Prior to thaccommomechanicThere are
0, 2010
ct Informa
010, BayCare Hospital NICmany patientsn addition tog rooms will all achieve LEE
tion has beendlines for phastructural co
olition of the eFinally, a renon green. Maicustomers sus, and intense
Figure 1. St. J
he start of coodate the poscal feeds will ce still provisio
ST. JOSE
ation
Health SysteCU Tower in ds as the existi standard patlso be constrED Certificatio
broken into ased turnoverncrete structexisting NICUovation of exintaining full ouch as premate planning in o
Joseph’s NICU
nstruction, Basibility of an acome from thns for new ai
EPH’S WO
Denn
m began conowntown Taming facilities, atient rooms, aucted within on, upon com
three phasesr. The first phture outlined in red, and tsting hospitaoperational stture babies, torder to be su
Phasing Plan. A
ayCare Healthaddition suchhe main chiller handlers an
MEN’S HO
nis Gibson
struction on mpa, FL. Theand do so wita new breast the new five
mpletion in Jul
s, which will rhase will incluin blue in Fighe constructil facilities wiltatus is the phe task will reuccessful.
ALS‐51A from
h system hadh as this. Theer plant and end pumps to b
OSPITAL –
n - CM | Fin
its newest ade new structuth fully exclushealth centestory structuly 2012.
equire the Baude the consture 1 below. ion of the fivel comprise thrimary conceequire strict a
100% CD’s, Co
d renovated aerefore, the melectrical roombe installed in
– NICU EXP
nal Thesis
ddition, the Stre is designedsive rooms foer, medical imural concrete
arton Malow truction of the The second e story connehe phase threern of the ownattention to d
ompliments of
ll major mechmajority of elem in the existn the sixth flo
PANSION
s Proposa
t. Joseph’s d to accommoor increased maging suites,building. The
team to meee new tower,phase will invector wing in e work, as sener, and withdetail, efficien
HKS, Inc.
hanical systemectrical and ing hospital. oor mechanica
al 4
odate
and e new
et , a volve
en h nt
ms to
al
December 10, 2010 ST. JOSEPH’S WOMEN’S HOSPITAL – NICU EXPANSION
Dennis Gibson - CM | Final Thesis Proposal 5
penthouse of the new facility, but the MEP effort has been greatly aided by the owner’s pre‐planning. Also, a cool roof is scheduled to be installed in an effort to reduce the cooling loads needed in the tropical climate. The façade itself consists of precast concrete panels and large windows, but phase two will manifest a large glass curtain wall on the North side, facing Martin Luther King, Jr. Blvd. and St. Joseph’s Hospital across the street. When completed, St. Joseph’s Women’s Hospital will house the premier Neonatal Intensive Care Facility in Central Florida.
In addition to challenges presented by the intense nature of constructing a healthcare facility, the St. Joseph’s project team must compete with a tight urban site, height restrictions imposed by local FAA laws, and the surgical demolition of a partially operational building. These and many other factors evoke the opportunity to study several construction process oriented topics to improve the overall efficiency of building this project.
Construction Analysis Topics
Analysis #1: Façade Redesign and Prefabrication
The FAA height restriction placed a limit on the size of the crane that could be used for the construction of the superstructure. This last minute issue forced the project team to resort to two smaller cranes, which approach the limits of their capabilities in this particular application. In an attempt to get the precast panel façade installed on the East side of the building, where the crane will be making the most difficult picks, the precast manufacturer was able to construct the panels out of lightweight concrete. This created the need for a different connection method of window frames, as the anchors to those frames were originally designed to be placed directly into the concrete panels. A Notice of Acceptance (NOA) rating number, which certifies the window for multiple tests including fire and blast resistance, as well as wind and rain leakage, had never been issued for the system that had to be designed. In a geographic region that is predisposed to hurricanes, there was little room for this detail to go overlooked. NOA testing takes time, so the possibility of schedule impact was very much a concern, although to date this issue has not affected the critical path.
Research Focus and Goal: Since the project team did not have time to redesign the façade for the field condition, it presents the opportunity to do so now. The real focus will not just be on the connection detail of the window frames to the precast panel, which is typically an architectural issue, but rather on the possibility of enhancing the prefabrication scope to include frames and glazing into the precast panels at the factory. Prefabrication has been a developing market in the construction industry in recent years, and will be a good way to reduce the time that will be needed for the glazing contractor to perform installations onsite. Additionally, the panel layout should be redesigned so that the crane can comfortably make the long picks needed to complete the East façade construction.
Means and Methods: The research for this task will include feasibility studies with the project team, precast concrete manufacturer, and glazing contractor. A basic understanding of the NOA rating points can be obtained from local building code literature, as well as interviews with the glazing manufacturer.
December 10, 2010 ST. JOSEPH’S WOMEN’S HOSPITAL – NICU EXPANSION
Dennis Gibson - CM | Final Thesis Proposal 6
A basic understanding of the structural requirements for the façade connections can also be obtained from an interview with the structural engineer. Once feasibility is established, the layout of the façade itself can be altered to allow window panes to be totally enclosed and sealed to the precast at the factory. Then the façade will be cut into sections that can be easily managed by the crane. Productivity analyses and cost analyses should be carried out to forecast the magnitude of cost savings and schedule savings, if any.
Expected Outcomes: The analysis is intended to achieve the following:
• Decide if the idea as a whole is conceptually feasible • Identify if there is a net schedule savings by eliminating the glazing contractor’s time onsite • Assure that the crane is able to safely and efficiently set the façade pieces • Identify if there is a cost savings by prefabricating the pieces in a manufacturing environment • Determine the quality control and safety advantages from prefabrication in a manufacturing
environment • Understand the NOA rating system
Analysis #2: Change of Structural Slab Design
Currently the two‐way flat plate structural floor slabs are 12” thick with double matted rebar. Approximately 4,500 cubic yards of f’c=5,000 psi concrete is estimated to be needed for the construction of only these slabs. At nearly $100 per yard, there exists an opportunity for savings if the amount of concrete can be reduced. Based on personal experience with structural concrete installations, post‐tensioned slab systems can offer a decent amount of thickness reduction, thus saving money on concrete costs. There are many other systems which may reduce this number as well, including precast solutions such as duct plank.
Research Focus and Goals: The main focus of this analysis will be to value engineer the structural slab system in an effort to reduce cost. This can be done by reducing material costs, or accelerating the schedule, thus reducing the general conditions costs, and field labor.
Means and Methods: The first step will involve creating a comparison matrix between multiple floor systems to see the benefits and disadvantages of each type of system. This matrix should be designed with cost in mind as the main driver. An example of this Weight Matrix can be found in Appendix C. From here, the selected system(s) will be designed at a basic level to create the basis for a detailed estimate. The detailed estimate will then be carried out and compared to the original design to evaluate savings.
Expected Outcomes: The analysis is intended to achieve the following:
• Determine if another construction type is found to be financially beneficial • Identify if the construction type chosen can accelerate the schedule
December 10, 2010 ST. JOSEPH’S WOMEN’S HOSPITAL – NICU EXPANSION
Dennis Gibson - CM | Final Thesis Proposal 7
• Correctly design the selected system at a basic level • Create a professional matrix that can be used as a template to weigh the decision between
structural floor systems • Above ceiling space is maximized to accommodate MEP equipment
Analysis #3: Phased Turnover & Resequencing of Construction
The three phase project has very critical milestone dates for turnover. The deadline for phase one completion marks the beginning of the owner’s move from the existing NICU facility into the new NICU tower. From here, the focus shifts to surgically severing and demolishing the existing NICU structure which is tied into the existing operational part of the hospital. There have only been twenty work days allotted for this work. That is extremely tight considering the extensive MEP equipment in the facility, and all of the connections running back into the existing hospital that will need to be cut, capped, and safed off prior to the demolition of the structure. Also ICRA protection and temporary facilities must be adjusted accordingly. Temporary sound attenuation must be installed in the new NICU tower to protect delicate premature babies from the intense sound that may occur during demolition. The existing NICU also has a few areas that will require abatement. The first area applies to the insulation around mechanical piping fittings. These fittings must be removed separately from the rest of the system, but can be cut on either side of every fitting so as to not have to penetrate the asbestos itself. While this is a safe method of abatement, it still must follow proper procedures and takes a significant amount of time. The second type is found under the old VCT flooring and in the form of mastic. Abatement of these areas require keeping the floor submerged in water so as to not allow the asbestos to become airborne. This is a safer abatement, but again requires time consuming procedures, as the concrete below will need to be recycled for the LEED credits.
Research Focus and Goals: The current schedule can be analyzed for possible alternative sequencing scenarios. With the new NICU tower being roughly twice as large as the current facility, there would not be a need for total completion of the new tower before the owner can begin partially occupancy. It would be feasible to finish three floors early to accommodate the existing patients, while leaving the remaining floors to be completed under less pressure. This will allow a little more time for the prep work and demolition of the existing facility. The demolition seems to be the current hot spot in the schedule so anything to create float for this activity would be well received. There may be additional areas for resequencing that can aid both the schedule, and constructability.
Means and Methods: Steve Williams from Barton Malow was consultedregarding this analysis as he is in charge of the schedule. While a scheduling consultant is currently used for this project, Barton Malow has the onsite knowledge needed regarding possible phasing opportunities. Additionally the GSA provides an online resource for 4D BIM which has provisions for phased occupancy. This would be a good place to begin drafting potential issues and requirements for carrying out phased turnover. Once some suggestions for resequencing are drafted, they should be presented to the owner for an operations review. The format of the document should consist of a critical task and risk assessment
December 10, 2010 ST. JOSEPH’S WOMEN’S HOSPITAL – NICU EXPANSION
Dennis Gibson - CM | Final Thesis Proposal 8
data. The idea would be to outline ahead of time potential weak points in the plan, who is responsible for them, and develop secondary procedures and mitigation processes to avoid the failure of proposed plans. This is almost like a JHA, but regarding schedule completion as opposed to safety. Maintaining hospital operations is the primary concern of the project team, so facilitating this will hold precedence over overall schedule savings. Based on feedback from the BayCare representatives, the project schedule should be revised then compared with the original baseline to evaluate where float had been shifted, and if the critical path had been accelerated.
Expected Outcomes: This analysis is intended to achieve the following:
• Determine if partial phasing for the new NICU tower is acceptable to the owner • Add days to the demolition activity without affecting the critical path • Draft a new detailed project schedule that yields a savings in overall project duration • There is a cost savings as a result of either general conditions or early profitable turnover of
certain parts of the building
Analysis #4: BIM Modeling and Shop Drawing Integration
The previous analysis was intended to analyze Green Design and the efficiency of the mechanical systems. From there, the intent was to create energy models and compare the initial design with a new design which would include more energy reducing methods. This proved to be a bit difficult for me to apply with the St. Joseph’s project for several reasons. Frist, both the existing hospital and new addition will be serviced from a central mechanical plant, requiring the modeling of existing facilities which may prove to be difficult. Second, the level of detail required to run the model to any type of accuracy would require a deeper knowledge base than I have.
In place of this analysis, I have chosen to study the integration of BIM models and shop drawings. There are several contractors that already use BIM, however, it is rare that the model is used to produce shop drawings even though it will eventually produce spool drawings for the manufacturer. For example, steel contractors often use a model for coordination with other trades, but when it is time to fabricate beams, the model is dissected into sheet drawings which are reviewed piece by piece “the old fashioned way.” Once the review is complete, the model is then converted to a different file format which allows the automated detailing of the material at the yard. Another example, which will be the primary focus of this analysis, will be the use of BIM for rebar shop drawings. In my brief time in the field working for a concrete contractor, and more notably this past summer in reviewing structural concrete rebar shop drawings on behalf of a construction manager at risk, I have found that the ambiguity and time involved with a manual review of paper rebar shop drawings is a difficult task, and if not done properly, will result in serious mistakes. Figure 2 Below shows a snapshot of Tekla Structures reflecting a reinforcing and embed model in a concrete wall.
Deecember 1
The site wrenovatiowhen talktype, whicespecially
Research underuseJoseph’s Parchived mresulting i
Means anthe issue selection efficiencybased on
0, 2010
F
was walked onon work, whicking about thech involves any of a post ten
Focus and God sector of BIProject, and smodel which in a safer pro
nd Methods: of inefficient should be may and feasibilitmy experienc
ST. JOSE
Figure 2. Snaps
n January 3rd,h is frequent e reasons for n extensive ansion system
oals: This issIM modeling show the benwill allow fut
oduct for the u
First a pollinshop drawinade to modelty of coordinace using the s
EPH’S WO
Denn
shot from Tekl
and the topifor BayCare a two‐way flmount of reinis chosen, so
ue provides acapabilities. efits of havinture penetratuser.
g of various cg review is a the reinforciation and revsoftware, and
MEN’S HO
nis Gibson
a Structures. C
c was broughHealth facilitiat plate slab.nforcing steethat penetra
an opportunitThe idea willg a model forion and or ex
construction cshared conceng. Once thiview will be asd feedback re
OSPITAL –
n - CM | Fin
Courtesy AECB
ht up about thies. This was Since they wl, this analysiations can be
ty to explore be to producr shop drawinxpansion wor
companies wern. Once this is chosen, assessed, and ceived from i
– NICU EXP
nal Thesis
Bytes.com.
he possibility in reference were partial tos will prove tmade with gr
into a relativce a sample mng review, as k to be bette
will be necessas is determina model will bthe system windustry prof
PANSION
s Proposa
of future to analysis two using this so be beneficireater confid
vely new and model for thewell as an r planned,
ary to determed, a softwarbe created, will be critiqueessionals.
al 9
wo, lab al, ence.
e St.
mine if re
ed
December 10, 2010 ST. JOSEPH’S WOMEN’S HOSPITAL – NICU EXPANSION
Dennis Gibson - CM | Final Thesis Proposal 10
Expected Outcomes: This analysis is intended to achieve the following:
• Identify if there is a general issue with the common paper shop drawing review and coordination methods.
• Select a software that promotes a balance of detail and efficient drafting. • Identify soft costs and productivity for using reinforcement modeling as a substitute to paper
shop drawings. • Provide an overall assessment of the effectiveness of using reinforcement modeling for both
construction and as‐built purposes.
Deecember 1
Analys
Below is tto changeanalysis.
Conclu
Based on likely to yredesign tof challenand const
0, 2010
sis Weight
the proposed e as project de
usion
the feedbackield the mostto incorporatnging issues intructability th
ST. JOSE
t Matrix
weighting mevelopments
Table
k provided frot beneficial ree more prefan the construchrough in dep
EPH’S WO
Denn
atrix for the foccur, and af
2. Grading We
om the Bartonesults for the abrication. Ovction industryth research a
MEN’S HO
nis Gibson
focus of eachfter initial fea
eight Matrix of
n Malow projproject. The verall, these ty, as well as pand compariso
OSPITAL –
n - CM | Fin
individual anasibility studie
f Analysis Focu
ject team, thestrongest deptopics will proproviding valuon.
– NICU EXP
nal Thesis
nalysis. This mes are conduc
s.
e above analypth analysis wovide the moue engineerin
PANSION
s Proposa
matrix is subjcted for each
ysis topics wilwill be the façst inclusive vng, time savin
al 11
ect h
ll be çade iew gs,
December 10, 2010 ST. JOSEPH’S WOMEN’S HOSPITAL – NICU EXPANSION
Dennis Gibson - CM | Final Thesis Proposal 12
Appendix A – Breadth Analysis Topics
December 10, 2010 ST. JOSEPH’S WOMEN’S HOSPITAL – NICU EXPANSION
Dennis Gibson - CM | Final Thesis Proposal 13
Breadth Requirements
In addition to the thorough analyses pertaining to the construction of the project, two breadths have been selected for further analysis which will tie back into the original analyses. They will consist of a structural design breadth, and a mechanical design breadth focused on energy reduction.
Structural Breadth
Based on the results of the structural slab constructability and cost comparison matrix, the most beneficial slab choice from Depth Analysis #2 will be chosen for further structural design analysis. A basic floor layout will be designed to incorporate this new system. There will be a need to consult with structural engineering faculty members and advisors at Penn State to review basic design procedures learned in 300 level Architectural Engineering structural courses, and likely expand more on that and into some 400 level knowledge of concrete systems. Once a design is correctly calculated, some sample construction documents can be drafted, including plans, sections, and details of the system.
Architectural Breadth
The façade redesign will require both architectural and structural provisions to be successful. While this analysis is intended to provide an exploration of my constructability knowledge, the architectural features must be maintained throughout the alteration of design. The challenge will be maintaining similar joints to the original design, and not changing the aesthetic qualities, while at the same time creating detailed connection methods to facilitate the NOA rating issues of the design, and factory installation and delivery of materials.
December 10, 2010 ST. JOSEPH’S WOMEN’S HOSPITAL – NICU EXPANSION
Dennis Gibson - CM | Final Thesis Proposal 14
Appendix B – Schedule for Development of Analyses, Spring 2011
Dennis Gibson St. Joseph's Women's Hospital NICU ExpansionLast Revision 12‐10‐10 Today 1‐17‐11AE 481W Tampa, FLCM Option Dr. Robert Leicht
27‐Dec‐10 3‐Jan‐11 10‐Jan‐11 17‐Jan‐11 24‐Jan‐11 31‐Jan‐11 7‐Feb‐11 14‐Feb‐11 21‐Feb‐11 28‐Feb‐11 7‐Mar‐11 14‐Mar‐11 21‐Mar‐11 28‐Mar‐11 4‐Apr‐11 11‐Apr‐11 18‐Apr‐11 25‐Apr‐11
Analysis
Milestone 1: Go / No Go Checks 2/18 Analysis #1: Façade Redesign (Architectural Breadth)
Milestone 2: Go / No Go Confirmation 2/25 Analysis #2: Structural Slab Redesign (Structural Breadth)
Milestone 3: Presentation Checklist 3/25 Analysis #3: Resequencing
Analysis #4: Reinforcing Steel Modeling
Prepare ReportPrepare Presentation
Presen
tatio
ns
Final Rep
ort D
ue April 7th, 201
1
Sprin
g Break ‐ 2
011 MCA
A Co
mpe
tition ‐ M
aui, HI
...Analysis
Cost & Schedule Analyses
Summary of Findings
Determine Additional RequirementsRecreate Schedule
WINTER BREAK SPRING SEMESTER 2011
Cost, Efficiency, and Overall
Cost Impact…
Select Software and Create Model
Spring 2011 Senior Thesis Analysis Development ScheduleDecember 2010 Through April 2011
Site Visit
Senior Ban
quet ‐ Ap
ril 29, 201
1
ABET
Ana
lysis /
CPE
P Upd
ateSite Visit & Feasability Studies
Perform Cost & Productivity AnalysesRedesign of Structural… … Slab System
Consult with ManufacturersRedesign of Façade Layout
Redesign of Structural Connections
Site VisitConsult with Construction Professionals
Site Visit with OwnerGSA 4D Software Analysis
Milestone 1 Milestone 2
Today 1/17/11 Milestone 3
December 10, 2010 ST. JOSEPH’S WOMEN’S HOSPITAL – NICU EXPANSION
Dennis Gibson - CM | Final Thesis Proposal 16
Appendix C – Slab Comparison Analysis Matrix
December 10, 2010 ST. JOSEPH’S WOMEN’S HOSPITAL – NICU EXPANSION
Dennis Gibson - CM | Final Thesis Proposal 16
Slab Type Comparison Matrix
• Each item will be ranked 1 to 5 under each category, with 5 being the most beneficial rating • An importance factor will be designated for each numerical column based on owner desires • The GC Impacts, Constructability Challenges, Schedule Impacts, and Miscellaneous Benefits Category will be assessed individually as
either positive or negative points based on importance • Slab system resulting in the highest numerical total is the most beneficial
Slab TypeAverage Cost/SF Material Costs Labor Costs
Average Productivity Design Fees GC Impacts Constructability Challenges Schedule Impacts Miscellaneous Benefits
Two‐Way Flat PlatePost TensionedWaffle SlabPrecast Duct PlankOne‐Way Slab and BeamCategory TotalsImportance FactorRevised Total